ER26-3515-000 · 2026-10-02 · FirstEnergy Service Company

Motion for Leave to Answer and Limited Answer of FirstEnergy Service Company to PJM Interconnection, L.L.C.’s 09/23/2026 Answer re Interim Resource Adequacy…

Text extracted from the eLibrary original (SHA-256 c032561e30f191f8…). Download the original from the official source.

Contents · 4 sections
  1. I. LIMITED ANSWER p. 2
  2. A. PJM Fails to Respond to Issues Raised by FirstEnergy That Are Material to p. 2
  3. B. Where PJM Does Respond to FirstEnergy, Its Arguments Are Unconvincing p. 3
  4. II. CONCLUSION p. 6

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

ER26-3515-000 MOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER OF FIRSTENERGY SERVICE COMPANY Pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, FirstEnergy Service Company, on behalf of its affiliates (“FirstEnergy”), respectfully moves for leave to answer and submits…
Read this passage Filed comments: Reliability and curtailment

I. LIMITED ANSWER

printed heading

I.
Read this passage

A. PJM Fails to Respond to Issues Raised by FirstEnergy That Are Material to

printed heading · Topic match: Registry access

PJM likewise fails to rebut FirstEnergy’s objection that the annual reallocation of IRAS curtailment obligations could unduly favor a new large load by reducing its obligation solely because unrelated generation enters or other load exits the region, even though the load itself has not brought…
Read this passage Filed comments: Registry access

B. Where PJM Does Respond to FirstEnergy, Its Arguments Are Unconvincing

printed heading · Topic match: Reliability and curtailment

PJM, therefore, should be required to address those differences and justify the proposed treatment of manufacturing and other industrial facilities before subjecting them to the same IRAS requirements as data centers.10 Finally, PJM’s assertion that it does not presently perceive a connection…
Read this passage Filed comments: Reliability and curtailment

II. CONCLUSION

printed heading

CONCLUSION For these reasons, FirstEnergy respectfully requests that the Commission accept this limited Answer, grant the relief requested in the FirstEnergy Protest and Comments, and direct PJM to correct the identified deficiencies through a compliance filing.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 2nd day of October, 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, D.C. 20005