ER26-3380-000 · 2026-09-23 · Northern Virginia Electric Cooperative, Inc.
Motion for Leave to Answer and Answer of Northern Virginia Electric Cooperative, Inc. to the Answer et al. of PJM Interconnection, L.L.C. filed on 09/10/2026
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
)
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC. TO MOTION FOR LEAVE
TO ANSWER AND ANSWER OF PJM INTERCONNECTION, L.L.C.
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) respectfully submits this motion for leave to answer and answer to PJM Interconnection, L.L.C.’s (“PJM”) motion for leave to answer and answer (“PJM Answer”)2 to NOVEC’s August 21, 2026, protest (“NOVEC Protest”)3 of the July 31, 2026, filing by PJM to revise its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish the Reliability Backstop Procurement (“RBP”).4
For the reasons set forth herein and in the NOVEC Protest, the Commission should reject the RBP as unjust and unreasonable. If the Commission does not reject the RBP, it should require revisions on compliance to eliminate or substantially reduce the nearly $2 billion collateral requirement that the RBP Proposal would impose on NOVEC, or set the collateral requirement for settlement and hearing judge procedures as suggested by PJM.51 18 C.F.R. §§ 385.212-213.2 PJM Interconnection, L.L.C., Motion for Leave to Answer and Answer, Docket No. ER26-3380-000 (Sep. 10, 2026) (Accession No. 20260910-5296) (“PJM Answer”).3 Northern Virginia Electric Cooperative, Inc., Protest, Docket No. ER26-3380-000 (Aug. 21, 2026) (Accession No. 20260821-5307) (“NOVEC Protest”).4 PJM Interconnection, L.L.C., Reliability Backstop Procurement, Docket No. ER26-3380-000 (July 31, 2026) (Accession No. 20260731-5214) (“RBP Proposal”).5 PJM Answer at 92-93.
PDF page 2
2
I. MOTION FOR LEAVE TO ANSWER
NOVEC respectfully requests leave to submit this answer. The Commission regularly allows answers for good cause shown, such as when the answers help ensure a more accurate and complete record, clarify the issues, or provide useful and relevant information that will assist the Commission in its deliberative process.6 This answer will correct PJM’s mischaracterizations of the context of the RBP framework, the unjust and unreasonable character of the RBP proposal, and the need to substantially revise PJM’s proposed collateral requirements for the Load Serving Entities (“LSE”) RBP Buyers. In addition, this answer provides useful and relevant information that will assist the Commission in its deliberative process. To the extent that this answer does not address an issue raised in PJM’s answer, that should not be construed as agreement with PJM.
II. ANSWER TO PJM’S ANSWER TO THE PROTESTS AND COMMENTS ON
THE RBP PROPOSAL
A. Mr. Coscia’s Supplemental Affidavit explains the many flaws in PJM’s proposed collateral requirement that cause that proposal to be disconnected from its stated purpose and fundamentally onerous and not just or reasonable.
With this answer, NOVEC includes a supplemental affidavit from Mr. Coscia.7 Mr.
Coscia approaches the PJM collateral requirement from a methodological perspective.8 He points out that the amount of collateral should be related to the risk that an LSE fails to pay an RBP Charge and PJM’s methodology does not secure against that loss because it is focused on the risk that a large load fails to materialize.9 Mr. Coscia challenges PJM’s use of a uniform Credit
6 See, e.g., City Utils. of Springfield, Mo. v. Sw. Power Pool, Inc., 168 FERC ¶ 61,085, P 51 (2019) (“We accept [the] answers…because they have provided information that assisted us in our decision-making process.”), order on reh’g & clarification, 170 FERC ¶ 61,024 (2020); Morgan Stanley Capital Grp., Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 FERC ¶ 61,017, at 61,036 (2000) (accepting an answer as “helpful in the development of the record”). See also, Hawtree Creek Farm Solar, LLC, 179 FERC ¶ 61,048, P 21 (2022); California Ridge Wind Energy, LLC, 175 FERC ¶ 61,110, P 25 (2021); Pleinmont Solar 1, LLC, 173 FERC ¶ 61,126, P 18 (2020).7 See Supplemental Coscia Affidavit included with the instant filing.8 Id. P 8.9 Id. PP 9-16.
PDF page 3
3
Rate.10 He then turns to a discussion of the opt-out and the undefined MW amount to be secured.11 The Commission should also eliminate the resulting subsidization of the PJM capacity market by NOVEC and a relatively small number of other LSEs that would be primarily responsible for providing financial security for the contracts that PJM would enter into with RBP Resources. Mr. Coscia reviews PJM’s explanation of the collateral overlap between the RBP Charge collateral and the Peak Market Activity under Attachment Q.12 He concludes his affidavit by addressing the need for a reduction mechanism for the collateral obligation, discussing the stakeholder process, and opining on the need for a comprehensive overhaul of the credit methodology in the hearing and settlement judge procedures.13
B. The capacity shortfall experienced by PJM resulted from a combination of causes in addition to growth of large customer load.
PJM recognized in its original filing that the capacity shortfall it is seeking to address is the result of many causes, stating that “it is well-documented and recognized that supply and demand in the PJM Region have converged, as a significant portion of PJM’s thermal generation fleet have retired while replacement resources are arriving at a slower pace than the unprecedented load growth” and “[t]ogether, these factors have strained the RPM Auction’s ability to procure sufficient capacity to meet the PJM Region Reliability Requirement in recent capacity auctions.”14 Despite the other causes, PJM in answering NOVEC now maintains that “[t]he entire PJM Region is facing a capacity shortfall because entities like NOVEC contracted to serve new large loads on an unprecedented scale at an extremely rapid pace—without
10 Id. PP 17-25.11 Id. PP 26-37. 12 Id. PP 38-45.13 Id. PP 46-61.14 RBP Proposal at 28.
PDF page 4
4
requiring any associated new capacity.”15 PJM’s new interpretation of the context in which it urges the Commission to consider its filing is premised on two incorrect presumptions.
