ER26-3380-000 · 2026-09-18 · East Kentucky Power Cooperative, Inc.

Motion For Leave to File Second Limited Answer and Second Limited Answer of East Kentucky Power Cooperative, Inc

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)
PJM Interconnection, L.L.C.

)

Docket No. ER26-3380-000

)

MOTION FOR LEAVE TO FILE LIMITED ANSWER,
AND LIMITED ANSWER, OF
EAST KENTUCKY POWER COOPERATIVE, INC.

Pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure,1 East Kentucky Power Cooperative, Inc. (“EKPC”) moves for leave to file this limited answer and answers the September 10, 2026 answer submitted by PJM Interconnection, L.L.C. (“PJM”) in the above-captioned proceeding.2 EKPC’s Protest opposed PJM’s proposed revisions to its Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”) to establish the Reliability Backstop Procurement (“RBP”) because the RBP Proposal is unjust and unreasonable, unduly discriminatory, inconsistent with the Commission’s cost-causation principles and the boundaries of federal and state jurisdiction, and contrary to the Ratepayer Protection Pledge.3 PJM’s Answer does not resolve those defects. For the reasons set forth herein and in the EKPC Protest, EKPC respectfully requests that the Commission reject the RBP Proposal.

EKPC also submits this Limited Answer to place PJM’s post-protest explanations and implementation materials in their proper context. PJM’s Answer relies on clarifications,

1 See 18 C.F.R. §§ 385.212, 385.213 (2026).
2 PJM Interconnection, L.L.C., “Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C.,” Docket No. ER26-3380-000 (filed Sept. 10, 2026) (“PJM Answer”).
3 See PJM Interconnection, L.L.C., “Protest of East Kentucky Power Cooperative, Inc.,” at 11–14, 15–49, Docket No. ER26-3380-000 (filed Aug. 21, 2026) (“EKPC Protest”); Affidavit of Adam Bednarczyk PP 7, 12, 14, 17, 27, 34, 38, 42, 46, 59–70, Attachment 1 to EKPC Protest (“Bednarczyk Protest Aff.”); Affidavit of Carl F. Coscia PP 57–58, 72– 80, 98, 109–121, 135–174, 175–210, Attachment 2 to EKPC Protest (“Coscia Protest Aff.”).

PDF page 2

2

concessions, and implementation descriptions that were not fully reflected in the July 31 filing or available for meaningful stakeholder review before protests were due.4 PJM itself characterizes its Answer as providing post-filing clarifications and adjustments and cites post-Critical Issue Fast Path (“CIFP”) workshops and implementation materials.5 EKPC therefore addresses those

developments to assist the Commission in evaluating whether the RBP Proposal as filed—not as subsequently explained or refined—satisfies PJM’s section 205 burden.

I. MOTION FOR LEAVE TO FILE LIMITED ANSWER
Although Rule 213(a)(2) generally prohibits answers to protests or answers absent
Commission authorization, the Commission accepts otherwise-prohibited answers when they
provide information that assists its decision-making,6 and clarify the record.7 Good cause exists here to justify the Commission’s granting this motion and accepting this Limited Answer. PJM’s Answer misconstrues or does not address central issues raised in EKPC’s Protest and First Limited Answer,8 including whether RBP costs and transmission owner exit fees bear a meaningful

relationship to cost causation, whether PJM treats Fixed Resource Requirement (“FRR”) entities and Reliability Pricing Model (“RPM”) self-supply load-serving entities (“LSEs”) comparably,

4 See PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads” (filed July 31, 2026) (“PJM RBP Filing”).
5 See PJM Answer at 8–10 & nn.31–32.
6 See PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting an answer that assisted with the decision-making process); N.Y. State Pub. Serv. Comm’n v. N.Y. Indep. Sys. Operator, Inc., 158 FERC ¶ 61,137, at P 29 (2017) (same), order granting in part and denying in part reh’g and clarification, 170 FERC ¶ 61,120, order on clarification, 171 FERC ¶ 61,114 (2020); Colonial Pipeline Co., 157 FERC ¶ 61,173, at P 23 (2016) (same).
7 See, e.g., Potomac-Appalachian Transmission Highline, LLC, 140 FERC ¶ 61,229, P 102 (2012) (accepting answer to an answer because it provided material evidence that corrected the record and informed the Commission’s decision- making process); High Island Offshore Sys., L.L.C., 113 FERC ¶ 61,202, P 8 (2005) (accepting an answer to a protest because it assisted the Commission with a more complete record); N.E. Utils. Servs. Co. v. NRG Energy, Inc., 101 FERC ¶ 61,327, P 17 (2002) (accepting answer to an answer because it helped clarify issues in the proceeding).
8 See PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Motion for Leave to File Limited Answer, and Limited Answer, of East Kentucky Power Cooperative, Inc.” (filed Sept. 4, 2026) (“EKPC First Limited Answer”) (supporting protests filed by transmission owners addressing PJM’s proposed Transmission Owner exit fee provisions of the RBP).

PDF page 3

3

and whether the proposed credit and default provisions define, secure, and allocate the relevant exposures in a just and reasonable manner. PJM also supplies new explanations and proposed concessions concerning severance of the buyer-side LSE credit rate, the timing and calculation of collateral, Peak Market Activity, and default allocation.9 This Limited Answer responds only to those matters and to PJM’s post-filing implementation explanations, will not prejudice any party or delay the proceeding, and will assist the Commission in evaluating whether PJM has carried its burden under section 205 of the Federal Power Act (“FPA”). The Commission should therefore accept this Limited Answer.

II. BACKGROUND AND SUMMARY
On July 31, 2026, PJM filed proposed revisions to its Tariff and RAA to establish a RBP intended to address identified capacity shortfalls associated with forecast large-load growth. EKPC’s Protest explained that a legitimate reliability objective does not excuse a rate design that fails to make costs, credits, collateral obligations, and default risks transparent, traceable, administrable, and reasonably tied to the entities that caused or benefit from the procurement.10 PJM’s proposed fallback allocation still spreads RBP costs to load without demonstrating that the charged LSEs caused the procurement need or receive commensurate benefits. Its disparate treatment of FRR entities and RPM self-supply LSEs remains unexplained. And severing one credit-rate input leaves unresolved the nature, timing, quantity, release, and default treatment of the exposure being collateralized.

PJM’s Answer does not cure those defects, and the allocation of the burden of proof matters. This is PJM’s section 205 filing. PJM therefore must establish, by record evidence and

9 See PJM Answer at 74–93, pts. I.J.1–I.J.6.
10 See EKPC Protest at 11.

PDF page 4

4

reasoned explanation, that the particular tariff rules it filed—not merely the reliability objective they pursue—are just and reasonable and not unduly discriminatory or preferential.11 EKPC need not design a superior replacement or disprove every possible justification that PJM might have supplied. If PJM has not shown how its allocation, offset, collateral, and default provisions produce lawful outcomes, the statutory prerequisite to the Commission’s acceptance of the RBP Proposal is absent. The Commission therefore should reject the RBP Proposal or, at minimum, reject or set for further procedures the unsupported provisions identified below.12

PJM’s evolving explanation of the buyer-side credit framework confirms that material aspects of the RBP Proposal remained under development after the PJM RBP Filing. PJM now offers to remove Tariff language concerning Peak Market Activity, clarifies that collateral is not due until 45 days before the first Delivery Year for which an LSE is responsible for RBP Charges, and consents to further procedures on the buyer-side credit rate.13 Whatever authority PJM has to make a section 205 filing, the relevant point is that the credit design now being defended was not fully presented in the stakeholder process or, most importantly for purposes of the Commission’s deliberation, in the filed tariff language presented in PJM’s RBP Filing. LSEs were asked to evaluate a proposal whose collateral mechanics, interaction with Peak Market Activity, timing, and exposure methodology were still being refined after protests were filed. That procedural history

11 See 16 U.S.C. § 824d(a), (b), (e); Hecate Energy LLC v. FERC, 126 F.4th 660, 662 (D.C. Cir. 2025) (explaining that section 205 requires the Commission to accept proposed changes only if they are just and reasonable and not unduly discriminatory); City of Winnfield v. FERC, 744 F.2d 871, 875 (D.C. Cir. 1984) (contrasting the filing utility’s burden under section 205 with a complainant’s burden under section 206); see also 18 C.F.R. § 35.13(e) (2026) (requiring support for proposed rate changes).
12 Failure in this Answer to specifically address a point raised by PJM should not be viewed as a concession by EKPC that it is no longer challenging that aspect of the RBP.
13 See PJM Answer at 78 n.234, 86 n.259, 92–93 & nn.282–86.

PDF page 5

5

reinforces—not replaces—EKPC’s substantive showing that the proposal lacks administrable tariff standards.

