ER26-3515-000 · 2026-09-25 · American Electric Power Service Corporation

Motion for Leave to Reply and Reply Comments of American Electric Power Service Corporation

Text extracted from the eLibrary original (SHA-256 a984892de73cea84…). Download the original from the official source.

Contents · 7 sections
  1. I. MOTION FOR LEAVE TO REPLY p. 2
  2. II. REPLY p. 2
  3. A. FRR Entities and RPM Entities Are Not Similarly Situated, and the p. 2
  4. B. The Commission Should Reject PJM’s Claims That AEP’s Proposed p. 6
  5. C. The IRAS Proposal Should Incentivize Alignment with Its Stated Goals p. 8
  6. D. Any Suggestion That AEP’s Ohio Large Load Tariff Is Not Protecting p. 9
  7. III. CONCLUSION p. 10

Read topic-matched comments in ER26-3515

Topics in the text: Cost allocation · Registry access · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

Adequacy Serv. and a Large Load Registry to Address Sys.
Read this passage Filed comments: Registry access

I. MOTION FOR LEAVE TO REPLY

printed heading

MOTION FOR LEAVE TO REPLY While Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure does not generally permit answers to protests, the Commission has permitted answers where the answer clarifies the issues or assists in creating a complete record.4 Accordingly, AEP respectfully…
Read this passage

II. REPLY

printed heading

II.
Read this passage

A. FRR Entities and RPM Entities Are Not Similarly Situated, and the

printed heading

An FRR Entity must identify the load it expects to serve and must own, build, or contract for the capacity necessary to serve that load in each delivery year.9 Critically, the FRR Entity must procure sufficient capacity to serve not only anticipated load but also any actual load that materializes…
Read this passage

B. The Commission Should Reject PJM’s Claims That AEP’s Proposed

printed heading · Topic match: Cost allocation

As PJM itself admits later in its answer, “[b]y definition, FRR Entities must bring new capacity for all new loads within their territory.”20 This obligation is embedded in an FRR entity’s overall obligation to include sufficient capacity in its FRR Capacity Plan for all of its load.21 Thus, by…
Read this passage Filed comments: Cost allocation

C. The IRAS Proposal Should Incentivize Alignment with Its Stated Goals

printed heading

The IRAS Proposal Should Incentivize Alignment with Its Stated Goals and Avoid Jurisdictional Vulnerability.
Read this passage

D. Any Suggestion That AEP’s Ohio Large Load Tariff Is Not Protecting

printed heading

Any Suggestion That AEP’s Ohio Large Load Tariff Is Not Protecting Retail Customers Is Unfounded.
Read this passage

III. CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, AEP respectfully requests that the Commission: (1) reject commenters’ claims that the IRAS Proposal’s treatment of FRR Entities is unduly discriminatory or preferential because FRR Entities are not similarly situated to RPM Entities (2) reject PJM’s claims that…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. on this 25th day of September, 2026. /s/ Jeannette Crooks Jeannette Crooks Steptoe LLP 1330 Connecticut Avenue, NW Washington, DC 20036