First, NOVEC does not have any control over which customers receive electric service.
Nor does NOVEC have a say in which customers choose to site in NOVEC’s service territory. NOVEC has an obligation under state law to serve its load, and NOVEC follows state law.
Second, unlike Regional Transmission Organizations (“RTO”) like the Midcontinent
Independent System Operator, Inc. (“MISO”), where the capacity market is a backup mechanism and LSEs are primarily responsible for meeting their resource adequacy requirements through bilateral arrangements,16 in PJM the Reliability Pricing Model (“RPM”) is the primary
mechanism for LSEs to procure capacity. The Base Residual Auction in the RPM may allow LSEs to bilaterally contract for their capacity needs,17 but PJM operates the RPM to “ensure that enough capacity is procured, at a reasonable cost, to maintain reliable grid operations” and the rules do not indicate a maximum amount that LSEs can receive from PJM’s relevant capacity auctions.18
For most utilities, the primary option is to buy capacity in the RPM, and there is no
requirement for an LSE to bring its own new capacity.19 There is no basis for PJM’s criticism
15 PJM Answer at 89.16 See Midcontinent Indep. Sys. Operator, Inc., 170 FERC ¶ 61,215, P 13 (2020) (“In other words, unlike the centralized capacity constructs used in the Eastern RTOs/ISOs, MISO’s Auction is not—and has never been—the primary mechanism for its LSEs to procure capacity.”) (emphasis in original).17 PJM Business Practice Manual No. 18 at § 1.2.1 (“Under RPM, each LSE that serves load in a PJM Zone during the Delivery Year shall be responsible for paying a Locational Reliability Charge equal to their Daily Unforced Capacity Obligation in the Zone multiplied by the Final Zonal Capacity Price applicable to that Zone. LSEs may choose to hedge their Locational Reliability Charge obligations by directly offering and clearing resources in the Base Residual Auction and Incremental Auctions or by designating self-supplied resources (resources directly owned or resources contracted for through unit-specific bilateral purchases) as self-scheduled to cover their obligation in the Base Residual Auction.”) (emphasis added).18 PJM Interconnection, L.L.C., 190 FERC ¶ 61,084, P 3 (2025).19 PJM is now seeking to impose such an obligation through the pending Interim Resource Adequacy Service (“IRAS”) filing in Docket No. ER26-3515. PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry, Docket No. ER26-3515-000 (Aug. 13, 2026) (Accession No. 20260813-5118) (“IRAS Filing”).
PDF page 5
5
that NOVEC did not secure its own generation, because NOVEC expected to procure capacity through the RPM as intended by the PJM Tariff. That does not make the shortfall NOVEC’s fault, or even its responsibility, as PJM now asserts.
By filing the RBP, PJM is conceding that its RPM did not function as intended because there is a shortfall. The Commission should consider the RBP Proposal in light of the true context, namely that there are multiple causes of the present shortfall, that NOVEC reasonably relied on the RPM to procure its capacity, and that NOVEC is being forced to finance the construction of generation that will provide benefit to the region, as well as post an excessive collateral obligation to do so.
C. The Commission should exercise its authority under NRG to require PJM to adopt the voluntary RBP framework approved in the stakeholder process, or in the
alternative, reject the RBP Proposal with guidance on filing a voluntary iteration.
The Commission should exercise its authority under NRG to require PJM to revise its RBP framework to conform to the voluntary, subscription-based, stakeholder-approved model, as NOVEC argued in its protest.20 PJM’s arguments do not establish that a voluntary model would not work. PJM contends that “a voluntary, subscription-based framework would not procure sufficient new capacity to meet demand and, in fact, would be highly likely to fail to cover that shortfall.”21 By way of evidence, PJM asserts that a voluntary framework is the “status quo”22 and that under the status quo, LSEs have not entered into bilateral agreements.23 PJM’s observation that LSEs have not entered into bilateral agreements prior to the filing of the RBP is immaterial and irrelevant. As NOVEC explained above, the RPM does not depend on bilateral
20 NOVEC Protest at 24-26.21 PJM Answer at 16.22 Id. at 14.23 Id. at 15.
PDF page 6
6
arrangements. The RPM is intended to set prices needed to attract adequate generation and should not have to rely on LSEs promising out-of-market payments to function.
That does not mean that the paradigm might not be subject to change on a going-forward basis and, indeed it should be subject to change if it is not working as currently designed. But the possible need for change is not grounds to criticize or blame market participants for conducting business in accordance with the current paradigm.
As NOVEC explained in its protest, the voluntary model would allow the load to
participate in the RBP or be interruptible.24 PJM’s own IRAS filing in Docket No. ER26-3515 is premised on the same mechanism to incentivize LSEs and load to “Bring Your Own New
Capacity” (“BYONC”).25 Under IRAS, if new large loads do not participate with BYONC, they are subject to curtailment if PJM would order it and, to avoid the risk of curtailment, the new large loads are expected to bring their own new generation resources. Thus, it is puzzling why PJM maintains that a voluntary RBP model would not work but maintains that its IRAS proposal is just and reasonable and effective.
