EL25-49-000 · 2026-10-27 · Exelon Corporation, American Transmission Systems and 23 others

Petition for Review filed in the U.S. Court of Appeals for the Third Circuit of Exelon Corp., et al. re 12/18/2025, 02/20/2026, 06/18/2026, and 08/20/2026…

PDF page 1

Document Accessig-P SP; 2QI:236-18 - 3g Wu men t:Filla EPAg9: g69,48/2pge Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 135 -
268.
Finally, we note that DCC's concerns regarding the terms and conditions of Interim NITS are misplaced arguments about the illustrative tariff PJM submitted in the paper hearing and are discussed in Part VI.H.

C. Necessary Studies
1. December Order
269.
The Commission directed PJM to revise the Tariff to clarify that an existing Interconnection Customer seeking to modify its ISA or GIA to allow its generator to serve Co-Located Load, including to reflect any reduction in its CIRs, must follow the Necessary Study process to effectuate such Co-Location Arrangement.647  In addition, the Commission directed PJM to add to the Tariff a description of the scope of the analysis that it will perform as part of the Necessary Study process when an Interconnection Customer seeks to use its existing generator to serve Co-Located Load, consistent with PJM's discussion of how it conducts necessary studies associated with Interconnection Customers seeking to amend their ISAs or GIAs to use existing generators to serve Co-Located Load, including to reflect any reduction in CIRs. The Commission found that PJM must include a description of the information that the Interconnection Customer must provide about the Co-Located Load for the purposes of the Necessary Study, and that the Necessary Study process must assess any special protection scheme that is part of a Co-Location Arrangement.648

270.
The Commission directed PJM to revise the Tariff to indicate that the
Interconnection Customer will be responsible for the costs of any modifications or Network Upgrades that are needed as a result of PJM's study of the change to the ISA or GIA to allow the existing generator to serve Co-Located Load, including to reflect any reduction in CIRs, inclusive of all necessary Network Upgrades.649  The Commission found that the Tariff should make clear that an existing generator may not commence service to a Co-Located Load until all required Network Upgrades, special protection schemes, and metering are in service.650  Finally, the Commission clarified that an existing generator may not begin serving Co-Located Load that is not Network Load until requiring the compliance filing constitute a collateral attack on the order requiring the compliance filing.").

647  December Order, 193 FERC ¶ 61,217 at P 226.
648 Id. P 227.
649 Id. P 228.
650 Id 292 of 515

PDF page 2

Document Accessigi
.Eqr2-W1 8-3RE6Unlent:Filtd EPAg:glig8/ 2PAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 136 -
it has delisted its CIRs for the portion of the generator to be designated to serve any Co-Located Load that is not receiving NITS.65'

2. PJM Compliance Filing
271.
PJM states that it proposes changes to Parts III and VIII of the Tariff to comply with the Commission's directives regarding the Necessary Study process for existing Interconnection Customers, including clarifying that customers must enter into a Necessary Study Agreement with PJM.652  PJM also proposes to require customers to provide PJM with all information needed to perform the Necessary Studies, which PJM proposes to detail in the PJM manuals.653  PJM states that a Project Developer may not make changes to its facilities until it has completed the Necessary Study process and the amended GIA is effective. PJM proposes that the Tariff state that Necessary Studies to be performed include thermal, short circuit, and stability studies under various seasonal and load conditions, as detailed in the PJM manuals, and assess any necessary control technologies and protection systems required. Lastly, PJM states that the Tariff will require the Project Developer to be responsible for the cost of any modifications or Network Upgrades necessary as a result of an Interconnection Customer's decision to serve the Co-Located Load.654

272.
PJM clarifies that these changes apply to all existing interconnection customers, regardless of whether they have effective interconnection agreements issued pursuant to Parts IV, VI, VII, or VIII of the Tariff.655  PJM states that, should an interconnection customer not have a three-party interconnection agreement involving PJM, the customer would need to first convert to a three-party agreement before following the Necessary Study process.

3. Pleadings
273. A number of parties have concerns with PJM's compliance filing. Several parties protest PJM's compliance filing and urge the Commission to require PJM to establish 651  Id. P 230.

