ER26-3515-000 · 2026-10-07 · East Kentucky Power Cooperative, Inc.

Motion for Leave to File Answer, and Answer, of East Kentucky Power Cooperative, Inc. to the 09/23/2026 Answer of PJM Interconnection, L.L.C

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)
PJM Interconnection, L.L.C.

)

Docket No. ER26-3515-000

)

MOTION FOR LEAVE TO FILE ANSWER,
AND ANSWER, OF
EAST KENTUCKY POWER COOPERATIVE, INC.

Pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure,1 East Kentucky Power Cooperative, Inc. (“EKPC”) moves for leave to file this answer and answers the September 23, 2026 answer submitted by PJM Interconnection, L.L.C. (“PJM”) in the above- captioned proceeding.2 EKPC’s Protest in this proceeding opposed PJM’s proposed revisions to its Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”) to establish an Interim Resource Adequacy Service (“IRAS”). As explained in EKPC’s Protest, certain provisions of PJM’s IRAS Proposal are unjust and unreasonable, unduly discriminatory, and inconsistent with the Commission’s cost-causation principles.3 PJM’s Answer does not cure those defects. It largely responds to arguments EKPC did not make or answers EKPC’s concerns only at a level of generality that avoids the implementation problems identified in EKPC’s Protest and the Affidavit of Marc D. Montalvo (“Montalvo Affidavit”). For the reasons set forth herein and in EKPC’s Protest, the Commission should reject or require revisions to those elements of the IRAS Proposal that would impose IRAS exposure, compensation costs, or curtailment risk on loads and Load Serving Entities (“LSEs”) that did not

1 See 18 C.F.R. §§ 385.212, 385.213 (2026).
2 PJM Interconnection, L.L.C., “Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C.,” Docket No. ER26-3515-000 (filed Sept. 23, 2026) (“PJM Answer”).
3 PJM Interconnection, L.L.C., “Limited Protest of East Kentucky Power Cooperative, Inc.,” Docket No. ER26-3515- 000 (filed Sept. 3, 2026) (“EKPC Protest”).

PDF page 2

2
cause the asserted resource adequacy deficiency or that have already supported their load through a prudent resource portfolio.

I. MOTION FOR LEAVE TO FILE ANSWER
Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure generally prohibits
answers to answers or protests unless otherwise ordered by the decisional authority. Good cause exists to accept this Answer because PJM’s Answer misconstrues EKPC’s portfolio-sufficiency, resource-attribution, and transferability arguments and does not resolve the real-time curtailment and compensation issues identified in EKPC’s Protest and supporting affidavits. This Answer will assist the Commission in its decision-making process4 and clarify the record.5 For these reasons, the Commission should accept this Answer.

II. ANSWER
A. PJM Failed to Address or Misstates Significant Concerns Raised in
EKPC’s Protest.
In its Protest, EKPC explained that a legitimate reliability objective does not justify the Commission’s acceptance of a proposal that has not been shown in its entirety to be just and reasonable, that is potentially unduly discriminatory, and that is inconsistent with the Commission’s cost-causation framework. EKPC’s Protest raised several concerns regarding

aspects of the IRAS Proposal, and PJM’s Answer misconstrues or does not address the central issues raised by EKPC.

4 See, e.g., PJM Interconnection, L.L.C., 189 FERC ¶ 61,110, P 22 (2024) (accepting answers to protests and answers because they assisted the Commission in its decision-making process); PJM Interconnection, L.L.C., 181 FERC ¶ 61,162, P 29 (2022) (same).
5 See, e.g., Potomac-Appalachian Transmission Highline, LLC, 140 FERC ¶ 61,229, P 102 (2012) (accepting answer to an answer because it provided material evidence that corrected the record and informed the Commission’s decision- making process); High Island Offshore Sys., L.L.C., 113 FERC ¶ 61,202, P 8 (2005) (accepting an answer to a protest because it assisted the Commission with a more complete record); N.E. Utils. Servs. Co. v. NRG Energy, Inc., 101 FERC ¶ 61,327, P 17 (2002) (accepting answer to an answer because it helped clarify issues in the proceeding).

