ER26-3515-000 · 2026-09-29 · Constellation Energy Generation, LLC
Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC to the Answers filed by Pennsylvania Governor Josh Shapiro et al. re the…
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.:
205(d) Rate Filing: Proposal to Establish
Interim Resource Adequacy Service & a
Large Load Registry to be effective
10/12/2026
)
)
)
)
)
)
Docket No. ER26-3515-000
MOTION FOR LEAVE TO ANSWER AND ANSWER
OF CONSTELLATION ENERGY GENERATION, LLC
Pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, Constellation Energy Generation, LLC (“Constellation”) respectfully moves for leave to answer and answers comments filed in this proceeding by PJM (“PJM Answer”) and Pennsylvania Governor Josh Shapiro (“Shapiro Answer”).1 Constellation seeks to respond to issues raised by the Answers to provide information that will assist in the Commission’s decision-making process as it relates to PJM’s August 12, 2026 Proposal (“PJM Proposal,” “IRAS Proposal,” or “Proposal”).
I. MOTION FOR LEAVE TO ANSWER
Constellation respectfully moves for leave to answer.2 The Commission routinely grants motions to answer for good cause.3 Good cause exists where an answer provides information that assists in the Commission’s decision-making process. 4 And good cause exists here, as Constellation’s Answer clarifies important issues raised in the Answers and thereby provides information that will assist the Commission in addressing the Proposal.
1 Together, those two filings are referred to in this filing as “the Answers.”2 This motion is made under FERC Rule 212, 18 C.F.R. § 385.212.3 See 18 C.F.R. §§ 385.101(e), 385.213(a)(2). 4 See, e.g., SunZia Transmission, 191 FERC ¶ 61053, at P 46 (Apr. 17, 2025); Columbia Gas Transmission, 182 FERC ¶ 61,171, at P 9 (Mar. 17, 2023).
PDF page 2
2
II. ANSWER
The Proposal exceeds the Commission’s jurisdiction. The Proposal also unlawfully discriminates based on load size, load date, and resource vintage, and its design is unjust and unreasonable in numerous respects. In arguing otherwise, the Answers misunderstand the applicable law and conveniently ignore key features of the proposed tariff. They also incorrectly suggest that the Proposal is the only way to address issues raised by new large loads and that the Ratepayer Protection Pledge somehow justifies violating limits set by the FPA—neither of which is true.
A. The Proposal Is Outside The Scope Of The Commission’s Jurisdiction
1. The Answers Incorrectly Contend That Judicial Decisions Support The
View That The Commission Has Jurisdiction Whenever An Action
Affects The Wholesale Market
The Answers are wrong about what courts have held in defining the scope of the
Commission’s jurisdiction. The Answers’ overall import is that any effect on the wholesale market is enough to make the Proposal jurisdictionally acceptable—a proposition that the Supreme Court has soundly rejected.
First, addressing Constellation’s “targeting” argument and relying heavily on FERC v. EPSA, 577 U.S. 260 (2016), PJM’s Answer contends that the question of whether an action crosses the jurisdictional line is all about the intent behind that action, defined at a high level of generality.5 That is self-evidently incorrect. As EPSA explains, the Commission could not “issue[] a regulation compelling every consumer to buy a certain amount of electricity on the retail market,” even though “[s]uch a rule would necessarily determine the load purchased on the wholesale market too, and thus would alter wholesale prices”6—regardless of whether (in PJM’s words) the “justification for” that
5 E.g., PJM Answer 19-20 (stating that whether targeting is occurring “turns on the justification for the rule”). 6 EPSA, 577 U.S. at 280.
PDF page 3
3
regulation was to benefit the wholesale market in some way.7 Were the law otherwise, the statutorily mandated limits on the Commission’s jurisdiction would essentially cease to exist, because—given the connection between the wholesale and retail markets—it would be easy to claim that almost any retail-market-targeted action was ultimately intended to have some wholesale-market effect.
In reality, the “targeting” question—which is just one of multiple relevant factors in assessing jurisdiction, all of which point against asserting jurisdiction here8—is a more practical one. It asks whether “the things [the] regulation is directed at, the control of rates and facilities … , are precisely the things over which FERC has comprehensive authority.”9 In EPSA, the answer was yes—not because it was possible to hypothesize some downstream wholesale-market related justification, but because the action in question addressed only transactions on the wholesale market and the justification for the action matched its target.10 Here, the answer is plainly no. The Proposal is directed at New Large Loads’ demand for power purchased at retail and seeks to control and regulate the terms of retail sales to those loads, including through the cudgel of curtailment. The fact that the Proposal’s ultimate goal may be to affect the wholesale market is of no moment, as EPSA makes clear: the Commission “cannot take an action transgressing th[e] limit” on intruding on the retail sphere “no matter how direct[] or dramatic” that action’s “impact on wholesale rates” may be.11
Second, citing New Jersey Board of Public Utilities v. FERC, 744 F.3d 74 (3d Cir. 2014), PJM’s Answer contends that IRAS is jurisdictionally permissible because it prevents States’ choices about “retail customers and retail rates” from “‘adversely affecting wholesale capacity rates.’”12 But
7 PJM Answer 19-20. 8 Constellation Protest 10-13.9 Schneidewind v. ANR Pipeline, 485 U.S. 293, 308 (1988).10 See EPSA, 577 U.S. at 282-83, 287.11 Id. at 280. 12 New Jersey, 744 F.3d at 98, quoted in PJM Answer 28.