III. LIMITED ANSWER
A. PJM Has Not Carried Its Affirmative Burden Under FPA Section 205.
Section 205 places the burden squarely on PJM to show that the RBP is just and reasonable. All jurisdictional rates and all rules and practices affecting them must be just and reasonable and not unduly discriminatory or preferential, and when a public utility proposes a change, “the burden of proof to show that the increased rate or charge is just and reasonable shall be upon the public utility.”14 The Commission’s regulations accordingly require a filing utility to submit the information necessary to explain and support the proposed change.15 The distinction from section 206 of the FPA is fundamental: PJM is not defending an existing rate presumed lawful against an EKPC complaint; PJM is asking the Commission to authorize new tariff provisions.16 PJM itself has publicly described the governing rule the same way: a public utility making a section 205 filing “has the legal burden of demonstrating” that its proposed change is just and reasonable.17 To satisfy this burden requires more than showing that a reliability problem exists or that PJM’s preferred mechanism is administratively convenient. PJM must connect the evidence to the specific rate design for which it seeks approval. And the Commission must evaluate the proposal actually filed on the record before it, provide a reasoned explanation for its conclusion, and respond

14 16 U.S.C. § 824d(a), (b), (e).
15 See 18 C.F.R. §§ 35.12, 35.13 (2026)  (any public utility filing a rate change must submit detailed data and statements to “sustain the burden of proof under the Federal Power Act of establishing that the rate increase is just and reasonable”).
16 See City of Winnfield, 744 F.2d at 875.
17 PJM Interconnection, L.L.C., Federal Law Guides Changes in PJM Governing Documents 1 (2025), available at: https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-sheets/federal-power-act-sections-205-and- 206.pdf.

PDF page 6

6

to material objections that cast doubt on the proposal’s lawfulness.18 The Commission therefore cannot presume answers that PJM did not supply, rely on conclusory assertions that the proposal is “tailored,”19 or treat unanswered cost-causation questions as EKPC’s failure of proof. A material evidentiary gap is PJM’s failure to carry its section 205 burden.

B. PJM Failed to Address EKPC’s Cost Causation Arguments.
Cost causation is not a subsidiary policy preference that the Commission may bypass once PJM identifies a regional shortfall. A rate must reflect, at least to some degree, the costs caused by the customers required to pay it, and an allocation based on benefits must be at least roughly commensurate with the benefits received.20 PJM’s own Answer invokes the same principle: costs should be recovered from customers that use the facilities and cause the costs to be incurred.21 But PJM does not carry that principle through the RBP Proposal.

PJM’s transmittal letter establishes a regional capacity shortfall and attributes much of the forecast growth to large loads.22 But PJM does not demonstrate each link necessary to justify the proposed charge. PJM does not identify how the forecast increment used to set the procurement target will be traced to the particular LSEs ultimately assessed RBP Charges, show that an Electric Distributor or state/Relevant Electric Retail Regulatory Authority (“RERRA”) allocation will preserve that causal link, require an offset or prudent existing supply to follow the LSE or load

18 See Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983); PSEG Energy Res. & Trade LLC v. FERC, 665 F.3d 203, 208 (D.C. Cir. 2011). 19 PJM Answer at 10 (the role of an Electric Distributor is “[a]ppropriately tailored”), 42 (the proposed gating criteria as “appropriately tailored”), 74 (the buyer-sider credit requirements are “appropriately tailored”).
20 See K N Energy, Inc., 968 F.2d 1295, 1300-01 (D.C. Cir. 1992) (“requiring that all approved rates reflect to some degree the costs actually caused by the customer who must pay them.”); Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368-69 (D.C. Cir. 2004) (same); Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 476-77 (7th Cir. 2009) (same); Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1260-61 (D.C. Cir. 2018) (same). EKPC Protest at 29–31; Bednarczyk Protest Aff. at PP 17–22, 27–40.
21 PJM Answer at 61–63 & nn.182–92.
22 See PJM RBP Filing at 1-2, 7.

PDF page 7

7

that provided it, explain why a Peak Load Contribution-based (“PLC”) fallback measures causation by the identified large-load growth, or establish that a customer charged under the fallback measure will receive a benefit roughly commensurate with its assigned costs. Moreover, PJM’s proposed Tariff text likewise supplies no objective standard that answers those questions. Describing the mechanics of a downstream allocation process is not evidence that the resulting allocation is just and reasonable.23

These are not isolated objections. Mr. Bednarczyk explained that the RBP fails to maintain a traceable link among incremental large-load responsibility, recognized mitigation, RBP Obligations (“RBO”) MW, RBP Charges, and collateral obligations.24 Mr. Coscia then showed that the credit construct compounds that defect because the collateral obligation is not derived from a measured exposure, is not tied to the timing of actual RBP settlement risk, and may itself create liquidity and default risk.25 PJM’s Answer addresses pieces of those critiques but does not supply the missing tariff standards needed to make the RBP framework administrable and causation- based.

PJM cannot cure the deficiencies by assigning the missing analysis to Electric Distributors, states, or RERRAs.26 Those entities may administer retail matters or choose how a valid wholesale obligation is recovered, but their later choices cannot supply the predicate showing PJM had to make when it filed the wholesale rate.27 If PJM’s Tariff does not provide a causation-based

23 See EKPC Protest at 15-21 (explaining that the PJM RBP Proposal is unjust and unreasonable because the resulting rate impact is uncertain).
24 Bednarczyk Protest Aff. at PP 12–22, 26–40, 47–58, 65–70.
25 Coscia Protest Aff. at PP 57–58, 72–80, 98, 109–121, 135–174, 201–210. 26 See EKPC Protest at 19-21, 37-38.
27 See 16 U.S.C. § 824d(c), (d); Atl. City Elec. Co. v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002) (“the power to initiate rate changes rests with the utility”).

PDF page 8

8

allocation rule, a state’s later decision cannot retroactively make the filed wholesale rate just and reasonable.

Nor may PJM’s Answer substitute new explanation for missing Tariff content. The
Commission evaluates the filed rate as proposed, and regulated entities must be able to determine their obligations from the governing tariff rather than from post-filing assurances.28 Where PJM now offers clarifications, concessions, or severance to answer protests, those responses confirm that the as-filed provisions did not themselves resolve material uncertainties and issues of the proposed rated.

Finally, the Commission may not save the RBP Filing by assembling a different proposal
from stakeholder alternatives or by supplying its own reasoning to reinterpret filed tariff revisions that PJM did not provide.29 The stakeholder-supported subscription alternative referenced by EKPC in its Protest is relevant because it demonstrates that causation-based approaches existed, not because EKPC bears a burden to prove that alternative uniquely just and reasonable.30 EKPC further observes that PJM’s RBP Proposal inappropriately relies on downstream state/RERRA

action. PJM could have adopted the stakeholder-supported proposal that relied on RERRA action at the outset of the backstop procurement process to ensure that LSEs serving Large Loads would

28 See e.g., NRG Power Marketing, LLC v. FERC, 862 F.3d 108, 114–16 (D.C. Cir. 2017) (holding that FPA section 205 did not authorize the Commission to transform a utility’s proposal into an “entirely new rate scheme,” notwithstanding the filing utility’s agreement to the Commission-imposed modifications); Western Resources, Inc. v. FERC, 9 F.3d 1568, 1578–79 (D.C. Cir. 1993) (distinguishing permissible conditions that leave the proposal’s essential structure intact from modifications that exceed the Commission’s authority); KeySpan-Ravenswood, LLC v. FERC, 474 F.3d 804, 811–12 (D.C. Cir. 2007) (vacating an order where the Commission permitted NYISO to use material conversion formulae not set forth in the filed tariff and the Commission failed adequately to explain why they need not be filed). See also EKPC Protest at 15-21 (a filed rate must provide specificity and allow impacted customers to estimate the cost impact).
29 See NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114-15 (D.C. Cir. 2017) (“Section 205 puts FERC in a ‘passive and reactive role.’” (quoting Advanced Energy Management Alliance v. FERC, 860 F.3d 656, 429 (D.C. Cir. June 20, 2017)).
30 EKPC Protest at 8-10; Bednarczyk Protest Aff. at P 44. PJM completely failed to address Mr. Bednarczyk’s affidavit in its Answer.

PDF page 9

9

subscribe to the auction to ensure that the capacity shortfall would be addressed through sufficient subscription. PJM’s concern with the stakeholder-supported proposal is that the PJM Board did not have confidence it addressed the capacity shortfall. However, reliance on states/RERRAs could have addressed the capacity shortfall concern while also affording certainty as to which LSEs would be receiving RBP allocations and be fully responsible for RBP costs and credit responsibilities and being consistent with cost-causation principles. More importantly, reliance on states/RERRAs at the start of a backstop procurement process would be consistent with establishing a valid wholesale obligation that would appropriately align with the state’s/RERRA’s responsibilities for retail rate determinations.

