ER26-3515-000 · 2026-09-30 · Google LLC

Answer of Google LLC in response to pleadings re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
)
)
)
)
         Docket No. ER26-3515-000

ANSWER OF GOOGLE LLC

Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”),1 Google LLC (“Google”) hereby moves to answer and answers the pleadings filed in this proceeding.  PJM is at a crossroads.  The record of this proceeding confirms that its resource adequacy challenges are real and, if left unaddressed, will degrade reliability for all customers.  And although some customers, including Google, are making the critical investments needed to serve their load growth, that is far from universal.  As a result, there is every reason to believe that forecasted demand for capacity will continue growing faster than supply.  Nevertheless, PJM has offered a proposal, Interim Resource Adequacy Service (“IRAS”), that will make the situation worse.  It will chill investment and undermine efforts by companies, like Google, that are committed to bringing their own new capacity to PJM. Accordingly, the Commission should use this proceeding to put PJM back on course to a resource- adequate future.  In particular, as discussed below, it should require PJM to adopt an interruptible capacity service similar to what exists in the natural gas transportation context under the Natural Gas Act (“NGA”).  This service will provide a mechanism for balancing supply and demand without undermining investment in new capacity in the way IRAS would.

1 18 C.F.R. § 385.213 (2026).

PDF page 2

-2-
Google agrees with the principle underlying IRAS: “New Large Loads that do not bring sufficient new capacity to offset their expected demand should be subject to curtailment prior to other firm wholesale customers during tight system conditions.”2  Consistent with that view and Google’s commitment to the Ratepayer Protection Pledge, Google is actively procuring new capacity to cover its projected load growth in PJM and will submit documentation to PJM showing that it has brought its own new capacity (“BYONC”) to reduce or offset its obligations under the Reliability Backstop Procurement (“RBP”) construct.3  For that reason, Google’s interest in this proceeding is not to avoid paying for new capacity.  Rather, Google’s concern is that IRAS will make it less likely that Google and other large customers can bring their own new capacity and avoid curtailment to a market governed by IRAS.

In addition, Google agrees with commenters arguing that reform is necessary.  Under the status quo, capacity market demand is already exceeding supply and it is likely to continue to do so in the future as Load Serving Entities (“LSEs”) sign up additional firm retail customers pursuant to applicable state law.   A situation in which demand for firm service regularly exceeds supply is an untenable outcome.  After all, while those retail arrangements are governed by state law, the physical limitations on the system are not.  The capacity market cannot supply more capacity than exists in reality.  But the PJM tariff does not provide LSEs with an option to procure anything other than firm capacity, meaning that, when supply exceeds demand, LSEs are left trying to try to procure something that does not exist.  An interruptible service—akin to what exists in the gas transportation context and building upon what the Commission required in the PJM Co-Location Order—is the missing link that would allow supply and demand to clear in the capacity market

2 PJM Interconnection, L.L.C., Protest of Google LLC, Docket No. ER26-3515-000, at 1 (filed Sep. 3, 2026) (“Google Protest”).
3 See PJM Interconnection, L.L.C., 196 FERC ¶ 61,245 (2026).

PDF page 3

-3-
without creating pervasive uncertainty that would interfere with investment in new capacity.  In the absence of such an interruptible service, PJM is providing what amounts to non-firm service without a non-firm service class in the tariff.  That result, Google submits, is unjust and unreasonable.

IRAS, by contrast, is not the solution.  The overwhelming weight of the record compiled in this proceeding indicates that IRAS is, for myriad reasons, illegal, ineffectual, and otherwise deeply flawed.4 It would, therefore, cast a long shadow over resource procurement in the region, meaning that “the result of IRAS will be less investment in new capacity in PJM—the exact opposite of what the region needs.”5  An order accepting IRAS will cause resource adequacy in PJM to deteriorate further.

The Commission must now guide PJM back on course.  To do so, it should use the logic of its recent PJM Co-Location Orders6 to require PJM to establish an interruptible service in the capacity market similar to what exists in the gas transportation context.7  It has two viable options to do so.  First, it could reject IRAS with guidance on how PJM can reform the proposal to actually improve resource adequacy in PJM.8  Any such order should make clear to PJM that it cannot condition the quality of wholesale service on retail customer characteristics and that a successor

4 Infra section II.A.
5 Google Protest at 2.
6 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“PJM Co-Location Order”).
7 Duke Energy Trading & Mktg., L.L.C. v. FERC, 315 F.3d 377, 378-79 (D.C. Cir. 2003).
8 This would be consistent with what PJM has requested the Commission to do if the Commission rejects IRAS. See PJM Answer at 5 (“PJM respectfully requests that, to the extent the Commission rejects any element of this filing, the Commission either direct prescriptive changes to be implemented on compliance or provide guidance to aid PJM and stakeholders to develop a just and reasonable approach. The issues outlined herein are simply too important, and the timing too critical, for PJM and its stakeholders to have to guess in such a case as to what the Commission would find acceptable.”).

PDF page 4

-4-
construct to IRAS must create the conditions necessary to facilitate investment in new capacity, not stymie it.  Specifically, it should create a class of interruptible service governed by transparent, clear rules that provide the regulatory certainty necessary to facilitate the at-risk investments that are the bedrock of a market-based approach to ensure resource adequacy.

Alternatively, the Commission could take the reins and begin the process to “transform” this section 205 into a section 206 proceeding.  Although in a typical proceeding under section 205 of the Federal Power Act (“FPA”), the Commission generally “undertakes ‘an essentially passive and reactive role’ and restricts itself to evaluating the confined proposal,” 9 the U.S. Court of Appeals for the D.C. Circuit has recognized an exception to that general rule.  Specifically, the court has explained that the Commission may transform a section 205 proceeding into a section 206 proceeding and impose its own replacement rate provided that it makes three findings. “[F]irst, it must conclude under § [205] that the [public utility] failed to carry its burden of proof that the proposed rate was just and reasonable; second, it must itself demonstrate that the default position, the prior rate, is no longer just and reasonable; and third, it must establish that its substitute rate is just and reasonable.”10

The record in this proceeding shows how the Commission can readily make all three
findings:  (1) for the reasons explained in Google’s initial protest and throughout the record, IRAS is unjust and unreasonable, unduly discriminatory, and in excess of the Commission’s jurisdiction;

9 Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017) (quoting City of Winnfield v. FERC, 744 F.2d 871, 875-76 (D.C. Cir. 1984)).

10 W. Res., Inc. v. FERC, 9 F.3d 1568, 1579 (D.C. Cir. 1993) (citing the parallel provisions of the Natural Gas Act); While Western Resources addressed sections 4 and 5 of the Natural Gas Act, its reasoning and framework nevertheless apply equally to FPA cases involving section 205 proceedings that the Commission converts into section 206 proceedings because “the relevant provisions of the [NGA and FPA] ‘are in all material respects substantially identical.’” Arkansas Louisiana Gas Co. v. Hall, 453 U.S. 571, 577 n.7 (1981) (quoting FPC v. Sierra Pacific Power Co., 350 U.S. 348, 353 (1956)); see also Monongahela Power Co., 164 FERC ¶ 61,217, at P 17 (2018) (applying Western Resources in an a proceeding that was initiated under FPA section 205).

