ER26-3515-000 · 2026-09-28 · Corporate Energy Buyers Association
Motion for Leave to Answer and Answer of Corporate Energy Buyers Association to PJM Interconnection, L.L.C.'s 09/23/2026 Answer re the Proposal to Establish…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
CORPORATE ENERGY BUYERS ASSOCIATION
Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (FERC or Commission) Rules of Practice and Procedure,1 Corporate Energy Buyers Association (CEBA) respectfully submits this motion for leave to answer and limited answer to the answer filed by PJM Interconnection, L.L.C. (PJM) in this proceeding.2 CEBA submits this answer to correct PJM’s characterization of CEBA’s position regarding customer-sponsored Peak Shaving Adjustments and to explain why the PJM Answer does not resolve the undue preference identified in CEBA’s protest.3
I. MOTION FOR LEAVE TO ANSWER
Although Rule 213(a)(2) does not generally permit answers to protests, the Commission permits answers for good cause shown, such as when an answer contributes to a more accurate and complete record or provides useful information that aids the Commission’s decision-making process.4 CEBA respectfully moves for leave to file this answer because it responds to
1 18 C.F.R. §§ 385.212, 385.213.2 PJM Sept. 23 Motion for Leave to Answer and Answer (PJM Answer).3 CEBA Sept. 3 Motion to Intervene and Protest (CEBA Protest).4 See, e.g., PJM Interconnection, L.L.C., 189 FERC ¶ 61,110, at P 22 (2024) (accepting answers to protests and answers because they assisted the Commission in its decision-making process).
PDF page 2
2
arguments raised in the PJM Answer that mischaracterize CEBA’s position. As discussed below, PJM’s arguments do not address an issue that the Commission must help resolve in order to ensure that large load customers can invest with confidence in a full range of solutions to the resource adequacy challenges confronting the PJM region. For this reason, good cause exists for the Commission to grant this motion.
II. ANSWER
The PJM Answer does not resolve the disparate treatment identified in CEBA’s Protest. Instead, PJM responds to an argument CEBA did not make. PJM characterizes CEBA and other intervenors as challenging the “omission of Peak Shaving Adjustment MW from [Bring Your Own New Capacity (BYONC)] arrangements” and ultimately concludes that Peak Shaving
Adjustments (PSAs) “cannot and should not qualify as BYONC MW capable of reducing
[Interim Resource Adequacy Service (IRAS)] exposure.”5 But CEBA did not ask PJM to treat PSA MW as BYONC, permit them to participate as Capacity Resources in capacity auctions (Reliability Pricing Model [RPM] Auctions), or make them dispatchable during an IRAS Action. CEBA asked for a tariff-based mechanism that recognizes incremental, customer-sponsored PSAs that reduce PJM’s capacity requirement, including qualifying investments elsewhere within the relevant utility service territory or zone.65 PJM Answer at 47–48, n.170 (characterizing CEBA and other intervenors as challenging the “omission of Peak Shaving Adjustment MW from BYONC arrangements” and concluding that Peak Shaving Adjustments “cannot and should not qualify as BYONC MW capable of reducing IRAS exposure”).6 CEBA Protest at 8–9 (requesting “a clear tariff-based mechanism” for recognition of “incremental, customer- sponsored Peak Shaving Adjustments that reduce PJM’s capacity requirement,” including qualifying investments elsewhere within the relevant utility service territory or zone, and explaining that the requested treatment would permit New Large Loads to address resource adequacy through “either incremental supply or an incremental reduction in the capacity requirement”).
PDF page 3
3
Fundamentally, CEBA seeks recognition of incremental, customer-sponsored PSAs for what they are: reductions in forecast peak demand that reduce the underlying capacity need associated with new load growth. The IRAS proposal is patently unjust, unreasonable, and unduly preferential insofar as it fails to recognize that core resource adequacy benefit of customer-sponsored PSAs.
