ER26-3650-000 · 2026-09-24 · ON Energy Storage, Inc.
Motion for Leave to Answer and Limited Answer of ON Energy Storage, Inc. in response to comments and protests re Midcontinent Independent System Operator,…
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc.
Docket No. ER26-3650-000
MOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER
OF ON ENERGY STORAGE, INC.
Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213, ON Energy Storage, Inc. (“ON.energy”) respectfully moves for leave to answer and submits this Limited Answer in response to comments and protests concerning the transition and grandfathering provisions in the Midcontinent Independent System Operator, Inc. (“MISO”) proposal to establish Interconnection Reliability Requirements for Large Loads (“IRR Proposal”).1 MOTION FOR LEAVE TO ANSWER
Rule 213(a)(2) generally prohibits an answer to a protest or an answer unless otherwise ordered by the decisional authority.2 To the extent leave is required, good cause exists to accept this Limited Answer. ON.energy filed a timely motion to intervene in this proceeding on September 18, 2026.3 The September 18, 2026 and September 21, 2026 pleadings present competing positions on the scope and design of MISO’s transition provisions. Google LLC (“Google”) supports MISO’s proposed grandfathering framework; the Data Center Coalition (“DCC”) and Rowan Digital Infrastructure, LLC (“Rowan”) urge greater reliance on objective
1 Midcontinent Indep. Sys. Operator, Inc., Interconnection Reliability Requirements for Large Loads, Docket No. ER26-3650-000, Accession No. 20260828-5278 (Aug. 28, 2026) (“MISO Filing”).2 18 C.F.R. § 385.213(a)(2). 3 Doc-less Motion to Intervene of ON Energy Storage, Inc., Docket No. ER26-3650-000, Accession No. 20260918- 5094 (Sept. 18, 2026).
PDF page 2
2
evidence of commercial maturity; Entergy Services, LLC (“Entergy”) identifies recently developed and late-stage projects that may not satisfy MISO’s proposed grandfathering criteria; and Verrus LLC (“Verrus”) generally supports MISO’s transition approach while seeking clarity for phased development.4 Other commenters and protestors, including the Organization of MISO States, Inc. (“OMS”), the Iowa Office of the Consumer Advocate and the other signatories to its joint protest (“Joint Protestors”), and Sierra Club and the other Public Interest Organizations (“PIOs”), question whether development status should determine exemption from the ramp and ride-through requirements, whether proposed Section 37A.II.3 permits MISO to act before an exempt Large Load causes a reliability problem, and how MISO will address the combined effect of multiple exempt Large Loads.5
This Limited Answer responds to the positions already placed before the Commission by
explaining why legitimate reliance interests can be protected through objective and time-limited transition treatment without foreclosing prospective assessment of the reliability consequences of ride-through exemptions. In particular, ON.energy asks the Commission to condition acceptance of MISO’s transition provisions on an outside energization date for Large Loads that receive transition treatment based on the MTEP/EPR Condition or any broader commercial-maturity test, and to direct MISO to clarify that exempt Large Loads will be subject to prospective, system-level reliability review under proposed Section 37A.II.3. ON.energy does not seek to introduce new
4 See Comments of Google LLC, Docket No. ER26-3650-000, at 2-5 (Sept. 18, 2026) (“Google Comments”); Motion to Intervene and Comments of the Data Center Coalition, Docket No. ER26-3650-000, at 26-29 (Sept. 18, 2026) (“DCC Comments”); Limited Protest of Entergy Services, LLC, Docket No. ER26-3650-000, at 3 (Sept. 18, 2026) (“Entergy Protest”); Comments of Rowan Digital Infrastructure, LLC, Docket No. ER26-3650-000, at 2-3 (filed Sept. 21, 2026) (“Rowan Comments”); Comments of Verrus, LLC in Support of MISO’s Interconnection Reliability Requirements for Large Loads, Docket No. ER26-3650-000, at 4 (Sept. 18, 2026) (“Verrus Comments”).5 See Notice of Intervention and Comments of the Organization of MISO States, Inc., Docket No. ER26-3650-000, at 4-5 (Sept. 18, 2026) (“OMS Comments”); Joint Protest of the Iowa Office of the Consumer Advocate et al., Docket No. ER26-3650-000, at 3-4 (Sept. 18, 2026) (“Joint Protest”); Protest of Sierra Club et al., Docket No. ER26-3650- 000, at 2-3, 12-15 (Sept. 18, 2026) (“PIO Protest”).
