Answer of Google LLC in response to pleadings re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service
Text extracted from the eLibrary original (SHA-256 5a5aa30fff868f20…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
The Commission must now guide PJM back on course.Read this passage Filed comments: Reliability and curtailment
I. MOTION FOR LEAVE TO ANSWER
printed heading
FERC, 9 F.3d at 1579; Monongahela Power Co., 164 FERC ¶ 61,217 at P 17. -6- the Commission may permit them for good cause.13 The Commission frequently accepts answers that clarify the issues before the Commission, ensure a complete record, or otherwise assist the Commission in its…Read this passage
II. ANSWER
printed heading · Topic match: Reliability and curtailment
The Commission must either reject IRAS with guidance to PJM to establish a legally durable approach that includes a clear and transparent category interruptible service that does not 13 18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, or a…Read this passage Filed comments: Reliability and curtailment
A. The Record Confirms that PJM Has Not Satisfied Its FPA Section 205 Burden
printed heading · Topic match: Reliability and curtailment
Google agrees that PJM is facing the prospect of a serious resource adequacy shortfall and that New Large Loads must step up and cover that capacity shortfall, consistent with the Ratepayer Protection Pledge.Read this passage Filed comments: Reliability and curtailment
B. The Current Tariff Is Unjust and Unreasonable
printed heading · Topic match: Retail and wholesale authority
Finally, while the Commission lacks authority over the rules governing whether and how LSEs sign up new retail customers, the creation of wholesale interruptible service would provide a framework by which states and LSEs could implement their preferences regarding which retail customers get firm…Read this passage Filed comments: Retail and wholesale authority
C. Replacement Rate
printed heading · Topic match: Reliability and curtailment
See Transmittal at 10 (consenting to modify/sever certain aspects of the IRAS proposal). -32- established in the PJM Co-Location Proceeding.93 The interruptible class of service would reflect the fact that demand cannot exceed supply and, if necessary, something must give to prevent that result and…Read this passage Filed comments: Reliability and curtailment
III. CONCLUSION
printed heading · Topic match: Reliability and curtailment
CONCLUSION Demand for capacity in PJM is exceeding supply, creating a significant resource adequacy shortfall.Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated: September 30, 2026 Washington, D.C. /s/ Bryan Shpall Bryan Shpall Wilson Sonsini Goodrich & Rosati 1700 K Street NW Fifth Floor Washington, DC 20006Read this passage