A. PJM conflates reducing the capacity need with providing a Capacity
Resource while failing to reconcile its position with its treatment of PSAs under the RBP proposal
PJM conflates two distinct ways of addressing a resource adequacy need: adding capacity to meet incremental demand and reducing the incremental demand for which capacity must be procured. PJM emphasizes that PSA MW are “adjustments to PJM’s load forecasts, not resources that may participate in RPM Auctions.”7 That distinction does not rebut CEBA’s argument; it is the premise of it. As CEBA has previously argued, PJM’s own rules recognize qualifying PSAs as reductions to forecast peak demand and, therefore, to the capacity requirement that PJM must satisfy when procuring capacity, whether through the RBP or RPM Auctions.8 The fact that the reduction occurs on the demand side rather than through the addition
7 PJM Answer at 47.8 CEBA Protest at 8, n.13 (citing PJM Manual 19, Load Forecasting and Analysis, § 3.2).
PDF page 4
4
of a Capacity Resource does not eliminate that resource adequacy benefit, nor does PJM offer evidence to the contrary.9
PJM’s discussion of the RBP reinforces this point. PJM notes that qualifying PSA MW may reduce the identified capacity shortfall for which the RBP will procure while PSA MW cannot serve as Qualifying RBP Offset UCAP MW or eligible RBP Resources. CEBA does not contend otherwise. The relevant feature of the RBP is that PJM recognizes qualifying PSAs on the demand side of the equation by reducing the capacity shortfall—quantified in the RBP Initial Procurement Target—that must be addressed through new supply. CEBA seeks comparable recognition here: not treatment of PSA MW as supply, but recognition that incremental, customer-sponsored peak shaving reduces the capacity need attributable to the sponsoring New Large Load.
B. PJM’s reliance on real-time dispatchability misses the point
PJM’s observation that PSA MW are not “real-time dispatchable” is irrelevant.10 As PJM itself explains, “[t]he impetus for IRAS is to incent New Large Loads to bring new capacity to meet their resource adequacy needs.”11 If an incremental, qualifying PSA reduces PJM’s forecast peak in the first instance and therefore reduces the amount of capacity that must be procured to meet a New Large Load’s resource adequacy needs, that capacity need has been reduced before any real-time IRAS Action ever occurs. PJM does not explain why real-time
9 Moreover, in the IRAS proposal, PJM itself recognizes that a Peak Shaving Adjustment may “reduce the amount of capacity needed to meet the PJM Region Reliability Requirement.” PJM Filing, Transmittal at 54.10 PJM Answer at 48 (explaining that Peak Shaving Adjustments are not a “real-time dispatchable product” and therefore, in PJM’s view, should not qualify as BYONC MW capable of reducing IRAS exposure).11 Id. at 45.
PDF page 5
5
dispatchability is necessary to recognize that reduction when determining the amount of a New Large Load’s demand that gives rise to IRAS exposure in the first place.12
C. PJM’s disparate treatment of customer-sponsored PSAs is unjustified and
counterproductive to state-led efforts to support resource adequacy
Under the IRAS proposal, the disparate treatment is straightforward. Consider two otherwise identical New Large Loads. One customer supports new Capacity Resources that PJM determines provide 25 MW of capacity toward addressing the incremental resource adequacy need associated with its load. The other finances qualifying incremental peak-shaving capability that reduces PJM’s forecast peak demand and, after application of the Forecast Pool Requirement, reduces PJM’s capacity requirement by the same 25 MW. PJM’s proposal recognizes the first customer’s contribution in determining its IRAS exposure but provides no comparable mechanism to recognize the second. PJM identifies differences between Capacity Resources and PSAs, but it does not explain why those differences justify treating differently two investments that reduce PJM’s otherwise-unmet capacity need by the same amount. In addressing other parties’ tangential arguments about BYONC gating criteria for Demand Resources and DER Capacity Aggregation Resources—both supply-side Capacity Resources—PJM implies that its skepticism toward customer-sponsored PSAs may similarly stem from concern that such investments will not produce “new and lasting” solutions to the capacity shortfall.13 Customer-sponsored PSAs can rely on the same types of distributed energy
12 Id. at 48.13 Id. at 49 (“IRAS is an operational tool designed to address the shortfall created by the absence of new Capacity Resources that offer lasting solutions to the capacity shortfall.”).