652 Compliance Transmittal at 24-25.
653  Id. at 25 (citing December Order, 193 FERC ¶ 61,217 at P 227).
654  Id at 25-28.
655  Id. at 24-25. 293 of 515

PDF page 3

Document AccessiggSg 4q1AeR18-3P6)9Unlent:Filld raq99: ge9A912pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 137 -
deadlines to complete the Necessary Study process.656  Constellation urges the Commission to direct PJM to detail the specific provisions in the PJM manuals to which the proposed Tariff language refers because it does not specify whether PJM is proposing to use the existing Necessary Study process or a new process, and the existing requirements set forth in PJM Manual 14C do not specifically reference the studies to be performed. Crusoe and Constellation urge the Commission to direct PJM to revise the proposed Tariff's scope'of the analysis to explicitly relate to reliability impacts only, rather than impacts generally.657  Crusoe contends that PJM should create a clear, published standard for what triggers the Necessary Study process.

274.
Energy Artisans argue that PJM's proposed Necessary Study requirements will force industrial users to fund thermal, short circuit, and stability studies and bear the costs of Network Upgrades, control technologies and protection systems, and redundant metering equipment identified during these studies. Energy Artisans allege that these requirements will force many industrial facilities to cease operations, which will lead to higher Network Loads and exacerbate resource adequacy issues in PJM.658 275.

Vistra and Constellation request that PJM clarify how the proposed Tariff revisions describing the Necessary Study process would apply to interconnection customers who have already submitted requests and are undergoing studies. Constellation and Vistra assert that Co-Location Arrangements will face significant delays if they must reenter the Necessary Study process.659  Vistra maintains that PJM's failure to include a transition mechanism is an unjustified departure from the Commission's approach to interconnection reform, in which the Commission has regularly required transition mechanisms to avoid disruption and stranded investments.66° Constellation proposes to clarify that Project Developers with existing requests for Necessary Studies for Co-Location Arrangements will be allowed to rely on the results of those studies to the extent relevant in light of the transmission service the Eligible

656  Constellation Protest and Comments on Compliance Filing at 12, 17; DCC Comments on Compliance Filing at 7; Crusoe Comments on Compliance Filing at 9.
657  Constellation Protest and Comments on Compliance Filing at 12-14; Crusoe Comments on Compliance Filing at 9.
658  Energy Artisans Protest of Compliance Filing at 1-2.
659  Constellation Protest and Comments on Compliance Filing at 15; Vistra Protest of Compliance Filing at 4, 6-8. 660 Vistra Protest of Compliance Filing at 4-5. 294 of 515

PDF page 4

Document Acces sig@SA: 22q-2-W.8- 34PCument:Fl il d
@g9: g.,39A 8/2  pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 138 -
Customer plans to request on behalf of the Co-Located Load.661  Constellation and Vistra argue that requiring interconnection customers to restart the process would be inconsistent with the filed-rate doctrine and rule against retroactive ratemaking and would effectively penalize parties for failing to comply with rules that did not exist at the time they acted.662

276.
Vistra contends that PJM neither justifies its proposal to require interconnection customers with older interconnection agreements to enter into the new pro forma GIA nor shows how this proposal is consistent with the Commission's directives. Vistra suggests that this proposal is unrelated to the Commission's compliance directives and requests clarity about when the interconnection customer needs to enter into the new GIA in the Necessary Study process. Vistra also asserts that PJM's proposal could result in disputes about whether and how provisions in the updated pro forma GIA apply to older generators, disrupting long-standing Commission precedent. Separately, Vistra indicates that, because PJM locates Necessary Study revisions in Part VIII, which applies to New Service Requests on or after October 1, 2021, it is unclear whether interconnection customers that entered the interconnection process before that date may use the Necessary Study process.663

277.
Joint Parties argue that PJM should be required to clarify that an existing interconnection customer can nominate a joint withdrawal limit in the Necessary Study process.664  Joint Parties argue that this clarification is necessary to realize the December Order's stated intent of ensuring that Co-Located Loads do not pay for services that they do not use and do not trigger Network Upgrades that they do not need.665  Joint Parties argue that PJM's proposed Tariff revisions appear to remain silent as to how it will treat energy withdrawals in studying Co-Located Load interconnection requests. Joint Parties state that they seek modest clarifications from PJM that, to the extent PJM performs interconnection study steps involving withdrawal assumptions for Co-Located Loads, an energy storage interconnection customer will be able to specify limits to the injection and

