ER26-3515-000 · 2026-10-01 · Data Center Coalition
Motion for Leave to Answer and Answer of Data Center Coalition to the answer of PJM Interconnection, L.L.C. and certain other comments and answers re the…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
)
MOTION FOR LEAVE TO ANSWER
AND ANSWER OF THE DATA CENTER COALITION
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”),1 the Data Center Coalition (“DCC”)2
hereby moves for leave to answer3 and answers the answer of PJM Interconnection, L.L.C.
(“PJM”)4 and certain other comments and answers filed by intervenors regarding PJM’s proposal to establish Interim Resource Adequacy Service (“IRAS”) and a Large Load Registry.5
I. ANSWER
As DCC explained in detail in its Protest, DCC strongly supports reforms to ensure that
large loads can be integrated into the grid while preserving reliability and protecting customers.
1 18 C.F.R. §§ 385.212 and 385.213.2 DCC is a membership organization of leading data center owners and operators. Public testimony and written comments submitted by DCC do not necessarily reflect the views of each individual DCC member. A list of current DCC members is accessible at https://www.datacentercoalition.org/members.3 DCC acknowledges that the Commission’s Rules of Practice and Procedure do not typically allow answers to answers. However, the Commission has accepted answers in the past when they have (i) assisted the Commission in understanding the issues presented, (ii) provided additional information for the Commission’s decision-making process, and (iii) helped ensure an accurate record. See, e.g., PJM Interconnection, L.L.C., 181 FERC ¶ 61,162, at P 29 (2022); Canal Generating LLC, 181 FERC ¶ 61,157, at P 14 (2022); Equitrans, L.P., 134 FERC ¶ 61,250, at P 6 (2011); Cal. Indep. Sys. Operator Corp., 132 FERC ¶ 61,023, at P 16 (2010). In this proceeding, DCC’s answer will help the Commission understand the issues presented by PJM and the other answers and comments filed in this proceeding and provide further information related to the issues in this proceeding to inform the Commission’s decision-making process. DCC therefore respectfully requests leave to file this answer and asks the Commission to consider this answer in its deliberations in this proceeding.4 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. (Sept. 23, 2026) (“PJM Answer”).5 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability (Aug. 13, 2026) (“Filing”).
PDF page 2
- 2 -
Along with the Virginia State Corporation Commission, DCC has called on states to develop model interruptible tariffs and load-reduction programs that would allow large loads to take interruptible service. DCC shares PJM’s commitment to ensuring that large load growth occurs in a way that is compatible with reliability and does not result in cost shifts to other customers.
But PJM’s proposal to impose a region-wide retail curtailment framework represents an unprecedented intrusion into the authority reserved to the states under the Federal Power Act (“FPA”) that must be rejected. Facing strong opposition in this proceeding from a range of parties including state regulators, utilities, generation owners, and data center developers, PJM’s Answer attempts to recast IRAS as focused exclusively on the wholesale markets. But the highly curated set of statements that PJM cites in support of this interpretation cannot overcome the overwhelming record evidence demonstrating that IRAS targets, and seeks to dictate, the rates, terms, and conditions of retail service. PJM’s acknowledgment that IRAS requires enlisting Electric Distributors and state regulators to implement PJM’s directives highlights that IRAS treads into areas that are beyond PJM’s and FERC’s jurisdiction. IRAS would invert the regulatory divide established by the FPA by imposing a federally approved retail curtailment framework where state authorities are charged with conforming their retail curtailment and compensation practices to align with PJM policy.
PJM continues to claim that states will be provided with complete discretion regarding how IRAS is implemented. But states have no ability to opt in or opt out of IRAS. PJM will issue directives to curtail New Large Load customers without regard to the preference of individual states. Failure to conform state policies to IRAS would risk subjecting all retail customers to interruption when PJM issues curtailment directives—a consequence that is so severe as to leave states with no option but to comply. IRAS effectively conscripts state authorities into enforcing a
PDF page 3
- 3 -
federal policy respecting matters that have been left to the exclusive judgment and oversight of the states under the FPA.
The record in this proceeding demonstrates the risks of PJM’s top-down approach to retail curtailment. As commenters point out, IRAS fails to account for the reliability contributions of state peak-shaving programs and similar measures that have been implemented by the states to encourage voluntary reductions by large load customers.6 Not only will this unduly discriminate against New Large Loads that have invested in technologies to reduce their loads, but the disconnect between IRAS and state programs has the potential to subject Electric Distributors to conflicting regulatory obligations and uncertainty.7
PJM accuses DCC of taking contradictory positions by arguing for “rejection of IRAS on one hand in favor of state jurisdiction but then bemoans that if states take different positions on curtailment, it will not be clear that IRAS will deliver its intended reliability benefits.”8 But the real contradiction lies within PJM’s defense of IRAS. Because IRAS so clearly targets matters within the exclusive authority of the states, PJM has no choice but to argue that the states retain discretion over implementation of IRAS in an effort to justify its proposal. Yet, its repeated assertions about state discretion, in turn, undercut PJM’s claims that IRAS can achieve its objectives.
While the jurisdictional defects in IRAS alone support rejection of PJM’s proposal, PJM also has not demonstrated that IRAS is just, reasonable, and not unduly discriminatory or
6 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of the Chief Energy Officer for the Governor of Virginia at 2-5 (Sept. 3, 2026).7 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Motion for Leave to Answer and Answer of the New Jersey Board of Public Utilities at 4-5 (Sept. 18, 2026) (“[I]t is unclear whether EDCs will face penalties for not curtailing the entire amount of the registered peak New Large Load amount directed by PJM, or if EDCs must curtail other customers in order to meet this IRAS obligation.”).8 PJM Answer at 28.
PDF page 4
- 4 -
preferential on its own terms. PJM does not offer any response to many of the objections that have been expressed by DCC and other parties, and the responses that PJM does provide are largely conclusory and do not respond to the substance of commenters’ concerns. For instance, DCC demonstrated that the design of IRAS will result in customers in zones with New Large Loads subsidizing rate reductions for other customers within the PJM footprint; yet, PJM’s Answer does not acknowledge or address these concerns.9 PJM also does not offer any response to concerns raised by DCC and others that IRAS will undermine the settled expectations of New Large Loads that have made investment decisions.10
PJM attempts to salvage IRAS by arguing that every aspect of its proposal is severable and inviting the Commission to rewrite the proposal to cure its defects. PJM even goes so far as to ask the Commission to impose a stand-alone requirement that all load-serving entities (“LSE”) bring new capacity to serve New Large Loads. Other parties ask the Commission to strike aspects of the IRAS framework that they argue go too far. But even with PJM’s consent, the Commission has no authority under FPA Section 205 to “go beyond approval or rejection of a proposal to adoption of an entirely different rate design.”11 And the Commission should decline PJM’s invitation to do so here.
