Motion for Leave to File Answer, and Answer, of East Kentucky Power Cooperative, Inc. to the 09/23/2026 Answer of PJM Interconnection, L.L.C
Text extracted from the eLibrary original (SHA-256 df0c17a00575f7dc…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
Pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure,1 East Kentucky Power Cooperative, Inc. (“EKPC”) moves for leave to file this answer and answers the September 23, 2026 answer submitted by PJM Interconnection, L.L.C. (“PJM”) in the above- captioned proceeding.2…Read this passage Filed comments: Reliability and curtailment
I. MOTION FOR LEAVE TO FILE ANSWER
printed heading · Topic match: Reliability and curtailment
Good cause exists to accept this Answer because PJM’s Answer misconstrues EKPC’s portfolio-sufficiency, resource-attribution, and transferability arguments and does not resolve the real-time curtailment and compensation issues identified in EKPC’s Protest and supporting affidavits.Read this passage Filed comments: Reliability and curtailment
II. ANSWER
printed heading
II.Read this passage
A. PJM Failed to Address or Misstates Significant Concerns Raised in
printed heading · Topic match: Reliability and curtailment
PJM Must Recognize the Value of an LSE’s Existing Portfolio.Read this passage Filed comments: Reliability and curtailment
B. Targeted Tariff Revisions.
printed heading · Topic match: Reliability and curtailment
If an Electric Distributor determines that the quantity of Eligible New Large Load available for curtailment is less than the quantity stated in an Interim Resource Adequacy Service Action, the Electric Distributor shall promptly notify PJM and implement the directive only to the extent consistent…Read this passage Filed comments: Reliability and curtailment
C. PJM Has Not Carried Its Affirmative Burden Under FPA Section 205.
printed heading
EKPC requests that the Commission reject those provisions or condition acceptance on the specific, limited relief requested above.Read this passage
III. CONCLUSION
printed heading · Topic match: Reliability and curtailment
CONCLUSION For the foregoing reasons and those set out in EKPC’s Protest and supporting affidavits, EKPC respectfully requests that the Commission accept this Answer and take such actions as set forth therein and herein.Read this passage Filed comments: Reliability and curtailment
Certificate of Service
printed heading
Dated at Washington, DC this 7th day of October, 2026. /s/ Kelly A.Read this passage