PDF page 3
3
technical ride-through, modeling, or equipment requirements, and it does not address the other issues raised in the comments and protests, such as the rule of reason, the definition of Large Load, forecasting, or cost allocation. ON.energy submits this Limited Answer promptly after the pleadings it addresses and well before the requested December 4, 2026 effective date. Acceptance of this Limited Answer will assist the Commission in resolving an issue already squarely presented by the parties and will not delay the proceeding or prejudice any participant. The Commission has accepted otherwise-prohibited answers where they provide information that assists its decision- making.6
Accordingly, ON.energy respectfully requests that the Commission grant leave to answer and consider the Limited Answer below.
LIMITED ANSWER
I. ON.energy Supports Reasonable, Objective, and Time-Limited Transition Treatment that Protects Legitimate Reliance Interests.
MISO’s filing establishes three principal transition categories. First, Large Loads with a Service Commencement Date on or before December 4, 2026 are fully exempt from proposed Section 37A with respect to the portion of the Large Load that has procured Transmission Service as of the Service Commencement Date. Second, projects that meet the MTEP/EPR Condition are subject to the visibility requirements but are exempt from the ramp and ride-through requirements. Third, certain projects submitted to EPR between June 19 and October 31, 2026 may receive a ride-through waiver only if MISO determines that the exemption would not have an adverse
6 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 187 FERC ¶ 61,202, at P 24 (2024); Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at P 58 (2026) (accepting answers because they provided information that assisted the Commission in its decision-making process).
PDF page 4
4
reliability impact and compliance would impose significant costs.7 ON.energy does not challenge the first category, which applies to Large Loads taking service by the proposed effective date, or the third, which conditions relief on a determination that the exemption would not have an adverse reliability impact. ON.energy does not advocate automatic retroactive application of new ride- through requirements to facilities already operating under existing requirements. Its concern is with the second category, which exempts qualifying Large Loads from the ride-through and ramp requirements without any limit on when they must begin taking service. As explained below, ON.energy asks that the second category, and any broader eligibility test the Commission may adopt, be bounded by an outside energization date.
ON.energy agrees with these commenters that transition provisions should recognize legitimate reliance interests, although it does not endorse each eligibility test they propose. For example, Google emphasizes commercial certainty and investments made under the rules in effect when projects were developed.8 DCC argues that MTEP or EPR status is not a reliable proxy for the commercial maturity of a Large Load project and proposes that grandfathering instead turn on objective evidence of material commercial arrangements, such as executed interconnection, transmission service, or utility service agreements, or major equipment orders, with qualifying projects exempt from the ride-through and ramp requirements.9 Rowan similarly asks that transition relief account for objective evidence of project maturity, procurement, engineering, and construction.10 Verrus generally supports MISO’s transition provisions and emphasizes the phased buildout of large load campuses.11 Entergy likewise notes that certain recently developed projects
7 MISO Filing, Transmittal Letter at 13-14; id., Proposed Tariff § 37A.II; id., Tab C, Prepared Direct Testimony of Beibei Li at 18-22 (“Li Testimony”).8 Google Comments at 1, 3-4.9 DCC Comments at 26-29.10 Rowan Comments at 2-3.11 Verrus Comments at 4.
PDF page 5
5
and projects in the late stages of negotiations may not satisfy MISO’s proposed grandfathering criteria or may qualify only for limited exemptions.12
Taken together, these comments identify a legitimate need to account for genuine late-stage reliance. ON.energy agrees that this need should be accommodated but believes the relief should be objectively bounded in time, under whichever eligibility test the Commission accepts, including any test based on commercial maturity, as DCC and Rowan request. This need can be met without open-ended relief for projects that are still being designed and developed.