Rather than approving a framework that conscripts state authorities into enforcing federal curtailment policies, the Commission should reject the Filing and encourage PJM to work with stakeholders and the states to develop emergency procedures that accommodate—rather than dictate—the retail curtailment priorities of individual states. Alternatively, if the Commission
9 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Motion to Intervene and Protest of the Data Center Coalition at 22-23 (Sept. 3, 2026) (“DCC Protest”).10 Id. at 30-34.11 NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 115 (D.C. Cir. 2017) (internal quotations omitted) (“NRG”).
PDF page 5
- 5 -
finds that PJM’s existing emergency procedures have been rendered unjust and unreasonable, it should initiate an FPA Section 206 proceeding to develop reforms that respect the jurisdictional boundaries established by the FPA. At a minimum, if the Commission does not reject IRAS outright, it should direct PJM to establish a meaningful transition mechanism and delay implementation until June 1, 2028 to provide New Large Loads and state authorities a reasonable timeline to adapt.
A. PJM’s Justifications Cannot Cure The Jurisdictional Defects With IRAS
1. IRAS Is Premised On An Overly Broad View Of FERC’s Jurisdiction
That Cannot Be Squared With The FPA
PJM argues that the jurisdictional concerns expressed by DCC and numerous other parties in this proceeding are misplaced. According to PJM, whether IRAS “‘targets’ retail or wholesale customers turns on the justification for the rule, not on whether or the extent to which the rule affects or even compels action of retail or wholesale customers.”12 PJM then offers a series of justifications that it claims eliminate any doubts about the legality of IRAS including that it will “support[] system reliability in the PJM region” and provide a new tool to address situations where supply shortfalls jeopardize system reliability.13
It is worth pausing for a moment on the breadth of authority that PJM seeks to claim for itself. Under PJM’s theory, the extent to which IRAS “affects or even compels action of retail” customers is immaterial to the jurisdictional analysis.14 All that matters is whether PJM can articulate some way in which its proposal will support reliability or allow it to more effectively manage its system when supply is tight. But if the sole test for Commission jurisdiction is whether a filing utility can articulate some nexus between the rule at issue and the reliability of the
12 PJM Answer at 19-20 (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 265 (2016) (“EPSA”)).13 Id. at 21.14 Id. at 20 (emphasis added).
PDF page 6
- 6 -
transmission system, there is virtually no aspect of the production, delivery, or consumption of electricity that would be beyond the reach of PJM and FERC. PJM could, on the same logic, adopt tariff requirements that require utilities to construct new generation facilities to resolve supply shortfalls, impose mandatory energy efficiency standards on their retail customers, or require all retail customers to participate in a mandatory demand-response program of PJM’s design—each time invoking the need to address supply shortfalls and manage transmission system reliability when the system is stressed.
But no precedent supports PJM’s theory of FERC’s jurisdiction. And even if the justifications offered by a filing utility were the sole benchmark for evaluating whether a proposal was consistent with the jurisdictional boundaries established by the FPA, IRAS would not survive scrutiny.
2. PJM Misinterprets Applicable Precedent Defining The Respective
Responsibilities Of FERC And The States
PJM’s arguments that the Commission need only consider PJM’s justification for IRAS are based on an unduly narrow and selective reading of applicable court and Commission precedent. While PJM relies heavily on FERC v. EPSA, nothing in that case stands for the proposition that FERC may regulate any matter that has an impact on the reliability of wholesale markets. To the contrary, the Court recognized that interpreting the FPA as providing FERC authority to regulate any matter that affects wholesale markets would extend FERC’s power beyond the scope of authority envisioned by Congress15 and that the FPA prohibited FERC from approving rules that target matters within the exclusive authority of the states “no matter how
15 EPSA at 277-278.
PDF page 7
- 7 -
direct, or dramatic, its impact on wholesale sales.”16 PJM’s interpretation of the scope of federal authority cannot be squared with the Court’s reasoning.
Nor did the Court confine itself to examining the justifications offered by the agency when evaluating whether FERC’s actions exceeded the bounds established by Congress. Although the Court noted the justifications offered by FERC in support of Order No. 745, the Court assigned equal—if not more—weight to the fact that rules adopted by the Commission addressed only “transactions occurring on the wholesale market.”17 “[W]hatever the effects at the retail level, every aspect of the regulatory plan happens exclusively on the wholesale market and governs exclusively that market’s rules.”18 As DCC explained in its Protest, this simply is not the case with IRAS.19
PJM argues that the Commission’s recent decision to approve Tri-State’s High Impact Large Load Tariff (“HILT”) demonstrates that the FPA does not prevent transmission providers from imposing obligations on utilities serving large loads merely because they “affect the quantity or terms of retail rate regulation.”20 But PJM’s reliance on Tri-State overlooks the Commission’s reason for approving the revised HILT proposal: it exclusively governed wholesale service to utility members without seeking to dictate the rates, terms, and conditions of retail service.21 The Commission was able to reach this conclusion with respect to Tri-State’s HILT proposal because its terms and conditions were entirely limited to wholesale sales (e.g., evaluation fees, resource
16 Id. at 277-278 (“[I]f indirect or tangential impacts on wholesale electricity rates sufficed, FERC could regulate now in one industry, now in another, changing a vast array of rules and practices to implement its vision of reasonableness and justice. We cannot imagine that was what Congress had in mind.”).17 Id. at 281.18 Id.19 DCC Protest at 8-15.20 PJM Answer at 25-26 (quoting Tri-State Generation & Transmission Ass’n, Inc., 196 FERC ¶ 61,127 (2026) (“Tri-State”)).21 Id. at PP 66-68.
