ER26-3515-000 · 2026-09-29 · Advanced Energy United

Motion for Leave to Answer and Answer of Advanced Energy United to PJM Interconnection, L.L.C.'s 09/23/2026 Answer re the Proposal to Establish Interim…

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)
PJM Interconnection, L.L.C

)

Docket No. ER26-3515-000

)

MOTION FOR LEAVE TO ANSWER AND ANSWER
 OF ADVANCED ENERGY UNITED

Pursuant to Rule 212 and 213 of the Federal Energy Regulatory Commission’s
(“Commission”) Rules of Practice and Procedures,1 Advanced Energy United2 (“United”)
submits this motion for leave to answer and limited answer to the answer of PJM
Interconnection, L.L.C. (“PJM”) in the above-captioned proceeding.3 United submits this limited answer because PJM’s Answer mischaracterizes the relief United actually requested regarding customer-sponsored Peak Shaving Adjustments (“PSA”),4 and because PJM’s stated rationale for declining that relief is inconsistent with positions PJM takes elsewhere in the same Answer.

I. MOTION FOR LEAVE TO ANSWER

Although Rule 213(a)(2) does not generally permit an answer to an answer, the
Commission grants leave where good cause is shown, including where an answer assists the Commission’s decision-making process by correcting the record or supplying information the

1 18 C.F.R. § 385.211
2 Advanced Energy United is a national association of businesses that are making the energy we use secure, clean, and affordable. Advanced Energy United is the only industry association in the United States that represents the full range of advanced energy technologies and services, both grid-scale and distributed. Advanced energy includes energy efficiency, demand response, energy storage, wind, solar, hydro, nuclear, electric vehicles, and more. The views expressed in these comments reflect the position of Advanced Energy United, but do not necessarily reflect the views of any particular member with respect to any issue.
3 Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26-3515-000, (Sept. 23, 2026) (“PJM Answer”)
4 Comments of Advanced Energy United, Docket No. ER26-3515-000, at 3 (September 3, 2026). (“United Comments”)

PDF page 2

2
Commission needs to resolve a disputed issue.5 Good cause exists here. PJM’s Answer directly addresses and rejects a specific request in United’s comments6, but does so by responding to a different, broader proposal than the one United actually made, and by relying on a rationale PJM does not apply consistently elsewhere in that same Answer. Leaving that mischaracterization and inconsistency unaddressed risks leading the Commission to resolve this issue based on an inaccurate description of the relief United requested. United accordingly requests leave to file this limited answer.

II. ANSWER

United's answer addresses three distinct flaws in how PJM’s Answer treats Peak Shaving Adjustments (“PSA”) under IRAS, each independent of the others. First, PJM’s rejection of PSAs as a verifiable tool to reduce resource adequacy need rests on a distinction PJM does not apply consistently elsewhere in its own Answer. Second, PJM defends against a broader proposal to treat PSA as a substitute for large loads supporting new capacity through Bring Your Own New Capacity (“BYONC”), rather than the narrower one United actually requested, which was that PSAs be taken into account when calculating IRAS exposure. Third, PJM treats PSA and BYONC as equivalent rather than recognizing that they address the same capacity gap from different sides and thus crediting one does not require relaxing requirements for the other. Taken

5 See, e.g., PJM Interconnection, L.L.C., 189 FERC ¶ 61,110, at P 22 (2024) (accepting answers to protests and answers because they assisted the Commission in its decision-making process). 6 PJM Answer at 47-48 (citing United Comments at 3).

PDF page 3

3
together, these flaws show that PJM’s Answer does not actually respond to the issue United raised.

A. PJM’s Rejection of PSA Credit to Displace IRAS Need Rests on an Internal Inconsistency in PJM’s Own Answer

PJM’s Answer rejects crediting PSA against a New Large Load’s IRAS exposure on the ground that PSA amounts are “adjustments to PJM’s load forecasts, not resources that may participate in RPM Auctions,” and are not a “real-time dispatchable product.”7 PJM reasons that this distinction settles the question: because PSA does not clear an auction and cannot be called upon in real time, it categorically cannot reduce the capacity need giving rise to IRAS curtailment.