An outside energization date would meet that need, and MISO’s second category does not currently include one. MISO explains that tying transition treatment to MTEP and EPR status recognizes the “more immediate, non-speculative, nature of the Load additions,” and it describes the October 31, 2026 cutoff for the third category as establishing “a finite transition period, after which prospective projects are expected to account for MISO’s ride-through requirements as part of their development and design.”13 The second category, by contrast, has a fixed eligibility date but no limit on when a qualifying Large Load must begin taking service. DCC itself observes that, under the MTEP/EPR Condition, a Large Load customer that “may have to wait several years to commence operations” could nonetheless qualify for exemption based on the timing of its associated transmission submissions.14 The PIOs similarly read the Commission’s directive to propose a “reasonable implementation period” as implying “a period after which implementation will be completed.”15 An outside energization date would align the second category with MISO’s
12 Entergy Protest at 3.13 MISO Filing, Transmittal Letter at 14; Li Testimony at 19:20-23, 22:1-4.14 DCC Comments at 27.15 PIO Protest at 14.
PDF page 6
6
own rationale without disturbing the reliance interests of projects that are genuinely near completion.
The Electric Reliability Council of Texas, Inc. (“ERCOT”) is addressing the same problem MISO faces here: establishing clear and achievable ride-through requirements that maintain system stability without being unduly burdensome to Large Loads. ERCOT’s framework shows that those objectives can be pursued together, and it offers a useful model for MISO. In particular, ERCOT’s transition framework shows that an outside energization date can work alongside the kind of commercial-milestone evidence DCC and Rowan propose. ERCOT’s ride-through exemption turns on objective milestones achieved by its November 14, 2025 grandfathering date, such as operation or written approval to energize, or executed interconnection agreements together with notice to proceed and funding of the required interconnection facilities. For a Large Computational Load that was not required to be in ERCOT’s interim Large Load interconnection process, the exemption also requires a written attestation from the interconnecting utility and Initial Energization by December 31, 2026.16 ERCOT thus tied eligibility to milestones achieved before its grandfathering date and, for one category of projects, to a defined outside energization date. That category offers the closest parallel to MISO’s situation. ERCOT applied its outside date to loads that were not required to go through its interim Large Load interconnection process, and MISO does not currently have a Load interconnection process at all; it relies instead on MTEP and EPR status.17 A similarly defined outside boundary in MISO could complement, rather than displace, the objective evidence of commercial maturity urged by DCC and Rowan, and could address the circumstances Entergy describes for recently developed and late-stage projects. It
16 See ERCOT, Nodal Operating Guides § 2.15(1)(a)-(d) (eff. Aug. 1, 2026); see also id. § 2.6.4(1) (parallel exemption from frequency ride-through requirements).
17 Li Testimony at 19:17-20.
PDF page 7
7
would also advance the commercial certainty emphasized by Google by allowing developers to know in advance the period during which transition treatment is available.
ON.energy therefore requests that the Commission condition acceptance of the second transition category on an outside energization date, so that transition treatment under that category is available only to Large Loads whose Service Commencement Date, the measure MISO already uses for the first category, occurs within approximately one year after the effective date of the new requirements. ON.energy recommends approximately one year as a reasonable outer limit and would leave the precise date and implementing details to MISO on compliance. If the Commission also accepts DCC’s and Rowan’s requests to base eligibility on commercial commitments, the same outside date should apply to that broader eligibility. A boundary of that general magnitude would separate projects with genuine near-term implementation constraints from projects that remain sufficiently prospective to account for ride-through requirements before energization, consistent with the Show Cause Order’s direction that MISO “propose a reasonable implementation period to ensure minimal disruption to such existing commercial arrangements” and “allow a reasonable amount of time to finalize ongoing agreements that are nearing completion.”18
II. Commercial Reliance Does Not, by Itself, Resolve the Reliability Questions Presented by a Ride-Through Exemption.
DCC would exempt qualifying projects from the ride-through and ramp requirements based on objective evidence of commercial commitments, and Rowan would extend transition relief on a similar basis.19 OMS and the Joint Protestors, by contrast, observe that the reliability risks of
18 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 5 (2026) (“Show Cause Order”); see MISO Filing, Transmittal Letter at 13; Google Comments at 4.19 DCC Comments at 28-29; Rowan Comments at 3.
