ER26-3531-000 · 2026-10-13 · American Transmission Company LLC

Motion for Reply and Reply of American Transmission Company LLC to Midcontinent Independent System Operator, Inc.'s 10/09/2026 Motion for Leave to Answer…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

American Transmission Company LLC

          Docket No. ER26-3531-000

MOTION FOR REPLY AND REPLY OF
AMERICAN TRANSMISSION COMPANY LLC

Pursuant to Sections 212 and 213 of the Commission’s Rules of Practice and Procedure,1 American Transmission Company LLC (ATC) by its corporate manager, ATC Management Inc. (collectively, ATC) hereby files this Motion for Leave to Reply and Reply to the Motion for Leave to Answer and Answer of the Midcontinent Independent System Operator, Inc. (MISO) filed on October 9, 2026.  On August 17, 2026, ATC filed its proposed revisions to Attachment FF-ATCLLC of MISO’s Open Access  Transmission, Energy and Operating Reserve Markets Tariff (Tariff) in response to the Commission’s Show Cause Order.2  ATC’s proposed revisions address the immediate need for large load integration in the ATC service territory and are just and reasonable and should be accepted without hearing or settlement proceedings with an effective date of October 17, 2026.

MISO does not dispute that ATC’s local planning has functioned successfully without issue for two decades or that differences within the region are commonplace, and MISO provides no evidence that ATC’s proposal will cause harm.  Instead, MISO avers that ATC’s proposal may differ from MISO’s processes at some point in the future that may create implementation and

1 18 C.F.R. § 385.212-213 (2026).
2 Midcontinent Indep. Sys. Operator, Inc., Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).

PDF page 2

2

reliability challenges.3  ATC appreciates MISO's recognition that immediate implementation of Attachment FF-ATCLLC addresses an important near-term need.  Approval of Attachment FF- ATCLLC should not be temporary or conditioned on future filings; however, ATC remains committed to working with MISO through the stakeholder process and evaluating any future Commission-approved requirements to determine whether further modifications are warranted. The issue before the Commission in this proceeding is whether ATC's proposed Attachment FF- ATCLLC is just and reasonable, not whether a future MISO proposal might ultimately be preferred.

I. REPLY
A. FPA Section 205 Requires that the Commission Accept ATC’s Proposal if It is
Just and Reasonable.

In this Section 205 proceeding, the Commission must evaluate whether ATC’s proposed changes to its Attachment FF-ATCLLC are just and reasonable.  It is not a question whether there are other just and reasonable alternatives or whether other parties suggest that there are changes to the proposal that they would prefer.4  ATC’s proposed changes to Attachment FF-

3 MISO Answer at 4.
4 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,210 (2026) (declining to address the alternative proposals raised by intervenors because proposed reforms were just and reasonable); Entergy Svcs., Inc. v. FERC, 40 F.4th 689, 701–02 (D.C. Cir. 2022) (finding that the Commission is not required to choose the best solution, only a reasonable one.); Cal. Indep. Sys. Operator Corp., 128 FERC ¶ 61,265, at P 21 (2009) (“Under the [FPA], the issue before the Commission is whether the [independent system operator’s] proposal is just and reasonable and not whether the proposal is more or less reasonable than other alternatives.”); Southwest Power Pool, Inc., 193 FERC ¶ 61,198 (2025) (Accreditation methodology need not predict the future with perfect accuracy, rather the filing party need only show that the proposed methodology would be sufficiently accurate so as to produce just and reasonable results.); Petal Gas Storage, L.L.C. v. FERC, 496 F.3d 695, 703 (D.C. Cir. 2007) (“[The Commission] is not required to choose the best solution, only a reasonable one.”); See PJM Interconnection, L.L.C., 169 FERC ¶ 61,038, at P 12 (2019) (citing OXY USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995) (finding that under the FPA, as long as the Commission finds a methodology to be just and reasonable, that methodology “need not be the only reasonable methodology, or even the most accurate one”)); Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984) (when determining whether a rate was just and reasonable, the

PDF page 3

3

ATCLLC are just and reasonable because they (1) provide an immediately implementable path forward for integrating large loads, consistent with ATC’s current practices and responsive to the requirements in the Show Cause Order, (2) provide certainty for large-load projects already underway in ATC’s footprint, (3) contain urgently needed protections against cost shifting among wholesale customers, and (4) align with Public Service Commission of Wisconsin retail tariff requirements.

