ER26-3650-000 · 2026-09-21 · Rowan Digital Infrastructure

Comments of Rowan Digital Infrastructure, LLC re the 08/28/2026 filing by Midcontinent Independent System Operator, Inc. proposing Interconnection…

Text extracted from the eLibrary original (SHA-256 b67f1ad0fbd8e177…). Download the original from the official source.

Contents · 7 sections
  1. I. COMPLIANCE RESPONSIBILITY SHOULD ALIGN WITH OPERATIONAL CONTROL p. 1
  2. II. MISO SHOULD CLARIFY MODELING AND MODIFICATION REQUIREMENTS p. 1
  3. III. FORECASTING REQUIREMENTS SHOULD REFLECT AVAILABLE OPERATING INFORMATION p. 2
  4. IV. RAMP REQUIREMENTS NEED A CLEAR BASIS AND SHOULD RECOGNIZE NET RAMP- p. 2
  5. V. RIDE-THROUGH REQUIREMENTS SHOULD COORDINATE WITH EXISTING PROTECTION SCHEMES p. 2
  6. VI. TRANSITION RELIEF SHOULD REFLECT ACTUAL PROJECT RELIANCE p. 2
  7. VII. CONCLUSION p. 3

Read topic-matched comments in ER26-3650

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

Rowan supports MISO's objective of reliably integrating large loads and requests targeted revisions to ensure that the obligations are clear, workable, and predictable, appropriately aligned with operational control, and supported by transparent compliance standards.
Read this passage

I. COMPLIANCE RESPONSIBILITY SHOULD ALIGN WITH OPERATIONAL CONTROL

printed heading

COMPLIANCE RESPONSIBILITY SHOULD ALIGN WITH OPERATIONAL CONTROL Proposed Section 37A makes the Transmission Customer responsible for compliance.
Read this passage

II. MISO SHOULD CLARIFY MODELING AND MODIFICATION REQUIREMENTS

printed heading

MISO SHOULD CLARIFY MODELING AND MODIFICATION REQUIREMENTS Proposed Section 37A.2 requires verified electrical models and detailed Load profiles.
Read this passage

III. FORECASTING REQUIREMENTS SHOULD REFLECT AVAILABLE OPERATING INFORMATION

printed heading

FORECASTING REQUIREMENTS SHOULD REFLECT AVAILABLE OPERATING INFORMATION Proposed Section 37A.4 requires day-ahead and real-time Load Forecasts by the later of the Service Commencement Date or September 1, 2027.
Read this passage

IV. RAMP REQUIREMENTS NEED A CLEAR BASIS AND SHOULD RECOGNIZE NET RAMP-

printed heading

MISO proposes initial limits of 30 MW per minute.
Read this passage

V. RIDE-THROUGH REQUIREMENTS SHOULD COORDINATE WITH EXISTING PROTECTION SCHEMES

printed heading

RIDE-THROUGH REQUIREMENTS SHOULD COORDINATE WITH EXISTING PROTECTION SCHEMES Proposed Section 37A.6 requires Computational Load to remain connected during voltage and frequency disturbances within criteria established in the Business Practice Manual.
Read this passage

VI. TRANSITION RELIEF SHOULD REFLECT ACTUAL PROJECT RELIANCE

printed heading

TRANSITION RELIEF SHOULD REFLECT ACTUAL PROJECT RELIANCE The proposal fully exempts the portion of a Large Load with a Service Commencement Date on or before December 4, 2026.
Read this passage

VII. CONCLUSION

printed heading

CONCLUSION Rowan respectfully requests that the Commission accept the IRR Proposal only subject to the targeted revisions described above, including revisions necessary to align compliance responsibility with operational control, establish objective and transparent compliance standards, coordinate…
Read this passage