PDF page 5

-5-
(2) the status quo is also unjust and unreasonable as LSEs are signing up more new retail customers than the region can reliably serve yet the PJM tariff lacks any mechanism for equilibrating supply and demand in the capacity market; and (3) as Google explained in its initial protest, “there are ample alternative avenues through which PJM, in cooperation with the States, could facilitate the goals underlying IRAS, rather than impeding them,”11 including the development of an interruptible service, modeled on what exists for natural gas transportation, that provides clear and transparent rules for determining which customers take interruptible service as well as when and how they will be interrupted to ensure supply and demand remain balanced. To implement this option, the Commission could find that all of IRAS is unjust and unreasonable or it could accept only the Large Load Registry.  Either way, it would simultaneously initiate a section 206 proceeding regarding the existing tariff (Western Resources Step 2 above) and potential replacement rates (Western Resources Step 3 above) and consolidate the record of this proceeding into that new one.12

It bears reiterating: Google’s interest in this proceeding is to ensure that PJM has a functioning resource adequacy construct that provides the incentives necessary to develop sufficient new capacity to meet demand in PJM over the short-, medium-, and long-term.  IRAS is emphatically not that.  Accordingly, Google urges the Commission to assert its leadership on these issues and put PJM back on course.

I. MOTION FOR LEAVE TO ANSWER
Although the Commission’s procedural rules generally do not allow answers to answers,

11 Google Protest at 16.
12 See Tennessee Gas Pipeline Co.v. FERC, 860 F.2d 446, 456 (D.C. Cir. 1988); W. Res., Inc. v. FERC, 9 F.3d at 1579; Monongahela Power Co., 164 FERC ¶ 61,217 at P 17.

PDF page 6

-6-
the Commission may permit them for good cause.13  The Commission frequently accepts answers that clarify the issues before the Commission, ensure a complete record, or otherwise assist the Commission in its decision-making.14  Google therefore respectfully requests that the Commission accept this answer, which will assist the Commission with its decision-making by setting forth the justification for the Commission action under the Western Resources framework, discussed above.

II. ANSWER
As Google explained in its initial protest, PJM is correct that the demand for electricity is outpacing supply, and reforms are necessary to manage periods in which demand exceeds supply and to incentivize the development of the new capacity to prevent those imbalances in the future. But IRAS would only make things worse.  As an overwhelming majority of commenters pointed out, IRAS is both illegal and likely to be counterproductive.  Rather than incentivizing New Large Loads to contract with new capacity, it will chill such investment and further erode resource adequacy in the region.  That uncertainty is the result of both IRAS’s patent legal deficiencies, which provide ample bases for it to be overturned on appeal, and the fact that PJM lacks authority to dictate retail curtailment priority, which means that IRAS will not provide the regulatory certainty that is necessary to incentivize investment in new capacity.

The Commission must either reject IRAS with guidance to PJM to establish a legally
durable approach that includes a clear and transparent category interruptible service that does not

13 18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, or a request for rehearing, unless otherwise ordered by the decisional authority.”).
14 See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that “provided information that assisted us in our decision-making process”); New Fortress Energy LLC, 174 FERC 61,207, at P 7 (2021) (accepting answers because they provided information that assisted the Commission’s decisionmaking process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage Co., L.L.C., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding the issues raised, and will ensure a complete record”).

PDF page 7

-7-
target individual retail customers or take the reins itself to do the same pursuant to the D.C. Circuit’s decision in Western Resources by “transforming” this section 205 proceeding into one under section 206.15

The Commission can satisfy all three Western Resources conditions here.  First, it should reject IRAS because it exceeds the Commission’s jurisdiction under the FPA and has not been shown to be just and reasonable and not unduly discriminatory or preferential.  Google explained these points in its initial protest, and the record established so far in this proceeding only confirms the point.  The one possible exception is the Large Load Registry, which could play a valuable information-sharing role without transgressing the FPA’s jurisdictional lines and could be severed from the rest of the filing consistent with PJM’s statements in its transmittal letter and the principles in NRG.16

Second, despite demand for firm capacity outpacing supply, there is no option in PJM’s tariff allowing LSEs to take interruptible service.  The absence of any interruptible service, and the resulting imbalance in the supply and demand for firm capacity, is eroding system reliability and will degrade the quality of firm service because PJM will inevitably have to manage supply and demand through the use of emergency procedures and curtailment of customers attempting to take firm service.  In addition to degrading the quality of Commission jurisdictional service, it also creates uncertainty that impairs investment in new capacity needed for PJM to eventually escape the current resource adequacy crisis.  Accordingly, the fact that the PJM tariff lacks a permanent,

15 W. Res., Inc. v. FERC, 9 F.3d at 1579; see also Monongahela Power Co., 164 FERC ¶ 61,217 at P 17.
16 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515-000, at 9 (filed Aug. 13, 2026) (“Transmittal”); NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114 (D.C. Cir. 2017) (holding that the Commission has “some authority to propose modifications to a utility’s [FPA section 205] proposal if the utility consents to the modifications”).

PDF page 8

-8-
clearly defined service option through which an LSE can procure interruptible, non-capacity backed service renders the PJM tariff unjust and unreasonable.

Third, the Commission should adopt a replacement rate that establishes an interruptible service option through which an LSE can elect to serve load on a non-firm basis.  Such service would not be capacity-backed, and PJM would not procure capacity to serve it.  Instead, load taking interruptible service could consume electricity when there is sufficient capacity on the system, subject to defined triggers to interrupt the provision of electricity as conditions tighten and before emergency procedures are triggered.  This service would be highly similar to interruptible service in the gas transportation context, which would allow additional demand to be served while preserving priority for firm customers.  It would also build on the reasoning underlying the Commission’s recent PJM Co-Location Order where it created interim Network Integration Transmission Service (“NITS”) to address a similar concept.

PJM should define this service in its tariff, including when it is available and when PJM would direct LSEs to curtail participating load. Curtailment would be a condition of interruptible service, triggered before emergency procedures become necessary.  States would then be responsible for determining which retail customers take interruptible retail service.   That approach both solves the basic supply and demand problem—because PJM knows to interrupt the interruptible customers when demand exceeds supply—and puts states in position to determine which customers qualify for firm service and which do not.  For example, the states could determine whether data centers can receive firm service only if they bring their own new capacity and customers, including data centers, would have the certainty they need to make investments in such new capacity because the regulator imposing the requirement also has authority over the curtailment priority.  In that way, this approach would address the basic motivation behind IRAS

PDF page 9

-9-
without the self-defeating uncertainty that it would create.  Additionally, to address a potential supply shortfall in the near term, PJM should establish a framework for curtailing large loads, including those with firm service, prior to other retail customers during emergency conditions when PJM is approaching a broad Manual Load Dump.

A. The Record Confirms that PJM Has Not Satisfied Its FPA Section 205 Burden
Google explained in its initial protest that IRAS falls well short of meeting PJM’s burden under section 205 to show that its proposal meets the just and reasonable standard and is not unduly discriminatory.  Instead, it is fatally flawed in several respects.  First, IRAS exceeds the Commission’s authority because it aims at, targets, and is impermissibly tethered to the retail sphere.17  Second, IRAS unduly discriminates on the basis of retail customer characteristics that are beyond the Commission’s jurisdiction to consider and, separately, for reasons that have nothing to do with the resource adequacy concerns that PJM is trying to address (e.g., when the large load began operating).18  Finally, IRAS is unjust and unreasonable because PJM would require IRAS curtailment before deploying demand response resources that have agreed to be curtailable and because PJM cannot ensure that New Large Loads that bring new capacity will receive firm service.19  Each of those several issues would provide an appellate court with sufficient justification to overturn an order accepting the IRAS proposal.

Were there any doubts about the legality of IRAS, the Commission need only look at the pleadings in this docket, which overwhelmingly confirm that IRAS has not been shown to be just and reasonable and not unduly discriminatory or preferential.  Indeed, the overwhelming majority

17 Google Protest at 8-11; see Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 385 (2015) (“Oneok”); FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 282 (2016) (“EPSA”); Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 166 (2016) (“Hughes”).
18 Google Protest at 11-13.
19 Id. at 13-16.