PDF page 3

3
The defects warrant different forms of relief. The Commission should reject the compensation provision and any interpretation of an IRAS Action that would permit curtailment of non-IRAS load because those provisions lack an adequate record basis and exceed the stated scope of IRAS. Additionally, the Commission should condition acceptance on tariff revisions establishing a portfolio-sufficiency pathway, interim recognition of operating resources pending their first available RPM commitment, reasonable reassignment of unused Bring Your Own New Capacity (“BYONC”) UCAP MW, and a Fixed Resource Requirement (“FRR”) exemption tied to a sufficient FRR Capacity Plan.

PJM Must Recognize the Value of an LSE’s Existing Portfolio. PJM’s Answer discusses flexibility within the BYONC construct, but it does not answer EKPC’s separate portfolio- sufficiency argument. PJM repeatedly states that the PJM Region needs new capacity, but that regional observation does not establish that every New Large Load served by every RPM- participating LSE lacks capacity support or contributes to the resource adequacy shortfall IRAS is intended to address. EKPC’s point is not that existing capacity should be “repackaged” as BYONC. Rather, a self-supply LSE that demonstrates, using PJM-validated UCAP values and Large Load included in the Registry and verified to be online in the relevant Delivery Year, that its portfolio is sufficient to serve its aggregate obligations, including incremental load growth, should not be treated as though its load is unsupported merely because PJM’s proposed eligibility rules recognize only BYONC (including BYONC tied to specific loads that ultimately may not need all allocated BYONC) or Allocated RBP UCAP MW. Curtailing portfolio-supported load also breaks the causal link on which PJM relies to justify IRAS because PJM has not shown that an LSE making that demonstration causes the deficiency IRAS purports to remedy. The Commission therefore should

PDF page 4

4
require PJM to establish a portfolio-sufficiency pathway with objective eligibility, verification, and anti-double-counting requirements.

RPM Auction Timing Disconnect for BYONC Qualification. PJM does not explain why a resource that is online, not committed outside PJM, capable of providing energy and ancillary services, and expected to be offered into RPM at the first available opportunity should provide no IRAS offset during the period between commercial operation and its first available RPM commitment. EKPC does not object to requiring a resource that offsets IRAS exposure to assume obligations comparable to those of an Reliability Pricing Model (“RPM”)-committed Capacity Resource. But making prior RPM commitment an absolute prerequisite goes further than necessary and can leave load exposed to curtailment after the underlying reliability concern has been addressed by an operating resource. The Liberty RICE and Cooper CCGT examples demonstrate that commercial-operation dates follow permitting, construction, testing, and interconnection schedules—not the June 1 Delivery Year boundary—and that an operating resource may support reliability for months before it clears an RPM auction.6 PJM’s filing therefore treats resources with comparable present reliability capability differently based solely on administrative timing. The Commission should require PJM to recognize an operating resource pending its first available RPM commitment where the resource: (1) has achieved commercial operation; (2) has PJM- confirmed deliverability and a PJM-determined accredited UCAP capability; (3) is not committed outside PJM or counted toward another obligation; (4) is subject to PJM dispatch, outage- reporting, testing, and performance requirements; and (5) is bound to offer into the first RPM Auction for which it is eligible.

6 EKPC Protest at 19. See also Montalvo Affidavit at PP 26-27 and Tucker Affidavit at PP 13-16.

PDF page 5

5
Committing Specific Capacity Resources to Specific Loads. PJM’s response answers a different question than the question raised by EKPC. EKPC did not argue that BYONC must be electrically deliverable to or physically serve a particular New Large Load.7 EKPC’s concern is that IRAS exposure turns on whether PJM recognizes specific UCAP MW as assigned to a specific New Large Load, rather than whether the serving LSE’s aggregate portfolio is sufficient to satisfy its aggregate load and reliability obligations. That remains resource-to-load attribution, even if PJM does not require the identified resource to physically serve the customer.8 Resource adequacy studies, integrated resource plans, reserve-margin analyses, and RPM obligations ordinarily test portfolios against aggregate load; they do not require permanent assignments between individual resources and individual retail customers. PJM has not explained why that portfolio-based paradigm suffices for FRR entities but not for self-supply LSEs participating in RPM. Because the resulting curtailment exposure can attach to load supported by an adequate portfolio, the Commission should reject the resource-specific attribution requirement or require PJM to accept a portfolio-sufficiency demonstration as an alternative.

