ER26-3515-000 · 2026-09-16 · Josh Shapiro, Governor of the Commonwealth of Pennsylvania

Motion for Leave to Answer and Answer of Josh Shapiro, Governor of the Commonwealth of Pennsylvania in Support of PJM Interconnection, LLC’s proposal to…

Text extracted from the eLibrary original (SHA-256 8fb083bda2d922fe…). Download the original from the official source.

Contents · 7 sections
  1. I. SUMMARY p. 1
  2. II. ANSWER IN SUPPORT OF IRAS p. 7
  3. A. IRAS properly targets wholesale sales and reliable operation of the bulk p. 7
  4. B. PJM’s proposed compensation framework provides appropriate solicitude to p. 12
  5. C. IRAS is not unduly discriminatory. p. 15
  6. D. IRAS is just and reasonable because it will encourage investment in new p. 20
  7. III. CONCLUSION p. 25

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Cost allocation · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

ER26-3515 ) MOTION FOR LEAVE TO ANSWER AND ANSWER OF PENNSYLVANIA GOVERNOR JOSH SHAPIRO IN SUPPORT OF PJM’S PROPOSAL TO ESTABLISH INTERIM RESOURCE ADEQUACY SERVICE AND A LARGE LOAD REGISTRY Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice…
Read this passage Filed comments: Registry access

I. SUMMARY

printed heading · Topic match: Reliability and curtailment

State regulators face barriers to know when the potential for inconsistency with a federal jurisdictional scheme genuinely warrant delay, or when such concerns lack merit and are raised to delay costly or burdensome reforms. 13 For example, PJM’s capacity shortage emergency procedures in Manual 13…
Read this passage Filed comments: Reliability and curtailment

II. ANSWER IN SUPPORT OF IRAS

printed heading

II.
Read this passage

A. IRAS properly targets wholesale sales and reliable operation of the bulk

printed heading · Topic match: Reliability and curtailment

For target MW reductions, PJM proposes to limit the total MWs of load reduction in a zone or area based on the share of new large loads (which PJM terms “Eligible New Large Loads”) that have failed to meet their capacity needs through BYONC or capacity procured pursuant to Reliability Backstop…
Read this passage Filed comments: Reliability and curtailment

B. PJM’s proposed compensation framework provides appropriate solicitude to

printed heading · Topic match: Retail and wholesale authority

Protestors separately challenge PJM’s provision of an opportunity for wholesale compensation for loads that provide IRAS as prescribing a retail rate.27 A number of state regulators who have not otherwise challenged IRAS raise questions and concerns about the proposed compensation structure, and…
Read this passage Filed comments: Retail and wholesale authority

C. IRAS is not unduly discriminatory.

printed heading · Topic match: Reliability and curtailment

For that purpose, existing capacity resources, which cannot serve those new large loads because they are already committed to provide capacity to the system, and new capacity (including new capacity that is created at existing generating facilities or at deactivated generating facilities), which is…
Read this passage Filed comments: Reliability and curtailment

D. IRAS is just and reasonable because it will encourage investment in new

printed heading · Topic match: Reliability and curtailment

The Large Load Registry that PJM proposes to establish will provide information to enable retail regulators and retail load customers to understand the basis for PJM’s determination of the MW quantity of load subject to curtailment in a zone or area during an IRAS event.
Read this passage Filed comments: Reliability and curtailment

III. CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, Governor Shapiro respectfully requests the Commission to accept PJM’s proposal, subject to modification consistent with NRG as necessary to ensure its implementation as soon as possible.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated: September 16, 2026 /s/ Nathan Lobel Nathan Lobel Roselle LLP 300 New Jersey Ave.