PDF page 10

-10-
of entities participating in this proceeding—utilities, independent power producers, data center operators, consumer advocates, industry trade groups, state public utility commissions, and individual retail customers—all oppose IRAS in whole or part.  Of the roughly 40 parties that filed initial pleadings in the docket, only a few embrace the IRAS proposal and recommend that the Commission accept it as proposed.  The number and quality of the protests provide compelling evidence both that PJM has not met its burden with respect to IRAS and that any order accepting it would face strong challenges on appeal.  Simply put, the record in this proceeding provides more-than-ample evidence for the Commission to conclude that IRAS exceeds the Commission’s jurisdiction and has not been shown to be just and reasonable and not unduly discriminatory or preferential.

Although the record reflects overwhelming opposition to IRAS, a handful of answers now seek to resuscitate the moribund case for accepting it.  Google appreciates that those answers reflect a genuine belief that IRAS will respond to the very real practical challenges caused by load growth that outstrips supply.  Nevertheless, as explained below and in Google’s initial protest, accepting IRAS would make matters worse by creating pervasive uncertainty that will exacerbate the region’s resource adequacy shortfall.  Although Google agrees that PJM and the Commission should do something, it is critical that PJM and the Commission do the right thing, lest PJM’s resource adequacy situation deteriorate further at a time when PJM can least afford it. Google agrees that PJM is facing the prospect of a serious resource adequacy shortfall and that New Large Loads must step up and cover that capacity shortfall, consistent with the Ratepayer Protection Pledge.  As noted above, that is exactly what Google is doing as it expands its operations in PJM.  Google has also made clear that New Large Loads that do not offset their demand with new capacity should be curtailed prior to other firm wholesale customers when system conditions

PDF page 11

-11-
warrant.  Accordingly, when it comes to Google, it is incorrect to suggest that opposition to IRAS “fl[ies] in the face of commitments . . . already made in the Ratepayer Protection Pledge, and [is] essentially an argument that the new capacity needed to serve data centers must be paid for by all PJM customers through higher capacity market prices rather than by the actual cost-causers.’”20 Instead, Google opposes IRAS because of its potential to exacerbate the region’s resource adequacy issues, harming all PJM customers.  Far from evincing any weakness in Google’s commitment to the Ratepayer Protection Pledge, our opposition reflects our commitment to well- functioning and rational markets as one of the central pillars by which the industry can realize the goals of the Pledge.

Below, Google addresses the key points in the answers filed to date and explains why they do not call into question the clear consensus among the initial comments that IRAS is fundamentally flawed and must be rejected.

1. Jurisdiction
IRAS exceeds the Commission’s jurisdiction.  The arguments to the contrary do not wrestle with the critical jurisdictional arguments, instead slaying strawmen and assuming away IRAS’s fundamental flaws.  Indeed, many of those arguments are variations on the theme that, because PJM does not direct the curtailment of individual retail customers, IRAS must not exceed the Commission’s jurisdiction.  For instance, PJM contends that “the issue of jurisdiction is about which entity gets to identify the retail customers who ultimately respond to PJM’s directives to reduce load.”21  But the FPA does not so rigidly elevate form over substance in the way some parties suggest.  Instead, courts have “emphasize[d] the importance of considering the target” of

20 Gov. Shapiro Answer at 5.
21 PJM Answer at 29.

PDF page 12

-12-
the regulation in question when considering jurisdictional challenges under the FPA. 22  It is that inquiry that recognizes the fact that the federal and state spheres of jurisdiction under the FPA are not “hermetically sealed”23 and, if not properly policed, a federal or state regulation that purports to address a jurisdictionally appropriate matter can, in fact, regulate a matter within the other’s exclusive jurisdiction.

IRAS’s target is evident from its very structure.  IRAS conditions the quality of wholesale service on the characteristics of retail customers.  Specifically, under IRAS, PJM would identify for each zone or area the Eligible New Large Load Amounts—i.e., the quantity of New Large Load demand that is not offset by new capacity.24  When system conditions warrant, PJM would instruct (“Electric Distributors”) EDs to curtail load in amounts equal to or less than the ED’s Eligible New Large Load Amount.25  In other words, the amount of load shed under IRAS depends entirely and exclusively on the characteristics of the retail load in each zone or area.  Retail customers are “the mechanism through which the rule operates.”26  That is the purpose of IRAS, not some unintended byproduct.  To see that clearly, it is worth considering what would happen if the IRAS MW load reduction in each zone or area was not determined by, and thus tethered to, individual retail customer characteristics.  In that hypothetical, PJM would have no mechanism for determining the amount of load to reduce in a given footprint, and, simply put, IRAS would cease being IRAS.  The retail customer targeting is therefore the defining feature of the proposal.

22 Oneok, 575 U.S. at 385; EPSA, 577 U.S. at 282 (citing Oneok, 575 U.S. at 385).
23 EPSA, 577 U.S. at 281.
24 Transmittal at 69.
25 See, e.g., id. at 86.
26 EPSA, 577 U.S. at 283.

PDF page 13

-13-
In arguing to the contrary, PJM fundamentally misrepresents the Supreme Court’s
“targeting” inquiry, arguing that “[w]hether such a rule ‘targets’ retail or wholesale customers turns on the justification for the rule, not on whether or the extent to which the rule affects or even compels action of retail or wholesale customers.”27  When it comes to determining whether a rate is jurisdictionally permissible under the FPA, the dispositive question is how it works in practice, not the relevant public utility’s transmittal letter.  While the justification a public utility provides can shed light on how the tariff works, the jurisdictional inquiry turns on what is actually on file with the Commission.28  After all, if the justification were all that matters, FERC could force a public utility to adopt time-of-use retail rates by listing their salutary effects on the wholesale market.

The Court’s precedents confirm that is how the FPA works.  In EPSA, the Court began by examining how “demand response works” and concluding that it was an exclusively wholesale construct before observing that the Commission’s justification was “all about and only about” the wholesale market.29  Similarly, in Hughes, although Maryland’s justification was to encourage construction of new in-state generation,30 that did “not save” the program because “States may not seek to achieve ends, however legitimate, through regulatory means that intrude on FERC’s authority.”31

27 PJM Answer at 18-19.
28 See 16 U.S. Code § 824d(c) (“[E]very public utility shall file with the Commission . . . and shall keep open in convenient form and place for public inspection schedules showing all rates and charges for any transmission or sale subject to the jurisdiction of the Commission, and the classifications, practices, and regulations affecting such rates and charges.”).
29 EPSA, 577 U.S. at 282.
30 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 158 (2016).
31 Id. at 163-64.

PDF page 14

-14-
Applying that framework here, the fact that PJM’s transmittal letter uses “reliability,” 32 “resource adequacy,”33 “reserve requirements,”34 and other wholesale-market verbiage cannot make IRAS legal.  That is because no number of synonyms for reliability can cure the fact that retail characteristics, including retail customer size and retail customer interconnection and ramp rates, are what determine whether and how IRAS applies.  As Google explained in its opening protest, it is not the wholesale-market growth rates that determine whether IRAS applies; wholesale-market growth is irrelevant.   Consider the following two examples.  First, IRAS would not apply to an ED that grows by 1,000 one-MW increments while it would apply to an ED that grows by 50 MW due to a single customer.  Second, an ED that adds an otherwise Eligible New Large Load on May 31, 2027 would not be subject to IRAS, while an identical ED that adds an Eligible New Large Load on June 1, 2027 would be.  In other words, while an ED’s aggregate load growth is the demand-side metric relevant to resource adequacy, it is not the focus of IRAS and does not determine whether IRAS applies.  That is what matters because, when it comes to FPA jurisdiction, actions speak louder than words.

