ER26-3515-000 · 2026-10-02 · FirstEnergy Service Company
Motion for Leave to Answer and Limited Answer of FirstEnergy Service Company to PJM Interconnection, L.L.C.’s 09/23/2026 Answer re Interim Resource Adequacy…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
MOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER OF FIRSTENERGY
SERVICE COMPANY
Pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, FirstEnergy Service Company, on behalf of its affiliates (“FirstEnergy”), respectfully moves for leave to answer and submits this limited answer to PJM Interconnection, L.L.C.’s September 23, 2026 Answer (“PJM Answer”) to various comments and protests addressing PJM’s Interim Resource Adequacy Service filing (“IRAS Filing”). Although Rule 213(a)(2) generally prohibits answers to protests and answers to answers, the Commission accepts otherwise-prohibited answers that clarify the record or assist its decision-making.1 Good cause exists here because PJM leaves material arguments in FirstEnergy’s Limited Protest and Comments (“FirstEnergy Protest and Comments”) unanswered and advances no compelling new law or facts that defeat FirstEnergy’s remaining objections. As the filing entity, PJM bears the burden under section 205 of the Federal Power Act.2 Its assertion that silence should not be treated as acceptance3 does not satisfy that
1 18 C.F.R. §§ 385.212, 385.213 (2025); see Baltimore Gas & Electric Co. v. Columbia Gas Transmission, LLC, 193 FERC ¶ 61,036, at P 34 & n.28 (2025) (accepting answers to answers because they provided information that assisted the Commission’s decision-making).2 16 U.S.C. § 824d(a)-(b); Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022); NorthWestern Corp. v. FERC, 884 F.3d 1176, 1182–83 (D.C. Cir. 2018); Midcontinent Independent System Operator, Inc., 194 FERC ¶ 61,050, at P 23 (2026).3 PJM Answer at 8 n.23 (“While PJM’s answer does not address every argument raised by intervenors, silence on any argument should not be deemed as acceptance of the arguments raised.”).
PDF page 2
2
burden. The Commission, therefore, should grant the relief requested in the FirstEnergy Protest and Comments.
I. LIMITED ANSWER
A. PJM Fails to Respond to Issues Raised by FirstEnergy That Are Material to
the Justness and Reasonableness of PJM’s IRAS Filing.
PJM fails to address a number of issues raised by FirstEnergy in its Protest and Comments. Most notably, PJM does not address FirstEnergy’s argument that its IRAS proposal improperly denies certain new large loads and associated generation access to the Fixed Resource Requirement (“FRR”) Alternative. As FirstEnergy explained, PJM’s proposal would permit new data-center load and associated generation within an existing FRR Service Area to remain outside the Reliability Pricing Model (“RPM”), while requiring Bring Your Own New Capacity (“BYONC”) resources associated with new loads outside an existing FRR Service Area to participate in RPM. FirstEnergy explained that Schedule 8.1, section B of the Reliability Assurance Agreement (“RAA”) permits an eligible Load Serving Entity (“LSE”) to demonstrate that “all or part” of its load falls within the RAA’s FRR Service Area definition and is supported by sufficient Capacity Resources. FirstEnergy, accordingly, argued that the “all or part” language contemplates use of the FRR Alternative for less than all of an eligible LSE’s load and that PJM has not justified denying new load and associated generation outside an existing FRR Service Area a comparable opportunity to use the FRR Alternative.4 PJM addresses other FRR issues but not FirstEnergy’s argument. PJM, therefore, has not rebutted FirstEnergy’s showing or carried its section 205 burden to justify the different treatment of new load and associated generation inside and outside existing FRR Service Areas.
4 FirstEnergy Protest at 6-7 & n.19 (citing PJM Reliability Assurance Agreement, Schedule 8.1, section B).
PDF page 3
3
PJM also does not squarely address several other FirstEnergy objections. PJM explains generally why IRAS distinguishes between new and existing load, but does not explain how its June 1, 2027 in-service date protects existing commercial arrangements or agreements nearing completion when the IRAS Proposal was filed. PJM likewise explains why existing Capacity Resources should not qualify as BYONC, but does not address FirstEnergy’s distinct argument that an Energy Resource, which is not presently a Capacity Resource, should be eligible to qualify as new capacity for purposes of BYONC. Nor does PJM substantively address FirstEnergy’s objection to terminating IRAS after three consecutive years of sufficient capacity, even though subsequent large-load additions could recreate the shortfall. PJM likewise fails to rebut FirstEnergy’s objection that the annual reallocation of IRAS curtailment obligations could unduly favor a new large load by reducing its obligation solely because unrelated generation enters or other load exits the region, even though the load itself has not brought capacity. PJM further offers no response to FirstEnergy’s objection to crediting a load with Reliability Backstop Procurement (“RBP”) capacity when that load was not included in the forecast supporting the procurement.5 Finally, although PJM separately clarifies that the capacity and Registry-reporting obligations fall on LSEs and that Electric Distributors receive load-reduction directives, it does not address FirstEnergy’s broader request that the proposed provisions consistently identify the entity responsible for each IRAS requirement.6 Clear assignment of those responsibilities is essential to effective planning, implementation, compliance, and enforcement.