PJM’s own Answer, however, shows that this distinction does not actually settle anything. In the same filing, PJM confirms that it already permits qualifying PSA MW “that qualify for an opt-out to potentially reduce the identified 2027/2028 Delivery Year capacity shortfall for which the RBP will procure.”8 That is, PJM already treats a PSA value, the identical kind of forecast adjustment PJM now calls too unreliable to be taken into account under IRAS, as sound enough to shrink the actual, binding quantity of capacity PJM goes out and procures through the companion Reliability Backstop Procurement mechanism.9 Just as a PSA value serves to reduce how much capacity PJM is targeting to procure under the RBP, it should be factored into how much of a load’s demand counts as unmet capacity need under IRAS. PJM offers no explanation for why the same PSA value should be treated as germane in one proceeding and irrelevant in the other. Both the RBP procurement target and the IRAS

7 Id.
8 Id.
9 See, PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000, (July 31, 2026) (“PJM RBP”)

PDF page 4

4
Eligible New Large Load Amount are wholesale-level calculations of how much capacity is actually needed to serve PJM’s system given the unmet demand from New Large Loads. PJM designed RBP and IRAS as companion mechanisms addressing the same shortfall, and PJM cannot now maintain two incompatible positions on the reliability of the same underlying data depending on which mechanism is more convenient in each instance.

If a qualifying PSA value is sound enough to reduce PJM’s own procurement target under RBP, it is sound enough to reduce the capacity need attributable to the New Large Load that sponsored it. The same treatment of PSA that already applies under RBP is equally relevant here and should be incorporated as a means to reduce IRAS exposure.

B. PJM’s “Not Dispatchable” Rationale Answers a Request United Did Not
Make

PJM’s Answer builds its rejection of PSA credit around PSA’s unsuitability as a substitute for BYONC, a tradable, must-offer capacity resource that PJM’s Tariff requires to satisfy specific capacity market obligations.10 On that framing, PSA fails because it cannot be dispatched, cannot clear an auction, and carries none of the ongoing capacity-market obligations BYONC carries.

PJM is drawing an unnecessary parallel between BYONC and PSA, and responding to a request United never made. United’s comments did not ask PJM to treat PSA as BYONC, to permit PSA to participate in RPM Auctions, or to make PSA dispatchable during an IRAS Action. United asked only that PJM’s Tariff “specify that the deduction under this formula for a qualifying Peak Shaving Adjustment or comparable state-authorized reduction shall equal the MW value calculated and verified by PJM pursuant to its applicable procedures.”11 That is a

10 PJM Answer at 47-48
11 United Comments at 4.

PDF page 5

5
request to reflect an already-measured reduction in resource-adequacy need, not a request to convert PSA into a capacity product it was never designed to be.

The distinction matters because PJM’s own Eligible New Large Load Amount
calculation is not itself a real-time dispatch decision. It is a forecast-based determination, built from registration data, load forecasts, and capacity commitments, that fixes a load’s exposure before any Interim Resource Adequacy Alert is ever called.12 A qualifying PSA reduces the underlying capacity need that calculation is meant to measure before any such Alert occurs, in exactly the same way BYONC and Allocated RBP UCAP MW do. Whether PSA could be dispatched during an emergency is beside the point; the reduction it represents has already occurred by the time PJM performs the calculation PJM proposes to use.

United respectfully requests that the Commission consider the argument in our original filing, which was that the IRAS exposure calculation should take into account a verified reduction in resource-adequacy need resulting from PSA, rather than PJM’s mischaracterization of that request as an ask to treat PSA as a dispatchable capacity resource.

C. PSA and BYONC Are Complementary, Not Competing, Categories
PJM’s Answer proceeds as though recognizing PSA within the Eligible New Large Load Amount formula would require treating PSA as a substitute for BYONC, competing for the same role BYONC already fills. It would not. BYONC and PSA address the same underlying problem, i.e., the gap between a New Large Load’s demand and the capacity available to serve it, from two different directions, and nothing in United’s request asks PJM to blur that distinction.