In addition, a voluntary RBP model is more likely to be effective because many
customers have already agreed to bear their costs through the Ratepayer Protection Pledge. While NOVEC is not, contrary to PJM’s assertion,26 a signatory to the Ratepayer Protection Pledge, NOVEC is supportive of the data center industry’s efforts to hold retail customers
24 NOVEC Protest at 25 (“In NOVEC’s view, that control was critical to the success of the RBP process, which should embody a bottom-up, rather than a top-down approach. The bottom-up process gives truly interested developers the option to subscribe to pay the RBP costs rather than accept an interruptible form of service which PJM has proposed in Docket No. ER26-3515 (the Interim Resource Adequacy Service or ‘IRAS’). Contrary to the PJM Board’s determination, the voluntary subscription framework would provide sufficient assurance that capacity equal to the identified near-term shortfall would actually be procured. Paired with IRAS, committed load is adequately incentivized to participate to avoid an interruptible service—their business models rely on reliable service.”).25 See IRAS Filing at 23.26 PJM Answer at 59.
PDF page 7
7
harmless by funding their own power and transmission needs. As PJM points out, many such entities have committed to “‘build, bring, or buy the new generation resources and electricity needed to satisfy their new energy demands, paying the full cost of those resources whether by building, or buying from, new or otherwise additive power plants.’”27 Participating in a voluntary RBP framework would be a natural choice to accomplish what these customers have already agreed to do.
PJM manifests a double standard in its comparison of a voluntary framework to its
preferred RBP alternative. PJM specifically criticizes NOVEC for recognizing that a voluntary RBP may not procure the entire shortfall,28 arguing that NOVEC’s perspective “would
effectively contradict the fundamental core reliability goal of the RBP to acquire the capacity shortfall….”29 However, in its transmittal letter, PJM conceded that because “RBP Resources shall not be partially cleared…there exists the possibility that PJM may clear a set of resources with a cumulative RBP UCAP MW total that does not exactly match the Final RBP Target.”30 In other words, PJM may not procure the entire shortfall through its own process. NOVEC should also add that, because of the expedited time frame, it is possible that an insufficient number of resources may bid at the required price level.31 It is unclear to NOVEC why PJM is willing to
27 Id. (quoting Ratepayer Protection Pledge, The White House (Mar. 4, 2026),
https://www.whitehouse.gov/releases/2026/03/ ratepayer-protection-pledge/ [https://perma.cc/N8PH-K82T]).
28 Without acknowledging NOVEC’s observation that the IRAS would mitigate the consequences of any failure to procure the entire MW target through the voluntary RBP. NOVEC Protest at 25-26. 29 PJM Answer at 16-17.30 RBP Proposal at 79.31 NOVEC Protest at 5 (“PJM’s timeline raises additional concerns that adversely affect the market. The success of the RBP depends on generators offering in sufficient quantities and at competitive prices. With only three weeks to make informed decisions based on the final, effective version of the RBP, some participants may not be able to prepare offers in time to participate. Indeed, PJM has requested FERC approval by September 29 so it can begin the RBP auction on September 30, which means that participants are expected to make decisions with impacts that last the better part of two decades in a span of a few weeks and without knowing what the actual rules or approved state regulator allocations will be.”).
PDF page 8
8
bear the risk that its preferred RBP alternative does not cover the shortfall in capacity, but views any risk that the voluntary model does not procure the total shortfall as a fatal flaw.
The imposition of a voluntary process would also eliminate the contradiction of PJM’s opt-out mechanism. As Mr. Coscia explains in his supplemental affidavit, PJM justifies its opt- out provision as addressing a limited regulatory gap faced by non-public utilities whose rates are not regulated by the states.32 In its answer, PJM argues that those customers are at the risk of an “overbuy” if large loads fail to materialize in the absence of state regulation.33 But the result is that one Virginia cooperative, Old Dominion Electric Cooperative, could opt out but another, NOVEC, could not.34 NOVEC’s exposure is not reduced by being state regulated because its customers may still have to absorb the cost of an overbuy notwithstanding state regulation.35 Mr. Coscia opines that “the economic rationale for the opt-out would be stronger if eligibility tracked the overbuy risk PJM identifies rather than state rate-regulatory status standing alone.”36 There are two ways to effectuate Mr. Coscia’s opinion and align risk with the opt-out and NOVEC would support either. The Commission could extend the opt-out to all non-public utilities in recognition of the presence of the overbuy risk. Or the Commission could require PJM to adopt the voluntary, subscription-based RBP framework which would give all utilities and their customers the ability to manage their own exposure. The voluntary RBP framework eliminates the need for an opt-out by allowing utilities and their customers to enter arrangements that can effectively manage any overbuy risk.
32 Supplemental Coscia Affidavit at P 26.33 PJM Answer at 30.34 Supplemental Coscia Affidavit at PP 27-28.35 Id. P 29.36 Id. P 31.
PDF page 9
9
The Commission should “exercise its authority under NRG to implement the voluntary
subscription model the stakeholders approved as part of the CIFP process.”37 The PJM
stakeholders sent the PJM Board an unambiguous message by achieving a clear consensus on a single proposal from more than a dozen considered.38 PJM’s observation that some stakeholders have supported the filed iteration of the RBP does not detract from the consensus achieved by the stakeholders on the voluntary, subscription-based framework.39 PJM’s removal of the ability of LSEs to accept RBP obligations fundamentally undermined the RBP process, which was
intended to embody a bottom-up,40 rather than top-down approach, and was one part of an
interconnected series of proposals intended to comprehensively address PJM’s resource
adequacy challenges.41 The Commission should honor the consensus achieved by the
stakeholders rather than allow PJM to pick and choose proposals it likes without regard for the compromises that led to the whole package, a process that undermines trust in the stakeholder process.
D. The Commission should reject PJM’s argument that NOVEC misrepresents the
cost-allocation standard because the RBP filing violates the Commission’s cost-
causation principles.
