ER26-3380-000 · 2026-09-23 · Northern Virginia Electric Cooperative, Inc.

Motion for Leave to Answer and Answer of Northern Virginia Electric Cooperative, Inc. to the Answer et al. of PJM Interconnection, L.L.C. filed on 09/10/2026

Text extracted from the eLibrary original (SHA-256 e73143e6cbd3e1d4…). Download the original from the official source.

Contents · 11 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 2
  2. II. ANSWER TO PJM’S ANSWER TO THE PROTESTS AND COMMENTS ON p. 2
  3. A. Mr. Coscia’s Supplemental Affidavit explains the many flaws in PJM’s proposed p. 2
  4. B. The capacity shortfall experienced by PJM resulted from a combination of causes in p. 3
  5. C. The Commission should exercise its authority under NRG to require PJM to adopt p. 5
  6. D. The Commission should reject PJM’s argument that NOVEC misrepresents the p. 9
  7. E. The collateral requirement is unjust and unreasonable because it is duplicative, p. 12
  8. F. The RBP Proposal is unjust and unreasonable because it does not address p. 19
  9. G. If the Commission does not reject the RBP Proposal, the Commission should p. 21
  10. H. While PJM has not proposed a just and reasonable collateral framework for the p. 22
  11. III. CONCLUSION p. 23

Read topic-matched comments in ER26-3380

Topics in the text: Credit and exit · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Credit and exit

If the Commission does not reject the RBP, it should require revisions on compliance to eliminate or substantially reduce the nearly $2 billion collateral requirement that the RBP Proposal would impose on NOVEC, or set the collateral requirement for settlement and hearing judge procedures as…
Read this passage Filed comments: Credit and exit

I. MOTION FOR LEAVE TO ANSWER

printed heading · Topic match: Credit and exit

MOTION FOR LEAVE TO ANSWER NOVEC respectfully requests leave to submit this answer.
Read this passage Filed comments: Credit and exit

II. ANSWER TO PJM’S ANSWER TO THE PROTESTS AND COMMENTS ON

printed heading

ANSWER TO PJM’S ANSWER TO THE PROTESTS AND COMMENTS ON THE RBP PROPOSAL
Read this passage

A. Mr. Coscia’s Supplemental Affidavit explains the many flaws in PJM’s proposed

printed heading · Topic match: Credit and exit

Coscia reviews PJM’s explanation of the collateral overlap between the RBP Charge collateral and the Peak Market Activity under Attachment Q.12 He concludes his affidavit by addressing the need for a reduction mechanism for the collateral obligation, discussing the stakeholder process, and opining…
Read this passage Filed comments: Credit and exit

B. The capacity shortfall experienced by PJM resulted from a combination of causes in

printed heading · Topic match: Reliability and curtailment

Operator, Inc., 170 FERC ¶ 61,215, P 13 (2020) (“In other words, unlike the centralized capacity constructs used in the Eastern RTOs/ISOs, MISO’s Auction is not—and has never been—the primary mechanism for its LSEs to procure capacity.”) (emphasis in original). 17 PJM Business Practice Manual No.…
Read this passage Filed comments: Reliability and curtailment

C. The Commission should exercise its authority under NRG to require PJM to adopt

printed heading · Topic match: Cost allocation

PJM specifically criticizes NOVEC for recognizing that a voluntary RBP may not procure the entire shortfall,28 arguing that NOVEC’s perspective “would effectively contradict the fundamental core reliability goal of the RBP to acquire the capacity shortfall….”29 However, in its transmittal letter,…
Read this passage Filed comments: Cost allocation

D. The Commission should reject PJM’s argument that NOVEC misrepresents the

printed heading · Topic match: Cost allocation

The cost-causation principle requires the Commission to have “an articulable and plausible reason” to believe that the benefits are roughly commensurate with the costs.45 PJM argues that NOVEC “seeks to establish a false standard for cost allocation approaches.”46 PJM argues that “all approved…
Read this passage Filed comments: Cost allocation

E. The collateral requirement is unjust and unreasonable because it is duplicative,

printed heading · Topic match: Credit and exit

“Magnitude is the measure of” limiting access to the market.76 NOVEC’s nearly $2 billion collateral requirement is close to a third of all collateral PJM held in 2025 to cover all market activities by all Market Participants.77 Further, NOVEC demonstrated that the collateral obligation contemplated…
Read this passage Filed comments: Credit and exit

F. The RBP Proposal is unjust and unreasonable because it does not address

printed heading · Topic match: Credit and exit

A prudent procurement of more than 1,600 MW cannot reasonably be completed within the period PJM proposes.
Read this passage Filed comments: Credit and exit

G. If the Commission does not reject the RBP Proposal, the Commission should

printed heading · Topic match: Credit and exit

Coscia points out that Section 18.6(e) permits a resource to remain committed for up to three Delivery Years and Section 18.8(b)(i)(A) does not have an “in- service” limitation, creating the risk that NOVEC could post collateral for an RBP Resource that does not operate during those three Delivery…
Read this passage Filed comments: Credit and exit

H. While PJM has not proposed a just and reasonable collateral framework for the

printed heading · Topic match: Credit and exit

While PJM has not proposed a just and reasonable collateral framework for the RBP, if the Commission does not reject the RBP Proposal, the Commission should follow PJM’s suggestion to set the matter for further proceedings to decide the collateral obligation.
Read this passage Filed comments: Credit and exit

III. CONCLUSION

printed heading · Topic match: Credit and exit

In the alternative, NOVEC respectfully requests that the Commission order PJM to modify the RBP as requested herein to eliminate or substantially reduce the collateral obligation and set the entire RBP buyer-side credit requirement for hearing and settlement judge procedures.
Read this passage Filed comments: Credit and exit

CERTIFICATE OF SERVICE