Comments of Google LLC on Midcontinent Independent System Operator Inc.’s Interconnection Reliability Requirements for Large Loads Proposal
Text extracted from the eLibrary original (SHA-256 1b6d80166d1eb106…). Download the original from the official source.
Contents · 6 sections
- I. COMMENTS
- A. Grandfathering Existing Loads Is Important and Consistent with Commission
- B. Large Loads Should Be Classified and Regulated Based on Their Objective
- C. The Success of the IRR Proposal Will Depend on Details that Will Be Included in
- D. The Breadth of Certain Provisions Could Make it Difficult for Entities to Comply
- II. Conclusion
Read topic-matched comments in ER26-3650
Topics in the text: Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Cost allocation
Ensuring electric reliability must continue to be job number one.Read this passage Filed comments: Cost allocation
I. COMMENTS
printed heading
COMMENTS As noted, Google supports the IRR Proposal.Read this passage
A. Grandfathering Existing Loads Is Important and Consistent with Commission
printed heading
At the same time, as noted above, ensuring electric reliability must remain job number one.Read this passage
B. Large Loads Should Be Classified and Regulated Based on Their Objective
printed heading
Large Loads Should Be Classified and Regulated Based on Their Objective Electrical Characteristics Rather than the Function they Perform The IRR Proposal regulates Large Loads based on the function they perform—e.g., computation—rather than their operational characteristics and their effects on the…Read this passage
C. The Success of the IRR Proposal Will Depend on Details that Will Be Included in
printed heading
Under the rule of reason, practices that “affect rates and service significantly,” “are realistically susceptible of specification,” and “are not so generally understood in any contractual arrangement as to render recitation superfluous” must be filed with the Commission, not housed in Business…Read this passage
D. The Breadth of Certain Provisions Could Make it Difficult for Entities to Comply
printed heading
The Breadth of Certain Provisions Could Make it Difficult for Entities to Comply with the IRR Proposal Finally, Google is concerned that some provisions in the IRR Proposal are framed so broadly that it will be difficult, if not impossible, for regulated entities to comply.Read this passage
II. Conclusion
printed heading
Conclusion Google supports the IRR Proposal, which will help MISO ensure reliability in this era of rapid load growth.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated: September 18, 2026 Washington, D.C. /s/ Bryan Shpall Bryan Shpall Wilson Sonsini Goodrich & Rosati 1700 K Street NW Fifth Floor Washington, DC 20006Read this passage