NOVEC explained in its protest that the RBP violates the Commission’s cost-causation
principle because it would assign all costs to one cause of the capacity shortfall without
37 NOVEC Protest at 24.38 Id. 24-25.39 PJM Answer at 13.40 As Mr. Coscia explains in his supplemental affidavit, the voluntary RBP MWs would be fully secured and would not expose ratepayers to additional risk above PJM’s proposal. Supplemental Coscia Affidavit at P 58.41 NOVEC Protest at 25; East Kentucky Power Cooperative, Inc., Protest, Docket No. ER26-3380-000, at Attachment 1 Affidavit of Adam Bednarcyzk at P 16 (Aug. 21, 2026) (Accession No. 20260821-5322) (“EKPC Protest”) (“By contrast, PJM's filed proposal largely treats procurement, cost allocation, and the forthcoming IRAS process as separate constructs. PJM states that the RBP does not depend on the IRAS framework. That separation breaks the direct connection between the entity creating the incremental reliability need and the consequences of failing to mitigate that need. Unlike the Coalition proposal, the filing does not establish a unified framework that carries responsibility from procurement through settlement and operational consequences. As a result, it does not provide the same transparent and traceable path for ensuring that large-load customers and their suppliers remain reliability neutral.”).
PDF page 10
10
recognizing the impact of other causes, such as generation retirement driven by state policy choices,42 and because it creates benefits for other capacity customers in PJM by forcing generation subsidized by NOVEC to bid into the capacity market as a price-taker.43 As NOVEC clarified, “PJM’s requirement that RBP Resources offer at $0 can affect the RPM clearing price, and any resulting price reduction benefits capacity purchasers beyond the LSEs required to bear the incremental costs of supporting those resources.”44 The reasoning behind the premise is simple. The cost-causation principle requires the Commission to have “an articulable and plausible reason” to believe that the benefits are roughly commensurate with the costs.45
PJM argues that NOVEC “seeks to establish a false standard for cost allocation approaches.”46 PJM argues that “all approved rates reflect to some degree the costs actually caused by the customer who must pay them”47 and “[t]o the extent an entity causes the costs to be incurred, it will have to pay its share.”48 PJM stresses that the Commission is not required to ensure full or perfect cost causation,49 and argues that the RBP Proposal “easily meets this standard.”50 PJM argues that it meets this standard because it tracked the Load Adjustments to the zones/areas where they occurred and allocated the costs to the Electric Distributor zones and this was the most granular way available to PJM to allocate costs.51
Granularity is beside the point. PJM cannot assert that NOVEC has articulated a false standard because PJM did not acknowledge or even engage with NOVEC’s arguments. PJM did
42 NOVEC Protest at 9-14.43 Id. at 15-17.44 Id. at 17.45 Illinois Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009).46 PJM Answer at 62.47 Id. (quoting KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992) (internal citations omitted)).48 PJM Answer at 62.49 Id. (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 88 (D.C. Cir. 2014)).50 PJM Answer at 62.51 Id. at 62-63.
PDF page 11
11
not challenge NOVEC’s argument that there are other causes for the shortfall besides load growth or that other customers will benefit from NOVEC paying for generation to bid as a price- taker in the RPM. NOVEC pointed out that thousands of MWs of retirements were caused by state policies and that a reduction in generation is a key cause of the shortfall.52 Bidding as price- takers can cause lower RPM prices because those offers “crowd out other capacity that is priced at a higher, cost-based rate” and thereby produce a lower clearing price.53 PJM explained that to “the extent an entity causes the costs to be incurred, it will have to pay its share,” which is exactly how NOVEC described the cost-causation principle and why PJM’s proposed cost
allocation violates that principle.
The Commission “may never approve unjust and unreasonable rates by allocating costs to
those who reap little to no benefit…nor may it choose not to allocate costs to ‘those who cause the costs to be incurred and reap the resulting benefits.’”54 In other words, the Commission cannot approve a cost-allocation scheme that ignores beneficiaries and other causes of the shortfall. If it does not reject the RBP Proposal as unjust and unreasonable, the Commission should modify PJM’s cost-allocation approach to reflect the benefits received by the rest of PJM by adjusting the RBP Charges to account for those benefits and reducing the RBP collateral requirement to reflect those same benefits.
52 NOVEC Protest at 11.53 New Jersey Board of Public Utilities v. FERC, 744 F.3d 74, 85 (3d Cir. 2014). It goes without saying that in addition to the price depressive effect benefiting other customers, it also distorts the PJM capacity market signals by altering the price signals being sent. The Commission should not lose sight of the fact that a cost-based intervention is not going to solve the problems with PJM’s market structure. It becomes, as former Chairman Christie warned, another iteration of the “perpetual tweaking” needed to keep the RPM moving forward. NOVEC Protest at 13 (quoting Mark C. Christie, It’s Time to Reconsider Single-Clearing Price Mechanisms in U.S. Energy Markets, 44 Energy L.J. 1, 26 (2023)). Before the Commission approves another kludge for the RPM, it should consider, as discussed above, whether the voluntary option interfaces better with PJM’s market design. 54 El Paso Elec. Co. v. FERC, 76 F.4th 352, 362 (5th Cir. 2023) (quoting Nat’l Ass’n of Reg. Util. Comm’rs, 475 F.3d 1277, 1285 (D.C. Cir. 2007) (emphasis added)).
PDF page 12
12
E. The collateral requirement is unjust and unreasonable because it is duplicative, excessive, and the initial credit rate is insupportably high. The collateral requirement should be revised to allow other forms of collateral.
a. The collateral requirement is subjective, unduly discriminatory, and unjust and unreasonable because it is excessive.
PJM’s proposed collateral requirement is not just and reasonable. PJM asserts that its methodology strikes an appropriate balance between protecting PJM’s markets and ensuring market participants have adequate flexibility to manage their collateral requirements.55 PJM notes that the Commission has cautioned against overly conservative credit requirements that are poorly correlated to credit risk that would impose costs.56 PJM’s methodology does not strike that balance.
