ER26-3650-000 · 2026-09-18 · Verrus LLC

Comments of Verrus LLC in Support of Midcontinent Independent System Operator, Inc.'s proposed Interconnection Reliability Requirements for Large Loads

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc.
)
Interconnection Reliability Requirements
)  Docket No. ER26-3650-000
for Large Loads
)
COMMENTS OF VERRUS, LLC IN SUPPORT OF MISO'S INTERCONNECTION
RELIABILITY REQUIREMENTS FOR LARGE LOADS
Pursuant to Rule 213 of the Commission’s Rules of Practice and Procedure1, Verrus LLC2 ("Verrus") respectfully submits these comments in support of the above-captioned filing by the Midcontinent Independent System Operator, Inc. ("MISO"), which proposes Interconnection Reliability Requirements ("IRR") for Large Loads.3 Verrus generally supports MISO’s proposed approach and offers the comments below to underscore that advanced, flexible computational loads — such as those Verrus develops — can, and should, serve as active contributors to grid reliability, not merely as loads that must be accommodated.

I.  BACKGROUND AND SUMMARY OF POSITION
MISO’s filing responds to the Commission’s June 18, 2026 order directing MISO to show cause why its Tariff remains just and reasonable absent provisions addressing ongoing operational requirements for large loads, including visibility, ramp rate, and disturbance ride-through.4 MISO’s IRR Proposal seeks to establish four categories of reliability requirements

— data, modeling, telemetry, and forecasting requirements (together, “visibility”), phasor measurement unit (“PMU”) requirements, ramp requirements, and ride-through requirements —

4Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026) ("Show Cause Order"); see also Transmittal Letter at 6, 8 (describing the Show Cause Order and MISO’s subsequent Abeyance Motion).
3Midcontinent Independent System Operator, Inc., Interconnection Reliability Requirements for Large Loads, Docket No. ER26-3650-000, Transmittal Letter (Aug. 28, 2026) ("Transmittal Letter"). 2Verrus LLC ("Verrus") is a developer, owner, and operator of a first-of-its-kind fleet of purpose-built, load-flexible data centers designed to function not only as digital infrastructure but also as active grid assets, capable of dynamically adjusting electricity consumption to support system reliability, efficiency, and affordability.  Verrus has been an active stakeholder participant in MISO’s Large Load Working Group ("LLWG") process addressing the Interconnection Reliability Requirements at issue in this filing, and has separately engaged before the Commission on large-load interconnection issues, including in Docket Nos. EL26-70-000 and RM26-4-000.  Contemporaneously with these comments, Verrus has filed a motion to intervene in this proceeding. 1 18 C.F.R. § 385.213. 1

PDF page 2

scaled to a newly defined “Computational Load” subset of “Large Load,” with the more intensive PMU, ramp, and ride-through obligations applied only to Computational Loads.5 Verrus supports this framework.

As explained below, Verrus (A) supports MISO’s
risk-scaled approach to applicability; (B) supports MISO’s choice to establish core obligations in the Tariff, while reserving implementation detail to the Business Practices Manual (“BPM”) and its ongoing stakeholder process; (C) offers its own facility design as an example demonstrating that advanced computational loads are capable of actively supporting reliability, not merely complying with minimum standards; (D) urges the Commission to ensure that MISO’s Tariff-based requirements remain harmonized with the ongoing NERC standard development effort; and (E) requests that MISO’s transition provisions continue to reasonably account for loads still progressing toward full interconnected capacity.

II.  COMMENTS
A. MISO’s Risk-Scaled Framework Reasonably Targets Requirements at the Loads That Present Reliability Risk

Verrus supports MISO’s determination to apply the full suite of PMU, ramp, and ride-through requirements only to the Computational Load subset of Large Load, while applying visibility requirements more broadly.6 This approach appropriately recognizes that not all large loads

exhibit
the
rapid,
power-electronic-driven
demand
changes
that
motivated
the
Commission’s concerns,7
and avoids imposing requirements on loads that do not present the
reliability risk those requirements are designed to address.
B. Verrus Supports Establishing Core Obligations in the Tariff While Reserving Implementation Detail to the BPM and Stakeholder Process

