Motion for Leave to Answer and Limited Answer of ON Energy Storage, Inc. in response to comments and protests re Midcontinent Independent System Operator,…
Text extracted from the eLibrary original (SHA-256 fcd1c66b536adbc4…). Download the original from the official source.
Contents · 5 sections
- I. ON.energy Supports Reasonable, Objective, and Time-Limited Transition Treatment
- II. Commercial Reliance Does Not, by Itself, Resolve the Reliability Questions Presented
- III. Prospective Reliability Review Can Provide Greater Commercial Certainty While
- IV. System-Level Review Should Consider the Aggregate Amount and Electrical
- V. Conclusion
Read topic-matched comments in ER26-3650
Topics in the text: Registry access · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
In particular, ON.energy asks the Commission to condition acceptance of MISO’s transition provisions on an outside energization date for Large Loads that receive transition treatment based on the MTEP/EPR Condition or any broader commercial-maturity test, and to direct MISO to clarify that exempt…Read this passage Filed comments: Registry access
I. ON.energy Supports Reasonable, Objective, and Time-Limited Transition Treatment
printed heading
Its concern is with the second category, which exempts qualifying Large Loads from the ride-through and ramp requirements without any limit on when they must begin taking service.Read this passage
II. Commercial Reliance Does Not, by Itself, Resolve the Reliability Questions Presented
printed heading
ON.energy believes both commercial reliance and reliability should be considered, but agrees with Google that “ensuring electric reliability must remain job number one.” Where a material reliability concern is identified, grid reliability should control.21 MISO’s own proposal recognizes this…Read this passage
III. Prospective Reliability Review Can Provide Greater Commercial Certainty While
printed heading
ON.energy therefore requests that the Commission accept Section 37A.II.3 and confirm, or direct MISO to clarify on compliance, that MISO will evaluate exempt Large Loads before energization, using objective criteria established in advance, and will require ride-through capability or other…Read this passage
IV. System-Level Review Should Consider the Aggregate Amount and Electrical
printed heading · Topic match: Reliability and curtailment
ERCOT has recognized that multiple large electronic load facilities “at nearby locations could trip or transfer 31 See OMS Comments at 4 (Computational Loads “can experience dramatic and coordinated changes in demand, potentially across multiple facilities”). 32 See NERC, Incident Review:…Read this passage
V. Conclusion
printed heading
Conclusion For the foregoing reasons, ON.energy respectfully requests that the Commission grant leave to answer and accept this Limited Answer.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Scottsville, Kentucky, this 24th day of September, 2026 /s/ Lucas Fykes Lucas Fykes ON Energy Storage, Inc. 2900 SW 28th Terrace, Suite 701 Miami, FL 33133 Phone: (614) 254-8565Read this passage