ER26-3515-000 · 2026-09-25 · American Electric Power Service Corporation
Motion for Leave to Reply and Reply Comments of American Electric Power Service Corporation
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
MOTION FOR LEAVE TO REPLY AND REPLY COMMENTS OF
AMERICAN ELECTRIC POWER SERVICE CORPORATION
American Electric Power Service Corporation, on behalf of its affiliates Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, and Wheeling Power Company (collectively, “AEP”), submits this motion for leave to reply and reply. AEP seeks leave to reply to several comments submitted in response to PJM Interconnection, LLC’s (“PJM’s”) proposed tariff revisions to the PJM Open Access Transmission Tariff (“PJM Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) proposed in the above-captioned docket to establish Interim Resource Adequacy Service (“IRAS”) effective October 12, 2026.1 AEP also seeks leave to reply to PJM’s Motion for Leave to Answer and Answer filed on September 23, 2026.2 As AEP discusses below, PJM’s treatment of the Fixed Resource Requirement (“FRR”) Alternative under its IRAS proposal, as clarified by AEP’s comments in this proceeding, is necessary to ensure
1 PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish Interim Res. Adequacy Serv. and a Large Load Registry to Address Sys. Reliability, Docket No. ER26-3515 (filed Aug. 13, 2026) (“IRAS Proposal”).
2 PJM Interconnection, L.L.C., Morion For Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26-3515 (filed Sept. 23, 2026) (“PJM Reply”).
PDF page 2
2
that the FRR Alternative remains viable and just and reasonable.3 Critically, the clarifications that AEP seeks from the Commission in its comments are also important to the viability of the FRR Alternative and do not seek to avoid the requirement to serve new Large Load with new capacity.
I. MOTION FOR LEAVE TO REPLY
While Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure does not generally permit answers to protests, the Commission has permitted answers where the answer clarifies the issues or assists in creating a complete record.4 Accordingly, AEP respectfully requests leave to reply to the relevant protests and, to the extent necessary, the relevant comments in the above-captioned docket. In several instances, the protests misrepresent or ignore the plain language of the IRAS Proposal and how the FRR Alternative will be addressed in the IRAS Proposal. Good cause exists to grant this motion for leave to answer because the answer corrects those unsupported misstatements and misrepresentations, leading to a full and complete record in this proceeding.
II. REPLY
A. FRR Entities and RPM Entities Are Not Similarly Situated, and the
IRAS Proposal’s Differential Treatment Is Therefore Just and
Reasonable.
Certain commenters argue that the IRAS Proposal is unduly preferential and discriminatory because FRR Entities are exempt from IRAS while load serving entities
3 PJM Interconnection, L.L.C., Comments and Request for Clarification of Am. Elec. Power Serv. Corp., Docket No. ER26-3515 (filed Sept. 3, 2026) (“AEP Comments”).4 18 C.F.R. § 385.213(a)(2) (2026).
PDF page 3
3
(“LSEs”) participating in the Reliability Pricing Model (“RPM”) are subject to it. These arguments fail because they rest on the flawed premise that FRR load is similarly situated to RPM load. It is not. The critical distinction is structural: RPM Entities may rely on the RPM auction as a backstop to meet their capacity obligations, whereas FRR Entities cannot. Instead, FRR load can come online only if it is served by capacity that the FRR Entity has contracted for or owns. This fundamental difference in capacity obligation design dooms the claims of undue discrimination or preferential treatment, because the Commission has long held that there is no undue discrimination when entities are
differently situated.5 Moreover, even if FRR Entities and RPM Entities were similarly situated—which they are not—PJM has articulated a sound basis for the differential treatment, and the Commission has confirmed that “there is no undue discrimination or preference [when] we have identified appropriate reasons for it.”6 Thus, the Commission should reject commenters’ discrimination arguments.