C. EKPC’s Protest Is Consistent with the Ratepayer Protection Pledge.
PJM suggests that EKPC’s execution of the Ratepayer Protection Pledge is inconsistent with its opposition to the RBP.31 The opposite is true. EKPC supports the principle that new large loads should build, bring, or buy the resources needed to serve their demands and bear the full associated costs. In fact, EKPC supported the Joint EDC & Data Center Coalition Reliability Backstop Procurement Proposal, which would have enabled states/RERRAs to act at the outset of an RBP process to ensure LSEs responsible to provide retail service to Large Loads subscribed to the procurement process so the appropriate amount of capacity is procured.  As noted above, this would have provided greater certainty, better aligned cost causation, and provided ratepayer protection by ensuring the appropriate LSEs are charged the costs they were directly responsible for incurring. EKPC protested the RBP because, as proposed, the RBP may shift those costs to LSEs and customers that prudently planned their portfolios and did not cause the residual

31 PJM Answer at 59.

PDF page 10

10

procurement need.32 A mechanism that can impose RBP charges, collateral burdens, or mutualized default exposure on non-causers conflicts with—rather than implements—the Pledge’s ratepayer- protection objective.33

PJM’s assertion that EKPC presently receives no direct RBP allocation does not answer
EKPC’s fundamental objections to the RBP proposal.34 EKPC challenges the RBP Proposal,
including its precedential and future effects, not merely its first illustrative assignment. Although PJM describes the RBP as a one-time process,35 the proposed Tariff and RAA language does not itself supply a clear one-time limitation, and PJM has publicly contemplated RBP or similar mechanisms in future reliability frameworks.36 The Commission must evaluate the filed provisions as proposed.

PJM’s reliance on the Ratepayer Protection Pledge to support its transmission-owner exit
provisions is similarly misplaced.37 Requiring entities that did not cause the RBP need to bear costs associated with pseudo-tying generation back into PJM after a transmission owner exits would

32 See EKPC Protest at 14 (“The PJM RBP Proposal creates unmitigable financial and reliability risk for LSEs that prudently planned for their load or otherwise did not cause the residual RBP procurement need.”), Bednarczyk Protest Aff. at P 34 (“an LSE that has already planned prudently and secured adequate resources could nonetheless incur a second long-term obligation that provides little or no additional reliability benefit. That outcome weakens incentives for proactive resource planning, socializes the benefits of prudent mitigation, and leaves the planning LSE exposed to residual charges, collateral obligations, and default-allocation risk.”).
33 See EKPC Protest at 28, 39, 48-49 (explaining why the RBP Proposal is inconsistent with the Ratepayer Protection Pledge).
34 PJM Answer at 67 n.205.
35 PJM similarly described the RPM price collar as a one-time, temporary measure but it has now been extended for multiple, additional delivery years. See PJM Interconnection, L,L.C., 195 FERC ¶ 61,076 (2026).
36 See PJM Interconnection, L.L.C., Draft Memorandum of Understanding Framework Between States and PJM Re: Reliability/Resource Adequacy (PJM “Commits to establish Reliability Backstop Procurements, or other similar mechanisms codified in Attachment DD of the PJM Open Access Transmission Tariff at the request of states and with the approval of FERC, to allow for the procurement of additional capacity where shortfalls have been identified and risk to system reliability is credible”) found at: https://www.pjm.com/-/media/DotCom/committees- groups/committees/mc/2026/20260819/20260819-item-08---2-memorandum-of-understanding-framework-between- pjm-and-states.pdf
37 See PJM Answer at 94.

PDF page 11

11

reproduce the same cost-causation problem.38 PJM does not explain why those costs should follow non-causing load rather than the transaction, entity, or circumstance that makes the pseudo-tie necessary.

D. PJM Does Not Justify Disparate Treatment of FRR Entities and RPM Self
Supply LSEs.

PJM fundamentally misunderstands EKPC’s argument with respect to treatment of FRR entities. Contrary to PJM’s assertion, EKPC does not argue that FRR entities should be subjected to the RBP.39 EKPC’s point is comparability.40 PJM recognizes an FRR entity’s existing portfolio and excludes its load and supply from RBP exposure, while an RPM self-supply LSE may receive no comparable recognition for resources it already owns or procured to serve its customers.41 Both entities may have taken materially similar planning actions to satisfy aggregate resource obligations. PJM does not identify a relevant operational or cost-causation distinction that justifies insulating one portfolio while disregarding the other.

That unexplained asymmetry raises classic undue-discrimination concerns. FPA section 205(b) prohibits an undue preference or advantage and any unreasonable difference in rates or service among similarly situated customers.42 That FRR entities face a deficiency rate does not cure the problem, particularly where that rate is not yet effective for the relevant period.43 Nor does moving related FRR language to the IRAS docket establish that the RBP’s differential

38 See EKPC First Limited Answer.
39 See PJM Answer at 55.
40 EKPC Protest at 45 (“PJM’s RBP Proposal’s treatment of FRR entities and the use of existing resources to satisfy FRR plans creates comparability concerns and unduly discriminates against RPM Capacity Market LSEs in several ways.”). See also Bednarczyk Protest Aff. at PP 59-60 (“The RBP also treats FRR entities and RPM self-supply entities differently in ways that raise comparability concerns.”).
41 EKPC Protest at 45.
42 16 U.S.C. § 824d(b); see Ark. Elec. Energy Consumers v. FERC, 290 F.3d 362, 367 (D.C. Cir. 2002).
43 See RAA, Schedule 8.1, Section D (7) (“For Delivery Years between the 2025/2026 Delivery Year through the 2028/2029 Delivery Year, no FRR Commitment Insufficiency Charge shall be assessed.”).

PDF page 12

12

treatment is just and reasonable.44 The Commission should require PJM to recognize comparable portfolio sufficiency or explain, with record evidence, why materially similar planning conduct warrants materially different RBP treatment.

E. PJM’s Proposed Credit-Rate Severance Does Not Cure the RBP’s Credit
and Default Defects.

As detailed in the EKPC Protest, PJM’s proposed collateral requirements are unjust and unreasonable and should be rejected.45 If the Commission nevertheless accepts PJM’s proposal to sever the buyer-side LSE credit rate for further procedures, the numerical rate is only one component of the defect.46 Any further proceeding must define the exposure being secured, the quantity to which the rate applies, the date on which the obligation arises, objective reduction and release standards, the interaction with Operating Agreement section 15.2.2, and the liquidity and default consequences created by the requirement. Severing one input cannot make the remainder of the RBP just and reasonable when the obligation’s basic operation remains uncertain. PJM’s Answer also contains unresolved inconsistencies. PJM states that EKPC would receive no RBP cost allocation or reallocation under proposed section 18.9(a), yet PJM invokes Operating Agreement section 15.2.2—and the need to protect PJM Members from LSE default— to justify the collateral requirement.47 If section 18.9 fully contains an RBP default within the pool of LSEs assigned RBP Charges, PJM should state that limitation in the governing Tariff text. If residual unpaid amounts may reach all PJM Members under Operating Agreement section 15.2.2, then EKPC’s lack of a direct RBP allocation does not eliminate its exposure. PJM cannot rely on

44 EKPC filed a limited protest in the IRAS proceeding and objected to the language at issue in that docket as well. See PJM Interconnection, L.L.C., “Limited Protest of East Kentucky Power Cooperative, Inc.,” 35-36, Docket No. ER26-3515-000 (filed Sept. 3, 2026).
45 EKPC Protest at 21–28; Coscia Protest Aff. at PP 61–121, 135–174, 201–210.
46 See PJM Answer at 92–93.
47 See PJM Answer at 67 n.205, 84 n. 252.

PDF page 13

13

mutualized Member exposure to defend the credit design while denying that the same exposure reaches EKPC.

PJM’s remaining clarifications likewise do not conform to the filed Tariff. First, PJM offers to delete the sentence stating that RBP settlement may be included in Peak Market Activity,48 but does not explain how an invoiced RBP billing item is excluded from Peak Market Activity or whether Attachment Q requires a conforming revision. Second, PJM states that no LSE collateral is required until an RBP Resource is in service for the applicable Delivery Year,49 but proposed section 18.8(b)(i)(A)—the buyer-side cumulative requirement—defines committed RBP UCAP MW without an express in-service limitation. Third, PJM states that collateral is based on committed MW,50 while section 18.8(b)(i)(B)(1) scales the LSE posting to the Final RBP Target. If procurement clears below that target, the filed language does not specify which quantity controls aggregate collateral.

PJM’s credit-migration analysis does not cure those defects. PJM extrapolates S&P’s ten- year transition study to fifteen years and reports an approximately 11 percent probability that a BBB obligor reaches default and 36.9 percent for a BB obligor.51 But that table measures migration arising in the ordinary course; it does not measure what happens to an LSE’s financial condition when PJM imposes a collateral obligation of the magnitude proposed here.52 On PJM’s own allocation, the cooperative with the second-largest zonal assignment would post approximately 114 percent of its total assets, roughly twice its equity, and about eight times its cash, while a 100-

48 PJM Answer at 86, n.259.
49 PJM Answer at 78, n. 234.
50 PJM Answer at 78, n. 234.
51 PJM Answer at 81-82, Table 2.
52 Coscia Reply Affidavit at P 26.