PDF page 8
- 8 -
studies, deposit requirements, and associated agreements)22 and transmission service (e.g., transmission cost allocation rules, reliability and transmission planning criteria) to Tri-State’s members.23 The Commission explained that Tri-State’s proposal thus did “not dictate the terms or conditions of retail service” but merely established pro forma terms for taking transmission service and provisions related to wholesale sales to its full requirements customers.24 Nothing about this arrangement, the Commission found, imposed requirements as to the retail arrangements Tri-State’s members could enter into with their customers.25
Unlike HILT, IRAS is not limited to the terms and conditions of wholesale sales or transmission planning. To the contrary, IRAS seeks to prescribe resource procurement and curtailment requirements for retail customers within the PJM region. PJM’s proposed tariff revisions direct Electric Distributors to curtail “Eligible New Large Loads,” establish a default rate for compensating customers for these curtailments to be recovered “in its retail rates,”26 and direct Electric Distributors to recover the costs of these payments from other retail customers. PJM also argues that the U.S. Court of Appeals for the Third Circuit’s decision in New Jersey Board of Public Utilities v. FERC affirming the Commission’s elimination of the state- mandated exemption from the minimum offer price rule demonstrates that FERC has authority to take steps to prevent the “state’s choices from adversely affecting wholesale capacity rates.”27 But the rule at issue in NJ BPU is easily distinguishable from IRAS. NJ BPU concerned the rules governing the submission of offers into the PJM capacity market. As in EPSA, the actions under
22 Id. at PP 12, 14.23 Id. at PP 13, 16.24 Id. at P 67.25 Id. at P 66. 26 Filing, Proposed Tariff, Att. DD-4 § X(a).27 PJM Answer at 27 (quoting N.J. Bd. of Pub. Util. v. FERC, 744 F.3d 74, 98 (3d Cir. 2014) (“NJ BPU”)).
PDF page 9
- 9 -
review in NJ BPU exclusively governed the rules for participating in the wholesale markets. IRAS, in contrast, invades state authority over retail rates by seeking to exercise control over the curtailment of retail customers and even the credits and charges passed through retail customers’ bills. Nothing in NJ BPU supports accepting IRAS.
IRAS bears a striking resemblance to the “far-fetched example” the Court in EPSA offered to illustrate the type of action that would unlawfully intrude on state authority—namely, a federally imposed requirement “compelling every consumer to buy a certain amount of electricity on the retail market.”28 IRAS effectively mandates that New Large Load customers procure sufficient capacity to cover their demand consistent with PJM’s bring your own new capacity (“BYONC”) requirements; if a customer does not, then PJM will issue instructions to Electric Distributors to curtail service to customers to enforce PJM’s procurement mandate. Although the growth of large loads has led PJM to propose frameworks that previously seemed far-fetched, the governing jurisdictional principles remain the same: PJM and FERC cannot seek to regulate the rates, terms, and conditions of retail service. And like the example provided by the Court in EPSA, IRAS exceeds the authority granted to FERC under the FPA.
3. PJM’s Statements And Tariff Language Support Rejection Of IRAS
As An Unlawful Intrusion On State Authority
While PJM encourages the Commission to focus on the justifications offered by PJM, PJM’s statements confirm that IRAS explicitly targets the rates, terms, and conditions of retail service. Among other things, PJM’s statements make clear that IRAS establishes a policy that retail customers must bring their own capacity or face service interruptions,29 seeks to identify and
28 EPSA at 280.29 PJM Answer at 17 (“PJM intends to establish the policy that New Large Loads must bring new capacity or PJM may request that they reduce their energy consumption to alleviate emergency conditions.”). See also id. at 3 (stating that absent compliance with PJM’s BYONC requirements, “New Large Loads must be flexible and, pursuant to PJM’s operational needs, reduce their energy demands when called upon during system emergencies”).
PDF page 10
- 10 -
target retail customers that do not meet BYONC requirements for curtailment,30 establishes a “default” rate and framework for Electric Distributors to pay retail customers that are curtailed under IRAS,31 and directs Electric Distributors to recover these costs from other retail customers through their retail rates.32 PJM also explains that IRAS is intended to ensure that states “re- evaluate” their retail curtailment practices and “enlists” states to implement PJM’s proposed framework.33
The target of IRAS is readily apparent from PJM’s proposed tariff language as well.
Although PJM claims that IRAS does not dictate which customers will be curtailed, its tariff language says otherwise. For instance, proposed Attachment DD-4 states that Electric Distributors “shall execute . . . PJM’s directives to implement Interim Resource Adequacy Service Actions among Eligible New Large Loads in the Electric Distributor’s zone/area.”34 This language does not provide Electric Distributors discretion regarding whether to curtail Eligible New Large Loads within their zone. To the contrary, an Electric Distributor that curtailed retail customers other than Eligible New Large Loads would be in direct violation of its obligations under the tariff. Likewise, PJM’s tariff language obligates Electric Distributors to implement a
compensation program that would provide Eligible New Large Loads with credits in their retail
30 Filing, Transmittal Letter at 28 (stating that the Large Load Registry will be used to track Large Loads within the PJM region to monitor whether they are complying with requirements to bring new capacity or should be subject to IRAS).31 Id. at 27 (explaining that Electric Distributors must “implement compensation program[s] consistent with” PJM tariff); id. at 102 (“PJM is proposing a rate for IRAS that is equal to 50% of the Non-Performance Charge Rate”); id. (“[A] rate of zero dollars for IRAS would apply where Eligible New Large Loads waive in their retail rates receipt of compensation for the provision of wholesale Interim Resource Adequacy Service”); id. at 104 (“[T]he IRAS rate is intended to be conjoined with retail rates and ultimately paid to Eligible New Large Loads that reflects a discount on capacity costs commensurate with the impact of Interim Resource Adequacy Service on addressing resource adequacy issues.”).32 Id. at 104 (explaining that payments to retail customers curtailed under IRAS will be recovered from retail loads consistent with Electric Distributors’ state-approved programs).33 Id. at 3, 107. See also PJM Answer at 3 (stating that IRAS establishes a “region-wide response” to “guide and provide a framework for the PJM states’ various disparate approaches”).34 Filing, Proposed Tariff, Att. DD-4 § III(a).