As a threshold matter, not even PJM can reasonably claim that its proposal ensures market participants have adequate flexibility to manage their collateral requirements. Market participants have no flexibility to manage their collateral requirements. They must post the full amount, with no exceptions for individual credit risk and subject only to intermittent and irregular reductions at PJM’s discretion.57 PJM has set the obligation so high for NOVEC that neither option is practicable.58 As Mr. Coscia explained in his affidavit, “[c]ash is not available” because the obligation “is approximately eight times [NOVEC’s] entire cash and temporary investments and approximately 3.4 times all of its current and accrued assets.”59 A letter of credit, if one could be had, “would have to be supported by [NOVEC’s] balance sheet.”60 The
55 PJM Answer at 84.56 Id. (quoting PJM Interconnection, L.L.C., 186 FERC ¶ 61,055, P 28 (2024)).57 RBP Proposal, Attachment A at § 18.8(b)(i)(A) (“...the RBP Credit Rate shall equal $1.5 million, as may be reduced, for reasons including a change in the total committed RBP UCAP MW, when total posted RBP Collateral is greater than the total remaining RBP Charges obligations, over time by the Office of the Interconnection to an amount sufficient to cover the total existing RBP Charges obligations….”) (italics added).58 NOVEC Protest, Rollins Affidavit at 3:7-16.59 NOVEC Protest, Coscia Affidavit at P 64 (“NOVEC Coscia Affidavit”).60 Id. P 65.
PDF page 13
13
Rural Utilities Service holds a mortgage over most of NOVEC’s assets and its loan documents limit the incurrence of additional secured obligations and liens.61 The carrying cost would consume NOVEC’s entire operating margin even under the most favorable circumstances, but, realistically, the cost is likely to be multiples of the margin, forcing NOVEC into a permanent net-loss position for the foreseeable future due to following the rules set out before it and then having those rules drastically changed without any consideration.62
PJM cannot reasonably claim that the collateral requirement is necessary to protect PJM’s markets because it has, at best, a limited correlation to the risk to PJM’s markets.63 Mr. Coscia explained that the RBP settles as a contract for differences and NOVEC pays the difference between the RBP price and the RPM clearing price for the year, multiplied by its allocated RBP UCAP MW.64 NOVEC does not pay the RBP price and when the RPM clears above it, NOVEC
receives a payment.65 As Mr. Coscia explains, PJM has not linked the collateral obligation to the risk of loss because it is based on the RBP Resources’ revenue and not what would remain payable on default.66 The credit rate is theoretical, dismissive of likely outcomes and disconnected from NOVEC’s obligation:
Because the Credit Rate makes no reference to RPM, the requirement bears
no stable relationship to what the cooperative will owe. Where RPM clears
close to the RBP price the difference approaches zero while the collateral
does not move. Where RPM clears far below it the difference widens and
61 Id.62 Id. P 66 (“Carrying cost compounds the problem. Taking the most favourable assumption available — that a letter of credit can be obtained at 100 basis points — the annual cost would be approximately $19.5 million. The cooperative reported patronage capital and operating margins of approximately $20.8 million for 2025, after existing interest expense of approximately $0.8 million. At 100 basis points the carrying cost alone would consume approximately 94 percent of that margin; at 150 basis points, approximately 141 percent; at 200 basis points, approximately 188 percent; and at 300 basis points, approximately 281 percent. Each is between approximately twenty-five and seventy-five times the cooperative's entire existing annual interest expense, and each would recur for as long as the requirement remains outstanding.”).63 See Supplemental Coscia Affidavit at P 12 (“Gross contractual value therefore is not itself a measure of loss on default.”)64 NOVEC Coscia Affidavit at P 38; see also RBP Proposal at 59-60.65 See NOVEC Coscia Affidavit at P 38.66 Supplemental Coscia Affidavit at PP 9-12.
PDF page 14
14
the collateral is unchanged again. A requirement calibrated to exposure
would vary with the second price; this one is fixed against the first.67
Mr. Coscia points out that a collateral requirement is ordinarily derived from three components: an identified position, a price at which the position would be replaced, and a period of time of exposure.68 The size of the residual loss should be identified before the amount of collateral to absorb it is decided and “a formula based on approximately one-half of gross contractual value does not establish that relationship.”69 Mr. Coscia attempted to estimate total exposure based on RPM clearing prices over 13 years and the full 15 years based on a conservative assumption that the RBP would clear at $555/MW-day.70
It is worth noting that PJM clarified that no collateral requirement would be required for years that RBP Resources are not in service.71 Mr. Coscia calculated an exposure at $200 to $290 million for two years without RBP Resources receiving the RPM clearing price because they were not in service.72 NOVEC will not have charges for that period, which means that his estimate for the 13-year exposure is closer to reality. Even using his lifetime exposure of 15 years, the total collateral obligation never dropped below the total exposure and was as high as ninefold.73 As a multiple of the 13-year exposure (the true lifetime exposure), the collateral obligation now ranges, depending on the RPM clearing prices, from multiples of 1.1 to 1,149. Although Mr. Coscia does not forecast the RPM clearing prices, he does opine that if the RBP “does not resolve the shortfall and the Interim Resource Adequacy Service is not implemented,
67 NOVEC Coscia Affidavit at P 40.68 Id. P 41.69 Supplemental Coscia Affidavit at PP 15-16.70 NOVEC Coscia Affidavit at PP 41-51.71 PJM Answer at n.234.72 NOVEC Coscia Affidavit at P 47.73 See id. P 49 (showing demonstrative table).
