ER26-3515-000 · 2026-10-01 · Data Center Coalition

Motion for Leave to Answer and Answer of Data Center Coalition to the answer of PJM Interconnection, L.L.C. and certain other comments and answers re the…

Text extracted from the eLibrary original (SHA-256 0d85887afe814cd6…). Download the original from the official source.

Contents · 8 sections
  1. I. ANSWER p. 1
  2. A. PJM’s Justifications Cannot Cure The Jurisdictional Defects With IRAS p. 5
  3. B. PJM Has Not Demonstrated That Curtailing Eligible New Large Loads Before p. 12
  4. C. PJM Has Not Demonstrated That Its Proposal Is Not Unduly Discriminatory p. 16
  5. D. PJM Has Not Demonstrated That Excluding Eligible New Large Loads From p. 21
  6. E. PJM’s One-Mile Rule Is Not Just and Reasonable p. 23
  7. F. The Commission Cannot Sever Components Of IRAS As PJM And Others p. 25
  8. II. CONCLUSION p. 27

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Retail and wholesale authority · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

ER26-3515-000 ) MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE DATA CENTER COALITION Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”),1 the Data Center Coalition (“DCC”)2 hereby moves for leave to answer3 and…
Read this passage Filed comments: Registry access

I. ANSWER

printed heading · Topic match: Reliability and curtailment

But PJM’s proposal to impose a region-wide retail curtailment framework represents an unprecedented intrusion into the authority reserved to the states under the Federal Power Act (“FPA”) that must be rejected.
Read this passage Filed comments: Reliability and curtailment

A. PJM’s Justifications Cannot Cure The Jurisdictional Defects With IRAS

printed heading · Topic match: Reliability and curtailment

Likewise, PJM’s tariff language obligates Electric Distributors to implement a compensation program that would provide Eligible New Large Loads with credits in their retail 30 Filing, Transmittal Letter at 28 (stating that the Large Load Registry will be used to track Large Loads within the PJM…
Read this passage Filed comments: Reliability and curtailment

B. PJM Has Not Demonstrated That Curtailing Eligible New Large Loads Before

printed heading · Topic match: Reliability and curtailment

While Demand Resources are committed through the capacity market to “avoid periods of involuntar[y] firm load shed or blackouts,”40 PJM now proposes to curtail service to Network Integration Transmission Service (“NITS”) customers serving Eligible New Large Loads prior to asking Demand Resources to…
Read this passage Filed comments: Reliability and curtailment

C. PJM Has Not Demonstrated That Its Proposal Is Not Unduly Discriminatory

printed heading · Topic match: Reliability and curtailment

Power Pool, Inc., 195 FERC ¶ 61,196, at PP 84-85, 87. 67 PJM Answer at 60. 68 16 U.S.C. § 824d(b) (stating that “no public utility shall make or grant any undue preference or advantage” or “subject any person to any undue prejudice or disadvantage”) (emphasis added).
Read this passage Filed comments: Reliability and curtailment

D. PJM Has Not Demonstrated That Excluding Eligible New Large Loads From

printed heading · Topic match: Reliability and curtailment

PJM’s proposal to pretend as if the demand from New Large Loads does not exist will result in capacity prices that are disconnected from the realities of the market and fail to provide the incentives needed to help pull PJM out of its current resource adequacy situation.
Read this passage Filed comments: Reliability and curtailment

E. PJM’s One-Mile Rule Is Not Just and Reasonable

printed heading · Topic match: Reliability and curtailment

PJM’s One-Mile Rule Is Not Just and Reasonable PJM proposes treating “all affiliated facilities within a one-mile radius” as “a single electric site” for determining which loads are “Large Loads” and could be subject to IRAS.87 PJM asserts that this one-mile rule is necessary to deter large loads…
Read this passage Filed comments: Reliability and curtailment

F. The Commission Cannot Sever Components Of IRAS As PJM And Others

printed heading · Topic match: Reliability and curtailment

It provides that an LSE serving a New Large Load must bring new capacity “or such New Large Load may be subject to load reduction requests during Emergencies prior to Pre-Emergency Load Management Response.”103 Section 7.8 thus gives LSEs and the New Large Loads they serve a choice to either (1)…
Read this passage Filed comments: Reliability and curtailment

II. CONCLUSION

printed heading

CONCLUSION For the reasons set forth above, DCC respectfully requests that the Commission issue an order consistent with its filings in this proceeding.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 1st day of October, 2026. /s/ Stephen J.