Motion for Leave to Answer and Answer of the New Jersey Board of Public Utilities to the protests and comments of Buckeye Power, Inc., et al
Text extracted from the eLibrary original (SHA-256 3fc0151882c04c04…). Download the original from the official source.
Contents · 3 sections
Read topic-matched comments in ER26-3515
Topics in the text: Registry access · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, LLC ) Docket No.Read this passage Filed comments: Reliability and curtailment
I. MOTION FOR LEAVE TO ANSWER
printed heading
MOTION FOR LEAVE TO ANSWER While Rule 213(a)(2) generally prohibits answers to protests and comments, good cause justifies the Commission’s granting this motion and accepting this answer because it provides useful and relevant information that will assist the Commission in its decision-making…Read this passage
II. ANSWER
printed heading · Topic match: Registry access
To this end, the Board requests clarification on how PJM will use real-time demand from New Large Loads to inform curtailment directives, either through a more dynamic database in PJM’s proposed Large Load Registry, or through the development and maintenance of a different system entirely to assist…Read this passage Filed comments: Registry access
III. CONCLUSION
printed heading
CONCLUSION The Board reiterates that it strongly supports PJM’s decision to propose a PJM-led resource adequacy service for New Large Loads that do not offset their registered peak load with sufficient capacity arrangements, and thinks its Proposal is largely workable.Read this passage
CERTIFICATE OF SERVICE
printed heading
By: /s/ Steven Chaplar Steven Chaplar Deputy Attorney General New Jersey Office of the Attorney General Department of Law & Public Safety P.O.Read this passage