ER26-3650-000 · 2026-09-18 · MISO Transmission Owners

Motion to Intervene and Comments of the MISO Transmission Owners re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing

Text extracted from the eLibrary original (SHA-256 7ebfd62d3ad318b7…). Download the original from the official source.

Contents · 5 sections
  1. I. COMMENTS p. 3
  2. A. MISO’s IRR Proposal Offers a Just and Reasonable Framework to p. 3
  3. B. The IRR Proposal Provides a Strong Foundation From Which MISO p. 6
  4. II. MOTION TO INTERVENE p. 7
  5. III. CONCLUSION p. 9

Read topic-matched comments in ER26-3650

Topics in the text: Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

By establishing tailored requirements for both Large Load and dynamic Computational Load, MISO proposes a scalable, risk-informed approach that protects grid operations.
Read this passage

I. COMMENTS

printed heading

I.
Read this passage

A. MISO’s IRR Proposal Offers a Just and Reasonable Framework to

printed heading · Topic match: Connecting load and generation

While MISO proposes reliability-based interconnection requirements for the region with the IRR Proposal, NERC is concurrently developing industry-wide guidelines.21 MISO notes that it crafted aspects of the IRR Proposal for consistency with those emerging industry practices.22 Through its IRR…
Read this passage Filed comments: Connecting load and generation

B. The IRR Proposal Provides a Strong Foundation From Which MISO

printed heading

The IRR Proposal Provides a Strong Foundation From Which MISO Should Continue Collaborating with Stakeholders to Finalize the Proposal’s Technical Details While the MISO Transmission Owners support the IRR Proposal as foundational to MISO’s response to the region’s exponential Large Load growth,…
Read this passage

II. MOTION TO INTERVENE

printed heading · Topic match: Reliability and curtailment

Johns III Wright & Talisman, P.C. 1200 G Street, NW, Suite 600 Washington, DC 20005-3898 (202) 393-1200 reed@wrightlaw.com fernandez@wrightlaw.com johns@wrightlaw.com 25 18 C.F.R. § 385.214(b)(2)(ii) (stating that a motion to intervene must demonstrate that “[t]he movant has . . . an interest which…
Read this passage

III. CONCLUSION

printed heading

CONCLUSION For these reasons, the MISO Transmission Owners request that the Commission grant this motion to intervene and accept the August 28 Filing as just and reasonable, effective December 4, 2026.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, DC, this 18th day of September 2026. /s/ Abraham F.