ER26-3650-000 · 2026-09-21 · Rowan Digital Infrastructure
Comments of Rowan Digital Infrastructure, LLC re the 08/28/2026 filing by Midcontinent Independent System Operator, Inc. proposing Interconnection…
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator,
Inc.
Docket No. ER26-3650-000
COMMENTS OF ROWAN DIGITAL INFRASTRUCTURE, LLC
Pursuant to Rule 211 of the Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.211, Rowan Digital Infrastructure, LLC ("Rowan") files these Comments, Request for Clarification, and Limited Protest, to the August 28, 2026 filing by the Midcontinent Independent System Operator, Inc. ("MISO") proposing Interconnection Reliability Requirements for Large Loads (the "IRR Proposal") in Docket No. ER26-3650-000. Rowan supports MISO's objective of reliably integrating large loads and requests targeted revisions to ensure that the obligations are clear, workable, and predictable, appropriately aligned with operational control, and supported by transparent compliance standards.
I. COMPLIANCE RESPONSIBILITY SHOULD ALIGN WITH OPERATIONAL CONTROL
Proposed Section 37A makes the Transmission Customer responsible for compliance. Compliance responsibility should be assigned to the entity that owns, operates, or controls the equipment, information, or operating function at issue. A Transmission Customer should not be held responsible or subject to enforcement for a function controlled by MISO, a Transmission Owner, or another entity, particularly where the Transmission Customer lacks the contractual or operational authority necessary to perform that function.
For Phasor Measurement Unit (“PMU”) equipment, proposed Section 37A.5 requires
installation by the Transmission Owner on its side of the Point of Withdrawal, at the Transmission Customer’s expense; the equipment becomes part of the Transmission Owner’s interconnection facilities, and the Transmission Owner provides the measurements to MISO. MISO should clarify that PMU siting, quantity, installation, testing, maintenance, operation, and data delivery are the Transmission Owner’s responsibilities, with cost responsibility addressed separately and any Transmission Customer costs limited to documented, reasonable costs directly attributable to the PMU facilities necessary to serve the applicable Large Load.
II. MISO SHOULD CLARIFY MODELING AND MODIFICATION REQUIREMENTS
Proposed Section 37A.2 requires verified electrical models and detailed Load profiles. MISO should identify with specificity the required load-flow and stability models customarily provided through interconnection studies, any additional model types, and the scope, format, granularity, and timing of any required detailed Load profiles, and should avoid duplicative submissions. The Tariff should also identify the applicable validation standard and distinguish information reasonably available to the Transmission Customer from information controlled by customers, equipment manufacturers, or other third parties.
MISO should also define “material modifications,” using objective, reliability-based criteria, establish specified and commercially reasonable review timelines, and limit prior approval to changes that are reasonably expected to materially affect Transmission System reliability. Routine maintenance, like-kind equipment replacement, and technology refreshes without such an effect should not be delayed or subjected to prior approval. At a minimum, the Tariff should provide an expedited review process and require MISO to identify the specific reliability concern supporting any denial or request for additional information.
PDF page 2
2
III. FORECASTING REQUIREMENTS SHOULD REFLECT AVAILABLE OPERATING INFORMATION
Proposed Section 37A.4 requires day-ahead and real-time Load Forecasts by the later of the Service Commencement Date or September 1, 2027. New and expanding facilities may lack representative operating history, and profiles may depend on tenant deployment, customer controlled operating decisions, and phased energization.
MISO should permit after-the-fact reporting where it satisfies the demonstrated reliability need. If prospective forecasts are required, MISO should define the required forecast horizon, data format, submission and accuracy standards, provide reasonable safe harbors during commissioning and phased energization, defer representative Load-profile requirements until sufficient operating history exists, and protect detailed operating data from unnecessary disclosure and limit its use to legitimate reliability purposes. Forecast accuracy should be evaluated in light of the information reasonably available to the Transmission Customer when the forecast is submitted, and good-faith forecast deviations should not constitute a violation if the Transmission Customer used the applicable forecasting methodology and the information reasonably available at the time.
