Motion to Intervene and Comments of the MISO Transmission Owners re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
Midcontinent Independent System
)
Docket No. ER26-3650-000
Operator, Inc.
)
)
MOTION TO INTERVENE AND COMMENTS OF
THE MISO TRANSMISSION OWNERS
Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure,1 the MISO Transmission Owners2 submit this motion to intervene and comments on the August 28, 2026 filing by Midcontinent Independent System Operator, Inc. (“MISO”) in which MISO proposes revisions to its Open Access Transmission, Energy and Operating Reserve Markets Tariff
1 18 C.F.R. §§ 385.212, 385.214.2 For purposes of this filing, the MISO Transmission Owners consist of Ameren Services Company, as agent for Union Electric Company d/b/a Ameren Missouri, Ameren Illinois Company d/b/a Ameren Illinois and Ameren Transmission Company of Illinois; Big Rivers Electric Corporation; Central Minnesota Municipal Power Agency; Citizens Electric Corporation; City Water, Light & Power (Springfield, IL); Cleco Power LLC; Cooperative Energy; Dairyland Power Cooperative; Duke Energy Business Services, LLC for Duke Energy Indiana, LLC; East Texas Electric Cooperative, Inc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy Rural Electric Cooperative, Inc.; Indiana Municipal Power Agency; Indianapolis Power & Light Company d/b/a AES Indiana; International Transmission Company d/b/a ITCTransmission; ITC Midwest LLC; Lafayette Utilities System; Michigan Electric Transmission Company, LLC; MidAmerican Energy Company; Minnesota Power (and its subsidiary Superior Water, L&P); Missouri River Energy Services; Montana-Dakota Utilities Co.; Northern Indiana Public Service Company LLC; Northern States Power Company, a Minnesota corporation, and Northern States Power Company, a Wisconsin corporation, subsidiaries of Xcel Energy Inc.; Northwestern Wisconsin Electric Company; Otter Tail Power Company; Prairie Power, Inc.; Southern Illinois Power Cooperative; Southern Indiana Gas & Electric Company (d/b/a CenterPoint Energy Indiana South); Southern Minnesota Municipal Power Agency; Wabash Valley Power Association, Inc.; and Wolverine Power Supply Cooperative, Inc.
PDF page 2
2
(“Tariff”) to establish Interconnection Reliability Requirements for Large Loads (“IRR Proposal”).3 The IRR Proposal includes establishment of the new Section 37A to the Tariff to house the proposal’s framework, addition of definitions for the term Large Load and the term Computational Load (a subset of Large Load), and requirements that directly address aspects of the Commission’s directives related to reliable Large Load interconnection from its recent Show Cause Order.4
MISO’s proposal represents a critical step in addressing the unprecedented, accelerated influx of large-scale facilities that seek to interconnect in the region. By establishing tailored requirements for both Large Load and dynamic Computational Load, MISO proposes a scalable, risk-informed approach that protects grid operations. MISO’s proposal also minimizes disruptions to late-stage commercial projects. During development of this proposal, MISO demonstrated its commitment to stakeholder engagement on the issues, interfacing with its Large Load Working Group (“LLGW”), as well as other stakeholder groups, including the MISO Transmission Owners and the Organization of MISO States, Inc. For the ultimate success of the proposed framework, the MISO Transmission Owners strongly encourage MISO’s continued collaboration with stakeholders in the ongoing development of related Business Practice Manuals (“BPM”) or further Tariff provisions, as needed. For these reasons, the Commission should accept the August 28 Filing’s proposed Tariff revisions, effective December 4, 2026.
3 Interconnection Reliability Requirements for Large Loads of Midcontinent Independent System Operator, Inc., Docket No. ER26-3650-000 (Aug. 28, 2026) (“August 28 Filing”). Capitalized terms not otherwise defined herein shall have the meaning set forth in MISO’s Tariff or the August 28 Filing.4 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).
PDF page 3
3
I. COMMENTS
A. MISO’s IRR Proposal Offers a Just and Reasonable Framework to
Support Regional Reliability Given the Significant Large Load Growth The MISO Transmission Owners generally support MISO’s IRR Proposal as a just and reasonable framework that will establish scalable, technically sound, and “risk- informed” requirements for reliable interconnection of Large Loads while providing certainty to Large Load projects already underway.5
The IRR Proposal is a part of MISO’s efforts to provide speed to power for the rapid load growth across the region while maintaining reliability, and it is made alongside ongoing and recently proposed initiatives. Specifically, the IRR Proposal will complement MISO’s other recent strategic initiatives, including: MISO’s proposal for a Zero Injection Generator Interconnection Agreement and study process to interconnect resources that intend to serve load at the same substation and voltage level as existing or proposed load;6 the Expedited Resource Addition Study, which provides a temporary accelerated interconnection process tailored to generators needed within the region to serve important, near-term new load; MISO’s improved Expedited Project Review process, part of the MISO Transmission Expansion Plan, which expeditiously studies network upgrades necessary for new Large Loads; and the MISO-Southwest Power Pool, Inc. (“SPP”) Joint Targeted Interconnection Queue Study, which provides a pathway to build large-scale, backbone transmission upgrades at the MISO-SPP seam.
