ER26-3380-000 · 2026-09-24 · New Jersey Board of Public Utilities
Motion for Leave to Answer and Answer of the New Jersey Board of Public Utilities to the Answer et al. of PJM Interconnection, L.L.C. filed on 09/10/2026
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
THE NEW JERSEY BOARD OF PUBLIC UTILITIES
On July 31, 2026, PJM Interconnection, L.L.C. (“PJM”) proposed revisions to the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) and the Open Access Transmission Tariff (“Tariff”) to establish the Reliability Backstop Procurement (“RBP”). On August 21, 2026, the New Jersey Board of Public Utilities (“Board”) submitted comments.1
On September 10, 2026, PJM filed a Motion for Leave to Answer and Answer.2 Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure, the Board respectfully moves for leave to answer and submits this Answer to provide additional information and context that will assist the Commission in its decision-making process.
I. Motion for Leave to Answer
While Rule 213(a)(2) generally prohibits answers to protests and comments, good cause justifies the Commission’s granting this motion and accepting this Answer because it provides
1 PJM Interconnection, L.L.C., Comments of the New Jersey Board of Public Utilities, Docket No. ER26- 3380 (Aug. 21, 2026) (“NJ BPU Comments”).2 PJM Interconnection, L.L.C., Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26-3380 (Sept. 10, 2026) (“PJM’s Answer”).
PDF page 2
2
useful and relevant information that will assist the Commission in its decision-making process.3 The information presented here came to the Board’s attention recently, during its efforts earlier this month to review Load Adjustments in New Jersey and compare those Load Adjustments to the proposed RBP cost obligations.4
II. Answer
PJM has proposed to use the 6.8 GW shortfall from the 2028/2029 Base Residual Auction (“BRA”) as the initial target amount for the RBP.5 As stated in its Comments to PJM’s RBP Proposal, the Board ultimately supports PJM using this value for setting the procurement target; the Board understands that aligning this target more directly with distinct large loads would require additional time, and the Board understands the importance of running this backstop procurement promptly.6
The Board submits this Answer to express concern over the inputs used to establish PJM’s cost allocation proportions set forth in its RBP Proposal. As explained in PJM’s Answer, the proposed RBP cost allocations are based on the Load Adjustments between 2026 and 2028 that the electric distribution companies (“EDCs”) submitted to PJM.7 Conceptually, the Board supports
3 See, e.g., PJM Interconnection, L.L.C., 142 FERC ¶ 61,019, P 23 (2013); PJM Interconnection, L.L.C., 145 FERC ¶ 61,035, at P 32 (2013); Wis. Pub. Serv. Corp., 144 FERC ¶ 61,093, at P 27 (2013); Iberdrola Renewables, Inc. v. Bonneville Power Admin., 137 FERC ¶ 61,185, at P 17 (2011); SW Power Pool, Inc., 119 FERC ¶ 61,199 at P 18 (2007); and Allegheny Elec. Coop. v. PJM Interconnection, 119 FERC ¶ 61,165 at P 10 (2007).4 A recent revision to PJM Manual 19, effective June 30, 2026, added a new step in the Load Forecast Adjustment process requiring submitters to provide their Relevant Electric Retail Regulatory Authority (“RERRA”) with an opportunity to review their adjustments. See Revision 39 to PJM Manual 19, Attachment B.5 See PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380 (July 31, 2026) (“PJM RBP Proposal”), Transmittal Letter at 31.6 NJ BPU Comments at 4.7 PJM’s Answer at 71.