Verrus also generally supports MISO’s approach of codifying the core visibility, PMU, ramp, and ride-through obligations in the Tariff while leaving technical details — communication protocols, specific thresholds, and testing and demonstration procedures — to the BPM for Large

7Show Cause Order at P 64.
6Transmittal Letter at 11, 15-22 (explaining that all Large Loads are subject to applicable visibility requirements, while the Computational Load component of a Large Load is separately subject to PMU, ramp, and ride-through requirements).
5Transmittal Letter at 3-4, 9-10, 22 (describing the categories of proposed reliability requirements and the Large Load / Computational Load definitions). 2

PDF page 3

Load, which is being refined in the the continuing LLWG process.8 That approach strikes an appropriate balance: it gives the Commission and stakeholders a clear, enforceable Tariff framework, while preserving the flexibility MISO and stakeholders need to refine technical requirements in a rapidly evolving area as operating experience increases.

C.  Advanced Computational Loads Are Capable of Actively Supporting Grid Reliability Verrus’ own facility design illustrates that computational loads that would be subject to MISO’s proposed requirements are not merely able to comply with them, but can affirmatively support system reliability. Verrus data centers employ behind-the-meter battery energy storage systems (“BESS”) and proprietary coordinated controls — which Verrus refers to as its StabiliGrid™architecture — that function as a buffer layer between the point of interconnection and IT load, managing ramp behavior and providing sub-second ride-through support during voltage and frequency disturbances.9 Testing and modeling of this architecture, conducted jointly with

the
National
Laboratory
of
the
Rockies,
demonstrates
materially
reduced
point-of-interconnection power deviation during severe grid disturbances relative to the conventional design baseline modeled in the study.10 Verrus offers this experience to illustrate that the Commission and MISO should continue their efforts to ensure that computational loads function as grid assets.

D. FERC Action on MISO’s Reliability Requirements Should Be Harmonized with the Parallel NERC Standards Effort

MISO’s own filing recognizes that its proposed ramp, PMU, and ride-through
requirements are being developed ahead of, but in alignment with, NERC’s emerging Computational Load definition and the ongoing work of NERC’s Load Modeling Task Force.11 NERC is separately developing large-load-related reliability requirements of its own, including through its Large Loads Task Force, Large Loads Working Group, and Project 2026-02

11Transmittal Letter at 28 (noting that MISO clarified that Tariff applicability for the ramp, PMU, and ride-through requirements aligns with NERC’s emerging definition of Computational Loads and the technical discussions of NERC’s Load Modeling Task Force).
10Talukdar et al., Mitigating Data Center Impact on Grid Stability: A Coordinated Control Strategy Using Verrus™ StabiliGrid™ Architecture, Technical Report NLR/TP-2C00-98424 (Feb. 2026), https://docs.nlr.gov/docs/fy26osti/98424.pdf, appended as Attachment A ("StabiliGrid Report").
9Verrus May 2026 LLWG Reliability Comments at 1 (describing Verrus’s use of a behind-the-meter battery energy storage system and proprietary control system as a “buffer layer” between the point of interconnection and IT load).
8Transmittal Letter at 21-27 (describing proposed Tariff Sections 37A.1 through 37A.8 and MISO’s corresponding Business Practices Manual for Large Load implementation). 3

PDF page 4

(Computational Load).12
Because the MISO and NERC are advancing large-load reliability
requirements in parallel (but not in fully synchronized processes), Verrus urges the Commission, in acting on this filing, to make clear that MISO’s Tariff-based requirements and any eventual NERC Reliability Standard(s) addressing the same operational characteristics should be harmonized — so that large loads such as Verrus, as well as utilities and other stakeholders, are not left navigating duplicative, inconsistent, or conflicting obligations.