PDF page 14

14

basis-point carrying cost would consume approximately 94 percent of one year’s operating margins.53 That cooperative is investment grade and among the 24 LSEs PJM itself classified as investment grade.54 At this scale, the migration PJM invokes to defend a credit-blind rate may be partly a consequence of the rate itself. Additionally, PJM applies credit sensitivity to sellers while declining to do so for buyers, without adequately explaining that asymmetry.55

The stakeholder record further confirms that credit-specific, causation-based alternatives existed, including that buyer-side credit could be managed through existing processes. 56 The June 30 Package Matrix also shows that the Joint EDC/Data Center Coalition proposed a pre- procurement registry identifying which LSEs must support collateral and for how many megawatts, with a gate preventing procurement for load whose responsible LSE or large-load customer could not post.57 PJM states that the filed LSE credit requirement has roots in the Joint EDC/ Data Center Coalition proposal,58 but the filed design adopts the assignment to LSEs without the registry, gate, or exposure-funding mechanics that tied credit responsibility to the load being procured for. This record reinforces that causation-based approaches existed on the precise credit issue; PJM did not justify discarding their limiting mechanics.

The economics also show why the gross payment stream is not a sufficient measure of RBP-specific exposure. For 6,000 MW with three years remaining, an RBP price of $555/MW- day, and an RPM price of $554/MW-day, the incremental contract-for-differences payment is only

53 Coscia Reply Affidavit at P 27.
54 Coscia Reply Affidavit at P 27.
55 Coscia Reply Affidavit at P 28. 56 Coscia Reply Affidavit at P 33.
57 Coscia Reply Affidavit at P 34. The June 30 Package Matrix is available at: https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-cifp---reliability-backstop-procurement--- options-and-packages-matrix---updated.xls
58 Coscia Reply Affidavit at P 35; PJM RBP Filing at 22.

PDF page 15

15

$2.19 million per year, or $6.57 million over three years.59 The $554/MW-day RPM component— approximately $3.64 billion over the same period—would settle through ordinary RPM billing and, absent the RBP, would be addressed through PJM’s existing credit processes.60 Thus, the gross three-year amount on which PJM relies consists almost entirely of future RPM payments rather than incremental RBP exposure.61 The filed provisions do not explain why, for example, a $1/MW- day contract-for-differences transforms the associated RPM stream into a separately collateralized long-term obligation or establish an objective method for reducing and releasing collateral as the contract-for-differences and remaining tenor decline.

Finally, PJM states that no LSE collateral is due until 45 days before the first Delivery Year in which an LSE is responsible for RBP Charges.62 That clarification does not justify postponing resolution of the buyer-side credit framework until shortly before collateral is due. The credit framework affects the economics, financeability, risk allocation, and potential creditworthiness of affected LSEs from the moment RBP commitments become binding, which is currently proposed to occur in December 2026.63

Appropriate buyer-side credit provisions are essential for the PJM RBP Proposal to be just and reasonable, and  PJM’s proposed buyer-side credit provision clearly do not meet this standard. Should the Commission decide to not reject PJM’s RBP Proposal outright, including the buyer- side credit provisions, it should require PJM to propose and obtain Commission approval of a complete, exposure-based buyer-side credit framework before RBP commitments become

59 Coscia Reply Affidavit at P 59 and Table 1.
60 Coscia Reply Affidavit at P 60.
61 Coscia Reply Affidavit at P 60.
62 PJM Answer at 78 n.234, 92–93 & n.285. 63 Coscia Protest Aff. at PP 72–80, 135–152, 201–210.

PDF page 16

16

binding. At an absolute minimum, the Commission should establish a date certain that gives affected LSEs, states, RERRAs, and large loads a meaningful opportunity to evaluate, challenge, finance, and implement any required credit support well before the first posting deadline. The urgency of securing capacity does not justify making long-term commitments (of a duration that is up to 15 years longer than any other PJM-administered market) first and resolving a fundamental allocation and credit issue years later.

F. The Commission Should Reject the Proposed Default Allocation.

The Commission should reject the default allocation because PJM has not demonstrated that shifting an unpaid RBP Charge among the remaining LSEs preserves any relationship to causation or benefits. The fact that the residual loss must be placed somewhere does not establish that PJM’s chosen recipients caused it or receive commensurate benefits from assuming it. PJM must support that choice under section 205 just as it must support the initial allocation. The Commission cannot infer a lawful nexus from the mere existence of default risk. At minimum, the Commission must require Tariff language confining RBP nonpayment to entities assigned RBP Charges and reasoning documented in the record as to why any reallocation among them remains just and reasonable.

G. PJM’s Portfolio-Benefit Theory Underscores the Mismatch.

PJM argues that one LSE’s actions can reduce other LSEs’ RBP obligations because pooled benefits are inherent in an RTO.64 But PJM recognizes portfolio benefits when they reduce its procurement target while denying comparable recognition to the owner or contracting LSE when determining offsets or exposure. In its Protest, EKPC explained that without a rule requiring offsets and existing-supply recognition to follow the responsible LSE or load, the RBP unfairly socializes

64 PJM Answer at 73.

PDF page 17

17

the benefit of prudent resource planning while leaving those LSEs that adequately covered their load obligations exposed to potential charges and collateral requirements.65 PJM has not explained why portfolio effects count when they reduce the regional procurement need but not when they demonstrate that a particular LSE prudently supplied its own load. That asymmetry is especially difficult to justify if PJM later repeats or repurposes the RBP.

IV. CONCLUSION
For the foregoing reasons, EKPC respectfully requests that the Commission accept this limited answer and reject PJM’s RBP Proposal. PJM bears the section 205 burden, and neither its transmittal letter, proposed Tariff language, supporting affidavits, nor Answer demonstrates that the challenged cost-allocation, offset, collateral, credit, default, and transmission owner exit fee provisions are just and reasonable and not unduly discriminatory or preferential. The Commission therefore lacks a reasoned record basis to accept those provisions; it cannot sidestep EKPC’s material cost-causation objections, presume facts PJM did not establish, or supply missing tariff standards on PJM’s behalf. Should the Commission be inclined to accept PJM’s RBP Proposal and accept PJM’s suggestion for severing the buyer-side credit provisions, EKPC respectfully urges the Commission to undertake additional administrative proceedings that would result in tariff language that clearly defines, measures, and confines RBP credit and default exposure  before the RBP commitments would be established (currently proposed to be in December 2026).  It is imperative that buyer-side credit requirements be certain before RBP commitments become binding, and that the buyer-side credit rules provide LSEs a meaningful opportunity to evaluate and arrange credit support well before any collateral posting obligation arises.

65 EKPC Protest at 31; Bednarczyk Protest Aff. at PP 27, 34.

PDF page 18

18

Respectfully submitted,

Denise R. Foster Cronin
Chief Compliance Officer and Senior Vice President

East Kentucky Power Cooperative, Inc. 4775 Lexington Road, P.O. Box 707

Winchester, KY 40392-0707
Tel.: 859-745-9615
Email: denise.cronin@ekpc.coop

On Behalf of East Kentucky Power
Cooperative, Inc.

/s/ Daniel E. Frank

Daniel E. Frank
Allison E. S. Salvia
Kelly A. Cuthbertson
Adriana J. Santana
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Tel.: 202-383-0100
Email: danielfrank@eversheds-sutherland.com allisonsalvia@eversheds-sutherland.com kellycuthbertson@eversheds-sutherland.com anasantana@eversheds-sutherland.com

Counsel for
East Kentucky Power Cooperative, Inc.

Dated: September 18, 2026

PDF page 19

Attachment 1
Reply Affidavit of Carl F. Coscia

PDF page 20

1

REPLY AFFIDAVIT OF CARL F. COSCIA, Ph.D.
On behalf of East Kentucky Power Cooperative, Inc.
PJM Interconnection, L.L.C., FERC Docket No. ER26-3380-000

I. PURPOSE, POSTURE, AND PRINCIPAL CONCLUSIONS
1. My name is Carl F. Coscia. I am the Principal of Toller Energy. I submitted an affidavit in this docket on August 21, 2026 (“Coscia Protest Affidavit”) in support of the protest of East Kentucky Power Cooperative, Inc. (“EKPC”).  My qualifications, the basis for my opinions, and the materials I reviewed are set out at paragraphs 1 through 5 of that affidavit and are not repeated here. The opinions expressed in this reply are my own. No part of my compensation is contingent on the outcome of this proceeding.

