ER26-3380-000 · 2026-09-18 · East Kentucky Power Cooperative, Inc.

Motion For Leave to File Second Limited Answer and Second Limited Answer of East Kentucky Power Cooperative, Inc

Text extracted from the eLibrary original (SHA-256 273b34f2e918b91b…). Download the original from the official source.

Contents · 24 sections
  1. I. MOTION FOR LEAVE TO FILE LIMITED ANSWER p. 2
  2. II. BACKGROUND AND SUMMARY p. 3
  3. III. LIMITED ANSWER p. 5
  4. A. PJM Has Not Carried Its Affirmative Burden Under FPA Section 205. p. 5
  5. B. PJM Failed to Address EKPC’s Cost Causation Arguments. p. 6
  6. C. EKPC’s Protest Is Consistent with the Ratepayer Protection Pledge. p. 9
  7. D. PJM Does Not Justify Disparate Treatment of FRR Entities and RPM Self p. 11
  8. E. PJM’s Proposed Credit-Rate Severance Does Not Cure the RBP’s Credit p. 12
  9. F. The Commission Should Reject the Proposed Default Allocation. p. 16
  10. G. PJM’s Portfolio-Benefit Theory Underscores the Mismatch. p. 16
  11. IV. CONCLUSION p. 17
  12. I. PURPOSE, POSTURE, AND PRINCIPAL CONCLUSIONS p. 20
  13. II. THE EXPOSURE THE REQUIREMENT SECURES HAS NOT BEEN p. 24
  14. III. PJM’S CREDIT MIGRATION ANALYSIS DOES NOT SUPPORT A UNIFORM p. 25
  15. IV. THE FILED REQUIREMENT IS NOT THE BUYER-SIDE DESIGN PJM p. 26
  16. V. THE QUANTITY ON WHICH COLLATERAL IS REQUIRED IS NOT DEFINED p. 27
  17. A. Whether the megawatts must be in service p. 27
  18. B. Whether the posting follows assigned megawatts or the Final RBP Target p. 28
  19. C. What applies where the Electric Distributor reports nothing p. 28
  20. D. Timing p. 29
  21. VI. THE EXPOSURE THE REQUIREMENT SECURES IS LARGELY ORDINARY p. 30
  22. A. Coordination with Attachment Q p. 30
  23. VII. PJM’S ILLUSTRATION OF THE REDUCTION PROVISION p. 31
  24. VIII. RECOMMENDATIONS FOR ADDITIONAL PROCEEDINGS p. 32

Read topic-matched comments in ER26-3380

Topics in the text: Credit and exit · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

For the reasons set forth herein and in the EKPC Protest, EKPC respectfully requests that the Commission reject the RBP Proposal.
Read this passage Filed comments: Cost allocation

I. MOTION FOR LEAVE TO FILE LIMITED ANSWER

printed heading · Topic match: Credit and exit

PJM also supplies new explanations and proposed concessions concerning severance of the buyer-side LSE credit rate, the timing and calculation of collateral, Peak Market Activity, and default allocation.9 This Limited Answer responds only to those matters and to PJM’s post-filing implementation…
Read this passage Filed comments: Credit and exit

II. BACKGROUND AND SUMMARY

printed heading · Topic match: Credit and exit

PJM therefore must establish, by record evidence and 9 See PJM Answer at 74–93, pts.
Read this passage Filed comments: Credit and exit

III. LIMITED ANSWER

printed heading

III.
Read this passage

A. PJM Has Not Carried Its Affirmative Burden Under FPA Section 205.

printed heading

PJM must connect the evidence to the specific rate design for which it seeks approval.
Read this passage

B. PJM Failed to Address EKPC’s Cost Causation Arguments.

printed heading · Topic match: Cost allocation

A rate must reflect, at least to some degree, the costs caused by the customers required to pay it, and an allocation based on benefits must be at least roughly commensurate with the benefits received.20 PJM’s own Answer invokes the same principle: costs should be recovered from customers that use…
Read this passage Filed comments: Cost allocation

C. EKPC’s Protest Is Consistent with the Ratepayer Protection Pledge.

printed heading · Topic match: Cost allocation

Although PJM describes the RBP as a one-time process,35 the proposed Tariff and RAA language does not itself supply a clear one-time limitation, and PJM has publicly contemplated RBP or similar mechanisms in future reliability frameworks.36 The Commission must evaluate the filed provisions as…
Read this passage Filed comments: Cost allocation

D. PJM Does Not Justify Disparate Treatment of FRR Entities and RPM Self

printed heading

Cir. 2002). 43 See RAA, Schedule 8.1, Section D (7) (“For Delivery Years between the 2025/2026 Delivery Year through the 2028/2029 Delivery Year, no FRR Commitment Insufficiency Charge shall be assessed.”). 12 treatment is just and reasonable.44 The Commission should require PJM to recognize…
Read this passage

E. PJM’s Proposed Credit-Rate Severance Does Not Cure the RBP’s Credit

printed heading · Topic match: Credit and exit

As detailed in the EKPC Protest, PJM’s proposed collateral requirements are unjust and unreasonable and should be rejected.45 If the Commission nevertheless accepts PJM’s proposal to sever the buyer-side LSE credit rate for further procedures, the numerical rate is only one component of the…
Read this passage Filed comments: Credit and exit

F. The Commission Should Reject the Proposed Default Allocation.

printed heading · Topic match: Credit and exit

At minimum, the Commission must require Tariff language confining RBP nonpayment to entities assigned RBP Charges and reasoning documented in the record as to why any reallocation among them remains just and reasonable.
Read this passage Filed comments: Credit and exit

