ER26-3515-000 · 2026-09-18 · New Jersey Board of Public Utilities
Motion for Leave to Answer and Answer of the New Jersey Board of Public Utilities to the protests and comments of Buckeye Power, Inc., et al
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, LLC
)
Docket No. ER26-3515-000
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
THE NEW JERSEY BOARD OF PUBLIC UTILITIES
On August 13, 2026, PJM Interconnection, L.L.C. (“PJM”) proposed revisions to the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) and the PJM Open Access Transmission Tariff (“Tariff”) to establish Interim Resource Adequacy Service (“IRAS”).1 On September 3, 2026, the New Jersey Board of Public Utilities (“Board”) submitted its Supportive Comments and Limited Protest of PJM’s Proposal.2
Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s
(“Commission” or “FERC”) Rules of Practice and Procedure,3 the Board respectfully moves for leave to answer and submits this Answer to the protests and comments of Buckeye Power, Inc. (“Buckeye Power”),4 Southern Maryland Electric Cooperative, Inc. (“SMECO”),5 East Kentucky
1 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515 (Aug. 13, 2026) (“PJM IRAS Proposal” or “Proposal”).2 PJM Interconnection, L.L.C., Supportive Comments and Limited Protest of the New Jersey Board of Public Utilities, Docket No. ER26-3515 (Sept. 3, 2026) (“NJ BPU Comments”).3 18 C.F.R. §§ 385.212, 385.213 (2020).4 PJM Interconnection, L.L.C., Limited Comments of Buckeye Power, Inc., Docket No. ER26-3515 (Sept. 3, 2026) (“Buckeye Power Comments”).5 PJM Interconnection, L.L.C., Comments and Limited Protest of Southern Maryland Electric Cooperative, Inc., Docket No. ER26-3515 (Sept. 3, 2026) (“SMECO Comments”).
PDF page 2
2
Power Cooperative, Inc. (EKPC”),6 Voltus,7 Equinix Inc. (“Equinix”),8 Tesla, Inc. (“Tesla”),9 the Chief Energy Officer for the Governor of Virginia,10 and Corporate Energy Buyers Association (“CEBA”).11 The Board submits this Answer to provide additional information and context that will assist the Commission in its decision-making process.
I. MOTION FOR LEAVE TO ANSWER
While Rule 213(a)(2) generally prohibits answers to protests and comments, good cause justifies the Commission’s granting this motion and accepting this answer because it provides useful and relevant information that will assist the Commission in its decision-making process.
II. ANSWER
i. IRAS Should Not Exceed Amount of New Large Load Demand in Real Time
Protests and comments submitted by Buckeye Power, SMECO, and EKPC raise issue with a specific component in PJM’s IRAS Proposal. In its Proposal, PJM proposes to issue load reductions to electric distribution companies (“EDCs”) in an amount “up to, and capped at, the pre-Delivery Year IRAS obligations they were assigned” when conducting an IRAS Action.126 PJM Interconnection, L.L.C., Limited Protest of East Kentucky Power Cooperative, Inc., Docket No. ER26-3515 (Sept. 3, 2026) (“EKPC Protest”).7 PJM Interconnection, L.L.C., Comments of Voltus, Docket No. ER26-3515 (Sept. 3, 2026) (“Voltus Comments”).8 PJM Interconnection, L.L.C., Protest, Request for Clarification and Comments of Equinix Inc. on the Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Adress System Reliability, Docket No. ER26-3515 (Sept. 3, 2026) (“Equinix Comments”).9 PJM Interconnection, L.L.C., Comments of Tesla, Inc., Docket No. ER26-3515 (Sept. 3, 2026) (“Tesla Comments”).10 PJM Interconnection, L.L.C., Comments of the Chief Energy Officer for the Governor of Virginia, Docket No. ER26-3515 (Sept. 3, 2026) (“Chief Energy Officer for the Governor of Virginia Comments”).11 PJM Interconnection, L.L.C., Motion to Intervene and Protest of Corporate Energy Buyers Association (“CEBA”), Docket No. ER26-3515 (Sept. 3, 2026) (“CEBA Protest”).12 PJM IRAS Proposal Attachment C, Affidavit of Christopher Pilong on Behalf of PJM Interconnection, L.L.C. at 42.
PDF page 3
3
These obligations are pre-determined and correspond to the peak load reported by the New Large Load in PJM’s proposed Large Load Registry. However, Buckeye Power, SMECO, and EKPC identify an important concern, which is that this pre-determined amount may not match the actual New Large Load demand being used in real-time.13 SMECO’s Comments highlight that this is not merely a hypothetical scenario, as IRAS amounts are set at a pre-Delivery Year MW quantity, yet an EDC’s assigned New Large Loads may not be yet energized, or may have only just begun a ramp or testing period that is below its expected draw when PJM issues an IRAS Action.14 If this is the case and PJM directs an amount of IRAS that corresponds to the peak load reported by the New Large Load, and this obligation is higher than the real-time demand of large loads in that zone, it is unclear whether EDCs will be required to reduce other customers in addition to New Large Load customers in order to meet the required IRAS MW amount. Buckeye Power, SMECO, and EKPC properly point out that this is clearly not PJM’s intent,15 with Buckeye Power’s Comments highlighting that “PJM’s goal of ‘prevent[ing] Manual Load Dump’ properly recognizes that keeping existing customers, particularly residential loads, online is the primary goal in the event of a grid emergency.”16 Ultimately, however, PJM’s IRAS Proposal does not provide the clarity needed for EDCs’ IRAS obligations in real-time. To this end, the Board requests clarification on how PJM will use real-time demand from New Large Loads to inform curtailment directives, either through a more dynamic database in PJM’s proposed Large Load Registry, or through the development and maintenance of a different system entirely to assist in this process. Furthermore, both Buckeye Power and SMECO seek clarification that EDCs will not be required
13 Buckeye Power Comments at 5; EKPC Protest at 12.14 SMECO Comments at 8-9.15 Buckeye Power Comments at 6; SMECO Comments at 9; EKPC Protest at 12.16 Buckeye Power Comments at 3 (quoting PJM IRAS Proposal at 81).