661  Constellation Protest and Comments on Compliance Filing at 14-15.
662  Id at 15; Vistra Protest of Compliance Filing at 4, 6.
663  Vistra Protest of Compliance Filing at 14-16.
664  Joint Parties Protest of Compliance Filing at 4-6. See also Earthjustice Reply Brief at 22.
665  Joint Parties Protest of Compliance Filing at 4-5. 295 of 515

PDF page 5

Document Accessig#SA: 2A2-1§Al 8 - 31:Aument:Flild  &qg9: e269A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 139 -
withdrawal rights reflecting the proposed integration of the storage and Co-Located Load facilities.666

278.
Parties argue that PJM's proposal for delisting CIRs may be unjust, unreasonable, unduly discriminatory, or inconsistent with the Commission's directives in the December Order. Vistra claims that PJM's proposal would require existing generators to provide PJM with the amount of reduction to CIRs to facilitate the Co-Located Load configuration, which Vistra argues is vague and potentially overbroad because it could be read to require that generators include in their CIR reduction any portion of a facility that will ever provide power to a Co-Located Load. Vistra and DCC express concern that PJM's proposal could require generators to delist more CIRs than necessary. 667  Vistra further contends that allowing secondary units to provide occasional, interruptible service to Co-Located Load and to retain their CIRs would be consistent with the Tariff. Vistra and Constellation argue that capacity resources that serve Co-Located Load on an interruptible basis should not be required to delist CIRs.668  Vistra presents an additional concern with PJM's proposal for reducing CIRs, namely, that PJM fails to explain how it will assess the impact of the reduction of CIRs.669  Vistra alleges that because PJM's proposal is vague on this point, PJM could, for example, improperly incorporate resource adequacy considerations into its Necessary Study process.

4. Determination
279.
We find that PJM's proposed revisions to its Necessary Study process partially comply with the directives set forth in the December Order and therefore accept the Tariff revisions in part, reject them in part, and direct a further compliance filing as discussed below.

280.
We accept PJM's proposed revisions to Part VIII, Subpart A, section 401 and Part IX, Subpart G of the Tariff to comply with the directives in the December Order by:

(1) adding a description of the scope of the analysis that it will perform as part of the Necessary Study process when an Interconnection Customer seeks to use its existing generator to serve Co-Located Load; (2) requiring the Interconnection Customer to be responsible for the costs of any modifications or Network Upgrades that are needed as a

666  Id at 5. 667  Vistra Protest of Compliance Filing at 8-10; DCC Comments on Compliance Filing at 7. 668  Vistra Protest of Compliance Filing at 11; Constellation Protest and Comments on Compliance Filing at 19. 669  Vistra Protest of Compliance Filing at 12. 296 of 515

PDF page 6

Document A„essigPA
:  2q-Agg18-349curnent:Flild rEN9:43/3.8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 140 -
result of PJM's study of the change to the ISA or GIA to allow the existing generator to serve Co-Located Load, including to reflect any reduction in CIRs, inclusive of all necessary Network Upgrades; and (3) clarifying that an existing generator may not commence service to a Co-Located Load until all required Network Upgrades, special protection schemes, and metering are in service.670  We also accept PJM's proposed revisions to Part IX, Subpart A, Form of Application and Studies Agreement to facilitate PJM's collection of the information necessary to perform requested Necessary Studies.671 However, with respect to Constellation's argument that PJM's proposed Tariff revisions may lack clarity, we direct PJM to specify in its compliance filing what types of additional detail about the studies will be available in the PJM manuals. 281. We also note in response to Constellation that, per the December Order, PJM's proposal seeks to clarify the existing Necessary Study process, not create a new one.672 While parties request that the Commission establish deadlines for the Necessary Study process, we note the December Order did not include any such requirement, and our review of these proposed Tariff revisions is limited to whether PJM complies with the directives in the December Order.673  In response to parties' requests regarding the trigger and scope of the Necessary Study process, we note that the Commission in the December Order directed PJM to clarify its study procedures for an Interconnection Customer that will use its generator to serve Co-Located Load but did not otherwise direct changes to the trigger or scope of the Necessary Study process. Per the Tariff, the scope of the Necessary Study is to determine whether planned modifications to an Interconnection Customer's facilities "will have a permanent material impact on the Transmission System and to identify the additions, modifications, or replacements to the Transmission System,