MISO agrees that its Show Cause Order compliance processes are working their way through the stakeholder process and could take many months to be final.  Yet MISO asserts that ATC’s Attachment FF-ATCLLC may be problematic at some point in the future.  For example, MISO asks the Commission to allow ATC’s proposed requirements only where MISO has no corresponding requirements,5 but MISO has no corresponding requirements that are effective to date.  Even if MISO develops corresponding requirements in the future, MISO only speculates that ATC’s requirements will cause harm.6  Alternatively, MISO asks the Commission to allow ATC to impose stricter requirements in cases where MISO has an established framework.7 Again, there is no established framework and any conjecture as to what might be stricter is unknown.8  The Commission should not judge ATC’s Attachment FF-ATCLLC planning framework based on MISO’s speculation that ATC’s proposal may conflict with MISO’s processes in the future and that such conflict will cause harm.  If a future conflict arises that may cause harm, it can be addressed at that time.

Commission properly did not consider “whether a proposed rate schedule is more or less reasonable than alternative rate designs”).

5 MISO Answer at 2.
6 Id. at 4 (suggesting that ATC’s proposal “ultimately could create a less stringent standard.”).
7 Id. at 2.
8 Id. at 4 (asserting that ATC’s framework “could result in ambiguity and uncertainty”).

PDF page 4

4

Thus, for purposes of Section 205 approval of ATC’s filing, MISO has not presented an alternative proposal that the Commission could consider.  A speculative future conflict does not justify delaying ATC’s requested October 17, 2026 effective date for revisions that are independently just and reasonable and responsive to the Show Cause Order.

B. Conditioning ATC’s Proposed Changes to Attachment FF-ATCLLC on
Compliance with Yet-Unknown Uniform Base-Level Rules Without a
Demonstrable Need Will Impose Unnecessary Costs in ATC’s Footprint and
Undermine Policy Goals to Advance AI.

MISO argues that uniform base-level rules are needed to address reliability concerns and that if ATC had different standards, it would create operational risk.9  MISO has asserted potential reliability concerns but has not demonstrated any specific reliability deficiency, operational limitation, or planning concern that would result from ATC's proposed framework. From a planning standpoint, there has been and will continue to be significant coordination between ATC and MISO regarding the planning of the system.  Indeed, all of ATC’s projects must be evaluated in MISO’s regional MTEP process—either through the regular planning cycle or through the Expedited Project Review (EPR) process.10  That will not change. From an operations standpoint, it should be abundantly clear that ATC's proposal does not prevent MISO from obtaining information necessary to maintain reliable system operations.  ATC is not proposing to displace otherwise applicable MISO requirements governing load forecasting, telemetry, real-time information, or operational visibility.11  The

9 Id. at 4.
10 ATC Answer at 2, 9.
11 ATC’s proposed changes to Attachment FF-ATCLLC include language requiring ATC to “maintain additional data monitoring, data retention, forecasting and design criteria in applicable ATCLLC Business Practices.”  ATC Transmittal Letter, Tab A, Redlined Attachment FF-ATCLLC, Section V.E.  While ATC maintains its own visibility requirements necessary for its operations, ATC’s requirements will not impact MISO’s load forecasting, telemetry, real-time information, or operational visibility requirements.

PDF page 5

5

material differences addressed by Attachment FF-ATCLLC concern ATC’s local planning, study, interconnection, and cost-allocation framework that are part of ATC’s local planning role, for which ATC has developed study-based criteria tailored to its system.  Attachment FF-ATCLLC will not affect MISO’s ability to obtain the operational information needed to operate the regional system.

Attachment FF-ATCLLC was adopted to fulfill ATC’s state law mandate.  Under the
Wisconsin law that enabled ATC to be formed, ATC is not permitted to delegate its planning obligations under state law to any other entity.12  Since the initial approval of Attachment FF- ATCLLC, the Commission has approved ATC’s proposed changes to comply with other major planning orders without concern for operational risks.  In compliance with Order Nos. 890,13 and 1000,14 the Commission approved (and MISO did not object) to ATC being the only transmission owner in the MISO footprint at that time to decline to integrate its local planning functions into MISO’s Attachment FF.15

