ER26-3531-000 · 2026-10-13 · American Transmission Company LLC

Motion for Reply and Reply of American Transmission Company LLC to Midcontinent Independent System Operator, Inc.'s 10/09/2026 Motion for Leave to Answer…

Text extracted from the eLibrary original (SHA-256 6d12a7ea519a9f93…). Download the original from the official source.

Contents · 6 sections
  1. I. REPLY p. 2
  2. A. FPA Section 205 Requires that the Commission Accept ATC’s Proposal if It is p. 2
  3. B. Conditioning ATC’s Proposed Changes to Attachment FF-ATCLLC on p. 4
  4. C. The Commission has Encouraged Individual Transmission Owners to Make p. 7
  5. II. MOTION FOR LEAVE TO REPLY p. 8
  6. III. CONCLUSION p. 9

Read topic-matched comments in ER26-3531

Topics in the text: Cost allocation · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION American Transmission Company LLC Docket No.
Read this passage

I. REPLY

printed heading

I.
Read this passage

A. FPA Section 205 Requires that the Commission Accept ATC’s Proposal if It is

printed heading · Topic match: Cost allocation

In this Section 205 proceeding, the Commission must evaluate whether ATC’s proposed changes to its Attachment FF-ATCLLC are just and reasonable.
Read this passage Filed comments: Cost allocation

B. Conditioning ATC’s Proposed Changes to Attachment FF-ATCLLC on

printed heading · Topic match: Cost allocation

ATC’s amendments to Attachment FF- ATCLLC are supported by studies used in developing the planning criteria to address the needs of its system and will apply to large loads in its footprint.17 We are not aware of any similar et.al., 132 FERC ¶ 61,119 at P 22 (2010) (order accepting compliance…
Read this passage Filed comments: Cost allocation

C. The Commission has Encouraged Individual Transmission Owners to Make

printed heading

The Commission has Encouraged Individual Transmission Owners to Make Section 205 Filings to Address the Show Cause Order Requirements and to Facilitate AI Development.
Read this passage

II. MOTION FOR LEAVE TO REPLY

printed heading

MOTION FOR LEAVE TO REPLY To the extent required, ATC respectfully requests leave to submit this Reply.
Read this passage

III. CONCLUSION

printed heading

ATC respectfully requests that the Commission grant leave to accept this Reply and accept the proposed revisions to Attachment FF-ATCLLC as just and reasonable, effective October 17, 2026.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 13th day of October 2026. /s/ Emily Starobin Emily Starobin Husch Blackwell LLP 1801 Pennsylvania Ave.