G. PJM’s Portfolio-Benefit Theory Underscores the Mismatch.

printed heading · Topic match: Credit and exit

In its Protest, EKPC explained that without a rule requiring offsets and existing-supply recognition to follow the responsible LSE or load, the RBP unfairly socializes 64 PJM Answer at 73. 17 the benefit of prudent resource planning while leaving those LSEs that adequately covered their load…
Read this passage Filed comments: Credit and exit

IV. CONCLUSION

printed heading · Topic match: Credit and exit

CONCLUSION For the foregoing reasons, EKPC respectfully requests that the Commission accept this limited answer and reject PJM’s RBP Proposal.
Read this passage Filed comments: Credit and exit

I. PURPOSE, POSTURE, AND PRINCIPAL CONCLUSIONS

printed heading · Topic match: Credit and exit

And PJM provides no analysis of whether the collateral requirement it proposes would itself constitute a liquidity stress event that degrades the credit quality of the population the requirement is intended to secure.
Read this passage Filed comments: Credit and exit

II. THE EXPOSURE THE REQUIREMENT SECURES HAS NOT BEEN

printed heading · Topic match: Cost allocation

Responding to the Kentucky Attorney General, PJM states that “in no event would EKPC be allocated any cost responsibility,” and that EKPC “would not be allocated any cost responsibility in the event of default by another LSE on paying RBP Charges, as PJM’s proposal would require such reallocation…
Read this passage Filed comments: Cost allocation

III. PJM’S CREDIT MIGRATION ANALYSIS DOES NOT SUPPORT A UNIFORM

printed heading · Topic match: Credit and exit

PJM reasons that under “an alternative, specific-LSE-driven credit approach … such declining creditworthiness would require PJM to request more and more collateral from such entities in order to compensate for the increasing default risk,” and that its methodology “is based on the committed…
Read this passage Filed comments: Credit and exit

IV. THE FILED REQUIREMENT IS NOT THE BUYER-SIDE DESIGN PJM

printed heading · Topic match: Credit and exit

At the same design component of the Package Matrix, the package proposed by the Joint Electric Distribution Companies and the Data Center Coalition provided that “[p]rior to the procurement, the LSE-Large Load registry will indicate the LSEs who must hold collateral and for what amount of MW,” that…
Read this passage Filed comments: Credit and exit

V. THE QUANTITY ON WHICH COLLATERAL IS REQUIRED IS NOT DEFINED

printed heading · Topic match: Credit and exit

PJM’s Answer and its implementation materials leave three questions about it unresolved: whether the megawatts must be in service; whether an individual LSE’s posting follows the megawatts its Electric Distributor assigns or is scaled to the Final RBP Target; and what quantity applies, if any,…
Read this passage Filed comments: Credit and exit

A. Whether the megawatts must be in service

printed heading · Topic match: Credit and exit

PJM’s Answer states that “no collateral would be required for RBP Resources [that] are not in service for that Delivery Year.” PJM Answer at 78 n.234. 39.
Read this passage Filed comments: Credit and exit

B. Whether the posting follows assigned megawatts or the Final RBP Target

printed heading · Topic match: Credit and exit

Section 18.8(b)(i)(A) sets the cumulative RBP credit requirement for all LSEs as the Credit Rate multiplied by committed megawatts.
Read this passage Filed comments: Credit and exit

C. What applies where the Electric Distributor reports nothing

printed heading · Topic match: Credit and exit

Section 18.8(b)(i)(B)(2) provides that where no RBP Obligations are reported for an Electric Distributor zone or area, LSEs serving load there “may be required to post” collateral calculated on “the [LSE’s] pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined in…
Read this passage Filed comments: Credit and exit

D. Timing

printed heading · Topic match: Credit and exit

An LSE cannot determine from the filed rate the quantity on which it must post.
Read this passage Filed comments: Credit and exit

VI. THE EXPOSURE THE REQUIREMENT SECURES IS LARGELY ORDINARY

printed heading

THE EXPOSURE THE REQUIREMENT SECURES IS LARGELY ORDINARY RPM ACTIVITY
Read this passage

A. Coordination with Attachment Q

printed heading · Topic match: Credit and exit

PJM proposes to delete the sentence providing that settlement of cleared RBP positions “may be included, as appropriate, in Peak Market Activity,” on the basis that it could cause confusion that RBP Charges may be captured in that calculation. 57.
Read this passage Filed comments: Credit and exit

VII. PJM’S ILLUSTRATION OF THE REDUCTION PROVISION

printed heading · Topic match: Credit and exit

The first reduction occurs in 2036/2037, the ninth Delivery Year, and PJM explains it in a note: “Credit requirement/collateral is reduced due to payment obligation is smaller than collateral held.” The requirement then tracks the remaining gross payment obligation to $20,257,500 in the final year.…
Read this passage Filed comments: Credit and exit

VIII. RECOMMENDATIONS FOR ADDITIONAL PROCEEDINGS

printed heading · Topic match: Credit and exit

It should also establish the 14 order in which collateral, the reallocation under section 18.9(a), and any mutualization under Operating Agreement section 15.2.2 apply, so that the residual loss the collateral is intended to secure can be identified. 72.
Read this passage Filed comments: Credit and exit

Certificate of Service

printed heading

Dated at Washington, DC this 18th day of September, 2026. /s/ Allison E.
Read this passage