2. Since submitting that affidavit I have reviewed PJM’s answer filed September 10, 2026 (“PJM Answer”);1 its Reliability Backstop Procurement Execution presentation of

September 14, 2026 (“September 14 Presentation”);2 and PJM’s written responses to questions I submitted to PJM on August 12, August 14, August 31 and September 15, 2026. I have also reviewed PJM’s Credit & Securitization Overview of March 4, 2026 (“March

4 Credit Overview”);3 its Reliability Backstop Procurement Design presentations of April 16-17, 2026 (“April 17 Design Presentation”),4 May 27, 2026,5 and June 10-11, 2026 (“June Design Presentation”);6 its Stage 1 Proposal Status Update of May 5, 2026 (“May 5 Status Update”);7 its Stage 4 proposal materials of June 30, 2026;8 and the CIFP-RBP Options and Packages Matrix updated June 30, 2026 (“Package Matrix”).9 References to the “July 31 Filing” are to PJM’s initial filing in this proceeding, including the proposed

1 PJM Interconnection, L.L.C., “Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C.,” Docket No. ER26-3380-000 (filed Sept. 10, 2026).
2 September 14 Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260914/20260914-item-01---reliability-backstop-procurement-execution---presentation.pdf
3 March 4 Credit Overview available here: https://www.pjm.com/-/media/DotCom/committees- groups/workshops/rbpw/2026/20260304/20260304-item-03---credit-and-securitization-overview---pjm- presentation.pdf 4 April 17 Design Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260417/20260417-item-05---pjm-reliability-backstop-procurement-design---pjm-presentation.pdf 5 May 27 Design Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260527/20260527-item-05---reliability-backstop-procurement-design---pjm-presentation---updated.pdf
6 June Design Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260610/20260610-item-04a---pjm-reliability-backstop-procurement-design-presentation.pdf
7 May 5 Status Update Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260504/20260504-item-03---pjm-proposal-update.pdf 8 Stage 4 proposal materials available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260630/20260630-item-02a---pjm-reliability-backstop-procurement-proposal---paper.pdf
9 Package Matrix available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260630/20260630-cifp---reliability-backstop-procurement---options-and-packages-matrix---updated.xls

PDF page 21

2

Tariff revisions submitted as Attachment A.10 Materials on which I rely are cited where used.

3. This reply addresses the new explanations, interpretations, and implementation positions PJM offered after EKPC’s protest. I do not repeat the analysis in my original affidavit except where needed to test those new positions. Where PJM has not answered an opinion in my original affidavit, that opinion stands as submitted, and I do not restate it.

4. Posture. PJM now states that the buyer-side Load Serving Entity (“LSE”) Credit Rate need not be effective for the Reliability Backstop Procurement (“RBP”) to proceed, and consents to additional procedures on that rate. A material element of the buyer-side credit design therefore remains unresolved. If the Commission addresses that methodology through additional procedures, the schedule for those procedures should account for the fact that measurable RBP exposure develops well before the filed collateral posting date.

5. PJM’s proposed schedule separates the development of measurable RBP exposure from the date on which buyer-side collateral is required. The procurement results and the 2029/2030 Base Residual Auction will make the first two Delivery Years of contract-for- differences exposure measurable in December 2026. Buyer-side collateral would not be due until approximately April 2028. Deferring the posting date does not defer the need for a governing methodology.

6. I also note what such procedures would need to reach. PJM’s Answer does not respond to most of the analysis in my original affidavit, and where it does respond, it characterizes that affidavit as addressing the stakeholder process rather than the merits. PJM Answer at 74 n.220. The paragraphs cited for that proposition, paragraphs 182 through 184, appear in the section addressing the stakeholder record for the seller-side requirement and were not offered as merits opinions. The matters set out at paragraphs 52 and 53 below, and the opinions at 7(a) through 7(i) and Sections III and VI through XI of my original affidavit, remain unaddressed.

7. Principal opinion. The central issue is methodological. PJM has not identified the residual loss that the buyer-side collateral requirement is intended to secure. Until that loss, the parties that bear it, the quantity and timing of the exposure, and the standards for recalculating and releasing collateral are defined, neither $1.5 million per MW nor a substitute figure can be evaluated in relation to the exposure secured. PJM’s Answer and implementation materials provide additional explanation, but they do not establish that relationship.

8. PJM’s new positions leave five issues unresolved: the loss being secured, the support for a uniform Credit Rate, the development of the buyer-side methodology, the controlling megawatt quantity and posting date, and the coordination of RBP collateral with ordinary RPM credit treatment. My conclusions on each follow.

9. Default exposure. PJM states that “in no event would EKPC be allocated any cost responsibility,” and that EKPC would not receive a reallocation following another LSE’s default because section 18.9(a) reallocates only among LSEs already paying RBP Charges.

10 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (“July 31 Filing”).

PDF page 22

3

PJM Answer at 67, n.205. PJM separately states that its approach “balances the protection of Members against the effects of LSE default,” citing Operating Agreement section 15.2.2. PJM Answer at 84, n.252.

10. PJM addressed the same question during the stakeholder process and answered it. Its April 2026 design presentation states, under the heading “Default Allocation,” that “[i]f a default occurs as a result of a nonpayment of a RBP charge, that amount would be handled as a default allocation assessment under the existing OA Section 15.2.2,” and adds that “[t]his is consistent with the RPM market today.” April 17 Design Presentation at 47. If unpaid RBP obligations can reach PJM Members under section 15.2.2, the absence of a direct RBP allocation does not establish that EKPC has no RBP-related default exposure. If section 18.9(a) instead confines an RBP default to the LSEs assigned RBP Charges, PJM should clarify their interrelationship and identify the role section 15.2.2 plays in the exposure the collateral requirement is intended to secure. The residual loss and the population that bears it are predicates to sizing the requirement, and the record does not presently establish either.

11. The requirement and credit migration. PJM defends a uniform Credit Rate that does not vary with an obligor’s credit condition, relying in part on a credit migration table extrapolated from S&P Global’s ten-year corporate rating transition study. PJM Answer at 82, Table 2. That table reports ordinary-course rating migration across the general population of rated United States corporate issuers. PJM does not explain why a generalized migration matrix is appropriate to the particular population at issue, which is the LSEs in the PJM region. PJM does not reconcile the table with its own measurement of that population, presented to stakeholders on March 4, 2026, which identified 105 LSEs, of which 24 were investment grade and 81 sub-investment grade, reported that 46 percent held tangible net worth below $5 million and 30 percent below $1 million, and stated that those figures indicate limited financial flexibility. And PJM provides no analysis of whether the collateral requirement it proposes would itself constitute a liquidity stress event that degrades the credit quality of the population the requirement is intended to secure. A migration study of ordinary-course outcomes does not answer that question, because the obligation in question is not an ordinary-course event for the entities on which it falls.

12. Peak Market Activity and the development of the Credit Rate. PJM now states that Peak Market Activity is unsuitable because it measures short-term, backward-looking exposure rather than the long-term forward exposure created by the RBP. PJM identified that limitation to stakeholders on March 4, 2026, when it presented that its credit policy “is primarily built for short-term settlement cycle and one-year capacity obligations” and that the construct “introduces 15-year contractual durations, which current PJM credit rules were not designed to mitigate.” PJM nevertheless proposed managing buyer-side credit through existing credit processes, including Peak Market Activity recalculation, from April 2026 through its Stage 4 proposal of June 30, 2026. The $1.5 million per MW requirement first appears in the July 31 filing.

13. EKPC does not contend, and I do not opine, that Peak Market Activity is the appropriate credit mitigant for the RBP obligation. PJM has offered two explanations at different times. Through June 30 it proposed that buyer-side credit be managed through existing credit processes, including Peak Market Activity recalculation, which secures a rolling period of billed activity. On July 31 it filed a fixed $1.5 million per MW rate derived from approximately one-half of the gross fifteen-year payment stream. Neither explanation

PDF page 23

4

establishes the relationship between the collateral required and the residual loss the requirement is intended to secure.

14. Quantity. PJM states that “no collateral would be required for RBP Resources [that] are not in service for that Delivery Year.” PJM Answer at 78 n.234. Proposed section 18.8(b)(i)(A) defines the quantity to which the Credit Rate applies as “the amount of RBP UCAP MW that receives a commitment through the Reliability Backstop Procurement minus each commitment of RBP UCAP MW that is rescinded pursuant to Tariff, Attachment DD, section 18.6(e).” PJM’s implementation presentation of September 14, 2026 describes the same term at slide 9 as “the level of RBP UCAP MW for which an LSE is allocated cost responsibility submitted for the buyer by the EDC,” and states in the same slide that “Committed MW is equal to the generation that is coming online for that delivery year.” Those are not the same quantity. The in-service interpretation also does not resolve the separate relationship between committed megawatts and the Final RBP Target, to which section 18.8(b)(i)(B)(1) scales each LSE’s posting.

15. Timing. PJM states that no LSE collateral is required until forty-five days before the first Delivery Year in which an RBP Resource is in service. On PJM’s schedule the Reliability Backstop Procurement results and the 2029/2030 Base Residual Auction results will both be known in December 2026. At that point the contract-for-differences amount for the first two Delivery Years of a fifteen-year commitment is determined rather than forecast. On the collared caps for both Delivery Years, derived at paragraphs 52 and 53 below, the determined exposure for those two years is approximately $163,217 per MW, or approximately $979 million on an adjusted target of approximately 6,000 MW. No collateral is required against that amount until approximately April 17, 2028. PJM states that the collateral requirement exists to protect load from the consequences of an LSE default. During the interval in which the near-term exposure becomes known and remains outstanding, the filed provisions require no security against it.

16. Peak Market Activity, the contract-for-differences, and release. PJM proposes to remove RBP settlement from Peak Market Activity while treating the Reliability Pricing Model (“RPM”) component of the RBP payment as part of a separately collateralized long- term obligation. That separation raises a further question as the commitment runs off. If a Base Residual Auction clears near the RBP commitment price, the incremental contract- for-differences amount approaches zero and substantially the entire payment occurs through ordinary RPM settlement, which PJM secures through its existing credit processes. The RBP obligation would then be excluded from Peak Market Activity while continuing to carry a separate collateral requirement, although the economic difference between it and an ordinary capacity obligation had narrowed to the contract-for-differences amount. PJM states that the Credit Rate may decline as remaining exposure declines. The filed provisions do not establish when that occurs, by how much, or when collateral is released.