PDF page 6
6
infrastructure, including distributed battery storage, that support aggregations participating as supply-side Capacity Resources. Yet PJM has established BYONC gating criteria to ensure that Demand Resources and DER Capacity Aggregation Resources provide “new and lasting capacity contributions to the capacity shortfall.”14 Although the criteria may differ, CEBA asks only that customer-sponsored PSAs have a similar opportunity to demonstrate that their underlying infrastructure investments can provide lasting resource adequacy benefits.
Lastly, PJM’s disparate treatment between customer-sponsored PSAs and Capacity
Resources could foreclose a valuable source of investment in precisely the types of near-term, distributed-scale solutions that states are actively seeking to develop, particularly in the face of persistent barriers to interconnecting new, utility-scale generation. Virginia and New Jersey, for example, are pursuing programs to deploy distributed battery storage and other distributed resources to reduce peak demand and associated capacity needs.15 A framework that recognizes customer investment in new Capacity Resources but provides no means to recognize customer investment in qualifying Peak Shaving Adjustments would eliminate an important incentive for New Large Loads to help finance these emerging pathways and frustrate legitimate state policy goals aiming to unlock these innovative approaches.
14 Id. at 48–49 (explaining the purpose of PJM’s requirement for BYONC that is backed by Demand Resources and DER Capacity Aggregation Resources to demonstrate Accredited UCAP each year of the 10-year BYONC commitment period).15 Chief Energy Officer for the Governor of Virginia Sept. 3 Comments at 2–3 (“Virginia has already acted to establish pathways for voluntary demand-flexibility programs that enable large loads to secure measurable and verifiable load reductions…. PJM’s rules should provide a clear, timely, and administrable process through which these state-supported arrangements can be recognized in IRAS…, with such reductions accounted for in a customer’s curtailment exposure and related obligations.”); see also New Jersey Board of Public Utilities Sept. 18 Motion for Leave to Answer and Answer at 4–5.
PDF page 7
7
D. Customer-sponsored PSAs and new Capacity Resources are complementary
pieces to the resource adequacy puzzle
To reiterate, CEBA is not asking the Commission to transform PSAs into Capacity Resources or to require PJM to count PSA MW as BYONC. Rather, PJM should revise proposed Tariff, Attachment DD-4, section V(b), to recognize the reduction in PJM’s capacity requirement attributable to a verified, incremental, customer-sponsored PSA when determining the sponsoring New Large Load’s Eligible New Large Load Amount.16 PJM should apply the Forecast Pool Requirement as needed to express that benefit in the units used by section V(b), and establish appropriate rules for verification and safeguard against double counting. This would recognize the PSA’s effect on resource adequacy without treating it as BYONC or as a resource PJM can dispatch during an IRAS Action.
This approach preserves the distinction on which PJM relies. BYONC supplies incremental capacity; PSAs reduce forecast demand. But both can support resource adequacy by reducing the incremental capacity need associated with a New Large Load. PJM has not explained why IRAS should recognize only one side of that equation.
III. CONCLUSION
For the foregoing reasons, CEBA respectfully asks that the Commission accept this answer in the record and find that PJM’s IRAS proposal is unjust, unreasonable, and unduly preferential insofar as it provides no mechanism to recognize the reduction in PJM’s capacity
16 PJM Filing, Attach. A, Proposed Tariff, Attach. DD-4, § V(b).
PDF page 8
8
requirement attributable to a verified, incremental, customer-sponsored PSA when determining the sponsoring New Large Load’s IRAS exposure. CEBA asks the Commission to require PJM to provide such a mechanism, with appropriate verification, attribution, and safeguards against double counting.
Respectfully submitted,
/s/ John Miller___________________
John Miller
Director, Transmission Policy
CEBA
1501 M Street, N.W., Suite 900
Washington, D.C. 20005
(240) 630-2201
jmiller@ceba.org
September 28, 2026
PDF page 9
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.
Dated at Washington, D.C., this 28th day of September 2026.
/s/ John Miller___________________
John Miller
Director, Transmission Policy
CEBA
1501 M Street, N.W., Suite 900
Washington, D.C. 20005
(240) 630-2201
jmiller@ceba.org