ER26-3515-000 · 2026-10-08 · Individual No Affiliation

Motion for Leave to File Supplemental Comments and Supplemental Comments of Persistence Analytics Group LLC re Validated Project State, Evidentiary…

PDF page 1

Docket No. ER26-3515-000
Page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-3515-000
MOTION FOR LEAVE TO FILE SUPPLEMENTAL COMMENTS AND
SUPPLEMENTAL COMMENTS OF PERSISTENCE ANALYTICS GROUP LLC
REGARDING VALIDATED PROJECT STATE, EVIDENTIARY CURRENCY, AND
REVALIDATION
I. MOTION FOR LEAVE TO FILE SUPPLEMENTAL COMMENTS
Persistence Analytics Group LLC ("PAG") respectfully submits these supplemental comments concerning PJM Interconnection, L.L.C.'s proposed Interim Resource Adequacy Service ("IRAS") and Large Load Registry. PAG submitted initial comments in this docket on August 13, 2026. Those comments recommended, among other things, that material large-load information carry sufficient context to distinguish projected or requested load from more mature states, that execution-critical assumptions have identifiable revalidation triggers, and that material registry inputs preserve useful provenance and validation timing. Since PAG's initial filing, PJM has published implementation materials that provide materially greater detail about the Phase 1 Large Load Registry and the Bring Your Own New Capacity ("BYONC") validation process. Those materials include PJM's Large Load Registry Field Definitions and Examples, a BYONC Officer Certification Template, and an October 7, 2026 presentation describing the reporting and validation process for the 2029/30 Base Residual Auction.

These materials could not have been addressed in PAG's August 13 comments and directly illuminate how several of the evidentiary issues raised there will be implemented. The supplemental comments are narrow, acknowledge the meaningful validation PJM has now established, and do not seek to delay the Phase 1 process or the upcoming auction. To the extent leave is required, PAG respectfully requests leave under Rule 212 of the Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.212, because consideration of this limited update will assist the Commission without prejudice to any participant.

II. PJM'S NEW MATERIALS ESTABLISH MEANINGFUL VALIDATION OF SPECIFIC
PROPOSITIONS
PJM's October 7 presentation describes Phase 1 as a temporary process used to determine the 2029/30 Variable Resource Requirement curve adjustment for BYONC, with an enhanced process and tool to be developed based on experience and feedback for determining eligible IRAS for the 2027/28 Delivery Year and forward. PJM, Large Load Registry and BYONC Reporting Process for 2029/30 BRA, at 2 (Oct. 7, 2026). The new implementation materials provide more assurance than a reporting-only registry. An Electric Distribution Company ("EDC") submits the New Large Load and associated BYONC information, and PJM states that the relevant BYONC contract must be executed. Where an LSE submits directly, PJM instructs the LSE to obtain EDC confirmation of the New Large Load and provide that confirmation to PJM. Id. at 5. The Capacity Market Seller must separately provide an officer certification. The template states that PJM and PJM Settlement are relying on the certification as evidence that the participant has an executed contract with the specified New Large Load for the 2029/30 Delivery Year; the officer also certifies that the arrangement identified in Attachment A is true and accurate and that the underlying resource qualifies as BYONC under the applicable Tariff requirements. PJM, BYONC Officer Certification Template, Officer Certification & Attachment A (Oct. 2026).

PJM then validates the registry information. For the large load, PJM checks for duplicates and uses EDC validation as needed. For BYONC, PJM verifies information against Capacity Exchange, ensures the resource meets Tariff criteria, checks for duplicates, and confirms submission of the executed-contract certification. PJM's determination of BYONC eligibility is then published in the Registry's BYONC Status field. PJM Oct. 7 Presentation at 8.

PDF page 2

Docket No. ER26-3515-000
Page 2
PAG supports those controls. They demonstrate that PJM is not treating every submitted representation as self-proving. They also sharpen the remaining question: what proposition has been validated, and for what later decision is that validation sufficient?

III. VALIDATION SHOULD IDENTIFY THE PROPOSITION VALIDATED
A verified contractual relationship is decision-grade evidence of that contractual relationship; it is not necessarily decision-grade evidence of future energized or sustained demand.

The current Registry field set appropriately identifies the customer, EDC interconnection request, location, zone, business segment, 2026/27 and expected 2029/30 peak load, BYONC contract status, associated resource identifiers, BYONC MW, submitter contacts, and PJM's BYONC Status. PJM, Large Load Registry Field Definitions and Examples (Oct. 2026). Those fields are useful and substantially improve visibility. The field set does not, however, appear to contain a structured project-state field that distinguishes whether the represented future load is reported or requested, contractually committed, executable, energized, or operating on a persistent basis. Nor does the validation label itself distinguish whether PJM has validated identity and duplicate status, an executed contractual relationship, Tariff eligibility, a forecast quantity, an executable project state, or an operating state.

That distinction matters because the same record can support different propositions with different degrees of confidence. An executed BYONC contract may be sufficient evidence for a BYONC contractual or eligibility determination while remaining insufficient, standing alone, to establish that the corresponding New Large Load will energize on the represented schedule or sustain the represented demand.