17. In my opinion, these matters go to the methodology of the credit requirement rather than to the selection of a replacement figure. If the Commission establishes additional procedures on the buyer-side Credit Rate, the elements identified in Section VIII below should be resolved before a rate is set.

PDF page 24

5

II. THE EXPOSURE THE REQUIREMENT SECURES HAS NOT BEEN
IDENTIFIED
18. A collateral requirement is sized to a loss. I addressed the RBP default provisions and the residual exposure under Operating Agreement section 15.2.2 at paragraphs 40, 152, 155 and 168 through 169 of my original affidavit. PJM did not respond to that analysis. I address here only PJM’s own characterization of the default consequence, which appears twice in the Answer and differs between the two.

19. Responding to the Kentucky Attorney General, PJM states that “in no event would EKPC be allocated any cost responsibility,” and that EKPC “would not be allocated any cost responsibility in the event of default by another LSE on paying RBP Charges, as PJM’s proposal would require such reallocation of cost responsibility among other LSEs already paying RBP Charges.” PJM Answer at 67 n.205.

20. Defending the magnitude of the requirement, PJM states that its approach “balances the protection of Members against the effects of LSE default,” citing Operating Agreement section 15.2.2. PJM Answer at 84 & n.252.

21. PJM therefore describes the consequence of an LSE default in two different ways without explaining how the two operate together. The first describes a defaulted RBP Charge as reallocated within the LSEs assigned RBP Charges. The second invokes the protection of Members, and Operating Agreement section 15.2.2, in support of the requirement. The two are not necessarily alternatives; they may describe successive levels of a default waterfall, and PJM should clarify their interrelationship. Operating Agreement section 15.2.2 allocates defaults, which could arise should any LSE from whom PJM seeks to collect RBP default payments be unable to pay, to the total number of Members with only a certain few exceptions. EKPC would be among those “total number of Members.” Section 18.9(a) states what happens to a defaulted RBP Charge in the first instance. It does not state what happens if the reallocated amounts are not collected, and it does not disclaim Operating Agreement section 15.2.2. The preamble to section 18.8 provides that “[n]othing in this Tariff, Attachment DD, section 18 supersedes the provisions of Tariff, Attachment Q.”

22. What remains after section 18.9(a) operates determines the amount. A requirement sized to protect the RBP-paying population from each other is a different calculation from one sized to protect the general membership from a residual loss. PJM has not stated which it reflects, and the derivation in the Kelly Affidavit, approximately one-half of gross contractual value, corresponds to neither.

23. It also determines who is protected. Collateral is posted only by LSEs allocated cost responsibility under section 18.3. If the exposure extends to Members generally, the entities posting and the entities protected are different populations. Section 18.9(a) compounds this by providing that a reallocated amount “may be offset by the RBP Collateral posted by the defaulting LSE.” Whether collateral is applied before or after mutualization determines the residual that reaches any further tier. See Coscia Protest Affidavit ¶ 155.

24. Opinion. Until PJM states what remains unpaid after section 18.9(a) operates, which parties bear that residual loss, and whether collateral is applied before reallocation and any mutualization under Operating Agreement section 15.2.2, the amount required cannot be derived from the exposure it is said to secure.

PDF page 25

6

III. PJM’S CREDIT MIGRATION ANALYSIS DOES NOT SUPPORT A UNIFORM
RATE
25. PJM defends a Credit Rate that does not vary with an obligor’s credit condition by reference to credit migration. It extrapolated S&P Global’s ten-year corporate rating transition study to a fifteen-year period and presents the result as Table 2 of its Answer. PJM Answer at 82. PJM reasons that under “an alternative, specific-LSE-driven credit approach … such declining creditworthiness would require PJM to request more and more collateral from such entities in order to compensate for the increasing default risk,” and that its methodology “is based on the committed obligation itself and avoids having the adequacy of the credit protection depend upon long-range predictions about individual LSE’s financials.” PJM Answer at 81, 83.

26. Table 2 reports ordinary-course rating migration across the general population of rated United States corporate issuers. It does not measure what happens to an obligor’s credit condition when the party imposing the requirement requires collateral comparable to or exceeding that obligor’s balance sheet. A requirement of that size can consume liquidity, encumber assets, absorb credit-facility capacity, or impose a recurring carrying cost. Those effects cannot simply be assumed to be independent of the future credit condition the migration analysis is used to address.

27. The illustration in my original affidavit gives the magnitude. On PJM’s figures, the NOVEC zone carries an initial allocation of 1,302.6 RBP UCAP MW and a collateral obligation of approximately $1.954 billion. Against the cooperative’s certified FY2025 report, that is approximately 114 percent of total assets of $1.716 billion, approximately twice total margins and equities of $920 million, and roughly eight times cash and temporary investments. The carrying cost at 100 basis points is approximately $19.5 million, or approximately 94 percent of the cooperative’s patronage capital and operating margins for the year. That cooperative is investment grade and is among the 24 LSEs PJM classified as investment grade on March 4, 2026, when it also reported that 81 of 105 LSEs were sub-investment grade, that 46 percent held tangible net worth below $5 million and 30 percent below $1 million, and that those figures indicate “limited financial flexibility.” March 4 Credit Overview at 7.

28. PJM applied a different approach to sellers. The seller requirement is twenty percent of the commitment price, the rate at which a non-performing seller is charged under section 18.6(d), applied over three years, discounted at 9.5 percent, and reduced as the commitment runs off “while taking into account the credit quality of the Market Participant.” April 17 Design Presentation at 43-45. The buyer requirement is approximately one-half of the gross fifteen-year contractual value, undiscounted, without the seller-side methodology’s express tenor-sensitive calculation or credit-quality adjustment.

29. On the same megawatt at the same $555.00/MW-day price, the seller posts $121,545 and the buyer posts $1,500,000. PJM cites the difficulty of predicting buyer credit quality over fifteen years as its reason for a uniform buyer rate. A requirement that discounts and declines with remaining tenor, as the seller requirement does, does not require that prediction.

30. Opinion. Table 2 establishes that credit quality varies over a fifteen-year horizon. That supports measuring and adjusting the requirement over that horizon. It does not support

PDF page 26

7

fixing a single, uniform amount at the outset, applied without regard to the obligor, in a magnitude large enough to affect the liquidity and financial condition of the obligors the requirement is intended to secure.

IV. THE FILED REQUIREMENT IS NOT THE BUYER-SIDE DESIGN PJM
PRESENTED TO STAKEHOLDERS
31. PJM’s Answer states that Peak Market Activity is not an adequate credit tool for RBP Charges, describing it as a backward-looking measure of short-term transactional exposure that does not prospectively collateralize the RPM component of the obligation.

32. PJM knew the RBP was long-dated from the outset and demonstrated an ability to model the resulting exposure. On March 4, 2026, it presented that its credit policy “is primarily built for short-term settlement cycle and one-year capacity obligations” and that the construct “introduces 15-year contractual durations, which current PJM credit rules were not designed to mitigate.” March 4 Credit Overview at 3. In the same presentation it modeled the procurement as a fixed-for-float swap and produced a potential future exposure (“PFE”) profile across the fifteen-year term. Id. at 12.

33. PJM nevertheless proposed to secure the buyer-side obligation through existing credit processes. In April it stated that “[c]redit and collateral requirements for EDCs are expected to be managed by the current credit processes, which include but are not limited to credit evaluation, PMA and use of other mitigation tools, such as posting of credit support and/or UCRs.” April 17 Design Presentation at 46. In June it stated the same for LSEs: “Upon notification by the Load Serving Entity (LSE) of the known changes to its load, credit, and collateral requirements for LSEs are expected to be managed by the current credit processes. These processes include, but are not limited to, credit evaluation, PMA recalculation and use of other mitigation tools, such as posting of credit support and/or UCRs.” June Design Presentation at 35. PJM carried that position into its Stage 4 proposal of June 30, 2026 and its entry at design component 22. June 30 Options and Packages Matrix. Over the same period, PJM recorded stakeholder feedback on the size of the requirement. Its status update of May 5, 2026 summarizes the Stage 1 meeting feedback under the heading “Credit” as “[c]ollateral requirements may be too high – are they competitive?”, and under the heading “Role of EDC” as “EDCs don’t want to wear the risk

– this may result in targets of 0.” May 5 Status Update at 2. PJM applied to sellers the term- sensitive methodology described at paragraph 28 above.

34. An alternative buyer-side design was also before PJM. At the same design component of the Package Matrix, the package proposed by the Joint Electric Distribution Companies and the Data Center Coalition provided that “[p]rior to the procurement, the LSE-Large Load registry will indicate the LSEs who must hold collateral and for what amount of MW,” that “[i]f an LSE-Large Load cannot post collateral, the load is not procured for through the backstop,” and that the collateral held “must ensure that any emerging buyer default exposure is recognized early, funded continuously, and contained entirely within the buyer over time.” That package was the only one of the thirteen voted at the close of Stage 4 to receive greater than two-thirds sector-weighted member support. It identified the obligated entity and its megawatt quantity before the procurement, conditioned the procurement on the ability to post, and measured exposure as it emerged.

