ER26-3515-000 · 2026-09-29 · Advanced Energy United

Motion for Leave to Answer and Answer of Advanced Energy United to PJM Interconnection, L.L.C.'s 09/23/2026 Answer re the Proposal to Establish Interim…

Text extracted from the eLibrary original (SHA-256 67c43a3378c1635b…). Download the original from the official source.

Contents · 6 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 1
  2. II. ANSWER p. 2
  3. A. PJM’s Rejection of PSA Credit to Displace IRAS Need Rests on an Internal p. 3
  4. B. PJM’s “Not Dispatchable” Rationale Answers a Request United Did Not p. 4
  5. C. PSA and BYONC Are Complementary, Not Competing, Categories p. 5
  6. III. CONCLUSION p. 7

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Interconnection, L.L.C ) Docket No.
Read this passage

I. MOTION FOR LEAVE TO ANSWER

printed heading

United accordingly requests leave to file this limited answer.
Read this passage

II. ANSWER

printed heading · Topic match: Reliability and curtailment

First, PJM’s rejection of PSAs as a verifiable tool to reduce resource adequacy need rests on a distinction PJM does not apply consistently elsewhere in its own Answer.
Read this passage Filed comments: Reliability and curtailment

A. PJM’s Rejection of PSA Credit to Displace IRAS Need Rests on an Internal

printed heading · Topic match: Reliability and curtailment

PJM’s Rejection of PSA Credit to Displace IRAS Need Rests on an Internal Inconsistency in PJM’s Own Answer PJM’s Answer rejects crediting PSA against a New Large Load’s IRAS exposure on the ground that PSA amounts are “adjustments to PJM’s load forecasts, not resources that may participate in RPM…
Read this passage Filed comments: Reliability and curtailment

B. PJM’s “Not Dispatchable” Rationale Answers a Request United Did Not

printed heading · Topic match: Reliability and curtailment

PJM’s “Not Dispatchable” Rationale Answers a Request United Did Not Make PJM’s Answer builds its rejection of PSA credit around PSA’s unsuitability as a substitute for BYONC, a tradable, must-offer capacity resource that PJM’s Tariff requires to satisfy specific capacity market obligations.10 On…
Read this passage Filed comments: Reliability and curtailment

C. PSA and BYONC Are Complementary, Not Competing, Categories

printed heading · Topic match: Reliability and curtailment

PSA works on the demand side: it reduces the capacity PJM must otherwise procure, or the amount of curtailment that may be necessary.
Read this passage Filed comments: Reliability and curtailment

III. CONCLUSION

printed heading

United asks the Commission to direct PJM to credit qualifying, verified PSA values in the Eligible New 17 PJM Answer at 48 (citing PJM Manual 19: Load Forecasting and Analysis, § 3.2 (rev. 39, June 30, 2026)). 18 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated this 29th day of September, 2026. /s/ Mike Haugh