B. Where PJM Does Respond to FirstEnergy, Its Arguments Are Unconvincing
5 FirstEnergy Protest at 7-9 (transition and existing commercial arrangements), 13-14 (Energy Resources), 14-15 (termination of IRAS), 15-16 (allocation of RBP capacity), 16-17 (reallocation of curtailment obligations).6 FirstEnergy Protest at 12-13; see also PJM Answer at 13, 17-18, 26-30.
PDF page 4
4
First, PJM claims that requiring BYONC resources to participate in RPM for ten years ensures that the capacity is “real and lasting.” 7 That rationale may support requiring an enforceable, durable capacity commitment, but it does not demonstrate that mandatory RPM participation for ten consecutive Delivery Years is reasonably tailored to that objective. PJM does not adequately explain why continued capacity availability could not be secured through the commercial arrangement supporting the resource or another enforceable commitment tied to the associated load. PJM, therefore, has not established that the specific ten-year RPM participation requirement is just and reasonable under section 205.
Second, PJM’s response does not cure the jurisdictional defect identified by FirstEnergy. PJM characterizes the payment as compensation to an LSE for a wholesale load-reduction service and establishes a default rate equal to 50 percent of the Non-Performance Charge Rate. Yet PJM permits state and retail regulatory authorities to reduce that purportedly wholesale rate, including to zero, and to determine which entities receive the compensation and which retail customers fund it.8 That substantial state control over the amount and allocation of the payment reinforces, rather than resolves, FirstEnergy’s objection that the proposed mechanism concerns retail rates and service. Nor does characterizing the LSE as the initial recipient change the fact that the PJM tariff creates a compensation framework based on curtailment that will ultimately be implemented at the retail level. PJM’s reliance on FERC v. Electric Power Supply Association and Tri-State Generation and Transmission Association, Inc. does not defeat that objection.9 As PJM describes 7 PJM Answer at 43 & n.161; see also FirstEnergy Protest at 5-6, 15.
8 PJM Answer at 54-58; see also FirstEnergy Protest at 3-5.9 PJM Answer at 19-30, 54-58 (citing FERC v. Electric Power Supply Ass’n, 577 U.S. 260 (2016), and Tri-State Generation & Transmission Association, Inc., 196 FERC ¶ 61,127 (2026)).
PDF page 5
5
it, Tri-State emphasized that the jurisdictional utility’s members retained discretion whether to flow the relevant terms through to their retail contracts. Here, by contrast, the PJM tariff itself would establish a default compensation mechanism based on load reductions that will ultimately be implemented at the retail level. PJM’s cited authorities therefore do not establish that the challenged compensation mechanism falls within FERC’s jurisdiction.
Third, PJM does not adequately justify applying the proposed Large Load definition to manufacturing and other industrial facilities. Although PJM asserts that FirstEnergy identified no basis for treating those facilities differently from data centers, it does not address FirstEnergy’s explanation that, unlike data centers, short-notice curtailment of manufacturing facilities may disrupt production and supply chains, strand inventory, damage equipment, and require costly cleaning and restart procedures. Those differences bear directly on whether subjecting both categories of load to the same IRAS obligations is just, reasonable, and not unduly discriminatory. PJM, therefore, should be required to address those differences and justify the proposed treatment of manufacturing and other industrial facilities before subjecting them to the same IRAS requirements as data centers.10
Finally, PJM’s assertion that it does not presently perceive a connection between the Large Load Registry and the forthcoming pro forma transmission-service agreement does not demonstrate that finalizing the Registry now will avoid overlapping, inconsistent, or duplicative requirements.11
FirstEnergy does not dispute that large-load growth presents resource-adequacy concerns requiring action. But the need for some action does not establish that each component of PJM’s
10 FirstEnergy Protest at 10–11; PJM Answer at 14–16.11 PJM Answer at 14 n.47; see also FirstEnergy Protest at 11-12.
PDF page 6
6
proposal satisfies section 205. PJM leaves material FirstEnergy arguments unrebutted and, as to the arguments it addresses, advances no compelling new law or facts that defeat FirstEnergy’s specific objections.
II. CONCLUSION
For these reasons, FirstEnergy respectfully requests that the Commission accept this limited Answer, grant the relief requested in the FirstEnergy Protest and Comments, and direct PJM to correct the identified deficiencies through a compliance filing.
Respectfully submitted,
/s/___Evan K. Dean_____________
Morgan Parke
Vice President - Associate General Counsel
Evan K. Dean
Managing Counsel
FirstEnergy Service Company
341 White Pond Drive
Akron, Ohio 44320
(330) 942-2519
edean@firstenergycorp.com
Counsel for FirstEnergy Service Company
PDF page 7
CERTIFICATE OF SERVICE
I hereby certify that I have served the foregoing document upon all parties listed on the official service list for the captioned proceeding in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.
Dated at Washington, D.C., this 2nd day of October, 2026.
/s/ Daniel Klein
Daniel Klein
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, D.C. 20005