PDF page 27

8

35. The July 31 filing established a separate RBP Credit Requirement at a Credit Rate of $1.5 million per MW, a figure that appears in none of the stakeholder materials I have reviewed. PJM states that the Board “adopted various concepts from the Coalition RBP Proposal that received a sector-weighted majority of stakeholder support,” and identifies the “credit requirement for Load Serving Entities” as among those with “roots in the Coalition RBP Proposal.” July 31 Filing at 22. The filed construct incorporates the assignment of the obligation to LSEs. It does not incorporate the registry, the identification of the obligated entity before the procurement, the requirement to post before the obligation attaches, or the continuous funding of exposure as it emerges.

36. Opinion. PJM is not obliged to adopt a stakeholder proposal, and it may reasonably have concluded that Peak Market Activity alone was insufficient for a fifteen-year obligation. What the Answer supplies is an explanation of why PJM now considers Peak Market Activity inadequate. What it does not supply is the analytical bridge from the approaches PJM had before it, its own March exposure modeling, the existing credit processes it proposed through June 30, and the Coalition’s exposure-based design, to a rate initially approximating one-half of the gross fifteen-year payment stream.

V. THE QUANTITY ON WHICH COLLATERAL IS REQUIRED IS NOT DEFINED
37. An LSE cannot calculate its posting unless the tariff identifies the controlling megawatt quantity. Proposed Tariff, Attachment DD, section 18.8(b)(i)(A) requires collateral equal to the RBP Credit Rate multiplied by “RBP UCAP MW committed.” The amount of the requirement therefore depends entirely on that quantity. PJM’s Answer and its implementation materials leave three questions about it unresolved: whether the megawatts must be in service; whether an individual LSE’s posting follows the megawatts its Electric Distributor assigns or is scaled to the Final RBP Target; and what quantity applies, if any, where the Electric Distributor reports nothing.

A. Whether the megawatts must be in service
38. PJM’s Answer states that “no collateral would be required for RBP Resources [that] are not in service for that Delivery Year.” PJM Answer at 78 n.234.

39. That in-service limitation does not appear in section 18.8(b)(i)(A). That provision defines the quantity as “the amount of RBP UCAP MW that receives a commitment through the Reliability Backstop Procurement minus each commitment of RBP UCAP MW that is rescinded pursuant to Tariff, Attachment DD, section 18.6(e).” Commitments received, less rescissions. There is no in-service condition, and PJM has proposed no revision to that provision.

40. Rescission under section 18.6(e) occurs only “where RBP UCAP MW fail to come online for three Delivery Years beginning with the first Delivery Year in which the RBP Resource was committed.” A resource that has not achieved commercial operation therefore remains within the quantity for up to three Delivery Years. PJM’s transmittal describes the same mechanic and identifies rescission as the operative event: the input “will change as committed resources fail to follow through on their commitment and do not achieve commercial operation,” and it is the rescinded commitment that “is subtracted from the input used to determine the uniform RBP credit requirement.” July 31 Filing at 116.

PDF page 28

9

41. The September 14 Presentation states the Answer’s position on one slide and applies the tariff definition on another. Slide 9 defines the quantity as “the level of RBP UCAP MW for which an LSE is allocated cost responsibility submitted for the buyer by the EDC,” and adds in a note that “Committed MW is equal to the generation that is coming online for that delivery year.”

42. Example #4 at slide 57 of the September 14 Presentation does the opposite. It addresses a unit that “does not come online for Delivery Year.” The example carries Committed MW (UCAP) of 50 throughout, assesses the RBP Shortfall Charge on all 50 committed megawatts under section 18.6(d), and computes RBP Credits on Daily Owned MW of zero. The commitment remains at 50 megawatts and settlement occurs on that quantity even though the resource is not in service. That is the filed definition, applied.

43. The two formulas use different quantities. RBP Credits, and therefore the RBP Charges assessed to load, are computed on Daily Owned MW, which is why the charge is zero in Example #4. The collateral requirement in section 18.8(b)(i)(A) is computed on RBP UCAP MW committed, which in the same example remains 50. The absence of a charge in a Delivery Year is a result of the credit formula. It does not change the quantity to which the Credit Rate applies.

B. Whether the posting follows assigned megawatts or the Final RBP Target
44. Section 18.8(b)(i)(A) sets the cumulative RBP credit requirement for all LSEs as the Credit Rate multiplied by committed megawatts. Section 18.8(b)(i)(B)(1) sets each individual LSE’s posting as $1.5 million multiplied by the RBP Obligation MW its Electric Distributor submits, “scaled, as necessary, in the event that the RBP Obligation MW values uploaded by the Electric Distributor do not sum to the fixed, Final RBP Target MW for the zone/area.”

45. Those provisions use different quantities, and PJM states the procurement may clear short of the Final RBP Target. Where it does, committed megawatts are fewer than the Target. The individual postings scaled to the Target under (B)(1) would then sum to more than the cumulative requirement calculated on committed megawatts under (A). Because the Credit Rate is $1.5 million per megawatt, each 100 megawatts of difference between the two quantities changes the aggregate amount posted by $150 million.

46. PJM has identified each quantity as governing. Footnote 234 states that the amount “would be based on the RBP UCAP MW committed for that Delivery Year.” PJM’s written response of August 14, 2026 stated that the Final RBP Target governs.

C. What applies where the Electric Distributor reports nothing
47. Section 18.8(b)(i)(B)(2) provides that where no RBP Obligations are reported for an Electric Distributor zone or area, LSEs serving load there “may be required to post” collateral calculated on “the [LSE’s] pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined in RAA, Schedule 8.” The September 14 Presentation states that measure at slide 70, while a footnote to the example at slide 69 describes the same fallback as a Peak Load Contribution allocation.

48. The provision is permissive, and PJM confirmed in writing on September 15, 2026 that it admits more than one outcome. An LSE may be required to post at the Credit Rate, may post at the Credit Rate and additionally be assessed under the Unreasonable Credit Risk

PDF page 29

10

provisions of Attachment Q, Section II, or may not be required to post at the Credit Rate but be subject to an unreasonable credit risk assessment. The provision states that an LSE “may be required to post.” It does not state that a Credit Rate posting is required in every case in which no RBP Obligations are reported.

49. The quantity also changes basis. Under (B)(1) an LSE posts on megawatts attributed to it through the allocation process. Under (B)(2) it posts on its share of total load. An entity with no RBP Obligation under section 18.3 has no requirement under (B)(1) and a requirement measured by its entire load under (B)(2).

50. Subsection (B)(2) is also difficult to square with PJM’s defense of the uniform rate. PJM states that its methodology “is based on the committed obligation itself and avoids having the adequacy of the credit protection depend upon long-range predictions about individual LSE’s financials.” PJM Answer at 82. The Unreasonable Credit Risk provisions of Attachment Q, Section II are an individualized assessment of a participant’s financial condition. Section 18.8(b)(i)(B)(2) routes directly into them, and PJM has confirmed that an assessment may be made in place of, or in addition to, a Credit Rate posting. PJM has therefore built individualized credit evaluation into the construct. It applies where an Electric Distributor fails to report, and not where the Electric Distributor reports.

D. Timing
51. Section 18.3(b)(iii) requires the initial allocation to be reported no later than sixty days before the Delivery Year, and collateral is due prior to forty-five days before. An LSE would have approximately fifteen days between learning which subsection applies to it, and on what quantity, and funding the requirement.

52. The timing differs from the forward-exposure rationale. PJM relies on the long-dated character of the obligation to distinguish it from Peak Market Activity, while requiring no security until shortly before the first applicable Delivery Year. The near-term exposure is determined well before then.

53. Both of the first two Delivery Years are subject to the price collar PJM extended through 2029/2030. The collar is expressed in installed capacity terms and converted to unforced capacity by the Effective Load Carrying Capability rating of the reference resource. The 2028/2029 Base Residual Auction cleared at the collared cap of $325.00/MW-day UCAP at a Gas CT Dual Fuel rating of 79 percent, and the 2027/2028 auction cleared at its collared cap of $333.44/MW-day at a rating of 77 percent. Both imply the same basis of $256.75/MW-day ICAP. PJM endorsed a Gas CT Dual Fuel rating of 76 percent for 2029/2030 on August 19, 2026, which places the collared cap for that Delivery Year at $337.83/MW-day UCAP and the floor at $181.91/MW-day UCAP.

54. At the $555.00/MW-day maximum willingness to pay, the differential is therefore $230.00/MW-day for 2028/2029 and $217.17/MW-day for 2029/2030, or $83,950 and $79,267 per MW respectively. The two-year total is $163,217 per MW, which on an adjusted target of approximately 6,000 MW is approximately $979 million, and approximately $1.115 billion on the full Initial RBP Target of 6,831.3 MW. These figures replace the $333.44 proxy I used at paragraph 92 of my original affidavit, the 2029/2030 parameters not having been endorsed when that affidavit was prepared. The amount is

PDF page 30

11

determined once the 2029/2030 auction clears in December 2026, and no collateral is required against it until approximately April 17, 2028.