PDF page 11
- 11 -
rates equal to 50% of the Non-Performance Charge Rate.35 Notably, while PJM characterizes its default rate as a cap that can be modified by state regulators, the only exception from this requirement recognized in the tariff is if the Eligible New Large Load agrees to “accept in its retail rates” a sum lower than the default rate or “waive[s] receipt in its retail rates” of the default rate.36 And if state regulators do not take action to permit implementation of these requirements, PJM states that Eligible New Large Loads may initiate state regulatory proceedings to enforce their rights to receive compensation.37
PJM’s arguments that states will retain full discretion regarding how IRAS is implemented cannot save IRAS. IRAS exhibits none of the “solicitude towards the States” that the Court relied upon in upholding the program at issue in EPSA.38 As discussed above, the level of discretion that PJM claims IRAS affords to the states is simply not reflected in the tariff. Nor do states have the ability to “opt in” or “opt out” of IRAS. If IRAS is approved, PJM will instruct Electric Distributors to curtail New Large Loads that have not complied with BYONC requirements regardless of the preferences of state authorities. And state authorities will have little choice but to modify their policies to align with IRAS to avoid the risk that the brunt of PJM’s curtailments will be borne by retail customers generally rather than the Eligible New Large Loads targeted by PJM.
Ultimately, PJM’s arguments about the discretion of state regulators miss the point. If the decisions at issue—how retail customers are served, which retail customers are subject to curtailment, under what terms, and at what rates—are properly within the states’ exclusive
35 Id., Att. DD-4 § X(a).36 Id., Att. DD-4 § X(c)(ii).37 Id., Transmittal Letter at 106-107 (“[I]f states decline to act, Eligible New Large Loads could initiate regulatory proceedings to develop retail pathways to recover wholesale IRAS rates.”).38 EPSA at 287.
PDF page 12
- 12 -
authority, then it is not PJM’s place to design the program that frames and compels those decisions in the first instance. Delegating implementation to the states does not change the fact that PJM is seeking to establish procurement requirements for large load customers, define the conditions under which curtailment is triggered, and prescribe a default compensation rate that is intended to be embedded in retail rate structures. These are retail policy and ratemaking choices and no amount of state-level implementation discretion transforms them into wholesale ones.39
B. PJM Has Not Demonstrated That Curtailing Eligible New Large Loads Before
Requiring Demand Resources To Perform Is Just, Reasonable, And
Consistent With Cost Causation Requirements
Under IRAS, Eligible New Large Loads will be required to bear the costs of Demand Resources cleared through PJM’s forward capacity market, but will not enjoy the benefits of this capacity. While Demand Resources are committed through the capacity market to “avoid periods of involuntar[y] firm load shed or blackouts,”40 PJM now proposes to curtail service to Network Integration Transmission Service (“NITS”) customers serving Eligible New Large Loads prior to asking Demand Resources to fulfill their capacity commitments. Yet, PJM continues to maintain that it is just and reasonable to force Eligible New Large Loads to bear the costs of these capacity commitments.
PJM does not deny that IRAS will result in Eligible New Large Loads paying for Demand Resources that will not be used to provide them with service. Instead, PJM claims that this treatment is justified because Eligible New Large Loads “failed to cover their capacity
39 Notably, if the proposed payments under IRAS are wholesale rates, then states have no authority to assert jurisdiction over them. Hughes v. Talen Energy Marketing, LLC, 578 U.S. 150, 163 (2016) (“FPA leaves no room either for direct state regulation of the prices of interstate wholesales or for regulation that would indirectly achieve the same result.”) (internal quotation and citations omitted). 40 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability at 14 (May 6, 2026), https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market- design.pdf.
PDF page 13
- 13 -
obligations.”41 But that is a non-answer to the concerns expressed by DCC and other commenters that PJM’s proposal will force customers “to pay for capacity without receiving commensurate reliability benefits.”42 Even if a New Large Load has not procured capacity that complies with PJM’s BYONC requirements, that does not change the fact that these loads will pay the cost of capacity procured through the PJM markets. And PJM has not demonstrated that it is just and reasonable to require Eligible New Large Loads to bear the cost of Demand Resources when these customers will be curtailed prior to when the Demand Resources they pay for have been deployed. PJM also claims that calling on Demand Resources prior to curtailing Eligible New Large Loads would be inappropriate because it would reduce the incentive for such loads to meet BYONC requirements.43 But the fact that a proposed rate may incentivize a particular customer class to take certain actions does not inherently render the rate as a whole just and reasonable. Indeed, by PJM’s logic, it would also be appropriate to curtail Eligible New Large Loads before PJM takes any other action to maintain reliability or to prevent Eligible New Large Loads from receiving service entirely since taking these actions would incentivize Eligible New Large Loads to meet BYONC requirements.
PJM further argues that its proposal to curtail Eligible New Large Loads before deploying Demand Resources is justified since it is consistent with its current approach to curtailing non- firm transmission service after economic generation and before Pre-Emergency Load Management because both non-firm transmission customers and Eligible New Large Loads have transacted in the PJM energy markets without having secured any capacity.44 But PJM’s comparison of Eligible
41 PJM Answer at 33-34.42 DCC Protest at 17.43 PJM Answer at 34.44 Id.
PDF page 14
- 14 -
New Large Loads to non-firm transmission customers overlooks that Eligible New Large Loads in fact pay for capacity while non-firm transmission customers do not. As PJM’s Answer concedes, “[t]hose entities that fail to arrange for BYONC will still be paying for capacity…”45 PJM’s entire basis for comparing the curtailment of non-firm transmission customers to Eligible New Large Loads is thus unfounded.
PJM attempts to justify its approach by noting that customers that are curtailed under IRAS will be eligible to receive compensation equal to 50% of the Non-Performance Charge Rate. PJM overlooks, however, that Eligible New Large Loads will be eligible for compensation only during the limited intervals each year when they are subject to curtailment under IRAS while they will be required to pay capacity charges reflecting the cost of Demand Resources every day during the Delivery Year even though these resources are not available to meet their load.46 PJM has not provided any evidence demonstrating that providing a limited reimbursement in a subset of hours will offset the costs borne by Eligible New Large Loads for capacity that they do not benefit from or otherwise result in these customers bearing costs that are roughly commensurate with the benefits they receive. PJM’s claim that the availability of compensation addresses any concerns rings particularly hollow given PJM’s repeated statements that this compensation may be reduced to zero.47
PJM also attempts to justify its proposal by introducing the concept of “Demand Resource fatigue.”48 PJM explains that the more often that Demand Resources are called upon, the more
45 Id. at 53.
46 Id. at 55-56.47 Id. at 55 (acknowledging that “the IRAS compensation rate may be reduced, even to 0%, by the states and/or appropriate RERRAs at the retail level.”).48 Id. at 36-37.
PDF page 15
- 15 -
likely it is that Demand Resources will become unwilling to provide Demand Response.49 As a result, PJM indicates that although “Demand Resources are paid the same daily rate as other Capacity Resources,” it cannot call upon Demand Resources to perform in the same way it does other Capacity Resources.50 PJM thus contends that it is appropriate not to call upon Demand Resources until after it has curtailed retail loads.