PDF page 8
8
Large Loads do not necessarily depend on when a load becomes operational.20 Both concerns are legitimate. The existence of legitimate commercial reliance addresses a different question from whether exempting a Computational Load from disturbance ride-through requirements can be accommodated without creating a material reliability concern. A project may have substantial sunk investment and genuine reliance interests while still presenting disturbance behavior that requires study or mitigation. Conversely, a late-stage project may present no material reliability concern and therefore warrant transition treatment without additional measures. ON.energy believes both commercial reliance and reliability should be considered, but agrees with Google that “ensuring electric reliability must remain job number one.” Where a material reliability concern is identified, grid reliability should control.21
MISO’s own proposal recognizes this distinction for one category of in-flight projects. For projects submitted to EPR between June 19 and October 31, 2026, MISO does not grant an automatic ride-through exemption. Instead, MISO may waive the ride-through requirement only where the applicable reliability assessment demonstrates that operation without full ride-through capability would not have an adverse reliability impact and compliance would result in significant costs. MISO’s supporting testimony states that, where such a reliability determination cannot be made, appropriate ride-through capability or mitigation would still be required.22
That same distinction should govern any request to broaden transition eligibility for other in-flight projects. Objective commercial commitments may be relevant to whether a project
20 OMS Comments at 5 (“reliability risks associated with Large Loads do not necessarily depend on when a load becomes operational”); Joint Protest at 3 (“Large Loads have reliability impacts regardless of operational date”).21 Google Comments at 5; see also id. at 1; Show Cause Order at P 58 (integrating large loads “poses specific challenges to transmission system operation given their size, operational behavior, and unique potential to impact the transmission system”); OMS Comments at 5 (asking “whether loads that present material reliability risks should be subject to appropriate reliability requirements regardless of their development status”).22 MISO Filing, Proposed Tariff § 37A.II.2(b)(ii); Li Testimony at 21:6-22:13.
PDF page 9
9
qualifies for transition consideration, but they should not substitute for evaluating the reliability consequences of the resulting ride-through exemption. Rowan’s own formulation reflects this distinction: it would provide relief where compliance would require material redesign or replacement of previously procured equipment “without a demonstrated reliability necessity.”23 ON.energy agrees with that formulation. If the Commission broadens transition eligibility based on commercial commitments, as DCC and Rowan request, ON.energy asks that any resulting exemption remain subject to MISO’s authority to require ride-through capability or other mitigation where MISO identifies a material reliability concern, as discussed in Section III below.
III. Prospective Reliability Review Can Provide Greater Commercial Certainty While Preserving MISO’s Proposed Backstop.
Google describes the “notwithstanding” language in proposed Section 37A.II.3 as important because it “allows [MISO] to continue monitoring the operational risks introduced by certain large loads and modify its approach where necessary to address reliability risks.”24 ON.energy agrees that this authority is an important backstop and should be preserved, and believes it will work best, for both reliability and commercial certainty, if MISO can apply it prospectively. A study before energization can identify a material reliability concern while the customer still has time to address it with less disruption, rather than after a problem has occurred in operation. DCC itself recognizes that “the timing of any such evaluation and the compliance timeline afforded to an affected customer will determine whether revocation is a manageable transition or a significant disruption to the customer’s operations.”2523 Rowan Comments at 3.24 Google Comments at 5.25 DCC Comments at 13.
PDF page 10
10
MISO’s tariff language does not expressly establish a prospective screening requirement for automatically exempt facilities. The proposed tariff states that MISO may require compliance where operation of a Large Load “results in a material adverse effect” and leaves the process for making that determination, as well as the requirements to be imposed, to the Business Practices Manual.26 The PIOs read that language as ambiguous regarding whether MISO may impose requirements before an exempt Large Load has caused a reliability problem.27 DCC has separately raised concerns that the standards and procedures governing withdrawal of an exemption are not sufficiently defined in the tariff.28 ON.energy agrees in part with both concerns. Section 37A.II.3 should permit MISO to act before an exempt Large Load causes a reliability problem, as the PIOs urge, and the criteria and process MISO will apply should be objective and known in advance, as DCC urges. ON.energy takes no position here on whether those details belong in the tariff or the Business Practices Manual.