PDF page 4
4
to shed more load than what is being used by New Large Loads in real-time, which the Board supports.17
ii. PJM Should Clarify How IRAS Directives Interact with Peak Shaving Adjustments The Board appreciates PJM’s consideration of state policies when it added a Peak Shaving Adjustment (“PSA”) provision in its Reliability Backstop Procurement Proposal (“RBP”) that would decrement a zone’s RBP obligation commensurate with its PSA arrangements.18 This provision recognizes the reliability benefits PSA programs provide to the region, and the Board submitted Comments in appreciation of this component that compliments the newly passed Data Center Fair Share Act in New Jersey.19 However, while PSA arrangements reduce RBP obligations, PJM has not explained how they will interact with Bring Your Own New Capacity (“BYONC”) obligations or IRAS obligations. Several commentators have raised concerns about this ambiguity.20 The Board likewise seeks clarity regarding how PSA arrangements interact with IRAS.
The Board thinks that New Large Loads with PSA agreements must be accounted for explicitly in PJM’s IRAS operations with real-time information regarding whether New Large Loads have already reduced their load due to PSA directives. In a scenario in which a New Large Load has already offset its load due to a PSA directive, it cannot reduce its total registered load amount in the event the EDC requires it during an IRAS Action. As discussed in reference to
17 Buckeye Power Comments at 7; SMECO Comments at 9-10.18 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from New Large Load Adjustments, Docket No. ER26-3380 (July. 31, 2026).19 PJM Interconnection, L.L.C., Comments of the New Jersey Board of Public Utilities, Docket No. ER26-3380 (Aug. 21, 2026).20 See e.g., Tesla Comments at 4-5; Voltus Comments at 23-24; CEBA Protest at 8-11; Chief Energy Officer for the Governor of Virgina Comments at 2-3.
PDF page 5
5
Buckeye Power’s Comments, it is unclear whether EDCs will face penalties for not curtailing the entire amount of the registered peak New Large Load amount directed by PJM, or if EDCs must curtail other customers in order to meet this IRAS obligation.
The Board recommends that PJM clarify that EDCs will not be required to curtail more than their New Large Load demand in real time, after accounting for any real-time load reductions achieved through programs such as PSA. Furthermore, the Board recommends that a more dynamic data-sharing method is developed for PJM, states, utilities, and New Large Loads to locate and utilize real-time New Large Load demand, IRAS, and PSA dispatch information for better information-sharing and accountability. In addition, the Board agrees with Equinix that the Large Load Registry should account for New Large Loads that are sponsoring PSAs at another site in the same zone in addition to PSAs associated with the load itself, which is not something PJM’s Proposal appears to do currently.21
III. CONCLUSION
The Board reiterates that it strongly supports PJM’s decision to propose a PJM-led resource adequacy service for New Large Loads that do not offset their registered peak load with sufficient capacity arrangements, and thinks its Proposal is largely workable. However, the Board underscores concerns other entities have raised and seeks clarity on specific elements that currently provide confusion and challenges in implementing IRAS. The Board is hopeful that this clarification will provide entities in New Jersey with the information they need to effectuate PSA programs, and that clarification pertaining to the IRAS MW amount will provide EDCs with the confirmation that they are not expected to curtail other customers during an IRAS Action. The Board thinks these elements can be addressed without fundamentally altering PJM’s IRAS
21 Equinix Comments at 16.
PDF page 6
6
Proposal, and the Board thinks it and other entities have proposed workable solutions to these challenges.
Respectfully,
PDF page 7
7
NEW JERSEY BOARD OF PUBLIC
UTILITIES
By: /s/ Paul Youchak
Ian Oxenham
Alex Cary
Amanda Lescano
Timothy Randazzo
Mahala Lahvis
Airi Kogishi
New Jersey Board of Public Utilities
44 South Clinton Ave.
Trenton NJ 08609
Paul.youchak@bpu.nj.gov
Ian.oxenham@bpu.nj.gov
Alexander.Cary@bpu.nj.gov
Amanda.lescano@bpu.nj.gov
Timothy.randazzo@bpu.nj.gov
Mahala.lahvis@bpu.nj.gov
Airi.kogishi@bpu.nj.gov
MICHAEL L. ZUCKERMAN
ACTING ATTORNEY GENERAL
OF NEW JERSEY
By: /s/ Steven Chaplar
Deputy Attorney General
Department of Law and Public Safety
Division of Law
P.O. Box 112
Trenton, NJ 08625
Steven.chaplar@law.njoag.gov
Attorneys for the New Jersey Board of
Public Utilities
Dated: September 18, 2026
Trenton, New Jersey
PDF page 8
8
CERTIFICATE OF SERVICE
I hereby certify that, on this 18th day of September 2026, I have caused the foregoing document to be served upon each party designated on the official service list compiled by the Secretary in this proceeding, by email.
By: /s/ Steven Chaplar
Steven Chaplar
Deputy Attorney General
New Jersey Office of the Attorney General
Department of Law & Public Safety
P.O. Box 112
Trenton, New Jersey 08625
Steven.chaplar@law.njoag.gov