East Kentucky Power Cooperative, Inc.’s (“EKPC”) arguments exemplify this
flawed reasoning. EKPC argues that the IRAS Proposal is unduly discriminatory because FRR Entities are exempt from IRAS while RPM Entities that have prudently planned
5 City of Anaheim, Opinion No. 483, 113 FERC ¶ 61,091, at P 130 (2005) (“Discrimination is undue when there is a difference in rates or services among similarly situated customers that is not justified by some legitimate factor.”) (citations omitted); PacifiCorp Elec. Operations, 54 FERC ¶ 61,296, at 61,855 (“[U]ndue discrimination can occur only when two similarly situated customers are treated differently, and there is no justification for the differing treatment.”) (citations omitted), reh’g denied, 55 FERC ¶ 61,461 (1991); Puget Sound Energy, Inc. v. All Jurisdictional Sellers of Energy, Opinion No. 537, 151 FERC ¶ 61,173, at P 43, n.105 (2015) (quoting Energy Transfer, 120 FERC ¶ 61,086, at P 169 (2007)), rev’d on other grounds, 157 FERC ¶ 61,026 (2016) (“It is well established that a finding of undue discrimination requires a showing that ‘(1) two classes of customers are treated differently; and (2) the two classes of customers are similarly situated.’”).6 Midwest Indep. Transmission Sys. Operator, Inc., 155 FERC ¶ 61,082 at P 31 (2016).
PDF page 4
4
capacity to serve their load remain subject to it.7 EKPC contends that, because both have planned capacity, FRR Entities and such RPM Entities are similarly situated.8 This contention is wrong. The question is not whether an entity has prudently planned capacity. Rather, the question is whether an entity has a guaranteed safety net in the RPM auction if its capacity position proves inadequate. FRR Entities do not have that safety net, while RPM Entities do. Thus, they are not similarly situated. The structural difference also determines whether the entity contributes to the RPM auction shortfall that IRAS is designed to address.
The FRR Alternative imposes stringent self-supply obligations that distinguish FRR Entities from RPM Entities. An FRR Entity must identify the load it expects to serve and must own, build, or contract for the capacity necessary to serve that load in each delivery year.9 Critically, the FRR Entity must procure sufficient capacity to serve not only anticipated load but also any actual load that materializes during the Delivery Year.10 If the FRR Entity’s forecast proves wrong, it has no safety net because it cannot turn to the RPM auction for additional capacity.11
RPM Entities face no comparable constraint. They are not required to own or contract for their own capacity. Instead, they may rely entirely on the RPM auction to
7 PJM Interconnection, L.L.C., Limited Protest of East Ky. Power Coop., Inc., Docket No. ER26-3515, at 13 (filed Sept. 3, 2026) (“EKPC Comments”).8 EKPC Comments at Attach. 1, Affidavit of Marc Montalvo at ¶¶ 40-41.9 See PJM Open Access Transmission Tariff, Attach. DD, section 1.10 Id.11 PJM Reliability Assurance Agreement, Schedule 8.1, section D.1.1.
PDF page 5
5
satisfy their capacity obligations.12 And even if an RPM Entity chooses to self-supply, the RPM auction remains available as a backstop if its capacity needs change.13 This access to the RPM auction is material to the IRAS Proposal because the RPM auction has experienced capacity shortfalls for upcoming delivery years. These shortfalls prompted PJM to propose IRAS. Because FRR Entities do not participate in the RPM auction and cannot draw on it as a backstop, it is logical to exclude them from the IRAS Proposal. The Commission should therefore reject claims that the IRAS Proposal’s differential treatment of FRR Entities and RPM Entities is unduly discriminatory or preferential. Commenters also contend that it is unduly preferential and discriminatory to permit FRR Entities to serve New Large Load using Existing Generation Capacity Resources while RPM Entities cannot.14 This argument, too, ignores the structural differences between the FRR Alternative and RPM. As noted above, unlike RPM Entities, which can satisfy capacity obligations through the auction, FRR Entities must own or contract for all the capacity needed to serve their loads. Allowing FRR Entities limited flexibility to deploy Existing Generation Capacity Resources for New Large Load recognizes that inflexibility in FRR Plan structuring could undermine the viability of the FRR Alternative altogether because it has no backstop or safety net.
12 PJM Open Access Transmission Tariff, Attach. DD, section 6.13 Id.14 PJM Interconnection, L.L.C., Protest of the Elec. Power Supply Assn., Docket No. ER26-3515, at 12 (filed Sept. 3, 2026) (“EPSA Comments”).