670 December Order, 193 FERC ¶ 61,217 at PP 227-228. We also accept the conforming edit to the definition of Necessary Study in Proposed Tariff, § VII.A 300, Definitions N (3.0.0) and § VIII.A 400, Definitions N (4.0.0).
671  Compliance Transmittal at 27; PJM, Proposed Tariff, pt. Ix, subpt. A, (Form of Application and Studies Agreement) (4.0.0).
672  See Compliance Transmittal at 25 ("The thrust of PJM's proposed revisions require any Existing Interconnection Customer that seeks to serve Co-Located Load to follow a clarified necessary study process detailed in Part VIII of the Tariff and the related Form of Necessary Study Agreement set forth in Tariff, Part IX, Subpart G.").
673  See, e.g., PJM Interconnection LLC, 119 FERC ¶ 61,179, at P 12 (2007) ("The purpose of a compliance filing is to make the directed changes and the Commission's focus in reviewing them is whether they comply with the Commission's previously stated directives.") (citing AES Huntington Beach, LLC, 111 FERC ¶ 61,079, at P 60 & n.25 (2005)). 297 of 515

PDF page 7

Document AccessigPsA qq23.6g-18 _31:29cument:Flil d IEN9:(269A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 141 -
if any, that are necessary, in accordance with Good Utility Practice, and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, to accommodate the planned modifications."674  Regarding Joint Parties' requests regarding study processes for Co-Located Loads paired with electric storage resources, we note that the December Order did not address or otherwise direct changes as to any generator interconnection study procedures for such resources.

282.
We reject in part PJM's proposed revisions to Part III of its Tariff regarding the requirement for Interconnection Customers with effective ISAs pursuant to Part VI of the Tariff or effective GIAs pursuant to Part VII of the Tariff to enter into a new GIA pursuant to Part VIII of the Tariff and the pro forma GIA in Part IX, Subpart B. We agree with Vistra that such a requirement is inconsistent with the Commission's recognition in the December Order that existing Interconnection Customers that seek to modify their ISAs or GIAs must follow the Necessary Study process to effectuate a Co-Location Arrangement.675  Interconnection Customers with effective ISAs or GIAs must be able to modify those agreements and undergo the Necessary Study process without entering into new GIAs.

283.
We also agree with protesters that PJM's proposed revisions lack clarity with respect to how they apply to Interconnection Customers that have already executed Necessary Study Agreements and for which PJM has already completed Necessary Studies.676  The Commission found in the December Order that the Necessary Study process lacked sufficient clarity and directed PJM to add the scope of the analysis it performs as part of the Necessary Study process to its Tariff.677  However, the Commission did not direct changes to the scope of the study, and PJM does not otherwise demonstrate why Interconnection Customers seeking to serve Co-Located Load cannot

674  PJM, Intra-PJM Tariffs, pt. WILA, § 400 (Definitions N) (2.0.0) (definition of Necessary Study).
675  December Order, 193 FERC ¶ 61,217 at P 226 ("[W]e direct PJM to submit, within 60 days of the date of issuance of this order, a compliance filing to revise the Tariff to clarify that an existing Interconnection Customer seeking to modify its ISA or GIA to allow its generating facility to serve Co-Located Load, including to reflect any reduction in its CIRs, must follow the necessary study process to effectuate such Co-Location Arrangement.") (emphasis added).
676  Constellation Protest and Comments on Compliance Filing at 15; Vistra Protest of Compliance Filing at 4, 6.
677  December Order, 193 FERC ¶ 61,217 at P 227. 298 of 515

PDF page 8

Document AccessigPSA: 2A-2-VA18- 3499u me nt:F1 Ad riDag
8/2PPe Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 142 -
rely on the results of Necessary Studies that have already been performed if the scope of the study has not changed.