Transferability. PJM misstates EKPC’s concern regarding the lack of transferability of BYONC by characterizing EKPC’s concern as a request for a liquid secondary market in BYONC.9 EKPC’s concern is narrower. PJM has not justified a rule that permanently strands unused UCAP MW when load does not materialize as initially forecast or when an LSE’s portfolio needs change. PJM permits a New Large Load to oversize BYONC for anticipated future growth,10 but prohibits

7 PJM Answer at 38–39.
8 See Montalvo Affidavit at PP 28–35; Tucker Affidavit at PP 12, 17–18.
9 PJM Answer at 39.
10 Proposed Tariff, Attachment DD-4, section VII(h).

PDF page 6

6
unused UCAP MW from being reassigned if that growth does not occur.11 Given that PJM defines BYONC as UCAP MW and already permits a physical resource to support multiple BYONC arrangements, this absolute restriction on transferability is not necessary to prevent double- counting. Verified reporting through the Large Load Registry can preserve the one-MW/one-offset rule without penalizing prudent forward procurement. The Commission should therefore require PJM to permit reasonable reassignment of unused BYONC UCAP MW subject to validation and anti-double-counting safeguards.

Large Load Definition. PJM’s Answer does not satisfy its burden of proof to justify applying the extraordinary IRAS curtailment and compensation framework to every qualifying form of commercial and industrial load growth.12 A Kentucky manufacturing facility below 50 MW today may become subject to IRAS when incremental growth causes the site to exceed 50 MW, even though the LSE has long served the existing facility and planned for ordinary industrial expansion through its integrated portfolio.13 PJM responds only that its 50 MW threshold follows Commission guidance and that EKPC showed no basis to distinguish computational load from other industrial load.14 PJM itself grounds IRAS principally in the speed, concentration, and scale of data-center growth.15 It has not shown that ordinary manufacturing or industrial expansion presents the same timing, concentration, or operational risks, or that subjecting such growth to the

11 Proposed Tariff, Attachment DD-4, section VII(e).
12 PJM attempts to shift the burden to the entities opposing its proposed Large Load and New Large Load definitions, and this attempt should be rejected. See PJM Answer at 16 (entities protesting the proposed definitions “have shown no basis for deviating from the Commission’s approach of treating data center or computational, manufacturing, industrial, or other types of Large Load the same.”).
13 See EKPC Protest at 25–27; Montalvo Affidavit at P 32.
14 PJM Answer at 14–16.
15 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, “Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability,” at 13-14, 21-24 (filed Aug. 13, 2026).

PDF page 7

7
same curtailment regime is narrowly tailored to the asserted reliability need.16 The Commission should require PJM either to narrow the definitions or to establish objective criteria demonstrating that non-computational load presents the same IRAS-relevant risks.

Non-IRAS Load May be Subject to Curtailment. Although PJM responds to EKPC’s
BYONC and FRR arguments, it neither cites the Montalvo Affidavit nor answers his showing, from an operational perspective, that an IRAS instruction may exceed the IRAS-eligible load then online and available for curtailment. PJM will calculate annual zonal IRAS availability from registered peak-load quantities and then issue an IRAS Action as a NERC Operating Instruction to the Electric Distributor. PJM’s IRAS Proposal does not require PJM to limit a real-time directive to the amount of Eligible New Large Load then online and capable of being curtailed, nor does it specify whether compliance will be measured by curtailment of IRAS-eligible load or by aggregate zonal load reduction. That ambiguity matters because a Reliability Coordinator’s Operating Instruction carries mandatory compliance consequences unless it cannot be physically implemented or would violate safety, equipment, regulatory, or statutory requirements. An Electric Distributor should not be forced to choose between noncompliance and curtailing firm customers outside the IRAS class. The Commission should therefore condition acceptance on inclusion of the tariff language set out below.17

Compensation. PJM’s Answer assumes the conclusion EKPC disputes: that IRAS
curtailment is a compensable wholesale service rather than a condition attached to taking service without recognized capacity support. If IRAS is justified because a New Large Load has not secured qualifying capacity, PJM must explain why interruption of that load constitutes a service

16 See Sw. Power Pool, Inc., 195 FERC ¶ 61,196, PP 84–87 (2026) (accepting differentiated treatment where narrowly tailored to the specific and unique characteristics of high-impact large loads).
17 See NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114–16 (D.C. Cir. 2017).