ON.energy believes that a prospective, study-based process can respond to both the PIOs’ and DCC’s concerns. For a facility that has not yet energized, MISO can evaluate expected disturbance performance before operation and inform the affected customer of any identified reliability limitation while the customer still has an opportunity to implement ride-through capability or another technically appropriate mitigation. For an operating or substantially completed facility, MISO can account for legitimate reliance interests when determining the timing and scope of any necessary action. In either case, ON.energy believes the relevant measure is the facility’s performance at its Point(s) of Withdrawal, and it defers to MISO’s Business Practices Manual process on the study methods and criteria used to evaluate that performance. ON.energy
26 MISO Filing, Proposed Tariff § 37A.II.3.27 PIO Protest at 12.28 DCC Comments at 12-13, 15-16.
PDF page 11
11
does not ask the Commission or MISO to prescribe any particular equipment, architecture, or technology.
This approach can provide developers with more certainty, not less. DCC seeks assurance that exemptions, once granted, will not be “summarily revoked based on a subjective MISO assessment without regard to the stage of development of their facilities.”29 Rather than granting an exemption subject to an undefined possibility that MISO may later impose additional requirements after an operating problem emerges, a prospective assessment can identify before energization the circumstances in which mitigation may be required. Nothing in this approach requires eliminating MISO’s Section 37A.II.3 backstop or subjecting all grandfathered loads to the full requirements irrespective of demonstrated need. ON.energy therefore requests that the Commission accept Section 37A.II.3 and confirm, or direct MISO to clarify on compliance, that MISO will evaluate exempt Large Loads before energization, using objective criteria established in advance, and will require ride-through capability or other appropriate mitigation where that evaluation identifies a material reliability concern.
IV. System-Level Review Should Consider the Aggregate Amount and Electrical
Concentration of Exempt Computational Load.
The PIOs note that the IRR Proposal does not explain how MISO would address
circumstances in which Large Loads that would not individually cause a material adverse effect on reliability could do so in combination.30 ON.energy agrees the question warrants attention and believes MISO should address it by evaluating exempt Computational Load, including load that has not yet energized, in its system stability studies and by requiring an appropriate reliability
29 DCC Comments at 15-16.30 PIO Protest at 13.
PDF page 12
12
response where those studies identify a material reliability concern. Ride-through risk is not solely an individual-project question. The reliability consequence of an exemption can depend on the aggregate amount, location, electrical concentration, and modeled coincident response of similarly situated Computational Loads.31 A facility that may not present a material concern when evaluated alone may contribute to a different system response when considered with other exempt load exposed to the same disturbance. This kind of coincident response has already been observed in ERCOT and in the Eastern Interconnection, where MISO also operates, and ERCOT has accounted for it in its ride-through framework, as discussed below.32
Several parties have raised concerns regarding the amount of existing and in-flight Large Load that could receive full or partial transition treatment.33 ON.energy does not contend that the aggregate quantity cited in those pleadings would disconnect simultaneously or that a nameplate total, standing alone, establishes a reliability violation. The analysis should focus on the amount and electrical concentration of exempt Computational Load that could respond coincidentally to a credible voltage or frequency disturbance.
ERCOT’s experience is relevant to MISO because the underlying mechanism does not
depend on market design: in any system, the question is whether the combined response of exempt load exposed to a common disturbance stays within that system’s stability limits. ERCOT has recognized that multiple large electronic load facilities “at nearby locations could trip or transfer
31 See OMS Comments at 4 (Computational Loads “can experience dramatic and coordinated changes in demand, potentially across multiple facilities”).32 See NERC, Incident Review: Considering Simultaneous Voltage-Sensitive Load Reductions at 2, 8 (Jan. 8, 2025) (approximately 1,500 MW of data center load reduction coincident with a July 10, 2024 transmission disturbance in the Eastern Interconnection); NERC, Incident Review: Voltage-Sensitive Crypto Load Reductions at 2 (Jan. 9, 2026) (ERCOT identified 26 ride-through events involving indirect load loss greater than 100 MW from one or more crypto facilities between January 2023 and September 2025); PIO Protest at 4-5 (describing a July 2026 event in PJM in which approximately 3.8 GW of load tripped offline).33 See OMS Comments at 5; Joint Protest at 3; PIO Protest at 2-3.