PJM also suggests that IRAS must be jurisdictionally sound because it would regulate issues at the confluence of federal and state jurisdiction, arguing that “entities that seek rejection of the IRAS proposal on jurisdictional grounds conveniently overlook the fact that integrating large loads in a manner that (1) ensures reliability; (2) allows for these loads to interconnect to the system; and (3) protects existing ratepayers, is a responsibility shared between the states and PJM.”35  Google agrees that both the Commission and the states have important roles to play in

32 PJM Answer at 21 (quoting Transmittal at 6).
33 Id. (quoting Transmittal at 3).
34 Id. (quoting Transmittal at 2).
35 Id. at 3.

PDF page 15

-15-
addressing the issues in this docket.36  But the fact that both the Commission and states have an important role to play does not give PJM license to redraw the FPA’s jurisdictional line to suit its preferences.

Other specific arguments advanced in defense of IRAS fare no better.  For example, parties contend that IRAS does not “target retail customers by making the characteristics of the retail customer the basis for a curtailment obligation.”37  But the same Answer disproves this argument, explaining that “PJM proposes to limit the total MWs of load reduction in a zone or area based on the share of new large loads . . . that have failed to meet their capacity needs through BYONC or capacity procured pursuant to Reliability Backstop Procurement (RBP) rules.”38  Similarly, the Public Interest Organizations argue that “PJM will respect jurisdictional boundaries by directing IRAS Actions at the wholesale level.  PJM will never curtail individual retail customers—instead, it uses the Registry and results from the most recent BRA to designate megawatt quantities of IRAS curtailment by zone.”39  But here too, the quoted language proves that the opposite is true because the individual retail customer characteristics in the Large Load Registry are what trigger the wholesale curtailments under IRAS, illustrating how IRAS is targeted at retail customers.  In short, no one in this proceeding has credibly shown that IRAS is “all about, and only about” the wholesale market.40  Instead, as even statements from supporters of IRAS demonstrate, retail customer characteristics are the trigger for IRAS, which illustrates how IRAS targets the retail

36 See infra section II.C. (explaining that the Commission could direct PJM to amend its tariff to establish a federal interruptible service framework that would accommodate state retail-level tariffs).
37 Gov. Shapiro Answer at 7 (cleaned up) (quoting Google Protest at 8-9).
38 Id. at 8; see id. (IRAS “[d]uly target[s] load reductions in zones or areas with non-capacity backed new large loads . . . .” (emphasis added)).
39 PIOs Comments at 19.
40 EPSA, 577 U.S. at 282.

PDF page 16

-16-
market by creating the sort of impermissible “tether” to the retail market that cannot be remedied by its wholesale market effects.41

The same goes for arguments that IRAS is about addressing transmission zones with capacity shortfalls.  For example, parties attempt to recast IRAS as “focus[ing] on zones or areas projected to have capacity shortfalls in real-time—through the existence of non-capacity backed large loads in the planning horizon.”42   But those descriptions overlook the defining feature of IRAS: how PJM determines the amount of load to be reduced under IRAS.  That determination depends entirely on the extent to which certain retail customers offset their demand with new capacity.  IRAS does not focus on areas projected to have capacity shortfalls; only on areas with retail customers that qualify as Eligible New Large Loads.  As explained above, a zone could have a GW capacity shortfall and be exempt from IRAS if its load growth is in the form of 1,000 one- MW loads (or, indeed, 20 49-MW loads), while another zone that does not have a shortfall but has one New Large Load that did not bring new capacity would be subject to IRAS.  Put differently, under IRAS, an LSE or an ED could be net long, with sufficient capacity to serve all of the loads in its footprint, but if a New Large Load comes online without offsetting capacity, that LSE/ED would still receive a curtailment instruction.  As the above hypothetical confirms, yet again, IRAS is about the transmission zone’s retail customers, not about its capacity shortfall. Parties claim that “protestors cannot logically claim both that PJM’s proposal unlawfully ‘targets retail customers’ and that PJM’s proposal is fatally flawed because it cannot guarantee

41 Hughes, 578 U.S. at 165-66 (explaining that States can encourage production of new or clean generation— which comes within the states’ jurisdiction of generation facilities—as long as the states’ actions are “untethered to a generator’s wholesale market participation.” (emphasis added)).
42 Gov. Shapiro Answer at 9.

PDF page 17

-17-
which individual retail customers are curtailed.”43  Supreme Court precedent says otherwise. Indeed, the Supreme Court developed its jurisprudence regarding the “target” or “aim” of a regulation precisely because it is possible for a regulator to nominally address a matter within its jurisdiction while actually “targeting” a matter outside its jurisdiction.44  In Oneok, Hughes, and the Court’s predecessor cases, the Court recognized the distinct possibility that a state or the Commission could impermissibly target or aim at a matter outside of its jurisdiction without literally regulating the matter in question.45  There is no logical inconsistency in the fact that IRAS is unlawfully targeted at retail customers even though PJM would not take the final step of carrying out the curtailment decisions.46

Elsewhere, parties claim that, as the region’s Reliability Coordinator, Transmission Operator, and Balancing Authority, PJM already has the authority to take the curtailment actions that it might have to under IRAS. 47  Google agrees that PJM has (and must have) the authority to curtail loads to protect reliability.  But that does not make IRAS legal.  The fact that PJM has the authority to order curtailments in general does not mean that any curtailment mechanism is necessarily legal.  Similarly, because, for the reasons explained above,48 IRAS would condition the quality of a wholesale service on retail customer characteristics, it would exceed the Commission’s jurisdiction though PJM can order curtailment in other circumstances.

43 Id. at 9-10; PJM Answer at 28 (quoting Gov. Shapiro Answer at 9-10).
44 See Hughes, 578 U.S. at 164; Oneok, 575 U.S. at 385; N. Nat. Gas Co. v. State Corp. Comm’n of Kan., 372 U.S. 84, 94 (1963); Nw. Cent. Pipeline Corp. v. State Corp. Com’n of Kan., 489 U.S. 493, 514 (1989).
45 See Hughes, 578 U.S. at 164; Oneok, 575 U.S. at 385; N. Nat. Gas Co., 372 U.S. at 94; Nw. Cent. Pipeline Corp., 489 U.S. at 514.
46 See Hughes, 578 U.S. at 164. 47 Gov. Shapiro Answer at 7 (“Indeed, actions that would be possible under IRAS are no different from other actions (or ‘Operating Instructions,’ as defined by NERC) that PJM has long been authorized to take as the region’s Reliability Coordinator, Transmission Operator, and Balancing Authority.”).
48 See supra section II.A.1.

PDF page 18

-18-

Next, parties suggest that protesters are arguing that PJM “is legally barred from acting on information about the characteristics of load growth in a zone or area, even if that information is directly relevant to reliable operation of the bulk power system and enables PJM to provide a just and reasonable wholesale product or service.”49  That is another strawman.  As explained above, PJM is emphatically not considering “load growth in a zone or area” or even capacity shortfalls in specific zones.50  IRAS does not apply based on any of those considerations.  Instead, IRAS applies based on retail customer characteristics.  As such, the question of whether the Commission could act on the basis of load growth itself is simply not presented in this proceeding.   In any case, Google’s position is not that PJM cannot consider “the characteristics of load growth in a zone or area.”  After all, Google supports the Large Load Registry as a valuable means of gathering that information, and PJM can and does consider the aggregate characteristics of each zone in regulating wholesale market participants, whether LSEs or EDs.  What PJM cannot do is condition the quality of wholesale service on individual retail customer characteristics. Further, parties are incorrect that “the protestors’ position would bar PJM from taking into consideration information about generating facilities—ramp rates, minimum run times, outage rates, and so on—because neither the Commission nor PJM have authority to directly regulate generation.”51  Generators participate in wholesale markets under Commission jurisdiction and those characteristics are directly relevant to and directly affect wholesale sales under the Commission’s jurisdiction.  In other words, rules regarding those factors can be aimed at and justified by a rationale that is “all about, and only about, improving the wholesale market.”52  The

49 Gov. Shapiro Answer at 10.
50 See supra section II.A.1.
51 Gov. Shapiro Answer at 11.
52 EPSA, 577 U.S. at 282.

PDF page 19

-19-
same cannot be said of retail customers or retail customer characteristics that never come within Commission jurisdictional markets.