PDF page 4
4
that decision does not support PJM’s position. It predates EPSA by two years, and so does not reflect the Supreme Court’s holding that a mere effect on wholesale rates is not enough to trigger this Commission’s statutorily defined jurisdiction.13 And in any event, New Jersey is distinguishable because the Commission action at issue there directly regulated the terms of capacity auctions and did not purport to reach into the retail sphere, although it permissibly had some effects there.14
2. The Answers Conveniently Ignore The Requirement In the Proposed
Tariff To Curtail A Particular Category Of Retail Customers And
Otherwise Mischaracterize The Proposal And Protestors’ Position
a. The Answers mischaracterize the proposed tariff and the effect on a specific class of retail customer, identified by retail characteristics. The Answers repeatedly contend that the Proposal does not dictate which particular retail customers will be curtailed and claim that this demonstrates that the proposed tariff does not intrude into States’ discretion to decide which customers should be curtailed.15 That is incorrect. The proposed tariff language requires that Eligible New Large Loads be curtailed, which is a means of penalizing them for not bringing their own new generation. Indeed, PJM’s Answer admits as much when it states that “only New Large Load may be eligible to provide IRAS.”16 As a result, the Proposal targets and seeks to dictate the terms of retail sales as to specific types of retail customers, identified by retail characteristics. That is a fatal jurisdictional problem— and the Answers have no rejoinder to it.
The express terms of the proposed tariff, which would govern if the Commission accepted the Proposal, make that problem clear. The proposed tariff states that “Electric Distributors” shall “execute the [PJM] Office of the Interconnection’s directives to implement Interim Resource
13 See EPSA, 577 U.S. at 282-83, 287.14 See New Jersey, 744 F.3d at 90-91, 98 (action preventing “uneconomic offers” from “clear[ing] the auction”).15 E.g., Shapiro Answer 10 (stating that the Proposal “neither targets nor directs specific retail customers to be subject to curtailment”); PJM Answer 29 (“[S]tates/RERRAs may determine which retail customers will implement the load reduction directives.”).16 PJM Answer 61.
PDF page 5
5
Adequacy Service Actions among the Eligible New Large Loads in the Electric Distributor’s zone/area.”17 It states that a proposed registry that contains only information about large loads will “inform which New Large Loads are eligible to be called on to provide” IRAS—that is, to be curtailed.18 And it states that compensation will be provided for those curtailed by “compensating all Eligible New Large Loads that provided [IRAS]”—i.e., the only retail customers that “provided” that “service.”19 The proposed tariff language leaves no doubt that Electric Distributors would actually violate the PJM tariff if they bypassed curtailment of Eligible New Large Loads and chose to curtail other retail customers instead.20
It is no surprise that the proposed tariff reads that way, because absent that specific direction about curtailing Eligible New Large Loads the Proposal could not function as intended. The whole point of the Proposal is to push New Large Loads, as PJM defines that term, to bring their own new capacity.21 If the curtailment consequence of a New Large Load’s failure to do so could fall on residential customers or on New Large Loads that had complied with the BYONC requirement, then there is no reason to believe that the Proposal would incentivize New Large Loads to bring their own new capacity—and nothing about the Proposal would help to solve the problem of system reliability that the Answers identify as the Proposal’s raison d’être.2217 Proposed Tariff Attachment DD-4 §§ II(e), III(a) (emphasis added); see id. (stating that the PJM “shall … request Electric Distributors to direct that a quantity of Eligible New Large Load Amounts … be reduced in accordance with an [IRAS] Action”); id. § IV(a) (“All Eligible New Large Loads shall be available to be requested to provide [IRAS] by the [PJM] Office of the Interconnection.”).18 Id. § I(a), I(c) (emphasis added).19 Proposed Tariff Attachment DD-4 § X(b)(i) (emphasis added); see id. § I(a), I(c) (IRAS “is a load reduction service” and “Eligible New Large Loads may be compensated for providing load reductions”).20 PJM’s transmittal letter says the same thing. See Constellation Protest 22 (citing examples); see also PJM Answer 61 (acknowledging that “PJM explain[ed] in the August 13 Filing” that “only New Large Load may be eligible to provide IRAS”).21 E.g., PJM Answer 48-49 (“underlying purpose of BYONC, and the reason BYONC may reduce IRAS exposure [i.e., curtailment]—is to incentivize new and lasting capacity contributions to the capacity shortfall”); id. at 61.22 There could be situations in which an Electric Distributor is instructed to curtail a certain number of megawatts
PDF page 6
6
In ignoring that central fact about the proposed tariff, the Answers engage in a sort of shell game. On one hand, they insist that Electric Distributors are totally free to decide which retail customers to curtail. On the other hand, they insist that the Proposal is needed because it will work to ensure that new large loads like data centers shoulder the burden of bringing their own new capacity and that the burden should not fall on existing loads that have (in the Answers’ view) already staked a claim to existing capacity.23 But both things cannot be true at the same time. And, as the proposed tariff language demonstrates, the first of those things is not true. Because PJM asks the Commission to put in place a regime that disfavors and curtails the service of a specific type of retail customer, thus affecting whether such customers receive the retail service for which they have paid retail rates, the Commission has no jurisdiction.24
It is no answer to assert without explanation (as the Answers do) that, within the disfavored group of Eligible New Large Loads, Electric Distributors can decide which particular Eligible New Large Loads will be forced to suffer curtailment. There is no jurisdictional distinction between regulation of a particular retail customer and regulation of a category of retail customer identified by specific retail characteristics.25 Any other jurisdictional rule would be irrational. If Congress’s jurisdictional limitation could be evaded with respect to a category of, say, three or four retail customers simply through identifying them by category rather than by name, then that limitation would be easy to circumvent and would create precisely the overlap between state and federal jurisdiction that Congress legislated to avoid.26
under IRAS but no Eligible New Large Loads have yet come online. In that specific situation, the curtailment would presumably fall on (and harm) other retail customers. See Part II.C.3, infra; N.J. BPU Answer 2-4.
