Answer of Northern Virginia Electric Cooperative, Inc. in Support of PJM Interconnection, L.L.C.’s Motion for Abeyance filed on 10/13/2026
Text extracted from the eLibrary original (SHA-256 06909a8a38c1bce5…). Download the original from the official source.
Contents · 2 sections
Read topic-matched comments in EL26-108
Topics in the text: Filing procedure · Cost allocation · Credit and exit
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
IN SUPPORT OF PJM INTERCONNECTION, L.L.C.’S MOTION FOR ABEYANCE Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) respectfully submits this answer in support of PJM…Read this passage
I. THE COMMISSION SHOULD GRANT PJM’S ABEYANCE MOTION
printed heading · Topic match: Filing procedure
ER26-3380-000 (Aug. 21, 2026) (Accession No. 20260821-5307) (“NOVEC Protest”). 5 Abeyance Motion at 2. 2 hearing proceeding in abeyance if PJM made such a filing because it may obviate the need for the paper hearing.6 As PJM states in its Abeyance Motion, holding the paper hearing in abeyance will…Read this passage
II. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission grant PJM’s Abeyance Motion.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 14th day of October, 2026. //s// Jessika Dziechciowska Jessika Dziechciowska Energy Practice Analyst Washington Energy Law LLP 900 17th Street, N.W., Suite 500-A Washington, D.C. 20006 Tel: (202) 326-9308 Email: jdziechciowska@washingtonenergylaw.comRead this passage