55. Opinion. An LSE cannot determine from the filed rate the quantity on which it must post. The tariff, the Answer, and the implementation presentation give different answers to whether the megawatts must be in service, and PJM’s own settlement example applies the tariff definition rather than the Answer’s. PJM has identified both committed megawatts and the Final RBP Target as governing an individual posting. And where an Electric Distributor reports nothing, whether an entity posts at all, on what quantity, and whether it is additionally assessed for unreasonable credit risk are matters the filed provisions leave to discretion. If PJM intends collateral to follow in-service megawatts, or the Final RBP Target, those are changes to section 18.8(b)(i) and should be made in the tariff.

VI. THE EXPOSURE THE REQUIREMENT SECURES IS LARGELY ORDINARY
RPM ACTIVITY
A. Coordination with Attachment Q
56. PJM proposes to delete the sentence providing that settlement of cleared RBP positions “may be included, as appropriate, in Peak Market Activity,” on the basis that it could cause confusion that RBP Charges may be captured in that calculation.

57. Removal of the clause does not establish how an invoiced RBP billing line item is excluded from the Peak Market Activity calculation in Attachment Q, section VII.A, and PJM has proposed no conforming revision to Attachment Q. Three provisions are unaffected by the deletion and bear on the coordination question. Nothing in section 18 supersedes Attachment Q. The RBP requirements are separate from and additional to credit requirements arising under Attachment Q. And under sections 18.8(b)(i)(B)(1) and (B)(2), PJM may evaluate an LSE for unreasonable credit risk under Attachment Q, Section II and require additional RBP Collateral, which as set out at paragraph 47 above may be done in addition to, or in place of, a Credit Rate posting.

58. PJM explains the separate requirement as securing the forward RPM component of the obligation together with the contract-for-differences amount, on the ground that Peak Market Activity does not prospectively collateralize the RPM component over the term. The RBP settles economically through RPM and a contract-for-differences: load pays the RPM clearing price through ordinary capacity billing and pays or receives the difference through the new billing line item.

59. To examine how that explanation operates, I apply it to a period in which three Delivery Years remain, at an RBP commitment price of $555.00/MW-day on 6,000 MW. I take a Base Residual Auction clearing price of $554.00/MW-day, at which the contract-for- differences is nearly extinguished. The result is set out in Table 1.

PDF page 31

12

Table 1. Illustrative RBP exposure and collateral, three Delivery Years remaining Measure

Amount
Contract-for-differences rate
$1.00/MW-day
Annual contract-for-differences amount
$2.19 million
Remaining contract-for-differences obligation $6.57 million
Four weeks of RPM payments
$93.1 million
Remaining gross payment stream at $555.00
$3.646 billion
Collateral at $1.5 million per MW
$9.0 billion

60. The discontinuity is in the treatment of the RPM component. At an RPM clearing price of $554.00, an LSE carrying an ordinary capacity obligation of that size would be subject to PJM’s ordinary Attachment Q credit processes. The same entity carrying the same RPM obligation, plus a contract-for-differences of $1.00/MW-day, has that RPM stream treated as part of a multi-year forward obligation supporting a separate collateral requirement. An incremental obligation of $2.19 million a year changes the credit treatment of approximately $1.2 billion a year of ordinary RPM payments.

61. Opinion. PJM has not explained why the existence of an RBP commitment changes the credit treatment of the forward RPM payment stream, or how that separate treatment should converge with ordinary RPM credit treatment as the contract-for-differences amount and the remaining term decline.

VII. PJM’S ILLUSTRATION OF THE REDUCTION PROVISION
62. I addressed the absence of a defined reduction and release standard at opinion 7(f) and paragraphs 47 and 155 of my original affidavit, including the comparison with Attachment Q, Section V.A and Section VI.B.3 and with the seller-side release in section 18.8(a). I do not repeat that analysis. PJM has since explained how the provision is intended to operate, and I address that explanation.

63. PJM states in its Answer that the Credit Rate can decline where previously required collateral exceeds the remaining expected payment exposure, and acknowledges that use of the actual weighted-average RBP price may be appropriate. PJM Answer at 80 & n.240.

64. The September 14 Presentation illustrates the result. Slide 69 sets out a roll-off schedule for a 100 MW RBP Obligation at the $1.5 million Credit Rate, assuming a $555.00/MW- day commitment price, an annual payment obligation of $20,257,500, and no change to committed megawatts over the fifteen-year term. Collateral of $150,000,000 is held without change for the first eight Delivery Years. The first reduction occurs in 2036/2037, the ninth Delivery Year, and PJM explains it in a note: “Credit requirement/collateral is reduced due to payment obligation is smaller than collateral held.” The requirement then tracks the remaining gross payment obligation to $20,257,500 in the final year.

65. The requirement does not decline for more than half the term. Over the first eight Delivery Years the remaining gross payment obligation falls from $303,862,500 to $162,060,000, a reduction of approximately forty-seven percent, while the collateral held remains at

PDF page 32

13

$150,000,000. PJM has separately modeled exposure on this construct. In the March 4 Credit Overview at 12 it modeled the procurement as a fixed-for-float swap and produced a potential future exposure profile that begins at zero, rises through the early Delivery Years, reaches a maximum within roughly the first third of the term, and declines to zero at expiry, stating that “[t]he value uncertainty goes higher deeper into the future, while quantity exposure decreases as time goes by. This makes PFE peaks at 1/3 of life.” Potential future exposure and remaining gross payments are different measures, and I do not suggest the schedule should replicate the March profile. What PJM has not explained is why the buyer-side requirement follows remaining gross payments rather than a profile sensitive to the exposure it is said to secure, when PJM has modeled that exposure itself.

66. The reduction, when it occurs, tracks the remaining gross payment obligation rather than the exposure. The schedule is built from the $555.00/MW-day commitment price applied to full committed megawatts; the annual figure of $20,257,500 is that price multiplied by 365 days and 100 MW. It contains no RPM clearing price and therefore no contract-for- differences input.

67. The schedule is an illustration rather than a rule. It appears in a presentation, it assumes committed megawatts do not change over the term, and nothing in section 18.8(b)(i)(A) requires PJM to follow it or establishes its frequency or inputs.

68. Opinion. PJM’s illustration shows collateral held flat for eight of fifteen Delivery Years and reducing thereafter on the remaining gross payment obligation, on an assumption the tariff does not require, under a provision that is permissive throughout. The illustrated requirement therefore does not respond to the contract-for-differences amount or observed RPM clearing prices, and it does not decline with remaining tenor during the first eight Delivery Years.

VIII. RECOMMENDATIONS FOR ADDITIONAL PROCEEDINGS
69. PJM has consented to the Commission resolving the buyer-side Credit Rate through additional procedures, and states that the buyer-side rules need not be effective for the Reliability Backstop Procurement to be conducted. The matters set out below should be resolved on a schedule that reflects when the underlying exposure becomes measurable, which, as set out in paragraph 5, is well before the filed posting date.

70. In my opinion, any additional procedures should define the exposure the requirement is intended to secure and the quantity and timing of that exposure before a replacement Credit Rate is selected. That includes the relationship among the RPM component of the payment, the contract-for-differences amount created by the RBP, the reallocation provided by section 18.9(a), and any residual exposure under Operating Agreement section 15.2.2. It also requires a defined meaning of “RBP UCAP MW committed” and its relationship to megawatts in service, megawatts allocated to an LSE, RBP Obligation MW reported by an Electric Distributor, and the Final RBP Target. The procedures should also establish when the resulting exposure arises and when collateral is required in relation to it.

71. The methodology should then provide objective standards for recalculating and releasing collateral as the relevant conditions change, including the RBP commitment price, observed RPM clearing prices and resulting contract-for-differences amounts, remaining tenor, committed quantity, and participant credit condition. It should also establish the

PDF page 33

14

order in which collateral, the reallocation under section 18.9(a), and any mutualization under Operating Agreement section 15.2.2 apply, so that the residual loss the collateral is intended to secure can be identified.

72. PJM’s Answer and implementation materials supply explanations that were not available when I submitted my original affidavit. They do not establish the relationship between the collateral required and the exposure secured.

73. The question presented by the buyer-side credit requirement is therefore not whether $1.5 million per MW is too high or too low. It is whether the amount, the quantity, the timing, the recalculation, the release, and the default treatment of collateral bear a defined relationship to the exposure the requirement is intended to secure. On the present record they do not.

74. This concludes my reply affidavit.

PDF page 34

VERIFICATION OF AFFIDAVIT
Pursuant to 18 C.F.R. § 385.2005(b)(3), I verify under penalty of perjury that the foregoing Affidavit is true and correct.

Executed September 18, 2026.
By: _____________________________
       Carl F. Coscia

PDF page 35

Certificate of Service
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, DC this 18th day of September, 2026.

/s/ Allison E. S. Salvia
Allison E. S. Salvia