ER26-3515-000 · 2026-09-29 · Constellation Energy Generation, LLC

Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC to the Answers filed by Pennsylvania Governor Josh Shapiro et al. re the…

Text extracted from the eLibrary original (SHA-256 123be9d8ce8a5470…). Download the original from the official source.

Contents · 7 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 1
  2. II. ANSWER p. 2
  3. A. The Proposal Is Outside The Scope Of The Commission’s Jurisdiction p. 2
  4. B. PJM’s Proposal Should Be Rejected Because It Would Violate The FPA By p. 12
  5. C. PJM’s Proposal Should Be Rejected Because Its Design Is Unjust and p. 17
  6. D. The Answers’ Suggestion That The Proposal Is the Only Solution To The p. 20
  7. III. CONCLUSION p. 21

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Retail and wholesale authority · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.: 205(d) Rate Filing: Proposal to Establish Interim Resource Adequacy Service & a Large Load Registry to be effective 10/12/2026 ) ) ) ) ) ) Docket No.
Read this passage Filed comments: Registry access

I. MOTION FOR LEAVE TO ANSWER

printed heading

I.
Read this passage

II. ANSWER

printed heading · Topic match: Cost allocation

They also incorrectly suggest that the Proposal is the only way to address issues raised by new large loads and that the Ratepayer Protection Pledge somehow justifies violating limits set by the FPA—neither of which is true.
Read this passage Filed comments: Cost allocation

A. The Proposal Is Outside The Scope Of The Commission’s Jurisdiction

printed heading · Topic match: Reliability and curtailment

The Proposal Asks The Commission To Assert Authority That It Has Never Asserted Before, And The Answers’ Arguments To The Contrary Are Incorrect Finally, the Answers try to counter Constellation’s jurisdictional arguments by asserting that IRAS involves actions “no different” from curtailment…
Read this passage Filed comments: Reliability and curtailment

B. PJM’s Proposal Should Be Rejected Because It Would Violate The FPA By

printed heading · Topic match: Reliability and curtailment

PJM’s Proposal Should Be Rejected Because It Would Violate The FPA By Treating Certain Load and Certain Resources Differently Without Relevant Justification Constellation’s Protest explains that PJM’s Proposal asks the Commission to unlawfully discriminate based on load size, load date, and…
Read this passage Filed comments: Reliability and curtailment

C. PJM’s Proposal Should Be Rejected Because Its Design Is Unjust and

printed heading · Topic match: Reliability and curtailment

PJM Unreasonably Proposes to Exclude New Large Load Without BYONC From the Demand Curve, Which Would Distort Market Dynamics And Worsen Resource Constraints PJM’s proposal would unreasonably remove New Large Loads that are subject to IRAS from the VRR Curve used to clear RPM Auctions.85 None of the…
Read this passage Filed comments: Reliability and curtailment

D. The Answers’ Suggestion That The Proposal Is the Only Solution To The

printed heading · Topic match: Cost allocation

Although the Answers point to the Ratepayer Protection Pledge and the Statement of Principles (issued by the White House and Governors) as support for the IRAS imperative, those documents contemplate solutions and responsive options for data-center demand.105 They do not establish that PJM’s…
Read this passage Filed comments: Cost allocation

III. CONCLUSION

printed heading · Topic match: Registry access

White Assistant General Counsel Constellation Energy Generation, LLC 250 Massachusetts Ave.
Read this passage Filed comments: Registry access

CERTIFICATE OF SERVICE

printed heading

Goldenberg MUNGER, TOLLES & OLSON LLP 601 Massachusetts Avenue NW Suite 500 E Washington, DC 20001 (202) 220-1100 Elaine.Goldenberg@mto.com