12 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No. ER26-3515-000, (Aug. 13, 2026)")

PDF page 6

6
BYONC works on the supply side: it adds new capacity to the system to match or offset a load’s demand. PSA works on the demand side: it reduces the capacity PJM must otherwise procure, or the amount of curtailment that may be necessary. A load that brings 50 MW of BYONC and a load that supports the reduction of the zonal or EDC peak by 50 MW through a qualifying PSA arrive at an identical outcome, from PJM’s perspective: the load’s otherwise- unmet capacity need shrinks by the same amount. The mechanism differs, but the resource- adequacy benefit does not, and thus large loads should be given the same credit. PJM itself recognized PSA and BYONC as different sides of the same coin in its Transmittal Letter when it excluded any locations from “new” BYONC status that had previously helped “reduce the amount of capacity needed to meet the PJM Region Reliability Requirement through a Peak Shaving Adjustment or Price Responsive Demand.”13

Recognizing the verified benefit of PSA does not require PJM to loosen any of the requirements applicable to BYONC, which would remain the only pathway to recognize a New Large Load’s contribution to bringing actual new capacity to the system, subject to must-offer requirements, capacity market participation, and the ten-year commitment discussed above.14 PSA would remain what it already is under PJM’s own rules, a verified reduction to the forecast peak demand from which a load’s capacity need is calculated.15 Because PJM already relies on PSA as a demand-side decrement in the RPM today, alongside other demand-side measures such as Price Responsive Demand (“PRD”),16 it is not a speculative or unverified figure. Rather, it is

13 Transmittal Letter at 54 (citing Proposed Tariff, Attachment DD-4, §§ VI(b)(ii)(1)-(2))
14 Id at 43-44.
15 Id at 47-48; see also, PJM Manual 19, Load Forecasting and Analysis, § 3.2 (explaining, “In cases where a zone contains a peak shaving program with an approved Peak Shaving Adjustment Plan, the zone’s forecast will be adjusted to reflect the program’s impact.”).
16 PJM committed 106.5 MW UCAP of PRD in the 2027/2028 Base Residual Auction (“BRA”) PJM Interconnection, L.L.C., 2027/2028 Base Residual Auction Report, at 3 n.1 (Dec. 17, 2025). PJM describes PRD as “a predictable change in the amount of electricity used, not as additional generation.” PJM Interconnection, L.L.C., “Price Responsive Demand Fact Sheet” at 2 (March 23, 2017).

PDF page 7

7
tied to a specific, state-authorized program, triggered by an objective measure, the actual maximum daily temperature-humidity index for the relevant zone, scored over a rolling three- year period, and verified through PJM’s own applicable procedures.17 PSA does not need to be dispatchable or tradable to be a reliable input into a forecast-based formula that is not itself a real-time dispatch determination. It only needs to be measured accurately, and PJM’s own rules already ensure that it is.

Consideration of both BYONC and PSA as complementary tools will result in a more accurate measure of a load’s true, net capacity need than a Tariff that recognizes only one side of that calculation. The success and impact of PJM’s IRAS proposal depends on getting that net figure right. The purpose of the Eligible New Large Load Amount formula is to identify how much of a load’s demand remains genuinely uncovered.18 A formula that credits new supply but ignores a verified reduction in peak demand does not measure that figure accurately, it systematically overstates it for any load that has taken real, verified steps to reduce the regional shortfall. PJM should be directed to correct the formula so that it reflects both halves of a New Large Load’s actual net capacity need. Failure to do so will result in a harmful over-estimation of IRAS need while diminishing the incentive for New Large Loads to pursue PSA as a mechanism to affordably and quickly reduce pressure on the strained PJM grid.

III. CONCLUSION

PJM’s Answer does not resolve the issue United raised; it responds to a different request while relying on a rationale PJM does not apply consistently elsewhere in the same filing. United asks the Commission to direct PJM to credit qualifying, verified PSA values in the Eligible New

17 PJM Answer at 48 (citing PJM Manual 19: Load Forecasting and Analysis, § 3.2 (rev. 39, June 30, 2026)).
18 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Aug. 13, 2026).

PDF page 8

8
Large Load Amount formula on the same basis PJM already applies under RBP. United respectfully requests that the Commission grant this motion for leave to answer and accept this answer.

Respectfully submitted,

/s/   Mike Haugh

Caitlin Marquis, Managing Director
Mike Haugh, Director
Jon Gordon, Senior Director
Kelsey Koenig, Associate
Advanced Energy United
1801 Pennsylvania Ave. N.W., Suite 410
Washington, D.C. 20006
cmarquis@advancedenergyunited.org
mhaugh@advancedenergyunited.org
jgordon@advancedenergyunited.org
kkoenig@advancedenergyunited.org

PDF page 9

9
CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated this 29th day of September, 2026.

/s/ Mike Haugh