ER26-3515-000 · 2026-10-06 · PPL Electric Utilities Corporation
Motion for Leave to Answer and Limited Answer of PPL Electric Utilities Corporation to the 09/23/2026 Answer et al. of PJM Interconnection, L.L.C
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)
Docket No. ER26-3515-000
MOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER OF
PPL ELECTRIC UTILITIES CORPORATION
Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure,1 PPL Electric Utilities Corporation (“PPL Electric”) submits this Motion for Leave to Answer and Limited Answer (“Limited Answer”) to the September 23, 2026 Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. (“PJM”) in the above-captioned proceeding.2
PPL Electric reiterates its appreciation for the effort that PJM, its staff, management, and Board have put into the proposed Interim Resource Adequacy Service (“IRAS”) Framework, and submits this Limited Answer solely to highlight an important clarification regarding the IRAS Filing3 that PJM provided on page 29 of its September 23 Answer. Specifically, PJM now clarifies in the record that under its proposal, state regulatory authorities4 have the power to ‘opt-out’ individual Eligible New Large Loads from the requirement to provide IRAS to PJM under the PJM Tariff by granting those Eligible New
1 18 C.F.R. §§ 385.212, 385.213.2 PJM Interconnection, L.L.C., Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26-3515-000 (Sept. 23, 2026) (“September 23 Answer”).3 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service & Large Load Registry, Docket No. ER26-3515-000 (Aug. 13, 2026) (“IRAS Filing”).4 As used in this filing, “state regulatory authorities” includes Relevant Electric Retail Regulatory Authorities (“RERRAs”), which can include local regulatory authorities.
PDF page 2
2
Large Loads the ability to “say no” under state law.5 This fact was not at all clear in PJM’s initial proposal and implementing tariff language, but if true: (i) raises significant policy concerns regarding undue discrimination and cost shifting in the application of IRAS across the PJM Region; and (ii) deepens PPL Electric’s initial concerns regarding the proposal’s legal foundation under the Federal Power Act (“FPA”).
PPL Electric respectfully requests that PJM quickly clarify this point in the record, and that the Commission address it directly in its eventual order, given its importance to the policy and legal underpinnings of this proceeding.
I. MOTION FOR LEAVE TO ANSWER
While an answer to an answer or protest is not a matter of right under the Commission’s regulations,6 the Commission routinely permits such answers when the answer provides useful and relevant information that will assist the Commission in its decision-making process,7 corrects factual inaccuracies and clarifies the issues,8 provides information helpful to the
5 September 23 Answer at 29 (“Third, the IRAS framework does not determine whether any specific retail customers can say no. Just as the identity of the retail customers who are ultimately implicated by PJM’s directives to reduce a MW quantity of load is not decided by PJM, under the IRAS framework, it is also not up to PJM to determine whether, as PPL puts it, retail customers can say no. That—and the regulation of the terms and conditions of retail rates, and the regulation of retail customers—remains within the exclusive jurisdiction of the states.”).6 18 C.F.R. § 385.213(a)(2).7 See, e.g., Pioneer Transmission, LLC v. N. Ind. Pub. Serv. Co. and Midwest Indep. Transmission Sys. Op., Inc., 140 FERC ¶ 61,057, at P 94 (2012); Sw. Power Pool, Inc., 131 FERC ¶ 61,252, at P 19 (2010), reh’g denied, 137 FERC ¶ 61,075 (2011) (accepting answers that “provided information that assisted us in our decision-making process”); Duke Energy Ky., Inc., 122 FERC ¶ 61,182, at P 25 (2008) (accepting answers to a protest that “provided information that assisted us in our decision-making process”); Tallgrass Transmission, LLC, 125 FERC ¶ 61,248, at P 26 (2008), reh’g denied, 150 FERC ¶ 61,224 (2015); PJM Interconnection, L.L.C., 120 FERC ¶ 61,083, at P 23 (2007) (answer to protests permitted when it provides information to assist the Commission in its decision-making process); Entergy Servs. Inc., 126 FERC ¶ 61,227, at P. 76 (2009).8 See, e.g., PJM Interconnection, L.L.C., 84 FERC ¶ 61,224, at 62,078 (1998).
PDF page 3
3
disposition of an issue,9 or permits the issues to be narrowed.10 This Limited Answer will assist the Commission in its decision-making process, clarifies the issues, and provides information helpful to the disposition of an issue. Accordingly, PPL Electric respectfully requests that the Commission grant leave and accept this Limited Answer.
