ER26-3380-000 · 2026-09-22 · American Transmission Systems, Inc., Mid-Atlantic Interstate Transmission and 6 others

Motion for Leave to Answer and Answer of Indicated PJM Transmission Owners to the Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. filed…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
)
)
)
)
)
)
)
)
)
Docket No. ER26-3380-000
INDICATED PJM TRANSMISSION OWNERS’ MOTION FOR LEAVE TO
ANSWER AND ANSWER TO THE ANSWER OF PJM INTERCONNECTION,
L.L.C.
Pursuant to Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure,1 the Indicated PJM Transmission Owners2 respectfully move for leave to submit this answer in response to the answer of PJM Interconnection, L.L.C. (“PJM”) filed on September 10, 2026.3 This proposed answer addresses a narrow but important issue:  whether it violates cost- causation principles to impose new exit fees related to a generation/capacity product on a transmission owner (“TO”) as opposed to a load-serving entity (“LSE”).  PJM’s answer does not confront that issue or the arguments raised by the Indicated PJM Transmission Owners in their initial protest in the instant proceeding.  PJM does, however, concede that the cause of

1 18 C.F.R. § 385.213(a)(2) (2026).
2 The Indicated PJM Transmission Owners are American Transmission Systems, Inc., Mid-Atlantic Interstate Transmission, LLC, Trans-Allegheny Interstate Line Company, Keystone Appalachian Transmission Company, Jersey Central Power & Light Company, Monongahela Power Company, and The Potomac Edison Company (collectively, “The FirstEnergy Transmission Companies”), and Duquesne Light Company. 3   See Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26- 3380-000 (Sept. 10, 2026) (“PJM Answer”).

PDF page 2

2
the Reliability Backstop Procurement (“RBP”) is loads (served by LSEs).4  And, thus, any and all costs associated with the RBP must be borne by LSEs, and not TOs.

Accordingly, the Commission should not allow the RBP to go into effect without removing its Exit Amendment that imposes exit fees on TOs.

I. MOTION FOR LEAVE TO ANSWER
Just as the Commission’s rules do not permit as of right PJM’s proposed answer to the various protests in this Docket, they do not permit as of right the Indicated PJM Transmission Owners’ proposed answer to PJM’s proposed answer.5  The Commission nonetheless retains authority to permit such an answer in its discretion.  The Commission should do so here because the Indicated PJM Transmission Owners’ proposed answer highlights an important concession in PJM’s proposed answer that bears on cost-causation principles that PJM otherwise does not address.

II. PROPOSED ANSWER
The Indicated PJM Transmission Owners’ protest explained that, under cost-causation principles and the Commission’s precedent applying them, RBP-related exit fees cannot be imposed on TOs as opposed to LSEs:  “The Commission has never allocated generation- and capacity-related costs to TOs and, more specifically, the Exit Amendment [of the RBP] conflicts with highly relevant precedent in the Duquesne Light Co. proceeding where the

4 PJM Answer at 86 (“Given that the RBP is to address the capacity shortfall from the 2027/2028 and 2028/2029 RPM Auctions, which is primarily driven by the unprecedented addition of large loads (in the form of Load Adjustments), the loads causing the RBP—through their LSEs—should bear the costs of the RBP Resources throughout the full term.”) (emphasis added).
5   See 18 C.F.R. § 385.213(a)(2).

PDF page 3

3
Commission notably did not apply generation-related costs to an exiting TO in its capacity as a TO,” but only in its capacity as an LSE.6

PJM’s answer does not address this argument or the relevant portion of Duquesne Light Company.7  It does, however, concede that loads and LSEs are the causes of the RBP:  “Given that the RBP is to address the capacity shortfall from the 2027/2028 and 2028/2029 RPM Auctions, which is primarily driven by the unprecedented addition of large loads (in the form of Load Adjustments), the loads causing the RBP—through their LSEs—should bear the costs of the RBP Resources throughout the full term.”8 (emphasis added).

PJM does not and cannot explain how it is consistent with Duquesne Light Company and cost-causation principles to impose RBP exit fees on a TO as opposed to an LSE.  At a minimum, therefore, even if all of the RBP’s other deficiencies could be overlooked, the Commission should strip out the exit fee provision before the RBP is allowed to go into effect.

III. CONCLUSION

For the foregoing reasons, the Indicated PJM Transmission Owners respectfully request that the Commission accept this answer and reject PJM’s proposed Exit Amendment. Dated:  September 22, 2026

Respectfully submitted,
/s/ Evan K. Dean

Evan K. Dean
Managing Counsel, Transmission Rates &
Services
FirstEnergy Service Company
341 White Pond Drive
Akron, Ohio 44320
/s/ Sanford I. Weisburst

Sanford I. Weisburst
Matthew Meyer
Madeleine Fleming
QUINN EMANUEL URQUHART
& SULLIVAN, LLP
295 Fifth Avenue, Ninth Floor

6   See Protest of the Indicated PJM Transmission Owners at 2 & n.3, Docket No. ER26-3380-000 (Aug. 21, 2026) (citing Duquesne Light Co., 122 FERC ¶ 61,039 (2008)); see also id. at 8-10.
7   See PJM Answer at 103-04 (referring interchangeably to an “LSE” and “Transmission Owner” and failing to distinguish between the two for purposes of responsibility for generation/capacity-related costs).
8   PJM Answer at 86 (emphasis added).

PDF page 4

4
Telephone: 330-620-9585
edean@firstenergycorp.com
New York, New York 10016
Telephone: 212-849-7000
Facsimile: 212-849-7100
sandyweisburst@quinnemanuel.com
matthewmeyer@quinnemanuel.com
madeleinefleming@quinnemanuel.com

/s/ Anthony Alden

Anthony Alden
QUINN EMANUEL URQUHART
 & SULLIVAN, LLP
865 S Figueroa St, 10th Floor
Los Angeles, CA 90017
Telephone: 213-443-3000
anthonyalden@quinnemanuel.com
Counsel for the FirstEnergy Transmission Companies

/s/ Michael Brechlin

Michael Brechlin
Manager Asst GC - Regulatory Law State
Regulatory
Duquesne Light Company
Nova Place
100 South Commons, Suite 118
Mail Drop OGC-L1
Pittsburgh, PA 15212
Telephone: 412-393-6431
mbrechlin@duqlight.com

Counsel for Duquesne Light Company

PDF page 5

5
CERTIFICATE OF SERVICE

I hereby certify that I have served the foregoing document upon all parties listed on the official service list for the captioned proceeding in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.

Dated at New York, NY, this 22nd day of September, 2026.

/s/ Sanford I. Weisburst
Sanford I. Weisburst
QUINN EMANUEL URQUHART
& SULLIVAN, LLP
295 Fifth Avenue, Ninth Floor
New York, New York 10016
Telephone: 212-849-7000
Facsimile: 212-849-7100
sandyweisburst@quinnemanuel.com