EL26-108-000 · 2026-10-14 · Northern Virginia Electric Cooperative, Inc.
Answer of Northern Virginia Electric Cooperative, Inc. in Support of PJM Interconnection, L.L.C.’s Motion for Abeyance filed on 10/13/2026
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
)
)
)
Docket Nos. ER26-3380-000
EL26-108-000
ANSWER OF NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC.
IN SUPPORT OF PJM INTERCONNECTION, L.L.C.’S MOTION FOR ABEYANCE
Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) respectfully submits this answer in support of PJM Interconnection, L.L.C.’s (“PJM”) motion for abeyance of the Reliability Backstop Procurement (“RBP”) paper hearing procedures to allow PJM to revise its RBP Proposal2 (the “Abeyance Motion”).3 For the reasons set forth herein and in the NOVEC Protest,4 the Commission should accept PJM’s Abeyance Motion.
I. THE COMMISSION SHOULD GRANT PJM’S ABEYANCE MOTION
PJM advised the Commission that it plans “to submit a new FPA section 205 filing that addresses, inter alia, cost allocation issues, Transmission Owner exit responsibilities, and LSE collateral requirements as they relate to RBP by October 29, 2026.”5 The Commission invited such a filing in its September 29, 2026, Order Accepting Reliability Backstop Procurement and Establishing Further Procedures and indicated that it would be open to holding the paper
1 18 C.F.R. § 385.213.2 PJM Interconnection, L.L.C., Reliability Backstop Procurement, Docket No. ER26-3380-000 (July 31, 2026) (Accession No. 20260731-5214) (“RBP Proposal”).3 PJM Interconnection, L.L.C., Motion for Abeyance, Docket Nos. ER26-3380-000 and EL26-108-000 (Oct. 13, 2026) (Accession No. 20261013-5141) (“Abeyance Motion”).4 Northern Virginia Electric Cooperative, Inc., Protest, Docket No. ER26-3380-000 (Aug. 21, 2026) (Accession No. 20260821-5307) (“NOVEC Protest”). 5 Abeyance Motion at 2.
PDF page 2
2
hearing proceeding in abeyance if PJM made such a filing because it may obviate the need for the paper hearing.6 As PJM states in its Abeyance Motion, holding the paper hearing in abeyance will allow PJM and all other interested stakeholders to focus on PJM’s forthcoming filing without having to work in parallel on initial paper hearing briefs that may never be needed.
II. CONCLUSION
WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the
Commission grant PJM’s Abeyance Motion.
Respectfully submitted,
//s// Alan I. Robbins
Alan I. Robbins
Debra D. Roby
Thomas B. Steiger III
Peter E. Colvin
Washington Energy Law LLP
900 17th Street. N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9313
Email: arobbins@washingtonenergylaw.com
droby@washingtonenergylaw.com
tsteiger@washingtonenergylaw.com
pcolvin@washingtonenergylaw.com
Counsel to Northern Virginia Electric Cooperative, Inc.
Dated: October 14, 2026.
6 PJM Interconnection, L.L.C., 196 FERC ¶ 61,245, P 24 (2026) (“…we anticipate that the Commission would grant a motion to hold that briefing in this proceeding in abeyance if PJM submitted a new section 205 filing within 30 days from the date of this order.”).
PDF page 3
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in ER26-3380 and EL26-108.
Dated at Washington, D.C. this 14th day of October, 2026.
//s// Jessika Dziechciowska
Jessika Dziechciowska
Energy Practice Analyst
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9308
Email: jdziechciowska@washingtonenergylaw.com