Perhaps most surprisingly, PJM tries to fit IRAS within the context of the Commission’s recent Tri-State order.  Specifically, PJM notes that the Commission’s most recent order held that in “addressing ‘concerns regarding the rapid growth of large loads,” Tri-State’s proposal “do[es] not constitute ‘an impermissible intrusion upon retail rate regulation.’”53  From that, PJM reasons that, “while the IRAS framework may ultimately affect retail customers, it cannot be said to ‘present an impermissible intrusion upon retail rate regulation.’”54  But beyond pointing out the obvious fact that both the Tri-State proposal and IRAS addressed large load growth, PJM never explains how Tri-State bears any resemblance to this case.55  That similarity cannot be enough to establish jurisdiction for IRAS.  After all, the Commission rejected Tri-State’s earlier filing addressing large loads on the ground that it exceeded the Commission’s jurisdiction. 56  In any case, the Tri-State HIL proposal applies to wholesale transmission customers—i.e., Tri-State Member Utilities—who have the discretion to decide whether to pass certain HIL-related obligations on to their retail customers.   The Tri-State proposal would not condition wholesale market service on the characteristics of specific retail customers.  Under IRAS, by contrast, the wholesale customer—i.e., the LSE or ED—is required to curtail transmission service and to do so in amounts determined solely based on the characteristics of retail customers.  Were the Tri-State proposal to actually resemble IRAS, as PJM claims, then the requirements that Tri-State imposes on its

53 PJM Answer at 25 (quoting Tri-State Generation & Transmission Ass’n., 196 FERC ¶ 61,127, at P 68 (2026)). 54 Id. at 26 (quoting Tri-State Generation & Transmission Ass’n., 196 FERC ¶ 61,127, at P 66).

55 See id. at 24-26. 56 See Tri-State Generation and Transmission Association, Inc., 193 FERC ¶ 61,070 (2025).

PDF page 20

-20-
Member Utilities would vary depending on the characteristics of the retail customers those Members serve.

2. Undue Discrimination
IRAS is also unduly discriminatory.  The Answers that contend otherwise fail to either wrestle with or rebut the arguments illustrating that IRAS would treat similarly situated entities differently without a legally cognizable basis for doing so.  As such, the discrimination inherent in IRAS cannot be “due.”

As a threshold matter, while parties contend that IRAS is not unduly discriminatory because it treats “novel forms of load” differently than “traditional forms of load,” this argument confirms that IRAS unlawfully “targets” the characteristics of certain retail customers. Specifically, protestors argue that new loads have different characteristics (i.e., they are larger, fast-paced additions, concentrated in a single location) than traditional retail customers and therefore it is not unduly discriminatory to treat them differently.57  All of those features—the size, speed, and geographic proximity of the loads within a transmission zone—are again characteristics of the retail customer, not the wholesale market.  The fact that defending IRAS requires distinguishing between retail characteristics to explain why one group of those retail customers should be curtailed only confirms that IRAS unlawfully targets retail customers.

In any case, the Commission cannot justify discrimination based on characteristics that the Commission is legally prohibited from regulating—i.e., retail customer characteristics—because such differences are not (and cannot be) “material to the inquiry at hand.”58  A conclusion to the

57 Gov. Shapiro Answer at 15-16.
58 N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at PP 10, 14 (2018) (“To say that entities are similarly situated does not mean that there are no differences between them; rather, it means that there are no differences that are material to the inquiry at hand.”); see also id. P 14 (finding that a difference between incumbent and non-incumbent

PDF page 21

-21-
contrary would open the door to a host of “surprising”59 new bases for Commission regulation. For example, if retail customer characteristics were a legitimate basis for wholesale market discrimination provided that the public utility could ascribe reliability benefits to the discrimination, there would be nothing to prevent the Commission from conceivably justifying withholding firm service to LSEs that serve a disproportionate number of single-family homes on the basis that LSEs that instead disproportionately serve apartment buildings are more electrically efficient and incentivizing apartments relative to single-family homes would enhance regional resource adequacy.  Yet such a scheme would clearly be impermissible because it so obviously discriminates against LSEs based on the retail loads in their footprints.  Nevertheless, that is the principle that PJM is asking the Commission to endorse by finding that retail customer characteristics could be valid bases for conditioning the quality of wholesale service in IRAS. Parties argue that the Commission has already distinguished New Large Loads in the

context of its June 18th Show Cause Orders and NERC’s forthcoming Reliability Standards.60 While the Commission has found that large loads are different in certain respects from organic load growth, those findings were made in proceedings addressing different issues and statutory authorities than here.  First, the Commission’s Show Cause Orders carefully target the transmission services that Eligible Customers—i.e., wholesale customers—take to serve New Large Loads based on how those Eligible Customers request service and use the transmission system. 61  For

transmission developers was not material to the issue at hand and therefore could not be the basis for discriminating between incumbents and non-incumbents).

59 EPSA, 577 U.S. at 277.
60 Gov. Shapiro Answer at 17. 61 See, e.g., PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at P 41 (2026) (“We today make a preliminary finding that PJM’s Tariff appears to be unjust and unreasonable because it lacks provisions that address, with sufficient clarity and consistency, how PJM and/or the Transmission Owners will timely study (i.e., within 60-90 days of receiving the request) the provision of transmission service to Eligible Customers on behalf of large loads.” (emphasis added)); id. P 45 (“Specifically, we find that it is within the Commission’s exclusive authority to ensure that

PDF page 22

-22-
instance, the PJM Show Cause Order preliminarily found PJM’s Tariff unjust and unreasonable because it does not sufficiently address how PJM and the Transmission Owners “will study the provision of transmission service to Eligible Customers on behalf of large loads.”62  That is distinctly different from IRAS where the retail customer characteristics are what determines the quality of wholesale service.  Second, NERC Reliability Standards are issued under Section 215 of the Federal Power Act, which applies to “all users, owners and operators of the bulk-power system.”63  Whether a New Large Load constitutes a user of the bulk-power system is irrelevant to the question at issue here:  whether two classes of customers are differently situated such that differential treatment is permissible under section 205.

Attempts to justify undue discrimination based on the vintage of the retail load fare no better.  Most notably, PJM is wrong to argue that “[n]ew, not existing load, is the reason for the shortfall, which drives the need for IRAS. Failing to make a distinction between New Large Loads and Large Loads for purposes of applying IRAS would fail to account for causation.” 64  As the D.C. Circuit has explained, all load is “economically marginal” in the sense that customers impose equivalent costs “whether by adding or merely continuing their usage” regardless of when they first took service, meaning that each MW of demand, whether new or existing, contributes equally to the region’s current resource adequacy picture.65

transmission provider and/or transmission owner tariffs include sufficiently clear and consistent provisions governing how transmission service to Eligible Customers on behalf of large loads interconnecting to the transmission system will be studied, including whether new or upgraded transmission facilities are necessary to provide the requested transmission service.”); id. P 49 (“In sum, we today exercise our authority to ensure that the process by which jurisdictional transmission providers and/or transmission owners will study the provision of jurisdictional transmission service to Eligible Customers on behalf of large loads.”).