23 E.g., PJM Answer 48-49.24 Constellation Protest 13-15.25 Constellation Protest 23.26 Constellation Protest 23; see 16 U.S.C. § 824(a).
PDF page 7
7
PJM’s Answer claims that the Commission’s recent decision in Tri-State Generation & Transmission Association, 196 FERC ¶ 61,127 (2026), illustrates that “tariff provisions addressing ‘concerns regarding the rapid growth of large loads[]’ do not constitute ‘an impermissible intrusion upon retail rate regulation’” so long as utilities have some discretion about exactly how those provisions affect their retail customers.27 But Tri-State does not illustrate any such thing. In an earlier 2025 decision, the Commission rejected a prior Tri-State proposal for addressing large loads that would have required Tri-State’s wholesale customers to set minimum load and energy requirements for retail customers with which they dealt.28 The Commission explained that the proposed tariff “require[d] specific terms and conditions of service by a Utility Member to an end- use [High Impact Load] Customer (i.e., a retail service)” and that the “specification of terms of sale at retail ‘is a job for the States alone.’”29 Subsequently, Tri-State revised its proposal to eliminate any requirement that a utility take action with respect to any retail customer; the new proposal placed requirements directly on utilities involving only “provision of transmission service and wholesale power,” without “dictat[ing] the terms or conditions of retail service.”30 The Commission’s 2026 decision deems that new proposal jurisdictionally acceptable because it “does not include provisions that establish” such terms or conditions, but instead “impos[es] obligations only on Tri-State’s Utility Members and leav[es] those same Utility Members full discretion as to whether they will flow … through” the consequences to retail customers.31
The Proposal here is like the first Tri-State proposal that the Commission rejected, not like the second Tri-State proposal that the Commission accepted. PJM’s Proposal unquestionably
27 PJM Answer 24-25, 29.28 Tri-State Generation and Transmission Ass’n, 193 FERC ¶ 61,070, at PP 49-50 (2025). 29 Id.30 196 FERC ¶ 61,127, at PP 65-68.31 Id.; see PJM Answer 29-30 (quoting Tri-State, 196 FERC ¶ 61,127 at P 25).
PDF page 8
8
“dictate[s] the terms or conditions of retail service,”32 because it requires that electric distributors interrupt retail customers’ service in certain specified circumstances—indeed, PJM’s proposed tariff requires curtailment of a certain specified category of retail customers.33 Nothing about that 2026 decision suggests that it is jurisdictionally permissible for a tariff to regulate retail sales, let alone categories of retail sales, so long as the tariff does not specify an individual retail customer who is to be affected. Rather, the decision simply accepts a proposed tariff that does not establish “terms or conditions of retail service” of any kind and leaves it entirely up to the utility whether and how the tariff’s terms might ultimately have a trickle-down effect on retail customers.34 Electric distributors have no such “full discretion”35 under PJM’s proposed tariff.
b. The Answers essentially admit that the Proposal’s compensation provisions are
jurisdictionally improper. As Constellation’s Protest explains, the proposed tariff’s compensation provisions fall on the wrong side of the jurisdictional line because they effectively regulate a retail rate by fixing the default amount that retail customers are paid for the interruption of their retail service under IRAS.36 The Answers respond only by asserting that the compensation provisions— albeit “confusi[ng]” and in need of “clarifi[cation]” 37 —“target[] wholesale rates for wholesale customers.”38 It is difficult to see how that could be so, and the Answers do not provide any relevant explanation. Under the proposed tariff, Eligible Large Loads would have their retail service curtailed and would be provided compensation for that retail curtailment in their retail rates—that is, they
32 Id.
33 See pp. 4-5, supra (discussing the text of the proposed tariff).34 Id.35 196 FERC ¶ 61,127, at PP 65-68.36 Constellation Protest 14. 37 Shapiro Answer 12.38 PJM Answer 54; see Shapiro Answer 12.