E. MISO’s
Transition Provisions Should Continue to Accommodate Loads Still
Progressing Toward Full Capacity
Verrus supports MISO’s proposed transition provisions, which appropriately distinguish between loads with a Service Commencement Date before the proposed effective date and those still progressing through interconnection.13

Consistent with comments Verrus has previously
offered in the LLWG process, Verrus encourages MISO to clarify that the ramp-up process for standards implementation accounts for the buildout period of a large load campus (which frequently extends over several years), rather than binding at a level calibrated to initial, partial energization.14

14Verrus May 2026 LLWG Comments at 1-2 (recommending that MISO clarify the load level at which the ramp requirement becomes binding during a phased site energization).
13Transmittal Letter at 13-14 (describing transition provisions applicable based on Service Commencement Date and MTEP/EPR status).
12Transmittal Letter at 7 & n.21 (citing NERC Large Loads Task Force and Large Loads Working Group whitepapers and alerts, and Project 2026-02 (Computational Load), a NERC Reliability Standard currently under development). 4

PDF page 5

III.  CONCLUSION
For the foregoing reasons, Verrus respectfully requests that the Commission accept MISO’s filing in Docket No. ER26-3650-000, and approve MISO’s requested effective date of December 4, 2026.15 Verrus looks forward to continuing to participate in MISO’s Large Load Working Group as further implementation details are developed.

Respectfully submitted,
/s/ Gabe Tabak
Gabe Tabak
Head of Energy Policy
Verrus LLC
gabe@verrusdata.com
/s/ Jeff Bladen
Jeff Bladen
Head of Energy
Verrus LLC
bladen@verrusdata.com
Dated:  September 18, 2026
Attachment A:  Talukdar et al., Mitigating Data Center Impact on Grid Stability: A Coordinated Control Strategy Using Verrus™ StabiliGrid™ Architecture (Feb. 2026) [to be appended]. 15Transmittal Letter at 30 (requesting an effective date of December 4, 2026). 5

PDF page 6

The National Laboratory of the Rockies is a national laboratory of the U.S. Department of Energy, Office of Critical Minerals and Energy Innovation, operated under Contract No. DE-AC36-08GO28308. This report is available at no cost from the National Laboratory of the Rockies (NLR) at www.nlr.gov/publications.

Technical Report
NLR/TP-2C00-98424
February 2026
Mitigating Data Center Impact on Grid
Stability: A Coordinated Control
Strategy Using Verrus™ StabiliGrid™
Architecture
Saurav Talukdar,1 Shilpa Marti,1 Ben Wheeler,1 Jeff Bladen,1 Deepthi Vaidhynathan,2 Kumaraguru Prabakar,2 and Steven Hammond2

1 Verrus LLC
2 National Laboratory of the Rockies

PDF page 7

The National Laboratory of the Rockies is a national
laboratory of the U.S. Department of Energy,
Office of Critical Minerals and Energy Innovation,
operated under Contract No. DE-AC36-08GO28308.
This report is available at no cost from the National Laboratory of the Rockies (NLR) at www.nlr.gov/publications.

National Laboratory of the Rockies
15013 Denver West Parkway
Golden, CO 80401
303-275-3000 • www.nlr.gov
Technical Report
NLR/TP-2C00-98424
February 2026
Mitigating Data Center Impact on Grid
Stability: A Coordinated Control
Strategy Using Verrus StabiliGrid
Architecture
Saurav Talukdar,1 Shilpa Marti,1 Ben Wheeler,1 Jeff
Bladen,1 Deepthi Vaidhynathan,2 Kumaraguru Prabakar,2 and Steven Hammond2

1 Verrus LLC
2 National Laboratory of the Rockies Suggested Citation Talukdar, Saurav, Shilpa Marti, Ben Wheeler, Jeff Bladen, Deepthi Vaidhynathan, Kumaraguru Prabakar, and Steven Hammond. 2026. Mitigating Data Center Impact on Grid Stability: A Coordinated Control Strategy Using Verrus StabiliGrid Architecture. Golden, CO: National Laboratory of the Rockies. NLR/TP-2C00-98424. https://www.nlr.gov/docs/fy26osti/98424.pdf.

PDF page 8

NOTICE
This work was authored in part by the National Laboratory of the Rockies for the U.S. Department of Energy (DOE), operated under Contract No. DE-AC36-08GO28308. Support for the work was provided by Verrus LLC under TSA2431261. This work was also supported by the Laboratory Directed Research and Development (LDRD) Program at the National Laboratory of the Rockies. The views expressed herein do not necessarily represent the views of the DOE or the U.S. Government.

