Motion for Leave to Answer and Limited Answer of PPL Electric Utilities Corporation to the 09/23/2026 Answer et al. of PJM Interconnection, L.L.C
Text extracted from the eLibrary original (SHA-256 5ab03a19a2edd28c…). Download the original from the official source.
Contents · 3 sections
Read topic-matched comments in ER26-3515
Topics in the text: Cost allocation · Reliability and curtailment · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
PPL Electric respectfully requests that PJM quickly clarify this point in the record, and that the Commission address it directly in its eventual order, given its importance to the policy and legal underpinnings of this proceeding.Read this passage Filed comments: Reliability and curtailment
I. MOTION FOR LEAVE TO ANSWER
printed heading
Accordingly, PPL Electric respectfully requests that the Commission grant leave and accept this Limited Answer.Read this passage
II. LIMITED ANSWER
printed heading · Topic match: Reliability and curtailment
As PPL Electric put it, “[t]he issue is not about which entity gets to identify the specific individual Eligible New Large Loads that must provide IRAS when PJM calls for 9 See, e.g., CNG Transmission Corp., 89 FERC ¶ 61,100, at 61,287, n.11 (1999). 10 See, e.g., New Energy Ventures, Inc. v.Read this passage Filed comments: Reliability and curtailment
III. CONCLUSION
printed heading · Topic match: Cost allocation
CONCLUSION In accordance with the foregoing, PPL Electric respectfully requests that the Commission grant leave and accept this Limited Answer into the record of this proceeding.Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading
Washington, DC 20006 Tel: 202.778.9064 stuart.robbins@klgates.com October 6, 2026Read this passage