II. LIMITED ANSWER
In its September 3 Protest, PPL Electric explained that because of how the applicable tariff language was written, if accepted without modification the IRAS Filing would mark the first time in history that the Commission would be requiring the mandatory and involuntary designation of end-use retail customers (Eligible New Large Loads) to provide a FERC- jurisdictional wholesale rate service (IRAS), and the compulsory provision of that FERC- jurisdictional wholesale rate service to a Regional Transmission Organization (“RTO”) pursuant to FERC-approved rates, terms, and conditions in a FERC-approved tariff.11 PPL Electric explained at length that, while PJM correctly defers to the applicable Electric Distributor and state regulatory authorities in determining which specific individual Eligible New Large Loads within a given zone should actually provide IRAS when called upon, the fact remains that all Eligible New Large Loads (end-use, retail customers) within a zone are assigned responsibility by PJM to provide this wholesale rate service, pursuant to FERC- jurisdictional rates, terms, and conditions, and must provide this wholesale rate service to PJM when called upon. As PPL Electric put it, “[t]he issue is not about which entity gets to identify the specific individual Eligible New Large Loads that must provide IRAS when PJM calls for
9 See, e.g., CNG Transmission Corp., 89 FERC ¶ 61,100, at 61,287, n.11 (1999).10 See, e.g., New Energy Ventures, Inc. v. S. Cal. Edison Co., 82 FERC ¶ 61,335, at 62,323, n.1 (1998).11 PJM Interconnection, L.L.C., Motion to Intervene, Protest, and Request for Clarification of PPL Electric Utilities Corporation at 2 (Sept. 3, 2026) (“September 3 Protest”).
PDF page 4
4
it,” but rather “[t]he issue is that, when called upon to provide IRAS under that process, the Eligible New Large Load cannot say no[,] [i]t must, pursuant to a FERC-approved Tariff, provide IRAS as a FERC-jurisdictional wholesale rate service to PJM.”12 In its September 23 Answer, PJM made a critical clarification in response to PPL Electric’s jurisdictional concerns on page 29:
PPL argues, to no avail, that “[t]he issue is not about which entity gets to identify the specific individual Eligible New Large Loads that must provide IRAS when PJM calls for it. The issue is that, when called upon to provide IRAS under that process, the Eligible New Large Load cannot say no.” First, the issue of jurisdiction is about which entity gets to identify the retail customers who ultimately respond to PJM’s directives to reduce load. PJM’s answer is straightforward—the states and/or RERRAs, in coordination with Electric Distributors and their LSEs and retail customers served by those LSEs ultimately identify those retail customers. Second, PJM has, in fact, been continuously consulting and communicating with states and other stakeholders on the design of IRAS for over a year. Third, the IRAS framework does not determine whether any specific retail customers can say no. Just as the identity of the retail customers who are ultimately implicated by PJM’s directives to reduce a MW quantity of load is not decided by PJM, under the IRAS framework, it is also not up to PJM to determine whether, as PPL puts it, retail customers can say no. That— and the regulation of the terms and conditions of retail rates, and the regulation of retail customers—remains within the exclusive jurisdiction of the states. As noted previously, PJM’s load reduction directives will be informed by the degree to which load in a certain zone/area’s IRAS responsibility has been reduced through MW of BYONC or Allocated RBP UCAP MW. However, PJM will direct load reduction directives to Electric Distributors, while states/RERRAs may determine which retail customers will implement the load reduction directives.
The concept that state regulatory authorities have the power to ‘opt-out’ individual Eligible New Large Loads from the requirement to provide IRAS to PJM under the PJM Tariff
12 Id. at 10.
PDF page 5
5
by granting those Eligible New Large Loads the ability to “say no” under retail service terms and conditions is not at all clear from PJM’s proposed tariff language, but if true is critically significant.
Unfortunately, if this is indeed the intent of the IRAS Filing, PPL Electric’s policy and jurisdictional concerns have only deepened. First, with respect to PPL Electric’s policy concerns, the implications of PJM’s clarification in its September 23 Answer are striking. If state regulatory authorities can exempt Eligible New Large Loads from IRAS curtailment obligations simply by permitting them to “say no” under state law or regulation, then there is a real risk of disparate treatment and cost shifting in the application of IRAS within the PJM Region. Specifically, if Eligible New Large Loads may ‘opt-out’ through localized arrangements with state regulatory authorities to limit (or even eliminate entirely) their individual IRAS exposure, the benefits of BYONC in reducing an Eligible New Large Loads’ individual IRAS curtailment exposure are, by definition, undermined. More importantly, the ability for state regulatory authorities to use that authority to remove the exposure of an Eligible New Large Load to IRAS curtailment creates the potential for the shifting of cost and reliability burdens onto other parts of the PJM Region that do not grant such protection. This is a recipe for undue discrimination in the implementation of IRAS, and constitutes the exact outcome that PJM is trying to avoid.
