NOVEC_Coscia Supplemental Affidavit
Text extracted from the eLibrary original (SHA-256 86e5ba2159a70bc9…). Download the original from the official source.
Contents · 8 sections
- I. PURPOSE, POSTURE, AND PRINCIPAL CONCLUSIONS
- II. PJM HAS IDENTIFIED A PAYMENT STREAM, NOT THE RESIDUAL LOSS TO BE
- III. PJM’S CREDIT-MIGRATION ANALYSIS DOES NOT SUPPORT A UNIFORM RATE
- IV. THE OPT-OUT DISTINCTION DOES NOT TRACK THE RISK IT IS SAID TO
- V. THE CONTROLLING MEGAWATT QUANTITY REMAINS UNDEFINED
- VI. PJM’S PEAK MARKET ACTIVITY CLARIFICATION DOES NOT RESOLVE THE
- VII. PJM’S REDUCTION MECHANISM REMAINS A GROSS-PAYMENT ROLL-OFF,
- IX. ADDITIONAL PROCEDURES SHOULD ADDRESS THE ENTIRE BUYER-SIDE
Read topic-matched comments in ER26-3380
Topics in the text: Credit and exit · Cost allocation · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
I. PURPOSE, POSTURE, AND PRINCIPAL CONCLUSIONS
printed heading · Topic match: Credit and exit
It does not establish that the figure corresponds to the loss that would remain after an LSE default, application of collateral, reallocation under Tariff section 18.9(a), and any further default allocation under Operating Agreement section 15.2.2. 6.Read this passage Filed comments: Credit and exit
II. PJM HAS IDENTIFIED A PAYMENT STREAM, NOT THE RESIDUAL LOSS TO BE
printed heading · Topic match: Credit and exit
In responding to EKPC, PJM states that an unpaid RBP Charge is reallocated among other LSEs already responsible for RBP Charges.Read this passage Filed comments: Credit and exit
III. PJM’S CREDIT-MIGRATION ANALYSIS DOES NOT SUPPORT A UNIFORM RATE
printed heading · Topic match: Credit and exit
The original affidavit compared approximately $34.4 million of existing PJM collateral with approximately $1.954 billion of incremental RBP collateral.Read this passage Filed comments: Credit and exit
IV. THE OPT-OUT DISTINCTION DOES NOT TRACK THE RISK IT IS SAID TO
printed heading
THE OPT-OUT DISTINCTION DOES NOT TRACK THE RISK IT IS SAID TO ADDRESS 26.Read this passage
V. THE CONTROLLING MEGAWATT QUANTITY REMAINS UNDEFINED
printed heading · Topic match: Credit and exit
NOVEC’s answer appropriately asks that this interpretation be reflected in the Tariff. 33.Read this passage Filed comments: Credit and exit
VI. PJM’S PEAK MARKET ACTIVITY CLARIFICATION DOES NOT RESOLVE THE
printed heading · Topic match: Credit and exit
PJM states that the separate RBP requirement must secure the forward RPM component as well as the contract-for- differences component, because Peak Market Activity does not prospectively collateralize the RPM component over the fifteen-year commitment.Read this passage Filed comments: Credit and exit
VII. PJM’S REDUCTION MECHANISM REMAINS A GROSS-PAYMENT ROLL-OFF,
printed heading · Topic match: Credit and exit
PJM states that the Credit Rate can decline when previously required collateral exceeds remaining expected payment exposure.Read this passage Filed comments: Credit and exit
IX. ADDITIONAL PROCEDURES SHOULD ADDRESS THE ENTIRE BUYER-SIDE
printed heading · Topic match: Credit and exit
At a minimum, the procedures should determine the residual loss the requirement secures, the parties that bear it, and the order in which collateral, section 18.9(a) reallocation, and any Operating Agreement section 15.2.2 allocation apply.Read this passage Filed comments: Credit and exit