PDF page 3
3
this approach because “[e]ach [EDC] zone/area’s proportional share of the total Load Adjustment MW is a means of capturing the zone/area’s proportional share of the influx of new large load that is projected to come online in the near future.”8 However, the Board is concerned that substantial discrepancies exist in the inputs each EDC zone/area used to develop the Load Adjustment, and that these discrepancies will result in a discriminatory cost allocation outcome. Undue discrimination occurs when entities are “similarly situated,” and there is “no legitimate reason for the difference in treatment.”9 Here, different EDC zones/areas may obtain different cost allocations due to differences in the assumptions and inputs used in forming their 2026 Load Adjustments, rather than differences in actual load growth alone. This inconsistent set of assumptions does not provide a legitimate reason for different treatment when establishing cost allocations.
To this end, the Board recommends that PJM run the backstop as proposed starting in September 2026,10 and requests that FERC require PJM to submit a compliance filing to reform its cost-allocation methodology using updated Load Adjustments. Specifically, the Board requests that this reformed methodology establish a consistent MW threshold (50 MW) for large loads reported across each zone/area so the Load Adjustments used for cost allocation in the RBP can appropriately capture each zone/area’s proportional share of large load growth.
i. Inconsistencies in Large Load MW Thresholds Across Zones/Areas Result in a Cost Allocation Result that is Discriminatory
8 Id. at 72.9 PJM Interconnection, L.L.C., 184 FERC ¶ 61,087, P 46 (2023) (citing Mo. River Energy Servs. v. FERC, 918 F.3d 954, 958 (D.C. Cir. 2019)). 10 PJM RBP Proposal at 3 n. 5.
PDF page 4
4
Board Staff recently met with the EDCs under its retail jurisdiction to discuss the 2027 Load Adjustments. This is a new process established under recent revisions to PJM Manual 19.11 The Board used this process to better understand the Load Adjustment process. It is now clear that the 2026 Load Adjustments used to determine PJM’s proposed cost allocation methodology12 relied on data from EDCs with substantially different characteristics across the PJM footprint.13 For example, the Board understands that, in New Jersey, while some EDCs reported load growth only for new large loads of 50 MW and above, other EDCs reported all Load Adjustments with no specific MW threshold. Importantly, PJM used these inputs in its Load Adjustment, which determines RBP cost allocation.
Presentations from PJM’s September 2025 Load Analysis Subcommittee suggest these inconsistencies could be regional, with the result being that EDCs receive different RBP cost allocations based not on load growth alone but on the characteristics they chose to include as Load Adjustments at the time. For example, FirstEnergy’s presentation states it uses loads 50 MW or greater as inputs to the Large Load Adjustment,14 while Duke Energy states that it reported expansions of 20 MW or greater15 – note, PJM later removed Duke Energy’s Load Adjustment
11 Revision 39 to PJM Manual 19, Attachment B (adding the RERRA Review requirement, effective June 30, 2026).
12 See PJM’s Answer at 71 (identifying the final RBP zonal allocation amounts).13 Manual 19 has been updated to specifically require load shifts using a 50 MW threshold for future Load Adjustments. PJM Manual 19, Attachment B (adding, under a June 30, 2026, revision, the 50 MW or greater threshold).14 FirstEnergy, PJM LAS Large Load Adjustment Presentation 4 (Sept. 16, 2025), https://www.pjm.com/- /media/DotCom/committees-groups/subcommittees/las/2025/20250916/20250916-item-04h---first- energy-large-load-request.pdf.15 Duke Energy, Approach to Large Load Adjustments 3 (Sept. 2025), https://www.pjm.com/- /media/DotCom/committees-groups/subcommittees/las/2025/20250916/20250916-item-04l--duke-large- load-request.pdf.
PDF page 5
5
because PJM determined its economic models would capture the load growth.16 It is unclear how pervasive these different treatments were because the EDC zones/areas providing Load Adjustments generally did not specify whether they used a MW threshold. Therefore, the Board thinks allocating costs using these inputs is unduly discriminatory because some loads that are less than 50 MW in one zone may need to take on RBP obligations, whereas loads of the same size in a different zone will not, solely because its EDC zone/area decided to include it or not in its Large Load Adjustment.