62 Id. P 51.
63 16 U.S.C. § 824o(b)(1). 64 PJM Answer at 61.
65 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268-69 (D.C. Cir. 2014) (citations omitted).

PDF page 23

-23-
While parties suggest that IRAS does not discriminate between new and existing loads and instead simply applies “on a forward-looking basis to new large loads after its acceptance,”66 this is not the case.  IRAS is not merely an extension of the Commission’s standard practice of accepting new rules on a prospective basis while grandfathering existing entities.  Instead, IRAS would switch on and off again based on future supply and demand conditions.67  If and when IRAS switches on again, it would reset what constitutes baseline and new, meaning that retail customers that would count as New Large Loads in 2027 might not be subject to IRAS in just a few years and would instead be considered baseline loads during a future invocation of IRAS.  Although there may be a reasonable policy justification for this approach, it shows that IRAS is not a one- time grandfathering mechanism but rather an arbitrary distinction that treats retail customers differently based on the background circumstances at the time they interconnected and ramped up their load.68

Finally, attempts to justify undue discrimination based on the fact that existing loads paid for capacity in previous years reveal a misunderstanding of the basic principles that underlie PJM’s capacity market.  The capacity market auction functions for resources to sell capacity for a specific delivery year.69  The market procures capacity to meet aggregate regional needs for that particular year; it does not provide specific individual customers the right to specific shares of capacity.  Nor

66 Gov. Shapiro Answer at 18 (emphasis added).
67 Transmittal at 52-53, 72.
68 But see BNP Paribas, 743 F.3d at 268 (“[T]he cost causation principle generally calls for giving the same treatment to new and continuing customers.”); 1 Alfred Kahn, The Economics of Regulation: Principles and Institutions 140 (The MIT Press 1998) (explaining that an existing customer that is “continuing to take service is just as responsible, in proportion to the amount they take, for the need to expand investment” to accommodate another customer’s increasing demand).
69 PJM, Open Access Transmission Tariff, attach. DD.5.4 (Reliability Pricing Model Auctions) (10.0.0), § 5.4.

PDF page 24

-24-
does it provide customers any claim to preferential treatment for subsequent years. 70  Otherwise, every new subdivision, factory, or business would need to bring its own new capacity because existing capacity can only be committed to serve existing loads.  By the same token, no capacity resource could ever retire or de-list because it would be obligated to continue serving as a capacity resource in perpetuity.

3. Unjust and Unreasonable
IRAS is also unjust and unreasonable.  Here too, there are multiple bases for that conclusion:  (i) the curtailment priority cannot be the product of reasoned decision-making and (ii) PJM cannot ensure that loads that bring new capacity to secure firm transmission service will, in fact, receive that service.  Either of these issues is sufficient reason to reject IRAS, and the Answers have not shown otherwise.

i. Curtailment Priority
As an initial matter, the suggestion that the curtailment priority, which is the central feature of IRAS, is a “policy judgment[] that do[es] not render the design unjust and unreasonable,” 71 is novel, unsupported by any citation to precedent or other authority, and incorrect.  The curtailment priority is part of the tariff language filed with FERC and therefore it must be just and reasonable, whether or not it implicates any policy judgment.72  A rule providing that the Commission could not reject a filing because it contained a policy judgment would fly in the face of the section 205’s plain language and be unworkable in the extreme.

The merits of the IRAS curtailment priority are equally problematic.

70 See BNP Paribas, 743 F.3d at 269 (“[T]he Commission doesn’t explain why the historic shippers’ earlier [payments] . . . give[] them a special equitable claim in perpetuity.”).

71 Gov. Shapiro Answer at 5.
72 Section 205 provides that all “rules and regulations affecting or pertaining to [Commission-jurisdictional rates] . . . shall be just and reasonable.” 16 U.S.C. § 824d(a).

PDF page 25

-25-
First, PJM’s answer all but concedes that curtailing Eligible New Large Loads before demand response resources violates cost causation principles.  According to PJM, “Eligible New Large Loads available to provide IRAS have not satisfied their respective capacity needs through BYONC, and therefore, should not obtain the capacity benefit of Demand Resources.” 73 Nevertheless, Eligible New Large Loads will be allocated capacity charges, which will include costs to pay for demand response resources providing capacity.  But those New Large Loads will not get any benefit for the portion of their capacity costs attributable to demand response resources. And that is not some rounding error that is acceptable in the name of a roughly commensurate cost allocation.74  Rather, it is a foundational feature of IRAS and reason enough to conclude that it has not been shown to be just and reasonable.

Nevertheless, PJM attempts to defend this result by asserting that Eligible New Large Loads “would be compensated [to curtail under IRAS], in part, to account for the fact” that those loads “would not be able to obtain the full benefit” of the demand response capacity they have helped finance.75  In other words, PJM is proposing to require New Large Loads to pay for capacity from which they will receive no benefits in exchange for the hope that those loads will receive an offsetting retail payment, which the Commission cannot ensure they will receive.  While cost causation does not require exacting precision, it requires more than the mere hope that wholesale costs will be offset down the line by retail compensation.

Second, PJM is also wrong to argue that the curtailment order “is consistent with PJM’s current processes to recall/curtail non-firm transmission service after economic generation and

73 PJM Answer at 31.
74 See Paragould Light & Water Comm’n v. FERC, 144 F.4th 287, 292 (D.C. Cir. 2025) (“[W]e do not require FERC to allocate costs with exacting precision.” (internal quotation marks omitted)).
75 PJM Answer at 56.

PDF page 26

-26-
before Pre-Emergency Load Management [because in] both instances, these entities transact in the PJM Energy Market without having secured any capacity.”76  For one thing, elsewhere PJM contends that Eligible New Large Loads are served by LSEs that take firm Network Integration Transmission Service,77 so the suggestion that they take non-firm transmission service is inconsistent.  Further, the statement that Eligible New Large Loads have not “secured any capacity” belies the fact that they have, nevertheless, paid for capacity, just without receiving the full benefit.

Third, PJM and some parties argue that curtailing New Large Loads before demand
response is necessary to avoid demand response fatigue, which would “reduce available capacity to meet regional needs by deterring demand response registration.” 78  If PJM cannot rely on demand response when system conditions are tight then, by definition, demand response is not “available capacity to meet regional needs.”79  To the extent demand response resources cannot perform the function for which they elected to provide under the terms for which they  were procured, the solution is to reform the demand response program—e.g., through the development of a bounded demand response product and adjusted accreditation 80—rather than develop a convoluted and illogical curtailment structure.

76 PJM Answer at 34.
77 Transmittal at 94. 78 Gov. Shapiro Answer at 5; see also Gov. Shapiro Answer at 24 (“Moreover, if called upon too frequently, demand response resources will be less likely to register over time, reducing the capacity available to serve the region at a time when every resource that can be quickly brought online is needed.”); PJM Answer at 36 (“The more often a load center is asked to reduce consumption the more disruptive the provision of demand response and the greater the opportunity cost. The result is load centers become less willing to provide demand response and support Demand Resources.”); New Jersey Board of Public Utilities (“NJBPU”) Comments at 5 (the IRAS curtailment scheme will “help maintain the participation of certain load management reduction resources, like DR, by minimizing ‘fatigue’ that can occur from being over-called on during stress events.”).
79 Gov. Shapiro Answer at 5. 80 Google Protest at 19.