284.
For these reasons, we direct PJM to submit a compliance filing within 60 days of the date of issuance of this order to remove the requirement for Interconnection Customers with existing ISAs pursuant to Part VI of the Tariff and GIAs pursuant to Part VII of the Tariff to enter into a new pro forma GIA. We recognize that removing the requirement for Interconnection Customers with existing ISAs pursuant to Part VI of the Tariff and GIAs pursuant to Part VII of the Tariff to enter into a new pro forma GIA will necessitate duplicating the appropriate Necessary Study Tariff provisions (Part VIII, Subpart A, section 401.H.3) in those Tariff sections, and therefore we direct PJM to include these Tariff revisions in its compliance filing. We find that this directive will ensure that Interconnection Customers with effective ISAs or GIAs will not be required to enter into new GIAs if they seek to modify their ISA or GIA to allow their generator to serve Co-Located Load.

285.
We also direct PJM to explain in its compliance filing how its changes ensure the prohibition on Interconnection Customers serving Co-Located Loads from existing generators until all required Network Upgrades, necessary control technologies and/or protection systems, and metering identified as necessary are complete and in service, applies to Interconnection Customers with currently effective GIAs, ISAs, and Necessary Study Agreements, in addition to Interconnection Customers seeking new Necessary Study Agreements and GIAs.

286.
In response to Constellation's request that the Commission clarify that Interconnection Customers with existing requests for Necessary Studies for Co-Location Arrangements may rely on the results of those studies to the extent relevant in light of the transmission service the associated Eligible Customer plans to request on behalf of the Co-Located Load, we clarify that the studies applicable to a transmission service request for one of the new transmission services are distinct from the Necessary Study process, which studies the modification of a generator interconnection. If an Eligible Customer seeks to take one of the new transmission services on behalf of Co-Located Load, it must request transmission service and follow the appropriate transmission service study procedures as directed in this order.

287.
With respect to Energy Artisans' argument that requiring industrial users to bear the costs of modifications or Network Upgrades will force industrial facilities to cease operations and exacerbate resource adequacy issues in PJM, we dismiss this argument as an untimely request for rehearing of the December Order's finding that PJM's existing retail BTMG netting rules were no longer just and reasonable.678  We reiterate that the

678  Id P 221; see supra P 232 & n.585. 299 of 515

PDF page 9

Document AccessigPSA 22q-Ag1.8 _3RWLIment:Flitd  rpAg: AO/g8/2
e Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 143 -
requirement to be responsible for costs of modifications or Network Upgrades applies only to Interconnection Customers that seek to modify their ISA or GIA to allow their generator to serve Co-Located Load, and this is a clarification of existing Tariff provisions in the pro forma ISA and GIA, as explained above.679  Interconnection Customers may choose to maintain their current ISAs or GIAs with no modifications, and Interconnection Customers who do not wish to bear these costs may choose not to pursue Co-Location Arrangements.

288. Consistent with our above discussion, we disagree with Vistra and Constellation that capacity resources should not have to reduce their CIRs to serve Co-Located Load.680 We also reject without prejudice PJM's proposed Tariff, Part IX, Subpart G, Form of Necessary Studies Agreement, because PJM has proposed changes to the Cost Responsibility section without explanation.681

D. Other
1. December Order
a. Definition of Co-Located Load
289. In the December Order, the Commission directed PJM to adopt the definition of Co-Located Load specified in the order: "a configuration that refers to end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer's side of the Point of Interconnection to the PJM Transmission System."682

b. Generation Interconnection Procedures, pro forma GIA,
and Common Service Provisions
290. The Commission also directed PJM to revise its Tariff, VIII, Subpart B, section 403 - Application Rules to add to the list of requirements for a New Service

679  Tariff, Intra-PJM Tariffs, OATT, Attachment O, Appendix 2, § 3.4(b) Modification Costs (0.0.0); id., Part IX.B, Appendix 2, § 3.4(b) Modification Costs (2.0.0). 688  See supra Part IV.C.2.a.iii.
681 PJM,

Proposed Tariff, pt. IX, subpt. G (Form of Necessary Studies Agreement) (3.0.0), § 15 (Cost Responsibility). Specifically, PJM proposes to raise the initial deposit for the Necessary Studies from $25,000 to $50,000.