PDF page 6
6
At the same time, the IRAS Proposal does not give FRR Entities unlimited flexibility. Recognizing that FRR Entities could otherwise draw Existing Generation Capacity Resources away from the RPM auction and exacerbate the capacity shortfall that IRAS seeks to remedy, the IRAS Proposal imposes limitations on FRR Entities. An FRR Entity may use Existing Generation Capacity Resources to serve New Large Load only if the FRR Entity owned or contracted for those resources before June 1, 2027.15 The June 1, 2027 cutoff serves dual purposes. First, it preserves the operational flexibility that FRR Entities need to structure their FRR Plans. Second, it protects the RPM auction by preventing FRR Entities from acquiring additional Existing Generation Capacity Resources after the cutoff date to serve New Large Load and ensures that the IRAS Proposal’s goal of addressing RPM auction shortfalls is not undermined by capacity migration to FRR service.16 Again, these arguments that IRAS is unduly discriminatory or results in preferential treatment fail and should be rejected.
B. The Commission Should Reject PJM’s Claims That AEP’s Proposed
Clarifications Will Allow It to Avoid The Requirement to Serve New
Large Load With New Capacity.
In its comments, AEP requests that the Commission clarify that, when the IRAS rules are lifted in times where capacity is not short, the FRR restrictions are similarly lifted.17 AEP also requests that the Commission clarify that when IRAS reactivates after
15 IRAS Proposal, Attach. B, Revisions to the PJM Open Access Transmission Tariff and Resource Adequacy Agreement, Schedule 8.1, section D.1.1, Docket No. ER26-3515 (filed Aug. 13, 2026) (“Proposed RAA”).
16 PJM Transmittal Letter at 73-74.17 AEP Comments at section IV.A.
PDF page 7
7
being dormant, FRR Entities be provided flexibility to serve any Large Loads that came online prior to that reactivation with Existing Generation Capacity Resources.18 As discussed above, this flexibility is critical to ensuring that FRR Entities can economically and reliably serve all FRR loads and recognizes the structural differences between FRR Entities and RPM Entities.
In response, PJM contends that these clarifications would “undermine the overarching policy driving IRAS and the Ratepayer Protection Pledge” because the clarifications would not result in FRR Entities serving new Large Load with new capacity.19 PJM’s response mischaracterizes how FRR works. As PJM itself admits later in its answer, “[b]y definition, FRR Entities must bring new capacity for all new loads within their territory.”20 This obligation is embedded in an FRR entity’s overall obligation to include sufficient capacity in its FRR Capacity Plan for all of its load.21 Thus, by definition any new Large Load served by an FRR Entity must be served by new capacity consistent with the policy driving IRAS and the Ratepayer Protection Pledge. The clarification AEP seeks is necessary to ensure that it has the flexibility to acquire and use that capacity, once brought online to serve all load when the IRAS takes effect on June 1, 2027, in the most efficient manner to address overall FRR needs in future years. This is critical to ensure that AEP can reliably and cost-effectively serve its customers.
18 Id. at section III.B.19 PJM Reply at 62.20 Id. at 63 (citing RAA, Article 1) (emphasis in the original).21 Id. at 63 & n.227 (citing RAA, Schedule 8.1D, section 7).
PDF page 8
8
Accordingly, the Commission should reject PJM’s claim and grant the clarifications sought by AEP in its comments.
C. The IRAS Proposal Should Incentivize Alignment with Its Stated Goals
and Avoid Jurisdictional Vulnerability.
AEP supports commenters who argue the Commission should ensure IRAS
incentivizes actions that align with the service’s goals and that the tariff changes are legally durable. For example, IRAS aims to address capacity shortfall in the RPM auction by requiring RPM Entities to Bring Your Own New Capacity (“BYONC”) for Eligible New Large Load, but commenters argue that the proposal leaves it uncertain whether BYONC will allow Eligible New Large Load to avoid being curtailed under IRAS.22 Commenters argue that the IRAS Proposal is structured in a way that leaves open the possibility that Eligible New Large Load could be curtailed under IRAS even if such load has BYONC.23 Thus, AEP encourages the Commission to address any incentive misalignment present in the IRAS Proposal.