PDF page 13
13
load at a level exceeding frequency and voltage stability limits during a common system disturbance.”34 When asked to move its grandfathering date, ERCOT evaluated the additional amount of exempt Large Load and concluded that expanding the exempt population could worsen existing reliability risk and increase the likelihood of real-time curtailment “to maintain necessary System Operating Limits to prevent load loss exceeding frequency stability thresholds.”35 ERCOT also evaluates Large Loads prospectively: new Large Loads must be included in its quarterly stability assessment to qualify for Initial Energization, and under its interim ride-through assessment it provided that energization would be conditioned on an appropriate System Operating Limit or Interconnection Reliability Operating Limit where the assessment identified a stability concern.36 ERCOT has since reported that its studies identified a load loss limit of 3,200 MW “to ensure frequency stability and reliable grid operations,” and that its most recent quarterly stability assessment identified three groups of Large Loads where a disturbance could cause a loss above that limit from loads without ride-through capability operating at or near full consumption. In each group, combined approved capacity already exceeds the limit, but ERCOT reports maximum simultaneous consumption well below it. ERCOT will implement constraints as actual consumption approaches the limit.37 Importantly, the aggregate reliability effect of transition treatment can be evaluated prospectively through system studies. MISO’s limits and load concentrations will differ from ERCOT’s, and ON.energy does not ask MISO to adopt ERCOT’s 3,200 MW limit or other ERCOT-specific thresholds.
34 ERCOT Comments on Nodal Operating Guide Revision Request 282, 282NOGRR-17, at 2 (Mar. 27, 2026).35 Id. at 5.36 ERCOT, Item 9: System Operations Update, Board of Directors Meeting, slide 6 (Sept. 14–15, 2026), available at https://www.ercot.com/files/docs/2026/09/07/9-System-Operations-Update.pdf (“ERCOT Board Update”); ERCOT, Market Notice M-A013126-01, Optional, Final Ad Hoc Interim Voltage Ride-Through Assessment for Large Loads Requesting Initial Energization Before July 1, 2026 (Jan. 31, 2026).37 ERCOT Board Update, slide 6.
PDF page 14
14
ON.energy therefore requests that the Commission direct MISO to clarify on compliance that MISO will evaluate the aggregate amount and location of exempt Computational Load, including load that has not yet energized, through appropriate post-fault voltage and frequency studies and other dynamic analysis, and, where those studies identify a material reliability concern, will require an appropriate reliability response, such as an operating limit or other mitigation, under criteria established in advance. Where the studies demonstrate that an exemption can be accommodated without material adverse effect, the project’s reliance interests can be respected without unnecessary additional requirements. Setting limits proactively and updating them as new Computational Load approaches energization, as ERCOT does, would help protect grid stability and give developers of facilities without ride-through capability earlier notice of any limits that may apply.
V. Conclusion
For the foregoing reasons, ON.energy respectfully requests that the Commission grant leave to answer and accept this Limited Answer. In acting on MISO’s filing and the competing requests concerning transition treatment, ON.energy requests that the Commission: (1) condition acceptance of the second transition category on an outside energization date limiting transition treatment to Large Loads whose Service Commencement Date occurs within approximately one year after the effective date, with the precise date specified by MISO on compliance; (2) if it broadens transition eligibility based on commercial commitments, as DCC and Rowan request, apply the same outside date to that broader eligibility and keep any resulting exemption subject to Section 37A.II.3; and (3) direct MISO to clarify on compliance that, under Section 37A.II.3, MISO will evaluate exempt Large Loads, individually and in the aggregate, before energization using objective criteria established in advance, and will require ride-through capability or other
PDF page 15
15
appropriate mitigation where that evaluation identifies a material reliability concern. These requests would preserve reasonable protection for legitimate reliance interests while keeping transition eligibility objective and time-limited and preserving prospective, system-level assessment of material reliability risks.
Respectfully submitted,
ON ENERGY STORAGE, INC.
/s/ Lucas Fykes
Lucas Fykes
Senior Director, Policy & Regulatory Affairs
ON Energy Storage, Inc.
2900 SW 28th Terrace, Suite 701
Miami, FL 33133
Email: lucas.fykes@on.energy
Phone: (614) 254-8565
Dated: September 24, 2026
PDF page 16
16
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.
Dated at Scottsville, Kentucky, this 24th day of September, 2026
/s/ Lucas Fykes
Lucas Fykes
ON Energy Storage, Inc.
2900 SW 28th Terrace, Suite 701
Miami, FL 33133
Phone: (614) 254-8565