PDF page 8

8
sold to the system rather than the consequence of conditional access. It does not. EKPC’s analogy to non-firm transmission service remains instructive because interruption is an inherent characteristic of service taken without the facilities or commitments necessary to support firm treatment, not a separately compensable product. PJM’s reliance on compensation and nonperformance rates for committed Demand Resources is inapposite because those resources assume an RPM capacity obligation, whereas an IRAS-exposed load has not. Nor has PJM identified the seller, buyer, measurable performance obligation, settlement quantity, or avoided wholesale cost associated with the asserted service. The proposed default rate may also weaken the incentive to secure qualifying capacity and, by charging other load in the zone, shift costs to customers that did not cause the underlying resource adequacy concern. Nor does PJM’s retail- level waiver option cure the federal default rate or Kentucky’s retained authority over load- management programs.18 PJM therefore has not shown that the proposed payment reflects a distinct wholesale service or that allocating its cost to other zonal load follows cost causation. EKPC requests that the Commission reject Tariff, Attachment DD-4, section X or, at minimum, sever that provision for a separate section 205 filing supported by an evidentiary record. PJM’s September 3 planning-parameter report exposes a separate defect in the proposed compensation formula. Attachment DD-4, section X(a), sets the default IRAS rate at 50 percent of the Non-Performance Charge Rate in Attachment DD, section 10A(e). Section 10A(e), however, calculates that rate using Net CONE for the applicable Locational Deliverability Area (“LDA”) and Delivery Year, while section X does not identify the LDA applicable to an Eligible New Large Load. If PJM intends to use the LDA in which the curtailed load is located, the 2029/2030

18 See EKPC Protest at 31-32 (the Kentucky Public Service Commission retained jurisdiction over demand-side management programs involving retail loads as a condition of integration of the Kentucky utilities that are members of PJM, which means PJM may not offer load interruption programs to retail consumers without the utilities’ consent and Public Service Commission approval).

PDF page 9

9
parameters imply a default rate of approximately $156/MWh in DOM and $3,109/MWh in COMED—a twenty-fold difference. That spread is driven by LDA-specific Net CONE, including forward E&AS offsets, rather than by any stated difference in the IRAS obligation or measured curtailment. If PJM intends another locational mapping, the tariff does not state it. Either way, PJM has not explained how the imported capacity-performance benchmark produces a just and reasonable rate for IRAS.

Implied IRAS Compensation Benchmark by LDA
Assuming Attachment DD-4, section X(a), uses the Net CONE for the LDA in which the curtailed load is located.19

LDA
2027/2028
2028/2029
2029/2030
DOM
$837/MWh
$822/MWh
$156/MWh
BGE
$682/MWh
$1,344/MWh
$764/MWh
SWMAAC
$1,028/MWh
$1,636/MWh
$1,016/MWh
DAYTON
$910/MWh
$1,329/MWh
$1,233/MWh
DEOK
$1,031/MWh
$1,442/MWh
$1,289/MWh
PJM West
—
—
$1,416/MWh
ATSI / Cleveland
$1,073/MWh
$1,486/MWh
$1,421/MWh
PEPCO
$1,373/MWh
$1,928/MWh
$1,529/MWh
RTO
$1,139/MWh
$1,565/MWh
$1,593/MWh
DPL South
$1,233/MWh
$2,027/MWh
$2,141/MWh
MAAC
$1,416/MWh
$2,244/MWh
$2,158/MWh

19 PJM’s 2027/2028 Planning Parameters are available here: https://www.pjm.com/-/media/DotCom/markets- ops/rpm/rpm-auction-info/2027-2028/2027-2028-planning-period-parameters-for-base-residual-auction-pdf.pdf; PJM’s 2028/2029 Planning Parameters are available here: https://www.pjm.com/-/media/DotCom/markets- ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-report.pdf; PJM’s 2029/2030 Planning Parameters are available here: https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2029-2030/2029-2030-planning- period-parameters-for-base-residual-auction-report.pdf.