PDF page 9
9
would pay less because, as end-users, they received interrupted service.39
But even assuming that it were true that the compensation prescribed in the proposed tariff is a “wholesale compensation level subject to change by the relevant retail authority,”40 a fatal jurisdictional problem remains. States can no more invade the federal government’s jurisdictional sphere than the Commission can invade the States’ jurisdictional sphere. Thus, a retail authority does not have the jurisdictional power to meddle in the wholesale-compensation arena by taking responsibility for setting the level of that compensation (below a tariff-imposed cap),41 and the Commission cannot authorize such a jurisdictional intrusion. 42
The Answers assert that there is precedent for giving States that kind of intrusive role: Order No. 719, in which “the Commission granted the relevant electric retail regulatory authority (RERRA) a veto over that existence of the wholesale [demand-response] transaction entirely.”43 According to the Answers, giving States the ability to reduce the amount of wholesale compensation is less intrusive than giving them a veto, so it must be permissible. That is wrong. For one thing, as noted above, this is a retail rate—and to say that the Commission can restrict state authority to set retail rates is completely unprecedented.
But even assuming that the rate here is a wholesale rate, the Answers’ argument still fails. It is one thing (as under Order No. 719) for a federal entity with jurisdiction over the wholesale sphere to show “solicitude”44 by honoring the States’ desire that wholesale demand-response not take
39 Proposed Tariff Attachment DD-4 § X. 40 Shapiro Answer 12.41 See Constellation Protest 14 (discussing the cap). 42 PJM’s proposed tariff allows Eligible New Large Loads (not States) to “elect” to choose a compensation level below the level PJM proposed. Proposed Tariff Attachment DD-4 § X. But there is no valid reason for a retail customer to ever elect a lower compensation rate of its own accord. A customer would make such an election only if required to do so by a state regulator.43 Shapiro Answer 13; see PJM Answer 57.44 EPSA, 577 U.S. at 287-88.
PDF page 10
10
place—and it is another thing entirely to give States independent power to regulate within the wholesale sphere (as PJM’s Proposal does) by varying and setting the amount of wholesale compensation. That involves the States directly reaching into and regulating the wholesale market, which the statute does not allow.45 If that state conduct were jurisdictionally permissible, nothing would stop the Commission from turning over all kinds of wholesale-regulatory responsibilities to the States—which, once again, would effectively erase the jurisdictional division that Congress created.
c. The Answers wrongly suggest that protestors’ position is that PJM must blind itself to load-growth information. The Answers also incorrectly suggest that protestors’ position is that “PJM must blind itself” to relevant data because “it is legally barred from acting on information about the characteristics of load growth in a zone or area, even if that information is directly relevant to reliable operation of the bulk power system.”46 That suggestion bears no relationship to Constellation’s actual position (or the position of other protestors). PJM is of course not barred from learning and acting on information about load-growth characteristics. PJM can use that information to take numerous permissible steps, including urging States to regulate retail markets differently and asking this Commission to take actions that do not “transgress[] th[e] limit” on intruding on the retail sphere47—some of which Constellation identified in its Protest.48
But neither PJM nor the Commission is entitled to act on such information by regulating the retail market based on the existence of certain retail characteristics, which “is a job for the States alone.”49 Yet that is exactly what PJM’s Proposal seeks to do. The problem is not only that “PJM
45 Constellation Protest 9-13; 16 U.S.C. § 824(a), (b)(1).46 Shapiro Answer 10. 47 EPSA, 577 U.S. at 280.48 Constellation Protest 24; see pp. 12, 21, infra.49 EPSA, 577 U.S. at 280; see id. at 266; California v. FERC, 495 U.S. 490, 497 (1990).
PDF page 11
11
proposes to base” the number of megawatts that must be curtailed on “whether the load growth in [a] zone or area is comprised of new Large Loads … and whether such new Large Load additions have been matched by addition of commensurate new supply.”50 The problem is also (among other things) that PJM proposes to require curtailment at the retail level “among the Eligible New Large Loads in [an] Electric Distributor’s zone/area”51; to dictate the default (and maximum) compensation to be paid to curtailed retail customers in that category; and ultimately to try to strongarm New Large Loads into obtaining retail service in a particular manner. Deeming those actions outside of the Commission’s jurisdiction does not amount to “blind[ing]” or unduly constraining PJM.
