Comments of Google LLC on Midcontinent Independent System Operator Inc.’s Interconnection Reliability Requirements for Large Loads Proposal
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator
Inc.
)
)
)
)
)
Docket No. ER26-3650-000
COMMENTS OF GOOGLE LLC
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 Google LLC (“Google”) submits these comments on Midcontinent Independent System Operator Inc.’s (“MISO”) Interconnection Reliability Requirements for Large Loads Proposal (“IRR Proposal”). Google supports the proposal as a reasonable and responsible step to bolster the near-term reliability of the nation’s electric grid.
Ensuring electric reliability must continue to be job number one. That responsibility has become increasingly complex, in large part due to the addition of large loads that may exhibit different operating characteristics than other loads. Google therefore commends MISO for prioritizing the reliability of the transmission system and working proactively to identify and mitigate the risks that certain Large Loads can pose to the power grid. In addition, Google supports MISO’s pragmatic approach to these issues, including its reasonable grandfathering of existing customers in a manner that respects reliance interests and investments made under the rules in effect at the time. An approach along the lines proposed in this proceeding is consistent with Google’s approach to responsible energy growth.21 18 C.F.R. § 385.211 (2026).2 See Amanda Peterson Corio, Supporting the White House Ratepayer Protection Pledge: Google's Approach for Responsible Energy Growth, Google: The Keyword (Mar. 4, 2026), https://blog.google/innovation-and- ai/infrastructure-and-cloud/global-network/affordability-pledge-responsible-energy-growth.
PDF page 2
-2-
At the same time, while Google supports this filing, additional work is needed to further refine MISO’s approach to reliability issues associated with new Large Loads. For example, the best way to ensure the reliability of the system is to tie any regulations or requirements to the electrical characteristics of the load rather than the specific type of end use they constitute. In other words, regulators should focus on imposing obligations based on the reliability challenges associated with a particular load (e.g., ramp rate, voltage sensitivity, etc.) rather than the nature of the retail customer (e.g., data center, arc furnace, etc.). In addition, several aspects of the IRR Proposal have yet to come into focus, either because they will be specified in the MISO Business Practice Manuals (“BPM”) or because the proposed tariff language gives MISO significant discretion over how it will implement the IRR Proposal. Those implementation questions will go a long way in determining the effectiveness and administrability of the IRR Proposal.
I. COMMENTS
As noted, Google supports the IRR Proposal. It offers the following observations and suggestions as MISO and the Commission continue to refine their approach to addressing the reliability implications of load growth driven by new Large Loads.
A. Grandfathering Existing Loads Is Important and Consistent with Commission
Policy
Google supports the grandfathering provisions in the IRR Proposal, which provide important commercial certainty to entities seeking to invest in the MISO region. The grandfathering paradigm is also consistent with Commission policy and analogous large load regulatory frameworks for other Independent System Operators (“ISOs”)/Regional Transmission Organizations (“RTOs”). Under the IRR Proposal, the extent to which MISO will regulate Large Loads varies depending on the date on which service to the Large Load begins, whether transmission projects or upgrades associated with the Large Load have been approved by the
PDF page 3
-3-
MISO Board in MTEP, and when transmission projects or upgrades associated with the Large Load are submitted to the MISO EPR process.3 For example, Large Loads with a transmission service commencement date on or prior to December 4, 2026—i.e., the proposed effective date of the IRR Proposal—will not be subject to certain IRR regulations.4
Data centers have operated safely and reliably within the MISO footprint for years (and in some cases, decades). Google applauds MISO for crafting regulations that reflect its considerable experience operating a grid that has long provided service to data center loads, rather than imposing on those loads a new regulatory regime meant to mitigate risks that those loads have never presented.
The grandfathering provisions do more than just reflect MISO’s experience to date; they also provide commercial certainty for parties that have already invested in electrical and digital infrastructure in MISO and send an important signal to prospective investors that they can rely on the regulatory landscape to remain predictable. This, in turn, creates the certainty necessary to deploy capital needed to upgrade digital and electrical infrastructure, including through investments that help make data centers better grid citizens. As Google has emphasized, during this time of rapid transformation, regulations that create uncertainty or raise the risk that investments made in reliance on the rules in effect at the time will be rendered obsolete decrease companies’ appetite to make those investments voluntarily.5 As such, greater regulatory uncertainty can lead to impaired reliability if it prevents companies from making the investments
3 Midcontinent Indep. Sys. Operator, Inc., Reliability Requirements for Large Loads, Docket No. ER26-3650- 000, 13-14 (filed Aug. 28, 2026) (“Transmittal”).4 Id. at 14.5 See generally PJM Interconnection, L.L.C., Protest of Google LLC, Docket No. ER26-3515-000 (filed Sept. 3, 2026).