12 ATC sought and thereafter became “a transmission company” which obligated ATC to engage in as “its sole purpose the planning, constructing, operating, maintain and expanding of transmission facilities, and the providing of transmission service, to provide for an adequate and reliable transmission system that meets the needs of all users that are dependent on the transmission system and that supports effective competition in energy markets without favoring any market participant.” Wis. Stat. § 196.485(ge) (2025) (emphasis added). 13 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, FERC Stats. & Regs. ¶ 31,241, order on reh’g, Order No. 890-A, FERC Stats. & Regs. ¶ 31,261 (2007), order on reh’g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890-C, 126 FERC ¶ 61,228 (2009), order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009). 14 Midwest Indep. Transmission Sys. Operator, Inc., 147 FERC ¶ 61,127 at P 76 (2014) (Order 1000 Compliance rehearing order); Midwest Indep. Transmission Sys. Operator, Inc., 130 FERC ¶ 61,232, P 36, on reh’g, 132 FERC ¶ 61,119, PP 20-22 (2010).  Midwest Indep. Transmission Sys. Operator, Inc., 123 FERC ¶ 61,165 (2008), order on reh’g, 127 FERC ¶ 61,169 (2009).
15 Midwest Indep. Transmission Sys. Operator, Inc., 123 FERC ¶ 61,164 at P 124, n.113 (noting that ATC declined to integrate its local planning process into MISO’s Attachment FF and instead  engages in local planning through a separate ATC-specific local planning process provided in Attachment FF-ATCLLC; Midwest Indep. Transmission Sys. Operator, Inc., et.al., 130 FERC ¶ 61,232 at PP 36-42 (accepting Attachment FF-ATCLLC with certain modifications); Midwest Indep. Transmission Sys. Operator, Inc.,

PDF page 6

6

Contrary to MISO’s claims, Attachment FF-ATCLLC does not exceed the traditional
bounds of ATC’s local planning criteria.  Large loads are retail customers of the local distribution companies in ATC’s footprint.  ATC’s planning for large loads interconnecting with the local distribution companies on ATC’s system is fundamental to ATC’s local planning function and will impact retail electric service in ATC’s footprint for many years to come.  Delegating that function to MISO is contrary to Wisconsin law and prior Commission orders, and would subvert ATC’s obligations to its stakeholders.

Moreover, contrary to MISO’s claims, ATC has adequately addressed cost allocation in Attachment FF-ATCLLC to comply with state retail tariff requirements.  Differences in cost allocation policies have not been problematic in the past.  In the generation interconnection context, ATC has had different network upgrade cost allocation provisions from the rest of the MISO region with no negative impacts.16

MISO’s alleged harm is based on conjecture and dependent on tariff provisions that have not yet been filed or accepted by the Commission.  ATC’s amendments to Attachment FF- ATCLLC are supported by studies used in developing the planning criteria to address the needs of its system and will apply to large loads in its footprint.17  We are not aware of any similar

et.al., 132 FERC ¶ 61,119 at P 22 (2010) (order accepting compliance filing and noting that ATC’s projects still must flow through MTEP.).

16 For several years, ATC had a roll-in cost allocation policy for generator interconnection network upgrades when MISO had adopted a participant funding methodology.  American Transmission Co. LLC, 120 FERC ¶ 61,221 at P 17 (2007)(“We likewise find that the proposal of ATC to adopt a 100% reimbursement policy is just and reasonable. As long-recognized by the courts, different rate proposals can be just and reasonable; there is no one correct method for calculating rates.”) order denying reh’g, 123 FERC ¶ 61,065 (2008).
17ATC engaged specialized power system consultants to study large loads, including flicker analyses, rotor-swing modes, generator-shaft studies to develop ramp-rate, and voltage-ride-through requirements. ATC Answer at 7.  The proposed changes to Attachment FF-ATCLLC’s operating requirements are based on these extensive studies and advance these proven large load processes developed over the past several years.

PDF page 7

7

studies by MISO.  MISO is assuming that its requirements will be more stringent than ATC’s but that remains unknown.  ATC’s studies were intended to build efficiencies in design, maintain safe and reliable service, and rein in costs.  Any perceived need for more stringent planning/operating requirements is not supported by studies.  Without additional technical support, uniformity for the sake of uniformity will add an unnecessary burden to large load customers in ATC’s footprint by requiring unnecessary and costly equipment requirements.  This poses the risk of driving up costs for customers and undermining the administration’s policy goals for advancing AI (or super intelligence).

ATC has already committed to adjusting its processes, if necessary, as MISO’s requirements develop through the stakeholder process.  It is unreasonable for MISO to suggest that ATC should defer or condition its proposal because it may conflict with MISO’s future Show Cause Order compliance filing.