3. The Proposal Asks The Commission To Assert Authority That It Has
Never Asserted Before, And The Answers’ Arguments To The Contrary
Are Incorrect
Finally, the Answers try to counter Constellation’s jurisdictional arguments by asserting that IRAS involves actions “no different” from curtailment authority PJM already possesses.52 But if PJM already could impose the IRAS curtailment regime under existing authority, PJM’s extensive Proposal (with its many specifications and purported justifications) would be unnecessary. Rather, as the discussion above makes clear, the Proposal seeks to do something that has never been done before, including choosing load to be curtailed based on specific retail characteristics of retail customers and regulating the retail rates for such curtailment. 53 PJM’s generic authority to coordinate emergency load shed does not involve those jurisdictionally significant features.54
PJM’s Answer also asserts that the Commission and the States both have some authority with
50 Shapiro Answer 10. 51 Proposed Tariff Attachment DD-4 § III(a).52 E.g., Shapiro Answer 7, 9. 53 See pp. 4-8, supra.54 See Constellation Protest 13; Patterson Affidavit 6-7 ¶¶ 13-15. The Answers also are wrong that the Proposal “align[s] IRAS” with zones experiencing “real-time capacity shortfalls.” Shapiro Answer 9. Under the Proposal, exposure to IRAS curtailment is calculated using New Large Load/BYONC status. See Proposal 70-71, 82.
PDF page 12
12
respect to resource adequacy.55 But the fact that the Commission can address resource adequacy does not make the specific action set forth in the Proposal jurisdictionally permissible. Instead, the Commission—and the States—must address the issue through jurisdictionally proper action.56
B. PJM’s Proposal Should Be Rejected Because It Would Violate The FPA By
Treating Certain Load and Certain Resources Differently Without Relevant
Justification
Constellation’s Protest explains that PJM’s Proposal asks the Commission to unlawfully discriminate based on load size, load date, and resource vintage.57 The Answers concede that the Proposal treats certain load and resources more favorably than others, yet fail to explain why that differential treatment does not amount to “undu[e] discriminat[ion]”58 under the FPA—including FPA Section 202(g), which specifically prohibits undue prejudice or disadvantage in the accommodation of anticipated capacity shortages but which the Answers never even mention.59
1. The Proposal Violates The FPA By Disfavoring New Large Loads Even
Though They Are Not Materially Different From Other Loads
There is no meaningful dispute that PJM’s Proposal treats New Large Loads differently— and worse—based on their size and date of entry.60 The Answers assert that the Proposal “neither targets nor directs specific retail customers to be subject to curtailment.”61 To be sure, the Proposal does not name individual customers—but that misses the point for discrimination purposes (as for jurisdictional ones). Under the Proposal, as PJM’s Answer expressly reaffirms, “only New Large
55 PJM Answer 23.56 Constellation Protest 24, 28-29; see p. 21, infra; PJM Answer 27 & n.105 (explaining steps taken by the Pennsylvania PUC and citing https://www.puc.pa.gov/pcdocs/1949305.pdf [https://perma.cc/7UFL-ZX6D]).57 Constellation Protest 29-40. 58 16 U.S.C. § 824e(a); see id. § 824d(b).59 Constellation Protest 29-30 (discussing Section 202(g)).60 Constellation Protest 31.61 E.g., Shapiro Answer 10.
PDF page 13
13
Load may be eligible” for curtailment.62 That is so, the Answers explain, because the “objective” of IRAS “is to protect native loads from the costs and reliability issues posed by New Large Loads that failed to bring new capacity.”63
The Answers do not provide any reason why that disfavored treatment is justified by any difference “material to the inquiry at hand.”64 As Constellation has explained, 50 MW of demand could come from one new customer, one existing customer, or multiple smaller new and/or existing customers. All three scenarios place the same resource-adequacy burden on PJM, but only the first scenario can give rise to IRAS curtailment. Although PJM suggests that New Large Loads warrant disfavored treatment because they “have failed to cover their capacity obligations,”65 that is exactly the point: discrimination against New Large Loads includes not only the risk of curtailment but also the requirement to make arrangements with new capacity, which is a burden not placed on other customers that also impose capacity requirements.
Indeed, PJM’s effort to justify its discrimination against New Large Loads actually confirms that its approach is unlawful. According to PJM, “[n]ew, not existing load, is the reason for the shortfall, which drives the need for IRAS.”66 But the D.C. Circuit has held that “imputing an exclusive or even primary causal role to the … demand” of the newest market entrants is not equitable.67 Rather, because “every shipper is economically marginal, the costs of increased demand may equitably be attributed to every user.”68 By contrast, PJM proposes to impose all of the burdens
62 PJM Answer 61; see Constellation Protest 16, 21; pp. 4-8, supra.63 PJM Answer 35; PJM Answer 31 (calling for IRAS load reductions before Demand Response “protects native loads from the cost and reliability impacts of such new large loads”); see also Shapiro Answer 19-20.64 Constellation Protest 30 (quoting Calpine, 171 FERC ¶ 61,035, P 318 (2020)) (emphasis added). 65 PJM Answer 31, 34; see id. at 35 (“the objective is to protect native loads from the costs and reliability issues posed by New Large Loads that failed to bring new capacity”).66 PJM Answer 61.67 BNP Paribas Energy Trading v. FERC, 743 F.3d 264, 269 (D.C. Cir 2014).68 Southeastern Michigan Gas v. FERC, 133 F.3d 34, 41 (D.C. Cir. 1998).
PDF page 14
14
of the system’s increased aggregate demand on a narrow group of customers. Because those customers are similarly situated to relevant comparators that would not bear those burdens, the Proposal is unlawfully discriminatory.