PDF page 15
15
prices would in my opinion almost certainly clear above the present cap once the collar comes off, at or near the level PJM has itself simulated.”74
Mr. Coscia comments that the table shows “that the filed requirement exceeds the
exposure at every path in the range.”75 PJM did not in its answer to NOVEC’s protest address the substance of the affidavit Mr. Coscia submitted on behalf of NOVEC, perhaps because it
confirms that PJM’s collateral obligation is excessive. Requiring NOVEC to post collateral that protects the PJM market potentially multiples above its total exposure is excessive and does not satisfy the Commission’s requirement that the collateral obligation strike an appropriate balance between protecting the market and facilitating market participation. “Magnitude is the measure of” limiting access to the market.76 NOVEC’s nearly $2 billion collateral requirement is close to a third of all collateral PJM held in 2025 to cover all market activities by all Market
Participants.77
Further, NOVEC demonstrated that the collateral obligation contemplated by the RBP
was partly duplicative of the collateral amounts already held by PJM.78 PJM argues that the RBP collateral is not duplicative of the Peak Market Activity collateral PJM requires for transactions
74 Id. P 50.75 Id. P 51.76 EKPC Protest, Attachment 2 Affidavit of Carl F. Coscia at P 61 (“EKPC Coscia Affidavit”) (“The Commission’s standard has two sides: an RTO must minimize the risk that a default is socialized among non-defaulting participants, while ‘ensuring that the credit or collateral requirements are not so stringent that they unnecessarily inhibit access to the marketplace.’ Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at P 19 (2009). Magnitude is the measure of the second. In what follows I compare the proposed requirement to the collateral PJM actually holds, to the relationship PJM maintains between collateral and market activity, and to the annual charge the requirement secures. On each comparison the proposed requirement stands apart from anything in PJM’s experience.”).77 See id. P 63.78 NOVEC Protest at 21-22 (“Second, the calculation assumes that the RBP buyers have to collateralize the entire $555/MW-day. In actuality, the RBP Charges will be the RBP clearing-price average (which can be less than $555/MW-day) net of revenues from the capacity auction. Effectively, RBP buyers are providing collateral to ensure that everyone in PJM pays the capacity costs associated with the RBP Resources. RBP buyers themselves already provide PJM collateral to ensure that they pay their capacity rates under Attachment Q, and so do all other capacity buyers. PJM is requiring duplicative collateral — at the most, RBP buyers should only have to provide collateral for the incremental cost of the RBP clearing price above the weighted RPM clearing price for the relevant delivery year. That is the only cost that RBP buyers will actually have to pay, and thus the only payments that need to be collateralized.”).
PDF page 16
16
in PJM’s markets because the “long-term” obligations to RBP Resources are “unlike any other commitment in PJM.”79 PJM distinguishes the two obligations by arguing that the capacity obligation is “backward-looking” and “to the extent an LSE defaults on its obligations, the provider of last resort for that load becomes responsible on a going-forward basis.”80 In contrast, PJM “envisions that an LSE’s obligation to pay RBP Charges should not be shunted to a provider of last resort—the idea is that the large load driving the need for the RBP should bear these costs—through its LSE, consistent with the Ratepayer Protection Pledge.”81 But even RPM capacity is procured through the Base Residual Auction held approximately three years before the Delivery Year and every “LSE carries, as a matter of course, a forward RPM capacity obligation extending roughly three years.”82
Notwithstanding PJM’s unclear argument premised on retail choice,83 the RBP Proposal indeed requires NOVEC to provide duplicative collateral.84 NOVEC provides PJM with a collateral amount that guarantees NOVEC will pay the recurring capacity costs every day. When NOVEC’s load grows by the Load Adjustment, it will likely provide additional collateral to account for the new capacity purchased above the original amount. At the same time, NOVEC would also be required to provide a collateral amount to PJM to guarantee its payment of the RBP Charge. The RBP Charge is a contract for difference.85 NOVEC will pay (or receive) the difference between the RBP Charge and the capacity clearing price. But PJM determines
79 PJM Answer at 76-77.80 Id. at 77-78.81 Id.82 Supplemental Coscia Affidavit at P 41.83 It is unclear what PJM means here because the paradigm of a “provider of last resort” is only applicable in a retail choice state. NOVEC does not operate in a retail choice state. But, to the extent that NOVEC is itself functionally a provider of last resort because it is, as previously explained, obligated by law to serve customers within its designated service area, PJM is already shunting RBP Charges to the provider of last resort by imposing such obligations directly on NOVEC, and doing so without knowing whether NOVEC will be able ensure that the large- load customers will bear these cost.84 NOVEC Protest at 21-22; see also EKPC Protest at 23; EKPC Coscia Affidavit at P 98.85 RBP Proposal at 59-60; NOVEC Coscia Affidavit at P 38.
PDF page 17
17
NOVEC’s RBP collateral obligation as if NOVEC were paying the entire RBP Charge, which means that NOVEC is providing collateral for the cost of capacity of its RBP MWs and providing collateral for the RBP clearing price, and not just for the difference between the RBP price and the capacity clearing price. The capacity obligation has a three-year forward-looking time horizon which is, functionally, renewed each year for a successive three-year period for existing load. In effect, PJM is seeking to require NOVEC to post collateral for the same MWs of capacity twice. In particular, Mr. Coscia demonstrates that in the final three-year period, “an ordinary LSE and an RBP buyer carry forward RPM obligations of the same horizon at essentially the same price.”86 Coupled with the magnitude of the $2 billion requirement, the duplicative nature of the collateral obligation makes it excessive, and so the Commission should find that the RBP Proposal is not just and reasonable and reject it.87
b. The Commission should require PJM to allow other methods of posting
collateral.