Importantly, PJM’s original goals for the Large Load Adjustment process were to enhance transparency, improve accuracy, and mitigate double counting,17 and, for this reason, it may not have been necessary for each EDC to use consistent methods during this initial reporting period. However, if PJM’s RBP Proposal is approved, these inputs will result in substantial RBP cost obligations for zones/areas and therefore, the Board thinks it is crucial to revisit these inputs to establish a consistent threshold and treatment.
Ultimately, the Board supports PJM’s use of Large Load Adjustments to determine RBP cost allocation because it is roughly commensurate with large load growth in zones/areas and these customers have contributed most to PJM’s resource adequacy shortfall. However, the Board thinks this element of the RBP must be revised so that zones/areas receive consistent treatment in the RBP. The Board thinks this issue can be resolved after the RBP is held but before the RBP cost
16 PJM Interconnection, L.L.C., Load Adjustment Request Summary for 2026 Load Forecast – Preliminary 9 (Nov. 24, 2025), https://www.pjm.com/-/media/DotCom/committees- groups/subcommittees/las/2025/20251124/20251124-item-03---large-load-adjustment-requests- summary.pdf.17 PJM Interconnection, L.L.C., Large Load Adjustment Process Improvement Discussion 3 (June 10, 2025), https://www.pjm.com/-/media/DotCom/committees- groups/subcommittees/las/2025/20250613/20250613-item-03---large-load-adjustment-process- improvement-discussion.pdf.
PDF page 6
6
apportionment and thinks that PJM should file a compliance filing that uses a consistent threshold across zones/areas in the Load Adjustment.18
III. Conclusion
The Board recently became aware of these significant reporting inconsistencies and appreciates FERC’s consideration of the Board’s Answer. The Board thinks these changes can be made without necessitating substantial reform of PJM’s underlying RBP Proposal.
Respectfully,
18 See PJM’s Answer at 8-9 (explaining that “PJM is amenable to discrete adjustments to incorporate intervenors’ suggestions into the RBP proposal in a compliance filing if so ordered by the Commission” and citing to Cal. Indep. Sys. Operator Corp., 134 FERC ¶ 61,140, at P 1 (2011) as support for Commission’s discretion to order a compliance filing revising tariff provisions meant to rectify inconsistencies with proposal’s intent.).
PDF page 7
7
NEW JERSEY BOARD OF PUBLIC
UTILITIES
By: /s/ Paul Youchak
Ian Oxenham
Alex Cary
Amanda Lescano
Timothy Randazzo
Mahala Lahvis
Airi Kogishi
New Jersey Board of Public Utilities
44 South Clinton Ave.
Trenton NJ 08609
Paul.youchak@bpu.nj.gov
Ian.oxenham@bpu.nj.gov
Alexander.cary@bpu.nj.gov
Amanda.lescano@bpu.nj.gov
Timothy.randazzo@bpu.nj.gov
Mahala.lahvis@bpu.nj.gov
Airi.kogishi@bpu.nj.gov
MICHAEL L. ZUCKERMAN
ACTING ATTORNEY GENERAL
OF NEW JERSEY
By: /s/ Jordan K. Mitchell
Deputy Attorney General
Department of Law and Public Safety
Division of Law
P.O. Box 112
Trenton, NJ 08625
Jordan.mitchell@law.njoag.gov
Attorneys for the New Jersey Board of
Public Utilities
Dated: September 24, 2026
Trenton, New Jersey
PDF page 8
8
CERTIFICATE OF SERVICE
I hereby certify that, on this 24th day of September, 2026, I have caused the foregoing document to be served upon each party designated on the official service list compiled by the Secretary in this proceeding, by email.
By: /s/ Jordan K. Mitchell
Jordan Mitchell
Deputy Attorney General
New Jersey Office of the Attorney General
Department of Law & Public Safety
P.O. Box 112
Trenton, New Jersey 08625
Jordan.mitchell@law.njoag.gov