PJM’s concession that it is paying Demand Resources as Capacity Resources yet cannot expect such resources to perform as Capacity Resources and thus will instead curtail retail loads is alarming. “All supply-side capacity resources, including Demand Resources, are required to meet the Capacity Performance requirements.”51 Demand Resources have been paid over $1.5 billion over the past two Base Residual Auctions alone on the basis that they can meet these requirements and maintain the reliability of the PJM system for the benefit of load.52 If PJM believes that it cannot rely on Demand Resources to consistently perform when called upon for the benefit of load that pays for their performance, it should take actions to reform its tariff to reflect that it cannot rely on these resources in the same way it does other Capacity Resources. But PJM should not be permitted to excuse Demand Resources from providing the capacity that customers have paid them for and instead curtail retail customers.5349 Id. at 36.50 Id.51 PJM Interconnection, L.L.C., 169 FERC ¶ 61,252, at P 2 (2019).52 See PJM 2028/2029 Base Residual Auction Report at 2-3, 5, 12 (July 14, 2026), available at: https://www.pjm.com/markets-and-operations/rpm.aspx (showing 7,641 MW of Demand Response clearing at $333.44/MW-day for 2027/2028 Delivery Year and 7,364 MW of Demand Response clearing at $325.00/MW-day for 2028/2029 Delivery Year).53 PJM’s purported concern about Demand Resource fatigue stands in stark contrast to recent efforts by PJM to expand the availability requirements imposed on Demand Resources to ensure that they are available when needed to maintain system reliability. PJM Interconnection, L.L.C., 191 FERC ¶ 61,103 (2025) (expanding availability windows for Demand Resources).
PDF page 16
- 16 -
Finally, PJM attempts to bolster its decision to curtail retail customers before calling upon Demand Resources by highlighting statements from states that purportedly attest to “the benefits and purpose of calling for IRAS prior to Pre-Emergency Load Management.”54 The statements that PJM cites, however, are limited to restatements of PJM’s assertions or claims that deploying Demand Resources prior to curtailing Eligible New Large Loads would shift costs to other customers and result in the curtailment of non-IRAS eligible load.55 But deploying Demand Resources that have voluntarily assumed a capacity obligation and agreed to curtail in exchange for capacity revenues is not shifting reliability burdens or costs onto other customers. It is merely requiring that Capacity Resources paid for their performance in times of system stress in fact perform. Requiring Capacity Resources to perform the service for which they are compensated is not an inappropriate cost shift and will not harm other customers.
C. PJM Has Not Demonstrated That Its Proposal Is Not Unduly Discriminatory
Or Preferential
1. PJM Has Not Justified The Disparate Treatment Of NITS Customers
Serving Eligible New Large Loads
PJM does not deny that NITS customers serving Eligible New Large Loads will receive inferior service to other NITS customers. Yet, PJM continues to argue that any difference in treatment is justified because these customers are large,56 drive “novel degrees of load growth,”57 or have not brought their own new capacity.58 But the FPA’s prohibition on undue discrimination is not satisfied solely by the utility identifying some differences between customer classes. As DCC explained in its Protest, PJM has the burden to demonstrate that there are identifiable factual
54 PJM Answer at 31-33.55 Id.56 Id. at 58-59. 57 Id. at 60 (quoting PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Answer of Pennsylvania Governor Josh Shapiro at 18 (Sept. 15, 2026) (“Governor Shapiro Answer”)).58 Id. at 61.
PDF page 17
- 17 -
differences between the customers that justify the specific rates, terms, and conditions imposed by the utility that are “material to the inquiry at hand.”59 While PJM offers generalities about the purported differences between Eligible New Large Loads and other customers, PJM never demonstrates how these differences justify the specific disparities in treatment that PJM has proposed in its Filing.
None of the factual differences identified by PJM justify the discriminatory treatment that would be afforded to NITS customers serving Eligible New Large Loads under IRAS. PJM argues that Eligible New Large Loads are not similarly situated to other customers because of their size.60 But 100 MW of load has the same effect on resource adequacy regardless of whether these MWs come from a single New Large Load or an aggregation of smaller retail customers. Yet, only NITS customers serving New Large Loads will be required to meet PJM’s BYONC requirements to receive the same level of service that PJM will provide to other NITS customers as a matter of course.
PJM asserts that these differences in treatment are appropriate because a NITS customer serving an Eligible New Large Load has not supported its load with new capacity meeting PJM’s BYONC requirements.61 But PJM does not require other NITS customers to demonstrate that they have offset any load growth with new capacity to obtain access to firm service. Indeed, there is no assurance that other NITS customers have fully covered any load growth within their service territories with new capacity. As a result, a NITS customer that has experienced 100 MW of load growth on its system from smaller industrial and commercial customers will not see any reduction in the quality of transmission service provided even if it has not secured new capacity to meet this
59 DCC Protest at 27 (quoting N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018)).60 PJM Answer at 58-59.61 Id. at 61.
PDF page 18
- 18 -
demand. Rather than justifying its proposal, PJM’s reference to the BYONC requirements only highlights the unduly discriminatory treatment that New Large Loads will receive under PJM’s proposal.
PJM attempts to defend its disparate treatment of large loads that come online after the June 1, 2027 cutoff on the grounds that “[n]ew, not existing load, is the reason for the shortfall, which drives the need for IRAS” and that providing comparable treatment “would fail to account for causation.”62 But PJM has not demonstrated that New Large Loads are in fact causing PJM’s capacity shortfall. The demand from New Large Loads contributes to PJM’s capacity shortfall just as much as the demand from existing loads. Moreover, PJM’s attempt to identify New Large Loads as the sole cause of its capacity shortfall overlooks that there are multiple factors that have contributed to PJM’s capacity shortage, including PJM’s broken generator interconnection process and the premature retirement of generation resources.63
Nor can PJM justify its proposal by making general references to the “uniqueness of large loads.”64 While PJM cites the Commission’s approval of Southwest Power Pool, Inc.’s Conditional High Impact Large Load Service (“CHILLS”) in support of its proposal, the Commission’s order in that case did not find that any difference in treatment is justified merely because of the size and characteristics of large loads.65 To the contrary, the Commission examined CHILLS to ensure that it treated large loads comparably to other customers and that any differences were tailored to reflect the nature of the service and characteristics of the customers at
62 Id.63 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability at 18 (May 6, 2026), https://www.pjm.com//media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability- through-marketdesign.pdf (acknowledging that “PJM’s generation interconnection queue could be viewed as a once- binding constraint.”).64 PJM Answer at 49.65 Id. at 59 (citing Sw. Power Pool, Inc., 195 FERC ¶ 61,196, at PP 84-85, 87 (2026)).