Governor Shapiro’s effort to justify discrimination against “new large computational loads” similarly underscores, rather than refutes, the Proposal’s unlawfulness.69 Although the Shapiro Answer offers perfunctory statements that the loads are “new,” “distinct,” and “novel,” it does not— and presumably cannot—explain why such loads are different with respect to their capacity needs and resource-adequacy burdens.70 In any event, the Shapiro Answer seeks to justify differential treatment of computational load, but the IRAS Proposal treats all New Large Loads (including traditional commercial and industrial load) worse than other loads. PJM has rejected the suggestion to distinguish “data center Large Loads/computational Large Loads” from “other types of Large Loads, such as manufacturing or industrial loads.”71
The Answers try to suggest that the Commission has previously approved similar arrangements as non-discriminatory, but those analogies fail. First, the cited decisions that purportedly differentiated large loads from other customers are distinguishable. 72 The Commission’s June 2026 Order to Show Cause recognized that large customers may create identifiable transmission and interconnection impacts—not that they pose specialized capacity or resource-adequacy concerns.73 And the Commission’s approval of the CHILLS proposal authorized
69 Shapiro Answer 3.70 See Shapiro Answer 3, 16.71 PJM Answer 16. 72 See PJM Answer 59 n. 212 (citing June 2026 Order to Show Cause, 195 FERC ¶ 61,211 at P 58; Sw. Power Pool, 195 FERC ¶ 61,196, at PP 84-85, 87 (2026)); see also Shapiro Answer 17 nn.38-40.73 June 2026 Order to Show Cause, 195 FERC ¶ 61,211, P 50 (2026); see also Reliability Standard(s) Pertaining to Computational Load Integration, 196 FERC ¶ 61,031, PP 1, 4 (2026) (addressing “integration of computational loads” and “timely and orderly interconnection of large loads”).
PDF page 15
15
a “voluntary” new large load service product—not a mandatory curtailment.74 Those examples are not remotely comparable to the present Proposal, which would force large new customers to face service interruption while sparing other customers that impose equivalent capacity needs. Second, the cited decisions that “grandfather[] existing entities under prior rules” do not justify discrimination based on load date under the IRAS Proposal. 75 Those decisions protect contractual reliance interests,76 distinguish identified resource types from speculative types with unknown attributes,77 or approve a transition process as a bridge to a new regime.78 The IRAS framework would not do any of those things. Instead, it would strip certain new entrants of service that has always been available to all comers, creating a permanent, stark, and unfavorable difference between otherwise identical customers.
2. The Proposal Violates The FPA By Discriminating Against Existing
Capacity Resources Even Though They Are Not Materially Different
From New Resources
The Answers also fail to meaningfully address the Proposal’s discrimination against existing capacity resources.79 PJM says only that the requirement to contract with new capacity is justified because “[t]he PJM Region needs new capacity.”80 But that ignores that existing and new resources can provide the very same benefit to the system, regardless of vintage.8174 Southwest Power Pool, 195 FERC ¶ 61,196, P 84 (2026). 75 Shapiro Answer 18 & n. 42; PJM Answer 61 & n. 218.76 PJM, 193 FERC ¶ 61,217 at P 224 (2025); MISO, 150 FERC ¶ 61,180 at P 21 (2015).77 ISO-NE, 162 FERC ¶ 61,205 at P 47 (2018) (distinguishing between identified eligible resources and “future resource types that are speculative” because details informing their classification were unknown).78 Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements, 184 FERC ¶ 61,054 at P 856 (2023) (adopting “transition process” to move to “new cluster study process”).79 See PJM Answer 44; compare Constellation Protest 37.80 PJM Answer 44.81 Constellation Protest 37-38; see also PJM Interconnection, 117 FERC ¶ 61,331, at P 141 (2006) (“In a competitive market, prices do not differ for new and old plants …”); id. P 77 (disagreeing that “proposal … which would provide additional payments to new generators but not to existing generators would support our objective of achieving an efficient market overall”).
PDF page 16
16
Governor Shapiro contends that differentiating between newly available capacity and existing capacity is appropriate because existing capacity resources are “already committed” to the system. 82 That contention rests on the mistaken premise that existing capacity resources are permanently tied to the market because they previously cleared an auction. To the contrary, “many existing resources have the capability to exit the RPM,” 83 which underscores that contractual arrangements with new or existing resources can provide the same capacity benefits. Governor Shapiro further argues that the new-resource requirement is “needed to prevent cross-subsidization” by existing ratepayers of new large load—that is, to prevent “new large loads” from contracting with “cheaper” “available capacity resources,” which will be motivated to “lock-in long-term contracts with new large loads.”84 That argument is economically incoherent, as there is no reason to expect that existing capacity is “cheaper” in a market that is set by competition among new and existing capacity. Moreover, existing ratepayers have no continuing entitlement to existing capacity resources. Prior payments those ratepayers made to pay for existing resources were only for prior obligations in prior Delivery Years; they did not guarantee permanent dedication of specific resources to particular customers. Governor Shapiro’s concern about cross-subsidization boils down to an attempt to enforce a policy that would preserve lower-cost capacity for incumbent load and relegate new load to more expensive and scarcer alternatives. That is not a legitimate justification for discrimination among capacity resources by vintage, but rather a concession that the purpose of the Proposal is to discriminatorily benefit existing customers at the expense of New Large Load.