This report is available at no cost from the National Laboratory
of the Rockies (NLR) at www.nlr.gov/publications.
U.S. Department of Energy (DOE) reports produced after 1991
and a growing number of pre-1991 documents are available
free via www.OSTI.gov.
Cover photos (clockwise from left): Josh Bauer, National Laboratory of the Rockies 61725; Visualization from National Laboratory of the Rockies Insight Center; Getty-181828180; Agata Bogucka, National Laboratory of the Rockies 91683; Dennis Schroeder, National Laboratory of the Rockies 51331; Werner Slocum, National Laboratory of the Rockies 67842.

The National Laboratory of the Rockies prints on paper that contains recycled content.

PDF page 9

iii
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications.
Table of Contents
Background … 1 July 10, 2024: Large Load Loss Incident … 1 Current State … 3 Innovation … 4 Results … 5 Conclusion … 10 References … 11

PDF page 10

iv
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications.
List of Figures
Figure 1. Grid voltage faults at Station C … 2 Figure 2. Aggregate grid load … 3 Figure 3. Coordinated response of a BESS-enabled data center during repeated undervoltage events … 7

Figure 4. Coordinated response of a BESS-enabled data center during an overvoltage event … 9

List of Tables
Table 1. Undervoltage Grid Contingency Event … 5 Table 2. Overvoltage Grid Contingency Event … 8

PDF page 11

1
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. Background

July 10, 2024: Large Load Loss Incident
On July 10, 2024 (NERC 2025), the fragility of modern load dynamics was exposed when a lightning strike in Northern Virginia caused a transmission-level fault, lasting less than 100 milliseconds (ms), which triggered the cascading disconnection of approximately 1,500 megawatts (MW) of data center load (see Figure 1). Despite the grid fault clearing in roughly 50 ms, sensitive internal protection schemes across dozens of facilities interpreted the voltage sag as a valid outage, transitioning information technology (IT) loads to backup power and severing grid connection. The resulting sudden drop in demand caused a voltage swell to 1.07 p.u., requiring manual operator intervention to stabilize the area.

Crucially, although the facilities in Northern Virginia effectively operated within the voltage immunity bounds of the Information Technology Industry Council (ITIC) curve, the event exposed a fundamental misalignment: The ITIC standard is designed to protect individual server hardware, not to maintain macro-grid stability. This resulted in the grid losing several hundred megawatts of load almost instantaneously, creating overvoltage and oscillation. This “near miss” has become a primary case study for North American Electric Reliability Corporation and Institute of Electrical and Electronics Engineers (IEEE) working groups, driving new regulatory frameworks that treat data centers not just as passive customers, but as large, dynamic loads that must possess robust voltage ride-through capabilities, adaptive protection, and coordinated control strategies. The Electric Reliability Council of Texas recently released its ride-through requirements (ERCOT 2025) for large electronic loads (which includes data centers), particularly to address these types of massive load disconnection concerns.

PDF page 12

2
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications.

Figure 1. Grid voltage faults at Station C (NERC 2025)

PDF page 13

3
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. Current State

In practice, many data centers use disturbance-count protection that locks out after three undervoltage events (below ~0.7–0.8 p.u.) within 60 seconds (s), transferring loads to backup power until a manual reset is performed. In the July 10 event shown in Figure 1, the third undervoltage (NERC 2025) triggered widespread lockouts, disconnecting approximately 1.5 gigawatts of data center load and amplifying grid instability as seen in Figure 2.

Figure 2. Aggregate grid load (NERC 2025)
Recently, some new data centers (Vaidhynathan et al. 2025) have incorporated commercial battery energy storage systems (BESS) units that typically include fault ride-through and undervoltage ride-through capabilities, as mandated by IEEE 1547 standards. However, these responses are typically self-contained and uncoordinated with data center protection logic or uninterruptible power supply (UPS) operation to provide a “plant-level” ride-through response. As a result, although the BESS remains connected during short faults, it is not synchronized to provide grid load recovery/ride-through behavior with UPS load transfer or point of interconnection (POI) protection timing. This results in delayed power restoration and short-term grid instability following voltage recovery persisting with conventional BESS. This observation highlights a key gap: Existing BESS operate effectively at the device level but lack integrated control with other critical data center assets needed for a grid-supportive response during and after “successive” undervoltage events.