PDF page 27

-27-
Finally, it is also incorrect to suggest that curtailing demand response first would allow New Large Loads to rely on demand response resources to provide capacity, which “would result in existing customers sharing the increased cost of calling on the demand response that is due to large load growth.”81  If existing loads were forced to pay for demand response capacity from which they derive no benefit, as parties suggest would happen under IRAS, this would violate bedrock cost causation principles, which require that costs be assigned in a manner that is roughly proportionate with benefits.82  To the extent load growth from New Large Loads leads to more reliance on demand response, cost causation and beneficiary pays principles require that those loads pay for their share of increased capacity costs.

ii. IRAS Will Not Incentivize New Large Loads to Bring New Capacity
As Google and others explained in their protests, one of the fundamental flaws of IRAS is that different entities are imposing the obligation to bring new capacity (PJM) and determining which retail loads are interruptible if not (EDs).  That bifurcation creates regulatory uncertainty about whether a load that brings new capacity will actually receive the firm service that it seeks. That regulatory uncertainty will, in practice, make it harder for companies like Google to sign the long-term off-take agreements that are necessary to actually develop significant quantities of new capacity and make PJM resource adequate again.

 PJM does not dispute that it lacks the authority to ensure that New Large Loads that bring new capacity will, in fact, receive the firm service that they have spent billions of dollars to receive.83  And while other parties claim that bringing new capacity will “materially decrease”

81 Gov. Shapiro Answer at 24.
82 See Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018).
83 See, e.g., Transmittal at 92.  Throughout this proceeding, PJM has consistently taken the position that it has no authority to order the curtailment of specific retail customers.  Nevertheless, PJM’s proposed tariff language could be read to suggest that PJM can do just that.  See Proposed Tariff, attach. DD-4, section III (“Electric Distributors

PDF page 28

-28-
their curtailment risk, that will not necessarily be the case.84  To see why, consider a hypothetical in which two new 50 MW loads—one offsetting its demand with new capacity and the other

bringing no new capacity to the system—begin operating in an ED’s footprint.  PJM has no
authority to determine which 50 MW the ED drops when PJM calls for IRAS curtailments; the ED is free to curtail either load.  The fact that PJM’s aggregate curtailment instruction to the ED may be lower if the new load brought its own capacity does not necessarily affect the ED’s likelihood of curtailing a specific retail customer.  For instance, the ED might be required to act pursuant to a state policy to curtail certain end uses of loads over others, regardless of which end user brought its own capacity.  Or the ED might simply have a better relationship with one end user rather than another.  In any event, it is not at all clear that a large load can actually decrease, much less materially decrease, its curtailment risk by bringing its own capacity.

We also disagree with the contention that “protestors’ arguments that IRAS will fail to
incentivize new large loads to invest in new capacity . . . is contradicted by arguments that IRAS is too harsh and must be mitigated by a more generous transition period.”85  Google’s concern about IRAS has never been that it is “too harsh.”  Google’s concern is that IRAS is illegal and will be ineffectual.  Further, there is nothing inherently inconsistent in pointing out, as Google and other protestors have, that IRAS will fail to incentivize investments in new capacity.  On both

shall: execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions among the Eligible New Large Loads in the Electric Distributor’s zone/area . . . .” (emphasis added)).  Given PJM’s representations about the extent of its jurisdiction, Google believes that the proposed tariff language should not reasonably be read to allow PJM to order EDs to curtail specific retail loads or classes of re-tail loads.  If PJM takes the opposite position, that would be inconsistent with both the FPA and PJM’s representations to the Commission.

84 Gov. Shapiro Answer at 21-22 (“PJM proposes to identify the total MW quantity of load subject to IRAS in a zone or area based on new large loads that have not addressed their capacity needs within that zone/area, and to leave the actual curtailment directions being made to end-use retail load to the Electric Distributer. As a result, individual large loads materially decrease their likelihood of being subject to curtailment by investing in new capacity.”).
85 Id. at 21.

PDF page 29

-29-
issues, the point is that investors require regulatory certainty to make the billion-dollar investments in new capacity in PJM that are necessary to resolve its resource adequacy challenges.  New Large Loads coming to the region need certainty that bringing new capacity will mean that they receive firm service, and IRAS does not provide that certainty.  There is nothing inconsistent in the idea that PJM’s market rules must create an investable environment.

B. The Current Tariff Is Unjust and Unreasonable
As for the second prong of the Western Resources framework, the record of this proceeding presents an ample basis to conclude that the status quo is unjust and unreasonable.86  Demand, largely in the form of New Large Loads, is outpacing supply to such a degree that near-term reliability and resource adequacy are now very much in question.87  Although some New Large Loads in PJM, including Google’s, are making the investment necessary to procure sufficient new capacity to cover their demand, that is the exception to the rule.  Instead, capacity market demand can and likely will continue to exceed supply for the foreseeable future and yet there is no option in PJM’s tariff for LSEs to take interruptible service.  That means that the PJM tariff lacks a mechanism to interrupt service in an orderly fashion or before PJM enters emergency procedures notwithstanding the inescapable fact that not all demand can be backed with firm capacity.  This subjects otherwise firm customers to curtailment, degrading firm service.

 In response to those circumstances, the Commission should find, now or following additional process, that the tariff is unjust and unreasonable because it does not provide a pathway for LSEs to take interruptible service similar to what is available in the natural gas transportation

86 That does not, however, prevent the Commission from conducting a further proceeding to supplement the record.  W. Res., Inc. v. FERC, 9 F.3d 1568; 16 U.S.C. § 824e.
87 Transmittal at 13; Gov. Shapiro Answer at 1.

PDF page 30

-30-
context.88  In the absence of such a pathway, there is pervasive uncertainty about how demand will be curtailed to maintain reliability and real risk that entities will be curtailed without any option to make investments or take other measures to avoid that result.89  An interruptible capacity service product, by contrast, would provide order and predictability by establishing when and under what circumstances customers subject to the service would be interrupted while also allowing the capacity market to clear under conditions where demand exceeds supply.

In this sense, the Commission would build on its findings in the PJM Co-Location Proceeding and the Large Load Show Cause Orders, which required and proposed to require, respectively, that creation of an interim service in part to promote efficient allocation of transmission capacity and “preserv[e] reliability for other . . .  customers.” 90  In so doing, the Commission would, in effect, extend that logic underlying its findings with respect to transmission service to the capacity market, requiring the creation of a non-capacity backed interruptible service.  In other words, whereas the PJM Co-Location Proceeding provided for interruptibility when there is inadequate transmission, this interruptible service would provide for interruptibility when there is inadequate capacity.

Finally, while the Commission lacks authority over the rules governing whether and how LSEs sign up new retail customers, the creation of wholesale interruptible service would provide a framework by which states and LSEs could implement their preferences regarding which retail customers get firm retail service and what steps they must take to qualify.  States, for example, could condition firm retail service for customers above a certain MW threshold on those customers

88 Duke Energy, 315 F.3d at 378-79 (distinguishing between firm and interruptible in the natural gas context).
89 See Vistra Protest at 4; Dominion Comments at 4 (“LSEs should have an affirmative obligation to procure new capacity to cover any new Large Loads they seek to interconnect and serve.”). 90 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 201; see id. P 177; PJM Interconnection, L.L.C., 195 FERC ¶ 61,211.

PDF page 31

-31-
bringing new capacity with those that do not being forced to take interruptible retail service backed only by a new interruptible wholesale service.  In this way, requiring the creation of an interruptible wholesale service could give states the impetus to address the fundamental problem—large load growth that is outstripping supply—which IRAS was in theory supposed to solve, but in manner that is legal and consistent with the FPA’s allocation of jurisdiction.