Second, with respect to PPL Electric’s jurisdictional concerns, PJM’s clarification in its September 23 Answer creates significant ambiguity regarding the legal foundation for IRAS under the FPA. As PPL Electric noted in its September 3 Protest, IRAS is:
1. a FERC-jurisdictional wholesale rate service;
2. established under the FERC-jurisdictional PJM Tariff;
PDF page 6
6
3. provided by a FERC-defined class of providers (Eligible New Large Loads); and
4. compensated pursuant to FERC-jurisdictional rates specified in the PJM Tariff. If the purpose of PJM’s clarification above is to emphasize that, notwithstanding all of these federal characteristics of IRAS, Eligible New Large Loads are not compelled under federal law to provide this FERC-jurisdictional wholesale service but instead are only compelled to do so if the applicable state regulatory authority forces them to, this simply reorients PPL Electric’s original jurisdictional concern. Specifically, it is unclear under what legal authority state regulatory authorities in the PJM Region would be able to compel end-use retail customers (Eligible New Large Loads) to provide a FERC-jurisdictional wholesale rate service to PJM. State utility law generally focuses on the entities providing a service to end-use retail customers, such as distribution utilities, and even then, the service being regulated is one established under state law itself. To the extent that PJM is imagining that a state would somehow use its regulatory authority to directly force end-use retail customers to provide this FERC-jurisdictional wholesale rate service to PJM, it would be an unprecedented use of state authority and raise bizarre issues of federalism. This is especially true in light of the fact that the Commission’s jurisdiction under FPA section 201 is “plenary” and extends “to all wholesale sales in interstate commerce except those which Congress has made explicitly subject to regulation by the States.”13 The FPA does not grant states the ability to compel the provision of FERC-jurisdictional wholesale rate services. To the contrary, “[t]he FPA leaves no room either for direct state regulation of the prices of interstate wholesales or for regulation that would indirectly achieve the same result.”1413 F.P.C. v. S. Cal Edison Co., 376 U.S. 205, 216 (1964).14 Fed. Energy Regulatory Comm’n v. Elec. Power Supply Ass’n, 577 U.S. 260, 287 (2016) [hereinafter FERC v. EPSA] (citing N. Natural Gas Co. v. State Corp. Comm’n of Kan., 372 U.S. 84, 91 (1963)).
PDF page 7
7
PPL Electric appreciates the fine line that PJM is attempting to walk under FPA section 20115 in this proceeding. But given the importance of establishing a sound legal basis for Commission approval of IRAS, PJM must fully explain and support the actual intent and jurisdictional basis of its proposal. Put simply:
1. What legal authority (federal or state/local) is being invoked to force the involuntary designation of end-use retail customers to provide a FERC-jurisdictional wholesale rate service (IRAS), and to compel those end-use retail customers to provide that service to PJM at rates, terms, and conditions established under the PJM Tariff?
a. If the answer is “federal,” then under what provision of the FPA does the Commission have that power?
b. Alternatively, if the answer is “state,” then again, under what legal basis do state regulatory authorities have this ability, given FERC’s plenary jurisdiction over wholesale rates, services, and markets?
PPL Electric encourages PJM and the Commission to consider the alternatives that PPL Electric provided in its September 3 Protest which, if adopted, would strengthen the jurisdictional foundation upon which IRAS is built. Specifically:
Option 1 -
Have PJM’s Tariff language stop at the issuance of the
Operating Instruction to Electric Distributors to curtail load, and
leave the rates, terms, and conditions of that load curtailment
service to state and local regulatory authorities—many of whom
have already signed the Ratepayer Protection Pledge. This
would avoid a scenario where federally imposed obligations are
colliding with state and local-jurisdictional law and tariffs,
including the statutory “obligation to serve,” and would provide
a much more jurisdictionally sound legal pathway to effectuate
connect and manage under FPA section 201.
Option 2 -
Alternatively, make IRAS a voluntary FERC-jurisdictional
service, whereby Electric Distributors and/or large load
15 16 U.S.C. § 824.
PDF page 8
8
customers themselves can voluntarily choose to participate like any other wholesale market service provider in PJM (including demand response providers). Given the enthusiasm with which many large load developers and Electric Distributors have signed the Ratepayer Protection Pledge,16 there should clearly be a high level of interest in voluntarily participating in such a program. Such a program would also be consistent with EPSA,17 where the Supreme Court affirmed the Commission’s ability to create programs that “lure,” rather than force, end-use retail customers into participating in FERC-jurisdictional wholesale markets.
III. CONCLUSION
In accordance with the foregoing, PPL Electric respectfully requests that the Commission grant leave and accept this Limited Answer into the record of this proceeding.
Respectfully submitted,
Steven Nadel
Senior Counsel
PPL Services Corporation
645 Hamilton Street, Suite 601
Allentown, PA 18101
Tel: 610.774.4102
SMNadel@pplweb.com
/s/ Thomas DeVita
Kimberly B. Frank
Thomas S. DeVita
Stuart B. Robbins
K&L Gates LLP
1601 K Street, N.W.
Washington, DC 20006
Tel: 202.778.9064
kimberly.frank@klgates.com
thomas.devita@klgates.com
stuart.robbins@klgates.com
October 6, 2026
16 See Ratepayer Protection Pledge, The White House (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/.17 FERC v. EPSA, 577 U.S. 260, 286 (2016).
PDF page 9
CERTIFICATE OF SERVICE
I hereby certify that I have this day of October 6, 2026 served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Respectfully submitted,
/s/ Stuart Robbins
Stuart B. Robbins
K&L Gates LLP
1601 K Street, N.W.
Washington, DC 20006
Tel: 202.778.9064
stuart.robbins@klgates.com
October 6, 2026