PDF page 14

4
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. Innovation

As data centers represent a larger percentage of overall grid load, it is increasingly critical that they stay connected and assist the grid during short-duration grid contingencies (<~5-s) to avoid causing wide-area outages. This is accomplished by intelligent control algorithms and/or parameter settings for controllable assets in a data center such as IT load, cooling load, UPS, protection settings, and distributed energy sources such as BESS and generators. The Verrus™ StabiliGrid™ data center architecture involves four steps for data center response that improve grid resilience:

1. Grid contingency event detection. Uses high-resolution power quality monitoring to detect grid state (during events such as undervoltage, overvoltage, underfrequency, and overfrequency).

2. Grid-resilient protection settings. POI settings that allow extended ride-through/grid- connected operation of the data center during the grid contingency, reducing the probability of an islanding event.

3. Control of assets. Depending on detection of grid event, enables grid-state-driven autonomous dispatch of the asset to improve grid resiliency (for example, reduce power draw from the grid during an undervoltage event or absorb more power from the grid during an overvoltage event).

4. Post-grid event response. Post-grid recovery and following a grid contingency event, coordinates data center assets to present firm load to the grid more quickly, similar to the levels before the grid contingency event.

PDF page 15

5
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. Results

Verrus explored the real-life incident shown in Figure 1 in its controller hardware in the loop (C- HIL) setup at the National Laboratory of the Rockies (NLR) to demonstrate the effectiveness of our data center design with large-scale BESS and Verrus StabiliGrid (applicable features described previously) in responding to the cascaded grid undervoltage events. The C-HIL setup is developed in the Advanced Research on Integrated Energy Systems virtual emulation environment at NLR and is based on a digital real-time simulation platform (Vaidhynathan et al. 2025).

Note although we present results from undervoltage events, the Verrus StabiliGrid design can contribute to grid resilience during other types of short-duration grid contingencies such as overvoltage, overfrequency, and underfrequency. Our work with NLR instantiates the previous four-step strategy for data centers to ride through short-duration grid contingencies (~ seconds) and provide grid support. Controllable assets used are BESS and UPS. Results from the undervoltage grid contingency event of Figure 1 are presented in Table 1. Table 1. Undervoltage Grid Contingency Event

1
Grid contingency event
detection
High-resolution power quality monitoring is used to rapidly detect the
grid’s state (e.g., undervoltage, overfrequency).
Use of protection relays and/or advanced power quality monitoring
capable of millisecond resolution sampling with communication
capabilities such as IEC61850.
Provides the necessary “fast” input signal for controllable assets such as the BESS and UPS to initiate a response.

In Figure 3a, the system simulates cascaded undervoltage events,
each dropping below 0.7 p.u., and initiates automatic mitigation
through Verrus StabiliGrid.
2
Grid-resilient protection
settings
Implementing POI protection settings aligned with standards such as
IEEE 1547 to enable “plant” ride-through response.
This crucial step changes the data center’s default behavior from
immediate disconnection (islanding) during a short fault to extended
ride-through/grid-connected operation, allowing a grid-resilience-
improving response to function.
Unlike conventional disturbance-count schemes that trigger lockout
after three undervoltage events, the adaptive logic within Verrus
StabiliGrid dynamically evaluates voltage magnitude, recovery rate,
and event duration to prevent premature disconnection during both
undervoltage and overvoltage transients.
3
Control of assets (during
undervoltage grid
contingency)
As shown in Figure 3b, the total power drawn from the grid is
momentarily reduced during the undervoltage events, stabilizing grid
loading.
The BESS discharges in volt-watt mode, supplying power to
compensate for voltage sags and offset the drop in utility import.
Simultaneously, UPS maintains continuous support for IT loads,
ensuring operational integrity as grid voltage fluctuates.
This controlled BESS discharge during undervoltage event minimizes
the net power imbalance seen by the grid and prevents cascading
instability.

PDF page 16

6
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. 4

Post-grid event response
BESS controls are modified to have UPS awareness.
As soon as grid voltage returns to a nominal state, the BESS begins
charging and continues until the IT load is no longer relying on the
UPS.
In Figure 3d, the data center’s total grid import returns to pre-fault
levels within 100 milliseconds of voltage normalization.
This immediate restoration of firm load prevents secondary
overvoltage or oscillation events and supports grid recovery
dynamics.