IV. RAMP REQUIREMENTS NEED A CLEAR BASIS AND SHOULD RECOGNIZE NET RAMP-
SMOOTHING
Proposed Section 37A.7 applies ramp limits during stable-state transitions, measured in aggregate across applicable Points of Withdrawal, and allows eligible generation or other resources to provide ramp smoothing. MISO proposes initial limits of 30 MW per minute.
MISO should provide the technical and reliability basis for the proposed ramp limits and specify the applicable measurement methodology, including the measurement interval, treatment of measurement error, aggregation methodology, the circumstances constituting a stable state transition, and how local planning criteria will be considered. MISO should also confirm that onsite battery energy storage and other qualifying resources may provide ramp smoothing and that compliance will be assessed on a net basis at the applicable Points of Withdrawal. Any site-specific limit should be based on documented system conditions, provided to the affected Transmission Customer with the supporting basis before it becomes enforceable, and accompanied by a reasonable implementation period.
V. RIDE-THROUGH REQUIREMENTS SHOULD COORDINATE WITH EXISTING PROTECTION SCHEMES
Proposed Section 37A.6 requires Computational Load to remain connected during voltage and frequency disturbances within criteria established in the Business Practice Manual. MISO should place all material and operative performance criteria, measurement standards, exceptions, and compliance pathways in the Tariff or otherwise subject them to Commission review before they become enforceable. The Tariff should not permit a Business Practice Manual to create or materially expand a Transmission Customer's substantive compliance obligations.
MISO should explain how ride-through requirements will coordinate with approved under- voltage and under-frequency load-shedding schemes, equipment protection settings, Transmission Owner requirements, and other applicable reliability obligations. The framework should not require a Computational Load to remain connected when shedding under an applicable protection scheme is the reliability-supporting response, and compliance with an approved or required protection scheme should not constitute a violation of Section 37A.6.
VI. TRANSITION RELIEF SHOULD REFLECT ACTUAL PROJECT RELIANCE
The proposal fully exempts the portion of a Large Load with a Service Commencement Date on or before December 4, 2026. Loads meeting the MISO Transmission Expansion Plan/Expedited Project Review (“MTEP/EPR”) Condition remain subject to Sections 37A.1 through 37A.5 and 37A.8
PDF page 3
3
but are exempt from Sections 37A.6 and 37A.7. Certain projects submitted for Expedited Project Review from June 19 through October 31, 2026, may receive a waiver from Section 37A.6. Transition relief should also account for objective evidence of project maturity, reasonable reliance, and binding commitments made before the Tariff’s effective date, including executed interconnection, energy service, or transmission service agreements, material equipment procurement commitments, completed engineering, and construction activities. Eligibility should not turn solely on milestones controlled by a utility, MISO, or transmission provider, or on the timing of a third party's processing or approval. The Tariff should identify the required waiver documentation, an objective standard for approval, commercially reasonable review timelines, and written decision criteria. MISO should also provide relief where compliance would require material redesign, replacement of previously procured equipment, or impairment of binding pre-effective date commitments without a demonstrated reliability necessity.
VII. CONCLUSION
Rowan respectfully requests that the Commission accept the IRR Proposal only subject to the targeted revisions described above, including revisions necessary to align compliance responsibility with operational control, establish objective and transparent compliance standards, coordinate potentially conflicting reliability requirements, and provide reasonable transition relief for projects undertaken in reliance on the existing framework.
Respectfully submitted,
ROWAN DIGITAL INFRASTRUCTURE, LLC
/s/ Tyler Petersen
Tyler Petersen
Director, Regulatory Affairs and Public Policy
1400 16th Street, Suite 330
Denver, Colorado 80202
tpetersen@rowan.digital
Dated: September 18, 2026