PDF page 19
- 19 -
issue.66 PJM’s assumption that the characteristics of large loads inherently justify less favorable treatment is unsupported by case law and inconsistent with the FPA.
PJM also implies that because IRAS is “limited and narrowly tailored” to address instances of capacity shortfall in the PJM region, it is somehow not unduly discriminatory.67 But the FPA does not provide an exception for undue discrimination that is narrowly tailored. Its prohibition on undue discrimination is absolute.68 The fact that PJM’s IRAS proposal is time-limited and intended to address capacity constraints says nothing about whether it is unduly discriminatory or preferential.
2. PJM’s Refusal To Credit New Large Loads For Their Demand
Reduction Is Unduly Discriminatory And Preferential
The IRAS proposal is similarly unduly discriminatory with respect to PJM’s refusal to acknowledge that New Large Loads may offset their demand through mechanisms other than Capacity Resources. Under IRAS, New Large Loads can avoid being subject to IRAS curtailment procedures by meeting BYONC requirements through arranging new Capacity Resources that offset their demand.69 The Capacity Resources that a New Large Load may rely on to offset its demand include Demand Resources since “capacity may also be supplied by demand-side
resources.”70 Yet despite its recognition that reductions in demand can appropriately be considered capacity, PJM has refused to allow a New Large Load to reduce its exposure to IRAS by
66 Sw. Power Pool, Inc., 195 FERC ¶ 61,196, at PP 84-85, 87.67 PJM Answer at 60.68 16 U.S.C. § 824d(b) (stating that “no public utility shall make or grant any undue preference or advantage” or “subject any person to any undue prejudice or disadvantage”) (emphasis added). In contrast to the FPA, Congress provided certain exceptions to FERC’s ability to regulate undue discrimination under the Natural Gas Act (“NGA”). See Dominion Cove Point LNG, LP, 164 FERC ¶ 61,107, at P 22 (2018) (finding that NGA section 4 grants broad authority to regulate undue discrimination by natural gas companies, while section 3(e)(4) applies only to discrimination in terms of service at LNG terminals, emphasizing Congress’s intentional distinction between the two sections).69 Filing, Transmittal Letter at 51.70 Id. at 54.
PDF page 20
- 20 -
participating in peak shaving programs and similar mechanisms.71
PJM has not justified its proposal to withhold crediting demand reductions under the Peak Shaving Adjustment or other load reduction mechanisms. PJM’s Peak Shaving Adjustment is defined as “a load forecast mechanism that allows load reductions by end-use customers” to result in downward zonal load adjustment.72 PJM has proposed to include information pertaining to Peak Shaving Adjustments in its Large Load Registry because such adjustments “inform PJM operators of Large Loads that are managing their resource needs through peak shaving adjustments under a state program.”73 Yet despite PJM’s acknowledgment that Peak Shaving Adjustments can reduce a load’s demand to meet its capacity needs, it is refusing to allow New Large Loads to offset their demand and meet BYONC requirements with Peak Shaving Adjustments or other load reduction mechanisms.74 In short, PJM is subjecting competing demand reduction approaches to disparate treatment “for no good reason.”75
In its Answer, PJM defends its proposal to exclude Peak Shaving Adjustments from reducing New Large Loads’ demand on the grounds that unlike other Capacity Resources, Peak Shaving Adjustments are not a real-time dispatchable product.76 But PJM does not explain why it is relevant that a reduction in a New Large Load’s demand be in the form of dispatchable capacity.77 If a New Large Load will be reducing its demand in a manner recognized by the PJM
71 See e.g., PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Protest, Request for Clarification and Comments of Equinix Inc. at 14-17 (Sept. 3, 2026) (“Equinix Protest”); PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments and Limited Protest of the NRG Companies at 7-10 (Sept. 3, 2026); PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of the Chief Energy Officer for the Governor of Virginia at 2-4 (Sept. 3, 2026).72 PJM Reliability Assurance Agreement, Art. 1 – Definitions (Peak Shaving Adjustment).73 Filing, Transmittal Letter at 41.74 PJM Answer at 48.75 Consol. Edison Co. of N.Y., Inc. v. FERC, 45 F.4th 265, 282 (D.C. Cir. 2022); State Corp. Comm’n of Kan.
v. FERC, 876 F.3d 332, 335 (D.C. Cir. 2017).
76 PJM Answer at 48.77 See Pub. Serv. Co. of Ind. v. FERC, 575 F.2d 1204, 1212 (7th Cir. 1978).
PDF page 21
- 21 -
tariff—as Peak Shaving Adjustments are78—then the amount of capacity needed to serve such load will also be reduced and the purpose behind PJM’s BYONC requirements—i.e., “to offset the capacity need presented by the New Large Load”79—will be fulfilled. The fact that the reduction in a New Large Load’s demand is not dispatchable is irrelevant. This is particularly true given that, as the Corporate Energy Buyers Association observes, demand reduction under a Peak Shaving Adjustment occurs “before any real-time IRAS Action ever occurs.”80
At a time when the PJM region “need[s] every megawatt [it] can get,”81 it should be incentivizing large loads to take any actions they can to reduce their demand. Yet PJM’s limits on the types of demand reductions that can reduce a customer’s exposure to IRAS will undermine the incentive for New Large Loads to invest in these capabilities and result in unduly discriminatory treatment of customers that have taken steps to manage their demand in accordance with state programs or otherwise.
D. PJM Has Not Demonstrated That Excluding Eligible New Large Loads From
The VRR Curve Is Just And Reasonable
PJM has proposed to exclude New Large Loads that do not meet BYONC requirements from the Variable Resource Requirement curve (“VRR Curve”) beginning with the 2029/2030 Delivery Year on the grounds that these loads should not impact the capacity prices paid by other customers.82 But if the VRR Curve does not reflect the total actual demand in the PJM market— as would be the case under PJM’s proposal—it cannot “produce accurate market signals that will
78 PJM Tariff, Att. DD-2.
79 Filing, Transmittal Letter at 51.
80 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Motion for Leave to Answer and Answer of Corporate Energy Buyers Association at 4 (Sept. 28, 2026). 81 Laila Kearney, America’s largest power grid is struggling to meet demand from AI, Reuters (July 9, 2025), available at: https://www.reuters.com/sustainability/boards-policy-regulation/americas-largest-power-grid-is- struggling-meet-demand-ai-2025-07-09/? (quoting PJM spokesman Jeffrey Shields).82 Filing, Transmittal Letter at 23.