Next, we show the four-step framework also enables ride-through capabilities for overvoltage events. Because of the lack of real-life overvoltage events, we look at a synthetic case of overvoltage to 1.1 p.u. in the grid for 1-second duration (see Table 2).

PDF page 17

7
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications.

(a)

(b)

(c)

(d) Figure 3. Coordinated response of a BESS-enabled data center during repeated undervoltage events (a; top) Grid voltage: Undervoltage events, each dropping below 0.7 p.u., detected within a 60-s window; (b) Utility power import: Controlled reduction in grid power draw during undervoltages and rapid (<100-ms) restoration to pre- fault levels once voltage normalizes; (c) BESS output power: BESS operating in volt-watt mode discharges to offset grid voltage dips, then transitions to controlled charging post-recovery in coordination with UPS hand-back; (d;) Data center UPS load: UPS provides transient support for IT loads during grid disturbances, maintaining uninterrupted operation and enabling seamless load transfer back to grid power.

PDF page 18

8
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. Table 2. Overvoltage Grid Contingency Event

1
Grid contingency event
detection
As shown in Figure 4a, illustrates the overvoltage scenario reaching 1.1 p.u. for a sustained 1-s period.

Upon detection, Verrus StabiliGrid activates the grid voltage support sequence, commanding the BESS to absorb excess grid energy to restore nominal voltage levels.

2
Grid-resilient protection
settings
The POI settings prevent unnecessary islanding during “short” overvoltage peaks.

By allowing ride-through, the data center remains grid-connected long enough for StabiliGrid to stabilize the voltage.

3
Control of assets (during
undervoltage grid
contingency)
Figure 4b and 4c illustrate the overvoltage response, where the BESS transitions into power absorption mode, drawing controlled power from the grid to support the voltage rise on the grid. The UPS supports the IT loads during the overvoltage event with no interruption or power quality degradation.

4
Post-grid event
response
Figure 4b shows a similar smooth recovery following the overvoltage event with no secondary oscillations or overshoot.

PDF page 19

9
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications.

(a)

(b)

(c)

(d) Figure 4. Coordinated response of a BESS-enabled data center during an overvoltage event (a; top) Grid voltage: A transient overvoltage reaching approximately 1.1 p.u., sustained for ~1 s before returning to nominal levels; (b) Utility power draw: The BESS operating in volt-watt mode charges to offset grid overvoltage, then transitions to controlled charging post-recovery in coordination with UPS hand-back; (c) BESS output power: The BESS transitions to absorption mode (negative power), dynamically drawing excess energy from the grid in proportion to the voltage deviation and gradually tapering as the voltage normalizes; (d; bottom) Data center UPS load: UPS provides transient support for IT loads during grid disturbances, maintaining uninterrupted operation and enabling seamless load transfer back to grid power.

PDF page 20

10
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. Conclusion

Through this coordinated strategy implemented in Verrus StabiliGrid, the data center achieves fault ride-through and rapid recovery for both undervoltage and overvoltage conditions without triggering protection lockouts. The digital real-time simulations demonstrate by synchronizing BESS, UPS, and protection logic behavior, the data center transitions from being a disturbance- sensitive load to an active, grid-supporting participant—a key requirement for future grid- integrated data center operations.

PDF page 21

11
This report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. References

Electric Reliability Council of Texas (ERCOT). 2025. “Large Electronic Load Ride-Through Requirements. www.ercot.com/files/docs/2025/12/01/6.2-NOGRR282-Large-Electronic-Load- Ride-Through-Requirements-and-NPRR1308.pdf. Austin, Texas.

North American Electric Reliability Corporation (NERC). 2025. “Incident Review: Considering Simultaneous Voltage-Sensitive Load Reductions.” Washington, D.C.

www.nerc.com/globalassets/our-work/reports/event-
reports/incident_review_large_load_loss.pdf.
Vaidhynathan, Deepthi, Kumaraguru Prabakar, Gregory Martin, Anand Ramesh, Ben Wheeler, Christopher Coco, Jimmy Clidaras, Matthieu Monsch, Sangsun Kim, Saurav Talukdar, and Shilpa Marti. 2025. Vulcan Test Platform: Demonstrating the Data Center as a Flexible Grid Asset. Golden, Colorado: National Laboratory of the Rockies.

docs.nlr.gov/docs/fy25osti/94844.pdf.