ER26-3650-000 · 2026-09-18 · Verrus LLC

Comments of Verrus LLC in Support of Midcontinent Independent System Operator, Inc.'s proposed Interconnection Reliability Requirements for Large Loads

Text extracted from the eLibrary original (SHA-256 816a9da2c772e8ec…). Download the original from the official source.

Contents · 11 sections
  1. I. BACKGROUND AND SUMMARY OF POSITION p. 1
  2. II. COMMENTS p. 2
  3. A. MISO’s Risk-Scaled Framework Reasonably Targets Requirements at the Loads That p. 2
  4. B. Verrus Supports Establishing Core Obligations in the Tariff While Reserving p. 2
  5. C. Advanced Computational Loads Are Capable of Actively Supporting Grid Reliability p. 3
  6. D. FERC Action on MISO’s Reliability Requirements Should Be Harmonized with the p. 3
  7. E. MISO’s p. 4
  8. III. CONCLUSION p. 5
  9. Attachment A: Talukdar et al., Mitigating Data Center Impact on Grid Stability: A Coordinated p. 5
  10. Background p. 11
  11. Conclusion p. 20

Read topic-matched comments in ER26-3650

Topics in the text: Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

ER26-3650-000 for Large Loads ) COMMENTS OF VERRUS, LLC IN SUPPORT OF MISO'S INTERCONNECTION RELIABILITY REQUIREMENTS FOR LARGE LOADS Pursuant to Rule 213 of the Commission’s Rules of Practice and Procedure1, Verrus LLC2 ("Verrus") respectfully submits these comments in support of the…
Read this passage

I. BACKGROUND AND SUMMARY OF POSITION

printed heading · Topic match: Filing procedure

As explained below, Verrus (A) supports MISO’s risk-scaled approach to applicability; (B) supports MISO’s choice to establish core obligations in the Tariff, while reserving implementation detail to the Business Practices Manual (“BPM”) and its ongoing stakeholder process; (C) offers its own…
Read this passage

II. COMMENTS

printed heading

II.
Read this passage

A. MISO’s Risk-Scaled Framework Reasonably Targets Requirements at the Loads That

printed heading

MISO’s Risk-Scaled Framework Reasonably Targets Requirements at the Loads That Present Reliability Risk Verrus supports MISO’s determination to apply the full suite of PMU, ramp, and ride-through requirements only to the Computational Load subset of Large Load, while applying visibility…
Read this passage

B. Verrus Supports Establishing Core Obligations in the Tariff While Reserving

printed heading

B.
Read this passage

C. Advanced Computational Loads Are Capable of Actively Supporting Grid Reliability

printed heading

Advanced Computational Loads Are Capable of Actively Supporting Grid Reliability Verrus’ own facility design illustrates that computational loads that would be subject to MISO’s proposed requirements are not merely able to comply with them, but can affirmatively support system reliability.
Read this passage

D. FERC Action on MISO’s Reliability Requirements Should Be Harmonized with the

printed heading

D.
Read this passage

E. MISO’s

printed heading

E.
Read this passage

III. CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, Verrus respectfully requests that the Commission accept MISO’s filing in Docket No.
Read this passage

Attachment A: Talukdar et al., Mitigating Data Center Impact on Grid Stability: A Coordinated

printed heading

Attachment A: Talukdar et al., Mitigating Data Center Impact on Grid Stability: A Coordinated Control Strategy Using Verrus™ StabiliGrid™ Architecture (Feb. 2026) [to be appended]. 15Transmittal Letter at 30 (requesting an effective date of December 4, 2026). 5 The National Laboratory of the…
Read this passage

Table of Contents

printed heading

List of Figures Figure 1.
Read this passage

Background

printed heading

This “near miss” has become a primary case study for North American Electric Reliability Corporation and Institute of Electrical and Electronics Engineers (IEEE) working groups, driving new regulatory frameworks that treat data centers not just as passive customers, but as large, dynamic loads that…
Read this passage

Conclusion

printed heading

Conclusion Through this coordinated strategy implemented in Verrus StabiliGrid, the data center achieves fault ride-through and rapid recovery for both undervoltage and overvoltage conditions without triggering protection lockouts.