PDF page 22
- 22 -
encourage appropriate capacity investment and achieve an adequate level of reliability.”83 The VRR Curve and PJM capacity markets will thus instead send a suppressed price signal that is disconnected from the actual level of demand in the PJM market and insufficient to drive needed investment in new capacity resources. PJM’s Answer fails to address this flaw. PJM instead defends the exclusion of New Large Loads that have not entered into BYONC arrangements from the VRR Curve on the grounds that it expects New Large Loads to bring their own new generation resources to meet demand—which it characterizes as an action that would occur outside the capacity market.84 But PJM’s expectation that New Large Loads will bring their own new generation to market to match their demand does not address the underlying market design flaw in PJM’s proposal. While many New Large Loads, including New Large Loads developed by DCC members, will indeed be bringing a significant amount of new generation capacity to the PJM market, not all new large load growth within the region may be matched by new generation capacity. It is thus important that the VRR Curve reflect the incremental new demand in the PJM region so that—as PJM initially recognized until being overridden by its Board85—PJM’s capacity markets send the price signals that appropriately incentivize investment in new resources. PJM’s proposal to pretend as if the demand from New Large Loads does not exist will result in capacity prices that are disconnected from the realities of the market and fail to provide the incentives needed to help pull PJM out of its current resource adequacy situation. PJM also argues that excluding Eligible New Large Loads from the VRR Curve is warranted because they have elected not to receive capacity service and are comparable to energy-
83 PJM Interconnection, L.L.C., 167 FERC ¶ 61,029, at P 19 (2019).84 PJM Answer at 51. 85 PJM CIFP – RBP / Connect and Manage - Stage 3 (May 27, 2026 – Meeting Materials), Connect and Manage PJM Package at 29 (May 27, 2026), available at: https://www.pjm.com/committees-and-groups/cifp-rbp.
PDF page 23
- 23 -
only resources.86 But the analogy fails. Energy-only resources are excluded from the capacity supply curve because they do not offer capacity into the market. Eligible New Large Loads, by contrast, are NITS customers that pay the same transmission and capacity charges as all other firm customers. They are not opting out of capacity-backed service—they are being involuntarily excluded from the VRR Curve by PJM while remaining obligated to pay for capacity that, under IRAS, will not be deployed to serve them.
E. PJM’s One-Mile Rule Is Not Just and Reasonable
PJM proposes treating “all affiliated facilities within a one-mile radius” as “a single electric site” for determining which loads are “Large Loads” and could be subject to IRAS.87 PJM asserts that this one-mile rule is necessary to deter large loads from circumventing its IRAS rules by siting a number of smaller loads with peak loads under 50 MW in the vicinity of each other.88 DCC agrees with its members and other commenters in this proceeding: PJM has not shown this component of its proposal is just and reasonable.89
First, the one-mile rule would subject facilities that have operated for decades to IRAS and potential curtailment simply because a separately developed facility is sited nearby.90 PJM’s anti-
86 PJM Answer at 53.87 Filing, Proposed Reliability Assurance Agreement, Art. 1 (Definition of “Large Load”).88 Filing, Transmittal Letter at 33.89 See Equinix Protest at 2, 12-14; PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of CyrusOne, L.P. at 4-6 (Sept. 11, 2026) (“CyrusOne Comments”).90 See Equinix Protest at 13 (explaining PJM’s proposal “would retroactively aggregate loads that were separately developed, separately studied, and separately contracted for service”); CyrusOne Comments at 4 (stating PJM’s proposed language “could potentially cause an existing, already-operational facility to become newly subject to IRAS curtailment risk solely because a later, unrelated facility happens to be developed nearby, even though the existing facility’s capacity needs were accounted for and arranged years earlier”).
PDF page 24
- 24 -
gaming rationale does not justify this treatment.91 Legacy loads predate IRAS and have already been planned for through the regional planning process.92
Second, PJM’s use of “affiliated” is unclear. PJM does not define “affiliated,” identify whose affiliation matters, or explain how it will make that determination,93 deferring the “method of calculating the one-mile distance and for examining different configurations” to the Manuals.94 For example, it is unclear whether facilities on a third-party-developed data center campus are “affiliated” merely because they share a developer, even where the end-use customers have no ownership or control relationship and may have separate service arrangements, distinct points of interconnection, independent development histories, or electrical and operational independence.95 It is also unclear whether PJM’s use of “affiliation” would result in large loads being considered at the same site based on shared upstream institutional investors or financing parties. These issues should not be deferred to the PJM Manuals. Whether facilities are “affiliated” determines whether they constitute a Large Load and, in turn, whether they may be required to arrange new capacity or face curtailment under IRAS. This is precisely the type of term that belongs in the tariff as it “affect[s] rates and service significantly,” is “realistically susceptible of
91 See Filing, Transmittal Letter at 34 (“The one-mile radius requirement is intended to avoid a scenario where, for example, a data center owner is not categorized as Large Load simply because the owner has elected to site a number of smaller data centers, each with peak loads below 50 MW, close together.”); id. (“Similarly, the reference to a single ‘electrical’ site is similarly intended to avoid a scenario where data centers and other Large Loads avoid the 50 MW threshold by configuring themselves into smaller loads.”).92 See Equinix Protest at 13.93 See, e.g., PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of Old Dominion Electric Cooperative at 8 (Sept. 3, 2026) (“PJM’s filing does not provide how affiliation will be determined for purposes of the one-mile radius measurement.”); PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Protest of the Independent Market Monitor of PJM at 30 (Sept. 3, 2026) (“PJM does not provide any details regarding the implementation of the one-mile radius rule”).94 Filing, Transmittal Letter at 34.95 See Equinix Protest at 3 (stating facilities should be able to argue they are not “affiliated” based on “factors such as separate service arrangements, points of interconnection, ownership and control, development history, or electrical and operational independence”); id. at 14 (similar); CyrusOne Comments at 4 (stating facilities should not be aggregated when they are not “commercially, contractually, or electrically independent”).
