ER26-3380-000 · 2026-09-24 · New Jersey Board of Public Utilities

Motion for Leave to Answer and Answer of the New Jersey Board of Public Utilities to the Answer et al. of PJM Interconnection, L.L.C. filed on 09/10/2026

Text extracted from the eLibrary original (SHA-256 d7f5d0f0ffbbed5d…). Download the original from the official source.

Contents · 3 sections
  1. I. Motion for Leave to Answer p. 1
  2. II. Answer p. 2
  3. III. Conclusion p. 6

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Reliability and curtailment · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.
Read this passage

I. Motion for Leave to Answer

printed heading

Motion for Leave to Answer While Rule 213(a)(2) generally prohibits answers to protests and comments, good cause justifies the Commission’s granting this motion and accepting this Answer because it provides 1 PJM Interconnection, L.L.C., Comments of the New Jersey Board of Public Utilities, Docket…
Read this passage

II. Answer

printed heading · Topic match: Cost allocation

Specifically, the Board requests that this reformed methodology establish a consistent MW threshold (50 MW) for large loads reported across each zone/area so the Load Adjustments used for cost allocation in the RBP can appropriately capture each zone/area’s proportional share of large load growth.…
Read this passage Filed comments: Cost allocation

III. Conclusion

printed heading

Conclusion The Board recently became aware of these significant reporting inconsistencies and appreciates FERC’s consideration of the Board’s Answer.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Mitchell Jordan Mitchell Deputy Attorney General New Jersey Office of the Attorney General Department of Law & Public Safety P.O.