5 See August 28 Filing, Transmittal Letter at 3; id., Tab C (Prepared Direct Testimony of BeiBei Li, Senior Manager of Strategic Assessment) at 8 (“Li Test.”).6 Zero Injection Generator Interconnection Agreement of Midcontinent Independent System Operator, Inc., Docket No. ER26-3552-000 (Aug. 18, 2026) (“ZGIA Filing”).
PDF page 4
4
MISO also designed the IRR Proposal to complement MISO’s existing processes for system planning, interconnection, and operations,7 while providing a framework of reliability-based requirements for Large Loads, including visibility requirements;8 Phasor Measurement Unit (“PMU”) requirements to monitor Computational Loads;9 ramp requirements addressing the rate at which Computational Loads may increase or decrease consumption during stable-state transitions;10 and ride-through requirements setting minimum disturbance performance for Computational Load during voltage and frequency disturbances.11
The IRR Proposal also includes a new defined term for “Large Load.”12 As proposed, the term Large Load will be any load with a gross demand of 50 megawatt (“MW”) or more behind one or multiple Points of Withdrawal,13 owned, operated, or controlled by one or multiple entities that coordinate with respect to the profile of the Load, but does not include Load exclusively used for charging an Electric Storage Resource.147 Li Test. at 7.8 August 28 Filing, Transmittal Letter at 15-16; Li Test. at 24-26.9 August 28 Filing, Transmittal Letter at 17-19; Li Test. at 26-30.10 August 28 Filing, Transmittal Letter at 19-20; Li Test. at 30-31.11 August 28 Filing, Transmittal Letter at 20-21; Li Test. at 32-34.12 August 28 Filing, Tab A (IRR Tariff Redlines) at Definitions – L (“Proposed IRR Tariff”); Li Test. at 12.13 As with the ZGIA Filing, the August 28 Filing proposes to add a definition for the term “Point of Withdrawal” to mean “[t]he point(s) where a non-transmission facility that is used to withdraw Energy from the Transmission System to serve Load connects to the Transmission System.” Proposed IRR Tariff at Definitions – P.14 Id. at Definitions – L.
PDF page 5
5
MISO notes that accounting for gross load, rather than net load, will allow MISO “visibility into the full electrical demand and characteristics of the facility.”15 MISO also strategically chose 50 MW as a reasonable threshold based on an extensive review involving “industry practices, consideration of reliability needs in the MISO region, and stakeholder feedback”16 and because the number is an “administratively clear starting point, consistent with industry precedent, and sufficiently significant to warrant application” of the IRR Proposal’s requirements.17
Additionally, MISO proposes a new defined term for “Computational Load,” which is a Large Load comprised of 25 MWs or more of gross demand from “information technology equipment, such as servers, storage, and networking hardware.”18 This distinction is important because it reflects a more targeted and risk-informed approach, i.e., applying enhanced requirements only to Large Loads with operating characteristics that warrant additional reliability consideration.
As MISO highlights, the IRR Proposal directly responds to concerns that the Commission raised regarding ongoing operational requirements for transmission
15 August 28 Filing, Transmittal Letter at 10.16 Id.; see also Li Test. at 12 (“MISO determined that 50 MW is a reasonable threshold based on industry precedent, . . . and the need for a clear and administratively workable means of identifying significant, concentrated loads that warrant additional reliability visibility.”).17 August 28 Filing, Transmittal Letter at 10.18 Proposed IRR Tariff at Definitions – C; August 28 Filing, Transmittal Letter at 11; see also Li Test. at 14 (“MISO’s proposed definition of Computational Load is closely aligned with [the North American Electric Reliability Corporation (“NERC”)]’s developing definition of computational load. Both approaches identify computational load based on electric demand associated with information technology equipment, such as servers, storage, and networking hardware.”).