PJM argues that the collateral obligation should only be secured with cash or a letter of credit because “there is a likelihood that even entities with investment grade credit may see their financial condition deteriorate over 15 years.”88 PJM overstates the risk because the RBP Charges that NOVEC could be responsible for represent, in any given year, a tiny fraction of the collateral PJM would require NOVEC to post.89 Further, while NOVEC agrees that it is possible for credit ratings to change, the greatest threat to NOVEC’s credit rating is PJM’s own RBP
86 Supplemental Coscia Affidavit at P 44.87 PJM commits to eliminating a sentence from proposed Tarif, Attachment DD to eliminate “confusion that RBP Charges may be captured in the Peak Market Activity credit tool, and therefore its omission from the accepted language would facilitate proper understanding of the RBP Credit rules.” PJM Answer at n.259. The tariff language remains in the proposal because PJM has not filed to revise it. Moreover, the structure still assumes that the RBP collateral’s pricing is not redundant of NOVEC’s other future obligations.88 PJM Answer at 85; EKPC Coscia Affidavit at P 53.89 NOVEC Coscia Affidavit at P 50.
PDF page 18
18
collateral requirement.90 PJM’s estimate that there is an 11% likelihood that an entity with a BBB rating could transition to default status is problematic because it is based on a study that includes non-utilities and because it does not consider NOVEC as an individual creditor.91 Mr. Coscia pointed out that PJM “bills [NOVEC] weekly, observes whether it pays, and has an unbroken record of that performance for as long as [NOVEC] has taken service in its markets.”92 In short, NOVEC maintains an investment-grade credit rating and has always met its obligations in PJM.93
PJM’s refusal to allow an unsecured credit allowance is inconsistent with every other credit policy it maintains. With respect to PJM’s existing credit policy, “[t]he general credit requirement is sized to Peak Market Activity, computed from a participant’s own observed billing history; unsecured credit allowances are keyed to creditworthiness and tangible net worth; and requirements are recalculated on an ongoing basis.”94 PJM’s only explanation for why it is refusing to allow an unsecured credit allowance is that in PJM’s experience, “Market Participants used their full amount of unsecured credit to cover their Peak Market Activity credit obligations” during hot and cold-weather events.95 As Mr. Coscia cogently explains, “[c]redit migration over a fifteen-year horizon is a legitimate credit consideration” but “it does not explain why [NOVEC’s] credit condition should be ignored.”96 In contrast with the buyers, PJM’s seller
90 Id. PP 30-31; Supplemental Coscia Affidavit at P 20 (“A generalized corporate transition matrix does not measure the effect of imposing collateral comparable to or exceeding an obligor’s balance sheet. A requirement of that magnitude can consume liquidity, encumber assets, absorb credit-facility capacity, and impose recurring financing expense. The requirement can therefore affect the very credit quality the migration analysis is used to predict.”).91 PJM Answer at n.245 (citing Default, Transition, and Recovery: 2025 Annual U.S. Corporate Default And Rating Transition Study, S&P Global Inc. (June 12, 2026), https://www.spglobal.com/ratings/en/regulatory/article/default- transition-and-recovery-2025-annual-us-corporate-default-and-rating-transition-study-s101688003 [https://perma.cc/7LTL-J8SQ]).92 NOVEC Coscia Affidavit at P 25.93 NOVEC Protest, Rollins Affidavit at 3:3-4 (“NOVEC has an investment-grade credit rating. Further, to my knowledge, NOVEC has always paid its obligations related to PJM membership.”).94 EKPC Coscia Affidavit at P 17.95 PJM Answer at 85.96 Supplemental Coscia Affidavit at P 18.
PDF page 19
19
methodology allows for reductions that take account of credit quality.97 In a section 205 proceeding, PJM bears the burden to show that its proposal is just and reasonable and this statement is insufficient explanation for why no allowance for unsecured credit should be extended to RBP Buyers. If the Commission does not reject the RBP Proposal as unjust and unreasonable, it should exercise its authority under NRG to require PJM to allow alternative demonstrations of creditworthiness to secure the collateral requirement.98
F. The RBP Proposal is unjust and unreasonable because it does not address
underlying practical implementation issues and imposes unrealistic requirements.
PJM relies in substantial part on the availability of mitigation to the RBP Charges and collateral obligation but gives only a limited window to make those arrangements. NOVEC would have to procure 1,619.2 MW to offset its obligation in the RBP auction.99 As a practical matter, NOVEC would not be able to prudently enter into the necessary transactions to procure such a large amount of power. The procurement process would require multiple counterparties and transactions, credit diligence, commercial and risk analyses, contract negotiations, internal approvals, and potential regulatory review, which could take from four to twelve months to negotiate.100 PJM has given NOVEC—and every RBP Buyer—ninety days.
The expedited process rests on the viability of unproven assumptions. The obligation is fixed for 15 years even if the underlying load is delayed, reduced, canceled, or never materializes. For instance, PJM is relying on NOVEC’s 2025 aggregate LSE-level forecast even
97 Id. P 24.98 NOVEC Protest at 24.99 RBP Proposal, Attachment C, Croop Affidavit at P 47.100 NOVEC Protest at 7 (“NOVEC in particular is prejudiced because the Initial Load Adjustment MW that it would need to offset to eliminate its obligation in the RBP auction is so high (1,619.2 MW) that NOVEC is unlikely to be able to secure bilateral contracts with new generators for anything approaching that amount… As a rural, not-for- profit cooperative and a transmission-dependent distribution utility, NOVEC faces a procurement challenge that is unusual both in magnitude and structure. A prudent procurement of more than 1,600 MW cannot reasonably be completed within the period PJM proposes. A procurement of this magnitude would likely require multiple counterparties and transactions, each involving counterparty and credit diligence, commercial and risk analysis, contract negotiations, internal approvals, and potentially regulatory review.”).
PDF page 20
20
though NOVEC’s 2026 forecast is lower. Or, for another example, PJM proposes to permit forecast-based RBP MW offsets for committed demand-side participation but does not explain how those commitments are reconciled with actual load.101 If the load does not materialize, it does not exist to be curtailed.