PDF page 4
-4-
that will go above and beyond to ensure that the grid remains safe and reliable. Grandfathering provisions, like the ones in the IRR Proposal, respect existing reliance interests and signal to investors and developers that the regulatory ground beneath them is less likely to shift unexpectedly.
Moreover, respecting reliance interests, including through existing contracts and commercial arrangements, is consistent with the Commission’s guidance in the MISO Large Load Show Cause Order where the Commission encouraged MISO to “(a) propose a reasonable implementation period to ensure minimal disruption to such existing commercial arrangements, and (b) allow a reasonable amount of time to finalize ongoing agreements that are nearing completion as of the date such Tariff provisions are filed with the Commission. Such proposed Tariff revisions should include a reasonable effective date that accommodates such considerations regarding these existing commercial arrangements.”6 The IRR Proposal grandfathering provisions do just that. Projects that begin operating before the effective date of the IRR Proposal will be subject to the regulations in effect when those projects were conceived, not the entirely new IRR regulatory regime, and projects that are verifiably in progress will only be subject to a subset of the IRR regulations, thus ensuring minimal disruption.
The grandfathering provisions in the IRR Proposal are also consistent with transition mechanisms that the Commission has approved for similar regulations in SPP. SPP’s HILLS construct imposes reliability requirements on large loads, which include load forecasting provisions, remote capability to disconnect load from the transmission system, installation of phasor measurement units for real-time load data, and ride-through requirements.7 SPP’s large
6 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 5 (2026).7 Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at PP 18-20, 63 (2026).
PDF page 5
-5-
load reliability requirements similarly do not apply to existing loads.8 Google urges the Commission to note the importance of this approach and encourage any other regions considering similar measures to follow suit and adopt an approach that, as noted above, facilitates the investment in the reliability measures that the country badly needs.
At the same time, as noted above, ensuring electric reliability must remain job number one. To that end, MISO has included important “notwithstanding” language in the grandfathering provisions of the IRR Proposal,9 which allows it to continue monitoring the operational risks introduced by certain large loads and modify its approach where necessary to address reliability risks. In so doing, MISO has struck an important balance that preserves reliance interests while also preserving its ability to adjust its approach as needed to ensure reliability.
B. Large Loads Should Be Classified and Regulated Based on Their Objective
Electrical Characteristics Rather than the Function they Perform
The IRR Proposal regulates Large Loads based on the function they perform—e.g., computation—rather than their operational characteristics and their effects on the grid. This means that MISO may end up regulating some Large Loads that do not pose a reliability risk to the transmission system while excluding non-data center loads that pose some of the same risks. Under the IRR Proposal, MISO would subject Computational Loads, which it defines as “Large Load comprised of 25 MW or more of Demand from information technology equipment, such as servers, storage, and networking hardware,”10 to more onerous regulatory requirements than Large Loads, which MISO defines as loads over 50 MW at a single substation behind one or more
8 Id. P 10 (“A load may be categorized as a HILL after the initial effective date of Attachment BA of the Tariff.”); id. P 10 n.23 (“Existing loads will not be considered HILLs or be subject to the requirements of Attachment BA unless they seek to increase load and otherwise meet the definitional requirements.”).9 Filing, Proposed MISO Tariff Revisions, § 37A(II)(3). 10 Transmittal at 11.
PDF page 6
-6-
Point(s) of Withdrawal from the Transmission System.11 Specifically, Large Loads would need to comply with visibility requirements while Computational Loads would also need to comply with ramp, PMU, and ride-through requirements. As MISO explains, “[d]efining Computational Load supports a more targeted and risk-informed approach, rather than applying the same requirements to all Large Loads regardless of facility type or operating behavior.”12
As noted above, Google believes reliability requirements like those in this proposal are important and need to be implemented promptly. Nevertheless, by proposing a scheme that turns on the function that a facility performs rather than on its electrical behavior, MISO has, in fact, created an approach that “appl[ies] the same requirements . . . regardless of . . . operating behavior.” To see why this is the case, consider industrial loads beyond data centers (e.g., arc furnaces, cryogenic facilities, hydrogen electrolyzers, etc.), which can exhibit identical electrical behaviors as certain data centers but would escape the ramp, PMU, and ride-through requirements in the IRR Proposal. At the same time, data centers that do not exhibit high-risk behaviors—e.g., because they have made investments or adopted operational protocols to reduce impact on the grid—would be regulated as Computational Loads. An approach that regulates loads based on their risks to and effects on the grid would not only be a more efficient system of regulation; it would also incentivize data center operators to make additional investments needed to mitigate or eliminate those effects entirely—a win-win situation for both customers and grid operators more generally.