PDF page 6
6
customers taking transmission service on behalf of large loads.19 Critically, and consistent with the Show Cause Order, MISO’s proposal provides a reasonable, tiered transition structure to minimize disruption to commercial business decisions.20 Additionally, MISO’s IRR Proposal and other upcoming proposals are designed to align with emerging guidance from NERC, which works to ensure the reliability and security of the bulk power system. While MISO proposes reliability-based interconnection requirements for the region with the IRR Proposal, NERC is concurrently developing industry-wide guidelines.21 MISO notes that it crafted aspects of the IRR Proposal for consistency with those emerging industry practices.22 Through its IRR Proposal, MISO offers a framework that meets the needs of the region, addresses several of the Commission’s concerns, and maintains consistency with emerging industry expectations. For these reasons, MISO’s IRR Proposal is a just and reasonable package of new and improved provisions to MISO’s Tariff.
B. The IRR Proposal Provides a Strong Foundation From Which MISO
Should Continue Collaborating with Stakeholders to Finalize the
Proposal’s Technical Details
While the MISO Transmission Owners support the IRR Proposal as foundational to MISO’s response to the region’s exponential Large Load growth, substantial collaborative work is still required. MISO’s IRR Proposal can be a successful framework
19 Show Cause Order at P 64.20 August 28 Filing, Transmittal Letter at 14.21 Id. at 3.22 See e.g., id. at 20 (“Consistent with emerging industry practices and NERC guidance, the proposed ride-through expectations are intended to establish scalable and reliability-based performance criteria proportional to demonstrated system risk and facility operating characteristics.”).
PDF page 7
7
for ensuring continued system reliability, but more granular technical parameters of the proposal, such as details about Load Forecast measurements, ramp rates, ride-through requirements, and PMU compliance, need transparent specification in the forthcoming manuals and potentially further Tariff provisions to ensure successful implementation. Throughout its filing, MISO details the LLWG’s extensive efforts in facilitating the development of the IRR Proposal and other upcoming proposals to address the regional Large Load growth.23 MISO should continue to engage collaboratively with the LLWG and other stakeholders to build out its “hub-and-spoke” BPM architecture—“consisting of a new Large Load BPM, the ‘hub,’ supported by updates to existing BPMs and manuals, the ‘spokes’”24—and develop additional Tariff revisions as needed to achieve clear and standardized implementation of the IRR Proposal.
The MISO Transmission Owners appreciate MISO’s collaborative and stakeholder- receptive process for developing the IRR Proposal and look forward to providing input on the technical details for its successful implementation.
II. MOTION TO INTERVENE
This proceeding involves revisions to MISO’s Tariff to establish a new framework of reliability requirements for the interconnection of Large Load, i.e., the IRR Proposal, with new Tariff definitions and a new Tariff section to house the requirements. As Transmission Owners within MISO that are subject to the Tariff, each of the MISO Transmission Owners will be affected by whatever action the Commission takes in this proceeding because the Tariff and its procedures for interconnection of Large Load impact
23 Id. at 27-29. 24 Id. at 29.
PDF page 8
8
the MISO Transmission Owners and their transmission facilities. Additionally, the MISO Transmission Owners have a vested interest in the MISO region’s ability to meet the need for speed to power while maintaining resource adequacy and reliability as well as addressing aspects of the Show Cause Order’s directives, all of which the August 28 Filing’s proposals do. Consequently, each of the MISO Transmission Owners has a direct, unique, and substantial interest in this case that is not and cannot be adequately represented by any other party.25 Therefore, the Commission should allow the intervention of each MISO Transmission Owner listed supra in note 2.
The MISO Transmission Owners also request that the Commission place the following individuals on the official service list26 for this proceeding: Wendy N. Reed
Anna Fernandez
Abraham F. Johns III
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC 20005-3898
(202) 393-1200
reed@wrightlaw.com
fernandez@wrightlaw.com
johns@wrightlaw.com
25 18 C.F.R. § 385.214(b)(2)(ii) (stating that a motion to intervene must demonstrate that “[t]he movant has . . . an interest which may be directly affected by the outcome of the proceeding”).26 To the extent necessary, the MISO Transmission Owners request waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3), to permit all of the persons listed to be placed on the official service list for this proceeding.
PDF page 9
9
III. CONCLUSION
For these reasons, the MISO Transmission Owners request that the Commission grant this motion to intervene and accept the August 28 Filing as just and reasonable, effective December 4, 2026.
Respectfully submitted,
/s/ Abraham F. Johns III
Wendy N. Reed
Anna Fernandez
Abraham F. Johns III
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC 20005-3898
(202) 393-1200
reed@wrightlaw.com
fernandez@wrightlaw.com
johns@wrightlaw.com
Attorneys for the
MISO Transmission Owners
September 18, 2026
PDF page 10
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, DC, this 18th day of September 2026.
/s/ Abraham F. Johns III
Abraham F. Johns III
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC 20005-3898
(202) 393-1200
johns@wrightlaw.com
Attorney for the
MISO Transmission Owners