C. Replacement Rate

Google strongly supports Commission action to adopt a legally durable path to ensuring resource adequacy in the face of load growth driven by New Large Loads.  As explained above, given the current—and likely continuing—imbalance between demand and supply in the PJM capacity market, a just and reasonable replacement rate will need to incorporate some form of interruptible service.  Below, Google presents a relatively surgical option for the Commission to set as a replacement rate, following the appropriate notice and opportunity for a hearing, that addresses the need for an interruptible service class while also achieving the goals underlying IRAS, but while doing so legally and without the investment-defeating uncertainty IRAS would create.91 The approach has two principal elements, which the Commission could make the basis for further elaboration and development in a paper hearing.92

First, the Commission would require PJM to create an interruptible class of capacity market service that, as discussed above, is similar to the analogous service available in the gas transportation context under the NGA and builds upon the interim interruptible NITS product

91 16 U.S.C. § 824e.
92 Monongahela Power Co., 164 FERC ¶ 61,217.  Separately, Google supports the Commission creating something akin to the Large Load Registry proposed by PJM, which the Commission could do this either by accepting the proposed Registry subject to a hearing on the appropriate data management and confidentiality guarantees, or by rejecting with guidance to PJM on the need to establish such guarantees.  The Commission has the authority to accept only the Large Load Registry and sever and reject the rest of PJM’s filing.  See Transmittal at 10 (consenting to modify/sever certain aspects of the IRAS proposal).

PDF page 32

-32-
established in the PJM Co-Location Proceeding.93  The interruptible class of service would reflect the fact that demand cannot exceed supply and, if necessary, something must give to prevent that result and ensure system reliability.   Instead of using a blunt, haphazard, or, in the case of IRAS, illegal approach, an interruptible class of service enshrined in the PJM tariff would provide an orderly means for equilibrating supply and demand and create the conditions for the regulatory certainty needed to make long-term investments in new capacity.  In addition, the creation of an interruptible class of service would also prevent the degradation of firm service by providing a tool to manage supply and demand without triggering emergency procedures and, if necessary, a manual load dump.

An interruptible service class would resolve several of the fundamental flaws in IRAS.  For example, because the service class would be available to LSEs directly, there would be no need for IRAS’s targeting of retail customer characteristics or, for that matter, any tethering to the retail market whatsoever.94  In addition, it would also address the price formation and retail ratemaking concerns associated with IRAS’s proposal to remove load from the VRR curve, but nevertheless charge and rebate capacity costs for customers that are subject to IRAS and ultimately curtailed. Because the service class is interruptible and, therefore, not backed by firm capacity, there would be no need to include this load in the capacity market at all or provide compensation to retail customers when it is interrupted.

Critically, a federal interruptible service framework would also establish the necessary foundation for BYONC to work in practice.  That is because any BYONC requirement could be enshrined in the state retail-level tariffs that by determining the rules and criteria by which retail

93 PJM Co-Location Order, 193 FERC ¶ 61,217 at PP 177, 201.
94 Supra section II.A.1.

PDF page 33

-33-
customers are subject to receiving or potentially receiving interruptible service, (e.g., loads that display defined electrical characteristics, are over a certain MW threshold, are of a certain vintage, etc.).  The retail tariffs would also enumerate what steps those loads need to take to secure firm service, such as by bringing their own new capacity and the requirements to qualify for having done so (e.g., the required quantity, resource eligibility, accreditation, location, generation type, if applicable).  In the event those loads do not meet the state-level requirements for firm retail service—e.g., because they did not secure sufficient capacity to cover their demand—their LSE would procure interruptible capacity service for them.

In addition, as part of the replacement rate, PJM would need to establish clear rules governing how state-designated interruptible loads are reflected in the relevant programs under its jurisdiction, including capacity procurement requirements, capacity obligations, and transmission planning.  Interruptible loads should be included in PJM’s gross load forecast and operating models because they will consume electricity under ordinary conditions and should thus be planned for accordingly.  A load’s verified interruptible capability, however, should be separately identified and reflected in the reliability analyses and procurement obligations applicable to that load.  PJM would need to establish rules to avoid treating interruptible load as indistinguishable from firm load and double counting the interruptible capability.  These measures could be addressed in further process before the Commission under FPA section 206 or by PJM in the first instance on compliance.

Second, to provide near-term measures to address a potential supply shortfall, PJM would establish a framework for curtailing large loads—including those with firm service95—prior to

95 Those under interruptible load tariffs would already have been interrupted by the time emergency conditions set in.

PDF page 34

-34-
other retail customers during emergency conditions when PJM is approaching a broad Manual Load Dump.  To create this framework, PJM would need to revise its emergency procedures to create a Priority Firm Large Load Reduction Action prior to Voltage Reduction and before Manual Load Dump (a new Step 9A).96

These “9A eligible loads” would be determined pursuant to the rules established in the retail tariff, with PJM seeing only the quantity of MWs to signal to each ED to reduce if Step 9A is reached.  Before each Delivery Year, EDs would report to PJM the aggregate quantity and location of firm large load subject to or that has volunteered for interruption at Step 9A, together with its response time, minimum service level, telemetry, restoration requirements, and other relevant operating characteristics.  PJM would incorporate this capability into its emergency operating plans but would not direct the curtailment of individual retail customers, which would be executed by the ED itself.  When system conditions warrant and the applicable emergency step is reached, PJM would direct the relevant ED to reduce a specified aggregate quantity of registered firm large load. The ED would then implement the instruction under its state-approved emergency load-shed plan. If the load reductions at 9A were insufficient to maintain system reliability, PJM could then proceed to a Voltage Reduction Action (would become Step 9B), and if still insufficient, a Manual Load Dump Action (Step 10).

Together, these two steps—creation of a wholesale interruptible service and the
establishment of a new Step 9A—would largely achieve the goals behind IRAS97—managing the circumstances when demand exceeds supply while also creating the foundation for an incentive

96 The Commission should also direct PJM to establish how these loads would be treated under other aspects of PJM’s tariff.  For example, loads included for curtailment at this new step 9A would continue to be treated as firm load for the purposes of capacity procurement, transmission planning, and ordinary system operations. 97 See, e.g., Transmittal at 7; PJM Answer at 2-3.

PDF page 35

-35-
for New Large Loads to bring their own new capacity—without violating the FPA or creating the investment-killing uncertainty inherent in IRAS.  In so doing, it would create a legally durable means of addressing the current resource adequacy situation in PJM without stymying the investment in new capacity that is the only way out of that situation.

III. CONCLUSION
Demand for capacity in PJM is exceeding supply, creating a significant resource adequacy shortfall.  Accepting IRAS would only worsen the situation.  Instead, the Commission should use this proceeding as the jumping off point to create a new interruptible capacity service.  In so doing, the Commission would put in place the conditions to manage the existing capacity shortfall while also establishing the foundation for States to exercise their retail authority to impose a legally durable BYONC obligation on New Large Loads should they choose to do so.  Accordingly, a new interruptible service would provide a legally durable path to achieve the goals underlying IRAS without the self-defeating uncertainty that IRAS would create.

Respectfully submitted,

/s/ Brian George
Brian George
Sr. Lead, US Energy Markets
Elizabeth Savage
Strategic Negotiator
Google LLC
655 New York Ave., NW
Washington, DC 20001
(202) 999-0990

briangeorge@google.com
eomsavage@google.com

Matt Christiansen
Sarah Greenberg
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871

mchristiansen@wsgr.com
sgreenberg@wsgr.com
bshpall@wsgr.com

Counsel for Google LLC
Dated:  September 30, 2026

PDF page 36

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.

Dated:  September 30, 2026
Washington, D.C.

/s/ Bryan Shpall
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006