C. The Commission has Encouraged Individual Transmission Owners to Make
Section 205 Filings to Address the Show Cause Order Requirements and to
Facilitate AI Development.

As the Commission noted in the Show Cause Order, ATC’s current Attachment FF- ATCLLC includes an approved distribution-to-transmission interconnection process and a load interconnection procedure, but it does not have procedures specific to large loads.18  ATC is following the Commission’s directive in the Show Cause Order with proposed revisions in this filing that are intended to fill that gap and to be tailored to work within the established Attachment FF-ATCLLC procedures.  The Commission has encouraged transmission owners to

18  Show Cause Order at n. 75.  The Commission recognized that ATC has established procedures for interconnection of large loads outside of the Tariff.  Id. at P 21, n. 77.

PDF page 8

8

propose tariff revisions to address issues pursuant to their applicable Section 205 filing rights.19 ATC’s proposal here is intended to comply with the Show Cause Order and formalize what ATC is already doing in its footprint to manage the challenges of large load integration and facilitate AI development, as well as adopt new practices required of the Show Cause Order.20

II. MOTION FOR LEAVE TO REPLY
To the extent required, ATC respectfully requests leave to submit this Reply.  The Commission’s Rules of Practice and Procedure prohibit answers to protests unless otherwise authorized.21  The Commission regularly allows answers for good cause shown, such as when the answers help ensure a more accurate and complete record, clarify the issues, or provide useful and relevant information that will assist the Commission in its deliberative process.22 ATC’s Reply will clarify the record, correct misinformation and ensure a more accurate and complete record.  Because this information will assist the Commission in its decision-making, ATC respectfully requests that the Commission accept this Reply for good cause shown.

19 Id. at P 36 (“We recognize that MISO and/or the Transmission Owners (to the extent the matters addressed herein implicate aspects of the Tariff over which they have the filing rights) may elect to address some or all of the issues discussed in this order by proposing revisions to the Tariff pursuant to their applicable FPA section 205 filing rights. We strongly encourage this.”).
20 See Interconnection of Large Loads to the Interstate Transmission System, Advance Notice of Proposed Rulemaking, Docket No. RM26-4-000 (Oct. 23, 2025) (ANOPR); see also Letter from Chris Wright, Sec’y, U.S. Dep’t of Energy, Docket No. RM26-4-000 (Oct. 23, 2025); Show Cause Order, Commissioner Rosner, concurring at P 2 (“It is also crucial that we unlock the immense economic opportunity that once- in-a-generation growth represents.”); Id. Commissioner Lacerte concurring at P 5 (“Time is of the essence. By inviting you to proceed under FPA section 205, we are giving you significant perks:  the benefits of first wielder of the pen and the relatively capacious standard under FPA section 205 that allows us to accept a potentially broad range of proposals provided they are shown to be just and reasonable and not unduly discriminatory or preferential.”).
21 18 C.F.R. § 385.213(a)(2).
22 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131 at P 24 (2025) (accepting answers to answers “because they have provided information that assisted us in our decision-making process”); Texas Eastern Transmission, LP, 122 FERC ¶ 61,205 at P 8 (2008) (accepting answer that completed the record); California Indep. Operator Corp., 105 FERC ¶ 61,284 at P 10 (2003) (accepting MISO’s answer that clarified the issues).

PDF page 9

9

III. CONCLUSION
For the foregoing reasons, ATC’s proposed revisions to Attachment FF-ATCLLC are just and reasonable and will provide greater clarity and transparency for the immediate and reliable interconnection of large loads in ATC’s footprint.  ATC respectfully requests that the Commission grant leave to accept this Reply and accept the proposed revisions to Attachment FF-ATCLLC as just and reasonable, effective October 17, 2026.

Respectfully submitted,

/s/  Linda Walsh
Ellen Nowak, Vice President, State

Linda Walsh
and Federal Affairs

Husch Blackwell LLP
Stephanie Neitzel, Senior Counsel

1801 Pennsylvania Ave., NW
ATC Management Inc., corporate manager of

Suite 1000
American Transmission Company LLC

Washington, DC 20006
P.O. Box 47

Tel: (202) 378-2308
Waukesha WI 53187-0047

linda.walsh@huschblackwell.com
Tel: (262) 506-6170

sneitzel@atcllc.com

Dated: October 13, 2026

PDF page 10

10

CERTIFICATE OF SERVICE

Pursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated at Washington, D.C. this 13th day of October 2026.