PAG therefore recommends that, as PJM develops the enhanced process, any material validation status identify the proposition validated. PJM need not create a public scoring system or adopt PAG's terminology. A concise status definition or associated metadata can make clear whether the validated fact concerns identity, contract execution, Tariff eligibility, forecast state, project execution, operational capability, or another defined proposition.

IV. EVIDENCE CURRENCY AND MATERIAL CHANGE SHOULD BE VISIBLE WHERE LATER
RELIANCE IS CONSEQUENTIAL
The Registry contains submitter identity and contact information, but the current field definitions do not appear to require an effective-as-of date for the underlying project-state evidence, a last-revalidated date, or a structured material-change indicator for the large-load state itself. That omission becomes more important when a validated record is reused for a different or later decision.

PJM's implementation schedule illustrates the speed with which the information can become consequential. The October 7 presentation shows the Phase 1 Registry closing on October 20, PJM finalizing validation on November 14, planning parameters posting on November 19, and the Base Residual Auction opening on December 9. PJM Oct. 7 Presentation at 3.

PAG does not recommend continuous resubmission of unchanged data. It recommends that a material validated state carry enough currency information to allow the relying entity to know when the relevant evidence was effective or last materially confirmed. Where the represented MW, energization timing, customer identity, EDC interconnection status, BYONC arrangement, resource status, or another fact supporting the earlier determination changes materially, the affected determination should be revalidated before that prior status is used as if nothing changed.

V. THE ENHANCED IRAS PROCESS IS THE APPROPRIATE PLACE TO MATCH EVIDENCE TO
THE DECISION
PJM expressly characterizes Phase 1 as temporary and states that it will implement an enhanced process and tool based on feedback and experience for eligible IRAS in later Delivery Years. That planned enhancement provides a practical opportunity to preserve the distinction between a validated reported state and a state sufficiently evidenced for a specific consequential decision.

PAG does not ask the Commission to direct a new public scoring methodology, create a separate approval layer, or displace PJM's technical judgment. Nor does PAG suggest that the current Phase 1 Registry must be

PDF page 3

Docket No. ER26-3515-000
Page 3
redesigned before the 2029/30 auction. The narrow recommendation is that the evidentiary maturity of a represented state be matched to the consequence of the decision for which PJM or another authorized entity relies upon it.

This can be implemented incrementally through status definitions, effective or validation dates, source categories where useful, and material-change/revalidation indicators. The goal is not more data for its own sake. It is to prevent a validated fact from being silently generalized beyond the proposition that the supporting evidence actually establishes.

VI. REQUESTED COMMISSION RECOGNITION
In light of PJM's new implementation materials, PAG respectfully recommends that the Commission recognize the following principles as PJM completes Phase 1 and develops its enhanced Large Load Registry and IRAS processes:

1. Validation should identify the proposition validated. A status showing that a contract, identity, duplicate check, or Tariff criterion has been validated should not be assumed to establish a more mature project or operating state unless the supporting evidence is suited to that proposition.

2. Material large-load states should preserve useful evidence currency. Where consequential reliance depends on a represented future state, the record should allow the relying entity to understand when the supporting evidence was effective or last materially validated.

3. Material change should trigger revalidation of the affected determination. Changes in represented MW, timing, customer or project identity, interconnection status, BYONC arrangement, resource status, or another decision-critical fact should not leave a prior validated state silently unchanged.

4. Evidence should be matched to the decision. Information sufficient for early planning visibility or a defined contractual determination may not be sufficient for an operational baseline, market parameter, infrastructure commitment, or other consequential reliance.

VII. CONCLUSION
PJM's new implementation materials meaningfully strengthen the Large Load Registry by requiring EDC- linked reporting, an executed BYONC contract, officer certification, duplicate checks, Tariff-eligibility review, and PJM validation. PAG supports those controls.

The remaining implementation issue is narrower but important: validation should make clear what has actually been validated, how current that evidence is, and whether a material change requires the affected determination to be revisited before continued reliance.

Validation should identify the proposition validated. Evidence sufficient for one determination should not silently become evidence sufficient for every later decision.

Recognizing these principles would build on PJM's current work, preserve implementation flexibility, and improve the ability of PJM, state commissions, Electric Distributors, and other authorized users to distinguish a validated reported state from a decision-reliance state.

Respectfully submitted,
Neil P. Osnato
Founder
Persistence Analytics Group LLC | United Grid™
82 Spring Lake Blvd.
Waretown, NJ 08758
neil@persistenceanalyticsgroup.com
609-464-9055
Dated: October 8, 2026
CERTIFICATE OF SERVICE

PDF page 4

Docket No. ER26-3515-000
Page 4
I hereby certify that on October 8, 2026, I served the foregoing Motion for Leave to File Supplemental Comments and Supplemental Comments of Persistence Analytics Group LLC electronically on the applicant's representatives identified in PJM Interconnection, L.L.C.'s filing in Docket No. ER26-3515-000 and, to the extent applicable, on all persons appearing on the official service list for this proceeding in accordance with Rule 2010 of the Commission's Rules of Practice and Procedure.

Neil P. Osnato
Persistence Analytics Group LLC
Dated: October 8, 2026