ER26-3515-000 · 2026-10-08 · Individual No Affiliation

Motion for Leave to File Supplemental Comments and Supplemental Comments of Persistence Analytics Group LLC re Validated Project State, Evidentiary…

Text extracted from the eLibrary original (SHA-256 ef1f4fd94656ce70…). Download the original from the official source.

Contents · 7 sections
  1. I. MOTION FOR LEAVE TO FILE SUPPLEMENTAL COMMENTS p. 1
  2. II. PJM'S NEW MATERIALS ESTABLISH MEANINGFUL VALIDATION OF SPECIFIC p. 1
  3. III. VALIDATION SHOULD IDENTIFY THE PROPOSITION VALIDATED p. 2
  4. IV. EVIDENCE CURRENCY AND MATERIAL CHANGE SHOULD BE VISIBLE WHERE LATER p. 2
  5. V. THE ENHANCED IRAS PROCESS IS THE APPROPRIATE PLACE TO MATCH EVIDENCE TO p. 2
  6. VI. REQUESTED COMMISSION RECOGNITION p. 3
  7. VII. CONCLUSION p. 3

Read topic-matched comments in ER26-3515

Topics in the text: Registry access · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

ER26-3515-000 Page 1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. MOTION FOR LEAVE TO FILE SUPPLEMENTAL COMMENTS

printed heading · Topic match: Registry access

To the extent leave is required, PAG respectfully requests leave under Rule 212 of the Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.212, because consideration of this limited update will assist the Commission without prejudice to any participant.
Read this passage Filed comments: Registry access

II. PJM'S NEW MATERIALS ESTABLISH MEANINGFUL VALIDATION OF SPECIFIC

printed heading · Topic match: Registry access

An Electric Distribution Company ("EDC") submits the New Large Load and associated BYONC information, and PJM states that the relevant BYONC contract must be executed.
Read this passage Filed comments: Registry access

III. VALIDATION SHOULD IDENTIFY THE PROPOSITION VALIDATED

printed heading · Topic match: Registry access

The current Registry field set appropriately identifies the customer, EDC interconnection request, location, zone, business segment, 2026/27 and expected 2029/30 peak load, BYONC contract status, associated resource identifiers, BYONC MW, submitter contacts, and PJM's BYONC Status.
Read this passage Filed comments: Registry access

IV. EVIDENCE CURRENCY AND MATERIAL CHANGE SHOULD BE VISIBLE WHERE LATER

printed heading · Topic match: Registry access

EVIDENCE CURRENCY AND MATERIAL CHANGE SHOULD BE VISIBLE WHERE LATER RELIANCE IS CONSEQUENTIAL The Registry contains submitter identity and contact information, but the current field definitions do not appear to require an effective-as-of date for the underlying project-state evidence, a…
Read this passage Filed comments: Registry access

V. THE ENHANCED IRAS PROCESS IS THE APPROPRIATE PLACE TO MATCH EVIDENCE TO

printed heading · Topic match: Registry access

Nor does PAG suggest that the current Phase 1 Registry must be Docket No.
Read this passage Filed comments: Registry access

VI. REQUESTED COMMISSION RECOGNITION

printed heading · Topic match: Registry access

REQUESTED COMMISSION RECOGNITION In light of PJM's new implementation materials, PAG respectfully recommends that the Commission recognize the following principles as PJM completes Phase 1 and develops its enhanced Large Load Registry and IRAS processes: 1.
Read this passage Filed comments: Registry access

VII. CONCLUSION

printed heading · Topic match: Registry access

CONCLUSION PJM's new implementation materials meaningfully strengthen the Large Load Registry by requiring EDC- linked reporting, an executed BYONC contract, officer certification, duplicate checks, Tariff-eligibility review, and PJM validation.
Read this passage Filed comments: Registry access

CERTIFICATE OF SERVICE

printed heading

ER26-3515-000 Page 4 I hereby certify that on October 8, 2026, I served the foregoing Motion for Leave to File Supplemental Comments and Supplemental Comments of Persistence Analytics Group LLC electronically on the applicant's representatives identified in PJM Interconnection, L.L.C.'s filing in…