Motion for Leave to Answer and Answer of Northern Virginia Electric Cooperative, Inc. to the Answer et al. of PJM Interconnection, L.L.C. filed on 09/10/2026
Text extracted from the eLibrary original (SHA-256 e73143e6cbd3e1d4…). Download the original from the official source.
Contents · 11 sections
- I. MOTION FOR LEAVE TO ANSWER
- II. ANSWER TO PJM’S ANSWER TO THE PROTESTS AND COMMENTS ON
- A. Mr. Coscia’s Supplemental Affidavit explains the many flaws in PJM’s proposed
- B. The capacity shortfall experienced by PJM resulted from a combination of causes in
- C. The Commission should exercise its authority under NRG to require PJM to adopt
- D. The Commission should reject PJM’s argument that NOVEC misrepresents the
- E. The collateral requirement is unjust and unreasonable because it is duplicative,
- F. The RBP Proposal is unjust and unreasonable because it does not address
- G. If the Commission does not reject the RBP Proposal, the Commission should
- H. While PJM has not proposed a just and reasonable collateral framework for the
- III. CONCLUSION
Read topic-matched comments in ER26-3380
Topics in the text: Credit and exit · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Credit and exit
If the Commission does not reject the RBP, it should require revisions on compliance to eliminate or substantially reduce the nearly $2 billion collateral requirement that the RBP Proposal would impose on NOVEC, or set the collateral requirement for settlement and hearing judge procedures as…Read this passage Filed comments: Credit and exit
I. MOTION FOR LEAVE TO ANSWER
printed heading · Topic match: Credit and exit
MOTION FOR LEAVE TO ANSWER NOVEC respectfully requests leave to submit this answer.Read this passage Filed comments: Credit and exit
II. ANSWER TO PJM’S ANSWER TO THE PROTESTS AND COMMENTS ON
printed heading
ANSWER TO PJM’S ANSWER TO THE PROTESTS AND COMMENTS ON THE RBP PROPOSALRead this passage
A. Mr. Coscia’s Supplemental Affidavit explains the many flaws in PJM’s proposed
printed heading · Topic match: Credit and exit
Coscia reviews PJM’s explanation of the collateral overlap between the RBP Charge collateral and the Peak Market Activity under Attachment Q.12 He concludes his affidavit by addressing the need for a reduction mechanism for the collateral obligation, discussing the stakeholder process, and opining…Read this passage Filed comments: Credit and exit
B. The capacity shortfall experienced by PJM resulted from a combination of causes in
printed heading · Topic match: Reliability and curtailment
Operator, Inc., 170 FERC ¶ 61,215, P 13 (2020) (“In other words, unlike the centralized capacity constructs used in the Eastern RTOs/ISOs, MISO’s Auction is not—and has never been—the primary mechanism for its LSEs to procure capacity.”) (emphasis in original). 17 PJM Business Practice Manual No.…Read this passage Filed comments: Reliability and curtailment
C. The Commission should exercise its authority under NRG to require PJM to adopt
printed heading · Topic match: Cost allocation
PJM specifically criticizes NOVEC for recognizing that a voluntary RBP may not procure the entire shortfall,28 arguing that NOVEC’s perspective “would effectively contradict the fundamental core reliability goal of the RBP to acquire the capacity shortfall….”29 However, in its transmittal letter,…Read this passage Filed comments: Cost allocation
D. The Commission should reject PJM’s argument that NOVEC misrepresents the
printed heading · Topic match: Cost allocation
The cost-causation principle requires the Commission to have “an articulable and plausible reason” to believe that the benefits are roughly commensurate with the costs.45 PJM argues that NOVEC “seeks to establish a false standard for cost allocation approaches.”46 PJM argues that “all approved…Read this passage Filed comments: Cost allocation
E. The collateral requirement is unjust and unreasonable because it is duplicative,
printed heading · Topic match: Credit and exit
“Magnitude is the measure of” limiting access to the market.76 NOVEC’s nearly $2 billion collateral requirement is close to a third of all collateral PJM held in 2025 to cover all market activities by all Market Participants.77 Further, NOVEC demonstrated that the collateral obligation contemplated…Read this passage Filed comments: Credit and exit
F. The RBP Proposal is unjust and unreasonable because it does not address
printed heading · Topic match: Credit and exit
A prudent procurement of more than 1,600 MW cannot reasonably be completed within the period PJM proposes.Read this passage Filed comments: Credit and exit
G. If the Commission does not reject the RBP Proposal, the Commission should
printed heading · Topic match: Credit and exit
Coscia points out that Section 18.6(e) permits a resource to remain committed for up to three Delivery Years and Section 18.8(b)(i)(A) does not have an “in- service” limitation, creating the risk that NOVEC could post collateral for an RBP Resource that does not operate during those three Delivery…Read this passage Filed comments: Credit and exit
H. While PJM has not proposed a just and reasonable collateral framework for the
printed heading · Topic match: Credit and exit
While PJM has not proposed a just and reasonable collateral framework for the RBP, if the Commission does not reject the RBP Proposal, the Commission should follow PJM’s suggestion to set the matter for further proceedings to decide the collateral obligation.Read this passage Filed comments: Credit and exit
III. CONCLUSION
printed heading · Topic match: Credit and exit
In the alternative, NOVEC respectfully requests that the Commission order PJM to modify the RBP as requested herein to eliminate or substantially reduce the collateral obligation and set the entire RBP buyer-side credit requirement for hearing and settlement judge procedures.Read this passage Filed comments: Credit and exit
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 23rd day of September, 2026. //s// Jessika Dziechciowska Jessika Dziechciowska Energy Practice Analyst Washington Energy Law LLP 900 17th Street, N.W., Suite 500-A Washington, D.C. 20006 Tel: (202) 326-9308 Email: jdziechciowska@washingtonenergylaw.comRead this passage