82 Shapiro Answer 19.
83 Patterson Affidavit 23 ¶ 48.
84 Shapiro Answer 16, 19.
PDF page 17
17
C. PJM’s Proposal Should Be Rejected Because Its Design Is Unjust and
Unreasonable
1. PJM Unreasonably Proposes to Exclude New Large Load Without
BYONC From the Demand Curve, Which Would Distort Market
Dynamics And Worsen Resource Constraints
PJM’s proposal would unreasonably remove New Large Loads that are subject to IRAS from the VRR Curve used to clear RPM Auctions.85 None of the purported justifications offered in the Answers overcomes the unreasonableness of that aspect of the Proposal.
First, according to PJM’s Answer, its demand curve approach is justified by the Pledge. But the Pledge is a policy statement that does not suggest that PJM’s IRAS Proposal is the only possible approach that can be taken here, let alone that the Proposal is legally sound or is consistent with other policies supporting new load development and infrastructure to serve that new load.86 Second, the Answers contend that New Large Loads that do not bring their own new capacity should be excluded from the VRR Curve because they are “effectively electing not to receive capacity service.”87 But that justification makes no sense, because under the Proposal New Large Loads without BYONC would be excluded even in delivery years when IRAS curtailment is not triggered.88 Similarly, in any period in which no such curtailment is taking place, the excluded load will be physically present and served, yet the VRR Curve will pretend that it does not exist. The categorical exclusion of certain New Large Loads from the VRR Curve thus is inconsistent with the realities of the market, which explains why it will undermine RPM’s structural integrity and unjustifiably mute market signals, ultimately worsening resource constraints.8985 PJM Answer 50.86 Ratepayer Protection Pledge, available at https://www.whitehouse.gov/releases/2026/03/ratepayer- protection-pledge/ (committing to “pay[] the full cost” of new generation resources and “add more capacity” “where possible”).87 PJM Answer 53; see Shapiro Answer 4.88 Constellation Protest 48.89 Constellation Protest 46.
PDF page 18
18
Third, Governor Shapiro states that “sufficient new capacity is not [coming] and perhaps cannot come online as fast as new large load demand,” so excluding the need for that supply from the market makes sense.90 But the purpose of the capacity market is not only to encourage new and immediately accessible generation. Capacity prices also encourage existing resources to remain in service in PJM, support uprates and demand response, affect long-term investment timing and incentives, and promote entry in future Delivery Years.91 If anything, limitations on speed and availability of new resources make an accurate demand signal more important, not less.
2. PJM Unreasonably Proposes To Sequence IRAS Before Demand
Response, Which Is Economically Irrational And Will Undermine Price
Formation in the Energy Market
PJM’s Proposal also is unreasonable because it would curtail New Large Load before calling on emergency resources. 92 Constellation’s Protest explains the economic irrationality of that sequencing, which prioritizes involuntary curtailment of customers with high interruption costs over curtailment of a self-selected and compensated population.93 PJM misunderstands this system-wide critique as an argument about the relative costs to individual customers.94 Its Answer reiterates that IRAS is intended to “burden … New Large Loads,” but it does not explain how the proposed emergency-response sequence advances the collective interests of the system as a whole.95 The Answers also argue that calling on Demand Resources first could risk “fatigue” of those resources.96 But that argument does not justify an economically irrational emergency response
90 Shapiro Answer 23.91 See, e.g., Hughes v. Talen, 578 U.S. 150, 155-56 (2016); see also FERC, Energy Primer: A Handbook of Energy Market Basics 85-86 (2024) (discussing RPM market). 92 Constellation Protest 42.93 Constellation Protest 43-44.94 PJM Answer 34-35.95 PJM Answer 35.96 PJM Answer 36; see Shapiro Answer 24.
PDF page 19
19
process. Instead, PJM could explore other ways to incentivize alternative capacity resources, including by developing more limited Demand Response products that would not threaten to fatigue providers.97
3. PJM Risks Curtailing The Very Customers It Claims To Protect, Which
Is Irrational And Unjust
PJM’s Proposal may threaten the service of the very residential customers it purports to protect. PJM proposes to calculate each zone/area’s IRAS obligation before the start of each Delivery Year using the peak load of Eligible New Large Loads.98 But the Proposal is not designed to ensure that the Eligible New Large Loads used to calculate the prospective amount of possible IRAS are actually online and available to provide that service when an IRAS Action occurs, which means that “this pre-determined amount may not match the actual New Large Load demand” in real time.99 In that circumstance, if PJM directs an amount of IRAS that is higher than the real- time demand of Eligible New Large Loads in that zone, the result could actually be that Electric Distributors are required to either (1) violate PJM’s tariff by failing to curtail enough load, given the limited pool of “eligible” load to curtail, or (2) violate PJM’s tariff by curtailing some customers that are not New Large Loads.100 Although PJM’s Proposal clearly targets and intends to curtail only New Large Loads, 101 the specified mechanics leave a hole that risks instead curtailing other customers, including residential loads that happen to be in zones where significant large load growth is forecasted.102 That would run directly contrary to the stated purpose of IRAS
97 Patterson Affidavit 11 ¶ 22; Constellation Protest 24.98 PJM Proposal 70 (“The amount of [IRAS] PJM may need to be available will be determined each Delivery Year for the PJM Region and each Electric Distributor zone/area”); Proposed Tariff, Attachment DD-4, § V(b); see also id., Attachment DD-4 §§ II(c), (e), IV(c)(ii); Pilong Aff. ¶¶ 28, 42-43.99 NJ BPU Answer 3 (citing other comments making the same point).100 E.g., NJ BPU Answer 3; Pilong Aff. ¶¶ 42-43. 101 See Parts II.A & II.B, supra.102 See PJM Answer 29; cf. Shapiro Answer 9-10.