Even if it were feasible to secure the RBP MW offsets, the procedures for an RBP Buyer to offset are not just and reasonable. Even though the Initial RBP Target is only 6,831.3 MW, PJM would require buyers to procure over 9,000 MW to eliminate their RBP allocations.102 NOVEC would have to procure over 300 MW above its RBP allocation to remove its RBP allocation.103 The excess MW provide additional value to the PJM capacity market for which the RBP Buyer is not compensated. Further, any reductions NOVEC achieves are in effect shared with other RBP Buyers and vice versa, which, in addition to being unfair, creates a perverse incentive to free ride on others’ efforts.104 These provisions also mean that NOVEC will not know what its individual obligation is until the auction’s conclusion, which can create a material economic impact for a participant with as much exposure as NOVEC has.105
PJM also asserts that NOVEC could use its existing collateral obligations with its customers to secure this new obligation or issue “low-interest, ratepayer-backed bonds” to meet the requirement.106 True or not, it is immaterial to the question of whether the collateral requirements asked by PJM are just and reasonable. To the extent that NOVEC can, NOVEC will explore every commercially reasonable option available to it if the collateral obligation is
101 RBP Proposal at 40.102 Id., Attachment C, Croop Affidavit at P 46.103 NOVEC Protest at 17.104 Id. at 17-18.105 Supplemental Coscia Affidavit at PP 35-36.106 PJM Answer at 90; id. n.274.
PDF page 21
21
imposed as PJM has requested. NOVEC requires a just and reasonable collateral obligation based on a just and reasonable methodology, which the RBP Proposal does not have.
G. If the Commission does not reject the RBP Proposal, the Commission should require PJM to revise the PJM Tariff to precisely reflect commitments made in the PJM Answer.
In its answer, PJM clarified that collateral for a Delivery Year will be based only on RBP UCAP MW committed for that year and that “no collateral would be required for RBP Resources [that] are not in service for that Delivery Year, and no RBP Charges would be assessed.”107 NOVEC supports this clarification. However, NOVEC has reviewed Section 18.8(b)(i)(A), and PJM’s interpretation relies on the meaning of the term “committed” as it pertains to that section. PJM should be required to revise the proposed Tariff section to explicitly state that NOVEC and other LSEs with RBP obligations will not be required to post collateral for RBP Resources that are not in service. Mr. Coscia points out that Section 18.6(e) permits a resource to remain committed for up to three Delivery Years and Section 18.8(b)(i)(A) does not have an “in- service” limitation, creating the risk that NOVEC could post collateral for an RBP Resource that does not operate during those three Delivery Years without clarification.108
PJM also stated in its answer that the total collateral obligation “can decline as the remaining exposure declines.”109 The Commission should not approve the RBP Proposal with a provision that grants PJM the discretion not to reduce a collateral requirement that NOVEC has shown is already excessive. “A reduction that occurs only after remaining gross payments fall below posted collateral can leave the requirement unchanged for years despite changes in market prices, remaining tenor, or credit condition.”110 Given the enormous sums involved, the Tariff
107 Id. at n.234.108 Supplemental Coscia Affidavit at PP 32-34.109 PJM Answer at 88.110 Supplemental Coscia Affidavit at P 49.
PDF page 22
22
should incorporate a mechanism to automatically reduce the collateral obligation with “objective, tariff-based standards…[that] state the frequency of review, the inputs used, the circumstances requiring a reduction, and the time within which excess collateral is returned.”111
H. While PJM has not proposed a just and reasonable collateral framework for the RBP, if the Commission does not reject the RBP Proposal, the Commission should follow PJM’s suggestion to set the matter for further proceedings to decide the collateral obligation.
To be clear, NOVEC believes that the RBP Proposal is not just and reasonable and should be rejected. However, to the extent that the Commission is inclined to approve the RBP Proposal, NOVEC would support the Commission “resolving the applicable buyer-side LSE RBP Credit Rate through additional procedures” as PJM suggests.112
PJM indicates that it consents to keying the credit rate “to the actual MW-weighted average of the levelized procurement cost of all selected RBP Sell Offers that results from the RBP and not the maximum of such value” and references the NOVEC Protest for clarity on the description.113 “Using the actual RBP procurement price would reduce the requirement if the procurement clears below $555/MW-day” but “[i]t would not resolve the underlying methodology.”114 NOVEC supports this minor modification to the credit requirement, but would stress to the Commission that, in order to be most conducive to settlement, the scope of the hearing and settlement judge procedures set on the RBP Buyer-side credit requirement should encompass the entire collateral framework.115111 Supplemental Coscia Affidavit at P 50.112 PJM Answer at 93.113 Id. at 92-93.114 Supplemental Coscia Affidavit at P 57.115 See id. P 58.
PDF page 23
23
III. CONCLUSION
WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission grant this motion for leave to answer, accept NOVEC’s answer, and reject the RBP Proposal. In the alternative, NOVEC respectfully requests that the Commission order PJM to modify the RBP as requested herein to eliminate or substantially reduce the collateral obligation and set the entire RBP buyer-side credit requirement for hearing and settlement judge procedures.
Respectfully submitted,
//s// Alan I. Robbins
Alan I. Robbins
Debra D. Roby
Thomas B. Steiger III
Washington Energy Law LLP
900 17th Street. N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9313
Email: arobbins@washingtonenergylaw.com
droby@washingtonenergylaw.com
tsteiger@washingtonenergylaw.com
Counsel to Northern Virginia Electric Cooperative, Inc.
Dated: September 23, 2026.
PDF page 24
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.
Dated at Washington, D.C. this 23rd day of September, 2026.
//s// Jessika Dziechciowska
Jessika Dziechciowska
Energy Practice Analyst
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9308
Email: jdziechciowska@washingtonenergylaw.com