PDF page 10

10
PL
$1,481/MWh
$2,325/MWh
$2,393/MWh
EMAAC
$1,685/MWh
$2,608/MWh
$2,687/MWh
JCPL
$1,877/MWh
$2,846/MWh
$2,961/MWh
PS / PS North
$1,904/MWh
$2,871/MWh
$2,975/MWh
COMED
$1,781/MWh
$2,772/MWh
$3,109/MWh

Applicability of IRAS to FRR Entities. PJM responds that FRR entities are not similarly situated to RPM LSEs because an FRR entity must provide capacity for all load in its service area and may incur an insufficiency charge.20 Even if FRR and RPM are distinct administrative frameworks, that does not justify an unconditional IRAS exemption where PJM’s premise for the exemption is that the FRR entity has provided adequate capacity support. Proposed Tariff, Attachment DD-4, section V(a), excludes New Large Load in an FRR Service Area without conditioning the exclusion on the sufficiency of the applicable FRR Capacity Plan. PJM’s Answer therefore does not explain why IRAS should never apply when the FRR Entity’s plan is insufficient. The relevant distinction is not FRR versus RPM in the abstract; it is whether the load is supported by sufficient capacity.21 A portfolio-based demonstration cannot be sufficient for FRR load while an equivalently adequate self-supply portfolio receives no recognition under RPM. The Commission should require PJM to condition the FRR exclusion on a sufficient FRR Capacity Plan and to provide a comparable portfolio-sufficiency pathway for self-supply LSEs.

20 PJM Answer at 61–63.
21 See also Montalvo Affidavit at PP 36–41. For the first two Delivery Years in which IRAS is proposed to be in effect, there is no applicable FRR Plan insufficiency charge. See PJM RAA, Schedule 8.1-D FRR Capacity Plans (“Delivery Years between the 2025/2026 Delivery Year through the 2028/2029 Delivery Year, no FRR Commitment Insufficiency Charge shall be assessed.”).

PDF page 11

11
PJM also fails to cure the ambiguity and overbreadth in proposed RAA, Schedule 8.1, section D.1.1, which would prohibit an FRR Entity from including Existing Generation Capacity Resources above the amount owned or contracted before June 1, 2027, to serve New Large Load.22 EKPC supports preventing an FRR Entity from withdrawing existing capacity from RPM to serve new load while the region is short, but the filed language is not limited to Delivery Years in which IRAS applies or a regional shortfall exists. A permanent restriction untethered to the condition that purportedly justifies it can foreclose cost-effective capacity and disadvantage future FRR elections after the asserted emergency has passed.23 The Commission must judge PJM’s filed rate as proposed and may not supply a narrowing construction that the tariff does not contain.24 The Commission should reject the restriction or require PJM to limit it to Delivery Years in which the relevant IRAS shortfall condition exists.

B. Targeted Tariff Revisions.
To provide the Commission with administrable relief that preserves the basic structure of PJM’s filing, EKPC proposes the following limited revisions to address the immediate operational risk without changing IRAS’s basic structure. The Commission should require PJM to address any necessary implementation and compliance procedures in a compliance filing.

Limitation on Interim Resource Adequacy Service Actions. Notwithstanding any other provision of Attachment DD-4, an Interim Resource Adequacy Service Action directed to an Electric Distributor shall not exceed the quantity of Eligible25 New Large Load within the

22 PJM Answer at 61–63.
23 See EKPC Protest at 35–36.
24 See NRG Power Mktg., 862 F.3d at 114–16 (explaining the Commission would violate its FPA section 205 authority if its proposed modifications accepted by the utility “involved the Commission’s own original notion of a new form of rate.”).
25 EKPC’s use of “Eligible” assumes that the Commission has addressed EKPC’s portfolio-sufficiency and interim qualifying-UCAP concerns.

PDF page 12

12
applicable Zone or other area specified in the directive that, at the time the directive is issued: (i) is consuming electric energy; (ii) remains subject to Interim Resource Adequacy Service; and (iii) may be curtailed in a manner consistent with applicable state law and regulatory requirements and without requiring the Electric Distributor to interrupt or reduce service to load that is not receiving Interim Resource Adequacy Service. Only a verified reduction in Eligible New Large Load then subject to Interim Resource Adequacy Service shall count toward compliance. A reduction in load not then subject to Interim Resource Adequacy Service shall not be required or credited for that purpose.