Commenters also highlight aspects of the IRAS Proposal that risk succumbing to legal challenge. They note that PJM’s proposal attempts to thread the needle between state and federal jurisdiction, but this narrow path to “cooperative federalism” is vulnerable to challenge.24 Unlike recent large load tariff reforms that PJM claims are analogous to IRAS,
22 PJM Interconnection, L.L.C., Protest of Google LLC, Docket No. ER26-3515, at 1-2, 3-7 (filed Sept. 3, 2026) (“Google Comments”).23 Id.24 See Google Comments at 5-6, 8-11; PJM Interconnection, L.L.C., Mot. to Intervene, Protest & Req. for Clarification of PPL Elec. Utils. Corp., Docket No. ER26-3515, at 15-16 (filed Sept. 3, 2026) (“PPL Comments”).
PDF page 9
9
such as SPP’s HILLGA proposal and MISO’s ERAS proposal, these commenters argue that the IRAS Proposal attempts to reach retail customers, beyond the bounds of federal jurisdiction.25 AEP urges the Commission to require PJM to address this jurisdictional risk. The Commission should not approve a version of the IRAS Proposal that could lead to lengthy litigation and may very well be successfully challenged—this would contravene the goals of IRAS to expeditiously address an urgent capacity shortfall.
D. Any Suggestion That AEP’s Ohio Large Load Tariff Is Not Protecting
Retail Customers Is Unfounded.
Finally, the Office of the Ohio Consumers’ Counsel (“OCC”) contends that AEP’s state large load tariff in Ohio26 “does not adequately protect consumers from the federal curtailments PJM is proposing for large load customers” under IRAS.27 To the extent OCC suggests that AEP’s Ohio large load tariff fails to protect Ohio retail customers, its assertion is unfounded. The AEP Ohio large load tariff was approved by the Public Utilities Commission of Ohio and is designed to recognize the importance of large loads and to ensure they can connect and be served while protecting retail customers from unnecessary cost increases. OCC provides no evidence that the AEP Ohio large load tariff is not working as intended. Any suggestion otherwise is misleading.
25 See Google Comments at 6-7; PPL Comments at 14-16.26 In the Matter of the Application of Ohio Power Co. for New Tariffs Related to Data Centers and Mobile Data Centers, Opinion and Order, Case No. 24-508-EL-ATA (Ohio PUCO Jul. 9, 2025); see also In the Matter of the Application of Ohio Power Co. for New Tariffs Related to The Standard Service Offer Service for Data Center Load, Finding and Order, Case No. 26-113-EL-ATA (Ohio PUCO Aug. 5, 2026).27 PJM Interconnection, L.L.C., Protest by Office of the Ohio Consumers’ Counsel, Docket No. ER26- 3515, at 26-28 (filed Sept. 3, 2026) (“OCC Comments”).
PDF page 10
10
III. CONCLUSION
For the foregoing reasons, AEP respectfully requests that the Commission: (1) reject commenters’ claims that the IRAS Proposal’s treatment of FRR Entities is unduly discriminatory or preferential because FRR Entities are not similarly situated to RPM Entities (2) reject PJM’s claims that the clarification sought by AEP will allow it to avoid the proposed requirement to serve new Large Load with new capacity; and (3) ensure the IRAS Proposal is legally durable and incentivizes actions that align with its stated goals.
John C. Crespo
Senior Legal Advisor
American Electric Power Service
Corporation
1 Riverside Plaza
Columbus, OH 43215
(614) 716-3727
jccrespo@aep.com
Respectfully submitted,
/s/ William M. Keyser
William M. Keyser
Megan McDowell
Steptoe LLP
1330 Connecticut Avenue, NW
Washington, DC 20036
202-429-8186
wkeyser@steptoe.com
mmcdowell@steptoe.com
Counsel for AEP
Dated: September 25, 2026
PDF page 11
11
CERTIFICATE OF SERVICE
Pursuant to Rule 2010, 18 C.F.R. § 385.2010, I hereby certify that I have this day caused the foregoing document to be served upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C. on this 25th day of September, 2026.
/s/ Jeannette Crooks
Jeannette Crooks
Steptoe LLP
1330 Connecticut Avenue, NW
Washington, DC 20036