11 Id. at 10.12 Id. at 11 (emphasis added).
PDF page 7
-7-
C. The Success of the IRR Proposal Will Depend on Details that Will Be Included in MISO’s Manuals
MISO has deferred critical details of the IRR regulatory paradigm—e.g., the 30
MW/minute ramp calculation methodology, voltage ride-through curve specifications, and deviation penalties—to its Business Practice Manuals. As such, the IRR Proposal is best described as a high-level framework rather than a comprehensive regulatory regime, which makes it difficult to evaluate whether the IRR Proposal will achieve its stated goals and, relatedly, the extent to which Large Loads will be able to comply with its requirements. Google recognizes that some of the terms and requirements that MISO has left unspecified are technical implementation details that should be set forth in the Business Practice Manuals. We urge MISO to work closely with stakeholders in fleshing out those details.
At the same time, the IRR Proposal gives MISO open-ended authority to impose what amounts to penalties on Large Loads that fail to comply with various new requirements (e.g., modeling, data, telemetry, etc.), which raises a particular risk of running afoul of the rule of reason. Under the rule of reason, practices that “affect rates and service significantly,” “are realistically susceptible of specification,” and “are not so generally understood in any contractual arrangement as to render recitation superfluous” must be filed with the Commission, not housed in Business Practice Manuals and the like.13 The Commission has previously found that penalty provisions that significantly affect the conditions of transmission service must be included in a transmission provider’s tariff.1413 City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985) (emphasis removed).14 See California Indep. Sys. Operator Corp., 175 FERC ¶ 61,245, at P 166 (2021), order on reh’g, 178 FERC ¶ 61,180 (2022).
PDF page 8
-8-
The penalty authority in the IRR Proposal could do just that. Specifically, for transmission customers that do not comply with the regulatory requirements in the IRR Proposal, MISO will have unbounded discretion to delay the commencement date for transmission service to the new Large Loads, impose operational limitations, or impose other remediation actions necessary to maintain the reliability of the transmission system.15 In other words, MISO is reserving to itself the power to penalize customers by imposing conditions on transmission service. While MISO itself acknowledges, “clarity is required as to potential consequences in the event a party fails to comply with applicable requirements,”16 it has yet to provide such clarity, and Google urges MISO to do so promptly and with the predictability necessary to avoid rule of reason concerns.
D. The Breadth of Certain Provisions Could Make it Difficult for Entities to Comply with the IRR Proposal
Finally, Google is concerned that some provisions in the IRR Proposal are framed so broadly that it will be difficult, if not impossible, for regulated entities to comply. Most notably, the IRR Proposal gives MISO the right to audit information “including, but not limited to, information related to the registration, claimed capacity, operations, modeling, inverter settings, metering, settlements, Large Load Equipment, and/or any other information related to the participation of the Large Load under this Tariff.”17 While Google believes that MISO should have the audit rights necessary to ensure that entities are complying with its tariff—after all, the reliability of the grid depends on it—giving MISO such unbounded and undefined powers could complicate compliance for Large Loads in the region. In the absence of limits on the information that MISO can request, Large Loads will be required to retain a nearly limitless amount of
15 Transmittal at 23. 16 Id.17 Filing, Proposed MISO Tariff Revisions, § 37A.8 (emphasis added).
PDF page 9
-9-
information. MISO should be able to access any information it needs to ensure that Large Loads (and the transmission customers taking service on their behalf) are complying with reliability requirements. That said, a regime under which entities need to retain everything because MISO can ask for anything will become unduly burdensome, unworkable in practice, and actually complicate the process of complying with these critical regulations.
II. Conclusion
Google supports the IRR Proposal, which will help MISO ensure reliability in this era of rapid load growth. But the work cannot end here. Eventually, the Commission should ensure that, where appropriate, the reliability requirements imposed by ISOs/RTOs align with the large load reliability standards that it has directed the North American Electric Reliability Corporation to develop.18 This will help to avoid a patchwork of reliability requirements across ISOs/RTOs, improving reliability and reducing compliance costs.
Respectfully submitted,
/s/ Brian George
Brian George
Sr. Lead, US Energy Markets
Stephen Lindeman
Lead, Energy Market Development
Google LLC
655 New York Ave., NW
Washington, DC 20001
(202) 999-0990
briangeorge@google.com
lindemans@google.com
Matt Christiansen
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
mchristiansen@wsgr.com
bshpall@wsgr.com
Counsel for Google LLC
Dated: September 18, 2026
18 See Reliability Standard(s) Pertaining to Computational Load Integration, 196 FERC ¶ 61,031 (2026).
PDF page 10
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.
Dated: September 18, 2026
Washington, D.C.
/s/ Bryan Shpall
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006