Insufficient Available IRAS Load. If an Electric Distributor determines that the quantity of Eligible New Large Load available for curtailment is less than the quantity stated in an Interim Resource Adequacy Service Action, the Electric Distributor shall promptly notify PJM and implement the directive only to the extent consistent with applicable state law and regulatory requirements. The Electric Distributor shall not be required to interrupt or reduce service to native load or other load that is not receiving Interim Resource Adequacy Service to satisfy the difference. An Electric Distributor’s inability to provide the remaining reduction because Eligible New Large Load is unavailable or because curtailment would conflict with applicable state law or regulatory requirements shall not constitute noncompliance with the IRAS Action or any NERC Operating Instruction through which PJM communicates that Action.

C. PJM Has Not Carried Its Affirmative Burden Under FPA Section 205.
EKPC’s Protest raised serious questions concerning the justness and reasonableness of the IRAS Proposal, and PJM’s Answer does not cure the identified defects. Section 205 places the burden on PJM to establish that the rates, terms, and conditions it filed are just and reasonable and

PDF page 13

13
not unduly discriminatory or preferential.26 Although the Commission may accept one of multiple just and reasonable approaches, it may do so only on the basis of the proposal and evidentiary record before it.27 It may not presume answers PJM did not provide or rely on post hoc reasoning to fill material gaps.28 Nor may PJM’s consent to modification supply a substitute design where the filed proposal lacks support for foundational elements.29 PJM has not supplied a reasoned record basis for the disputed provisions identified above. EKPC requests that the Commission reject those provisions or condition acceptance on the specific, limited relief requested above.

III. CONCLUSION
For the foregoing reasons and those set out in EKPC’s Protest and supporting affidavits, EKPC respectfully requests that the Commission accept this Answer and take such actions as set forth therein and herein. Specifically, the Commission should reject the proposed compensation provision and any interpretation that would permit curtailment of non-IRAS load. If the Commission otherwise accepts IRAS, it should condition acceptance on tariff revisions that recognize an adequate self-supply portfolio; provide interim recognition to operating resources pending their first available RPM commitment; permit reasonable reassignment of unused BYONC UCAP MW subject to verification and anti-double-counting safeguards; limit resource- to-load attribution where an LSE demonstrates aggregate portfolio adequacy; require objective criteria before applying IRAS to non-computational load; condition the FRR exemption on a sufficient FRR Capacity Plan; and limit the FRR resource restriction to the period in which the

26 16 U.S.C. § 824d(a), (b), (e); 18 C.F.R. § 35.13.
27 See Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984); PSEG Energy Res. & Trade LLC v. FERC, 665 F.3d 203, 208 (D.C. Cir. 2011).
28 See Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983); PSEG Energy Res. & Trade LLC v. FERC, 665 F.3d 203, 208 (D.C. Cir. 2011).
29 See NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114–16 (D.C. Cir. 2017).

PDF page 14

14
asserted shortfall exists. Without these revisions, IRAS could impose curtailment and compensation costs on customers and LSEs that did not cause the resource-adequacy shortfall, all contrary to the Commission’s cost-causation principles.

Respectfully submitted,

Denise R. Foster Cronin
Chief Compliance Officer and Senior Vice
President
East Kentucky Power Cooperative, Inc.
4775 Lexington Road, P.O. Box 707
Winchester, KY 40392-0707
Tel.: 859-745-9615
Email: denise.cronin@ekpc.coop

On Behalf of East Kentucky Power
Cooperative, Inc.

/s/ Daniel E. Frank

Daniel E. Frank
Allison E. S. Salvia
Kelly A. Cuthbertson
Adriana J. Santana
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Tel.: 202-383-0100
Email: danielfrank@eversheds-sutherland.com
allisonsalvia@eversheds-sutherland.com
kellycuthbertson@eversheds-sutherland.com
anasantana@eversheds-sutherland.com

Counsel for
East Kentucky Power Cooperative, Inc.

Dated: October 7, 2026

PDF page 15

Certificate of Service
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, DC this 7th day of October, 2026.

/s/ Kelly A. Cuthbertson

Kelly A. Cuthbertson