PDF page 25
- 25 -
specification,” and is not “so generally understood in any contractual arrangement as to render recitation superfluous.”96
F. The Commission Cannot Sever Components Of IRAS As PJM And Others
Have Proposed
Several parties—including PJM itself—make recommendations that the Commission sever
or reframe elements of PJM’s proposal in an attempt to improve its legal posture.97 But the Commission’s authority to direct modifications to PJM’s filing under Section 205 of the FPA is limited, even with PJM’s consent. While the Commission may accept a proposed rate with “minor deviations” when the filing utility consents,98 any change that “impose[s] a new rate scheme” or follows “‘a completely different strategy’ than, or is ‘methodologically distinct’ from, the proposed rate” exceeds the Commission’s authority regardless of consent.99 This limitation exists because customers must receive “adequate notice of the proposed changes” and “an adequate opportunity to comment on the proposed changes.”100
Many of the recommendations made by PJM and other parties to sever and reformulate
PJM’s Filing go far beyond the minor modifications permitted under Section 205 of the FPA. For
96 City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985).97 See, e.g., PJM Answer at 6-7 (requesting timely approval of only “discrete elements” of the IRAS proposal); PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of Dominion Energy Services, Inc. at 6 (Sept. 3, 2026) (requesting revisions to the IRAS BYONC provisions because “PJM’s proposed framework, however, moves needlessly from federal wholesale jurisdiction into retail jurisdiction and is likely to cause confusion and potential legal challenges”); Governor Shapiro Answer at 14-15 (“reformulat[ing]” compensation mechanism because “PJM confusingly appears to be speaking about compensation that would be provided to individual retail customers”); PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of the Pennsylvania Public Utility Commission at 5-7 (Sept. 3, 2026) (“Pennsylvania PUC Comments”) (proposing changes to address the fact that “[a]s written, the language of PJM’s tariff does not contemplate application of state regulatory authority to either prohibit or determine NLL curtailment compensation as necessary to regulate recovery through retail rates”). See also PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Supportive Comments and Limited Protest of the New Jersey Board of Public Utilities at 13 (Sept. 3, 2026) (recommending severance of the IRAS compensation mechanism because “PJM’s compensation structure is ambiguous, unclear, and unnecessary”).98 See NRG at 115 (quoting Western Resources Inc. v. FERC, 9 F.3d 1568, 1579 (D.C. Cir. 1993)).99 Id. (quoting Western Resources Inc., 9 F.3d at 1578-79).100 Id. at 116-117. See also City of Winnfield v. FERC, 744 F.2d 871, 876 (D.C. Cir. 1984) (“Section 205 authorizes the Commission to ‘make . . . orders’ only ‘after full hearings,’ and that requirement unquestionably imposes the duty to give adequate notice of the subject to which the orders pertain.”).
PDF page 26
- 26 -
example, PJM suggests that the Commission approve only its proposed Large Load Registry, the definition of “Large Load,” and proposed RAA Section 7.8.101 But PJM materially mischaracterizes what Section 7.8 requires. PJM repeatedly describes Section 7.8 as requiring LSEs to “bring new capacity in an amount that equals or exceeds its New Large Loads’ peak load.”102 But the proposed tariff language does not say that. It provides that an LSE serving a New Large Load must bring new capacity “or such New Large Load may be subject to load reduction requests during Emergencies prior to Pre-Emergency Load Management Response.”103 Section 7.8 thus gives LSEs and the New Large Loads they serve a choice to either (1) bring new capacity, or (2) accept the possibility of curtailment under IRAS. It does not prohibit New Large Loads from interconnecting in the PJM region unless they bring new capacity. Converting that choice into a mandatory new-capacity requirement would impose a fundamentally different tariff design than PJM filed and is not permitted under Section 205 of the FPA.
Governor Shapiro’s and the Pennsylvania Public Utility Commission’s recommendations suffer the same defect. Governor Shapiro proposes that the Commission modify proposed Attachment DD-4 terms related to compensating Eligible New Large Loads by removing references to “Eligible New Large Loads” and adding language specifying that state compensation provisions apply.104 The Pennsylvania Public Utility Commission makes a similar
101 PJM Answer at 7.
102 See Id. at 7 and n.20 (“The revisions to the RAA clarify an LSE’s obligation to bring new capacity in an amount that equals or exceeds its New Large Loads’ peak load or be subject to load reduction requests during Emergencies prior to Pre-Emergency Load Management Response”) (citing Proposed Reliability Assurance Agreement § 7.8); id. at 16 (“Based on the filings in this proceeding, there is widespread support for the notion that all LSEs in PJM serving New Large Loads via Network Integration Transmission Service … must bring new capacity to satisfy the resource adequacy needs of such New Large Load.”); id. at 62 (“The resource adequacy needs of New Large Loads will be met through new capacity. PJM proposed new RAA, section 7.8 to memorialize this policy as an obligation on all LSEs, including the LSEs within FRR Entities’ service territories.”).103 Filing, Proposed Reliability Assurance Agreement § 7.8.104 Governor Shapiro Answer at 15.
PDF page 27
- 27 -
recommendation.105 But under PJM’s Filing, the New Large Load itself elects whether to waive or accept reduced compensation.106 Making the changes recommended by Governor Shapiro and the Pennsylvania Public Utility Commission would result in an entirely different rate scheme than the one proposed by PJM and would exceed the Commission’s authority under Section 205 of the FPA.
II. CONCLUSION
For the reasons set forth above, DCC respectfully requests that the Commission issue an order consistent with its filings in this proceeding.
Respectfully submitted,
/s/ Stephen J. Hug
Morgan A. Sipple
Director, Energy Policy – FERC and RTOs
DATA CENTER COALITION
1250 H Street, N.W.
Washington, D.C. 20005
morgan@datacentercoalition.org
Data Center Coalition
Stephen J. Hug
Ben N. Reiter
AKIN GUMP STRAUSS HAUER & FELD LLP
2001 K Street, N.W.
Washington, D.C. 20006
Tel: (202) 887-4000
shug@akingump.com
breiter@akingump.com
Dated: October 1, 2026
Counsel for the Data Center Coalition
105 Pennsylvania PUC Comments at 6-7.106 Filing, Proposed Tariff, Att. DD-4 § X(a).
PDF page 28
CERTIFICATE OF SERVICE
I hereby certify that I have this day served a copy of the foregoing document on the persons designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C., this 1st day of October, 2026.
/s/ Stephen J. Hug
Stephen J. Hug