PDF page 20
20
to protect existing customers, particularly residential loads103—and is yet another reason why the Proposal is unjust and unreasonable and must be rejected.
D. The Answers’ Suggestion That The Proposal Is the Only Solution To The
Challenges Presented Is Wrong, And The Commission Should Not Be Swayed
By It
Threaded through the Answers is a repeated insistence that, whatever flaws the Proposal might have, the Commission should accept it because it is the only possible solution to an overwhelming problem that needs to be solved this very instant.104 That is a false construct. Although the Answers point to the Ratepayer Protection Pledge and the Statement of Principles (issued by the White House and Governors) as support for the IRAS imperative, those documents contemplate solutions and responsive options for data-center demand.105 They do not establish that PJM’s version of IRAS is a necessary, reasonable, or lawful implementation of public policy. Nor do they override other policy statements that emphasize the need to support “vast AI infrastructure and the energy to power it.”106
Even more fundamentally, PJM’s Proposal violates the statutory limits on the Commission’s jurisdiction—regardless of PJM’s policy motivations. Congress is empowered to decide how to divide up responsibility for such problem-solving between the federal government and the States, and the Commission cannot step in just because industry participants—or even States themselves— believe that Commission action would be a more convenient or superior way of addressing a particular issue. Jurisdictionally improper action by this Commission is, in fact, deeply
103 PJM Proposal 9; see id. at 5-6, 15, 23-24, 90-91.
104 E.g., PJM Answer 3 (juxtaposing IRAS with “the myriad risks that doing nothing presents”); Shapiro Answer 5 (“IRAS is necessary … in response to the severe challenges facing the region”).105 PJM Answer 2; Shapiro Answer 2.106 E.g., White House, America’s AI Action Plan (July 2025); Executive Order 14318, Accelerating Federal Permitting of Data Center Infrastructure (July 23, 2025).
PDF page 21
21
counterproductive in the end. It will not only encourage further violations of Section 201(b) but also is very likely to be undone on judicial review, thus creating regulatory uncertainty, disruption, and delay that need never have existed.
The Answers are also wrong in asserting that the Proposal is the only possible form of “coordinated” action that can be taken here.107 The States are free—perhaps with PJM’s help and consultation—to coordinate with each other, and even less-than-complete state coordination would still advance the ball. Moreover, there are steps that the Commission can take that do not have the same jurisdictional flaws as the Proposal, including (as supply-side companies have previously proposed) adding voluntary demand response projects with limited call options.108 At the very least, the Commission should try those other steps and see what effect they have before accepting PJM’s siren call to venture into jurisdictionally hazardous territory.
III. CONCLUSION
The Commission should reject PJM’s Proposal (other than the proposal to create the Large Load Registry).
107 Shapiro Answer 6.108 Constellation Protest 24 & n.100.
PDF page 22
22
Respectfully submitted,
By: /s/ Elaine J. Goldenberg
Carrie Hill Allen
Sr. Vice President & Deputy General
Counsel
John M. White
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
john.white@constellation.com
Christopher A. Wilson
Vice President, Federal Regulatory Affairs Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Elaine J. Goldenberg
MUNGER, TOLLES & OLSON LLP
601 Massachusetts Avenue NW
Suite 500 E
Washington, DC 20001
(202) 220-1100
Elaine.Goldenberg@mto.com
Henry Weissmann
MUNGER, TOLLES & OLSON LLP
350 South Grand Avenue, 50th Floor
Los Angeles, CA 90071-3426
(213) 683-9100
Henry.Weissmann@mto.com
Teresa Reed Dippo
MUNGER, TOLLES & OLSON LLP
560 Mission Street, 27th Floor
San Francisco, CA 94105
(415) 512-4000
Teresa.ReedDippo@mto.com
Counsel for Constellation Energy Generation, LLC
Dated: September 29, 2026
PDF page 23
23
CERTIFICATE OF SERVICE
I hereby certify that I have on this 29th day of September 2026 served a copy of the foregoing upon all parties on the service list in this proceeding in accordance with the Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.
By: /s/ Elaine J. Goldenberg