682  December Order, 193 FERC ¶ 61,217 at P 164. 300 of 515

PDF page 10

Document AccessigPSg 4 -2-Y%q18-3QKUrnent:Filtd IPACW A0A 8 / 2PAe Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 144 -
Request that an Interconnection Customer who will use its generator to serve Co-Located Load must specify an Eligible Customer who will take transmission service on behalf of the Co-Located Load.683  The Commission further directed PJM to submit revisions to the generation interconnection procedures to specify any operational procedures or data exchange requirements that PJM deems necessary for Co-Location Arrangements to remedy the Tariff deficiencies, such as unique operational procedures and data exchange requirements.684  The Commission noted that these revisions would establish a requirement in the Tariff for the Eligible Customer to be charged for transmission and ancillary services that the Eligible Customer must take on behalf of the Co-Located Load. The Commission clarified that, should an Interconnection Customer wish to serve Co-Located Load using its generator but not identify an Eligible Customer, then the Interconnection Customer may take steps to terminate its generator's interconnection to the PJM transmission system and serve the Co-Located Load fully islanded from PJM's transmission system.685

291.
The Commission also directed revisions to the Tariff, Part IX, Subpart B GIA to specify that an Interconnection Customer that will use its generator to serve Co-Located Load must specify an Eligible Customer that will take transmission service on behalf of the Co-Located Load.686  The Commission directed PJM to add a new provision to Part I, Common Service Provisions, of the Tariff that requires Interconnection Customers with ISAs or GIAs executed, or requested to be filed unexecuted, prior to the effective date of the revised generation interconnection procedures and pro forma GIA directed in this order that wish to add Co-Located Load or are currently serving Co-Located Load to publicly notify PJM of that addition and identify the Eligible Customer that will take transmission service on behalf of that Co-Located Load.

2. PJM Compliance Filing
a. Definition of Co-Located Load
292.
On April 16, 2026, the Commission issued an order rejecting the portion of PJM's first compliance filing proposing to define Co-Located Load in a manner that deviated 6831d. P188.

684 Id. P 188 & n.405.
685Id P 189.
686 Id. P 190. 301 of 515

PDF page 11

Document Accessig
qq-2y:6-18 _39e9Liment:FlAd rpaqg9: A0A8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al. -
- 145 -
from the December Order, without sufficient explanation, by replacing the term "Point of Interconnection" with "Point of Change in Ownership."687

293. In the instant filing, PJM states that it proposes modifying the definition of Co-Located Load directed by the Commission in the same manner as proposed in PJM's first compliance filing.688  PJM states that changing "Point of Interconnection" to "Point of Change in Ownership" is consistent with or superior to the December Order's directive because it provides additional clarity to interconnection parties, is easier to administer, and reduces litigation potentia1.689  PJM further explains "[w]hile Point of Change in Ownership describes where a developer's portion of the Interconnection Facilities connect to the Transmission Owner's portion of the Interconnection Facilities, Point of Interconnection is a technical and physical term about `where' those Interconnection Facilities connect to the PJM Transmission System."69°  PJM states that the Commission has broad authority to establish the replacement rate under FPA section 206 and that "one stakeholder's conditional protest in Docket No. ER26-1088 offers another alternative for the Commission to consider in reliance on this Commission authority."691  PJM explains that "Point of Change in Ownership" will reduce litigation because parties "know what interconnection facilities they own and can plan the connection of Co-Located Load to such facilities accordingly" but that the protest in Docket No. ER26-1088 "does not appear inconsistent with recognizing the principle that Co-Located Loads should only interconnect to a Project Developer's portion of the Interconnection Facilities."692  PJM notes that under the GIP, the Project Developer's Interconnection Facilities are the Interconnection Facilities between a Generating Facility and the Point of Change in Ownership, and include the facilities and equipment and any modification to those facilities and equipment that are necessary to physically and electrically interconnect the Generating Facility.693

687  PJM Interconnection, L.L.C., 195 FERC ¶ 61,030 (2026).
688 Compliance Transmittal at 31 (citing PJM, Transmittal, Docket No. ER26-1088-000, at 3 n.14 (filed Jan. 20, 2026)). 689  Id. at 31-32. 690  Id at 32. 69  Id at 33.
692  Id. at 33-34.
693  Id at 34-35. 302 of 515

PDF page 12

Document AccessigPS:: 2A-Aetg18 _ 3RKUrnellt:Flild
AO/4 8 / 2 ;12*e Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 146 -
b. Generation Interconnection Procedures, pro forma GIA,
and Common Service Provisions
294.
PJM states that it proposes the prescriptive clarifications directed in the December Order. PJM explains that the proposed Tariff revisions comply by: (1) adding to the list of requirements for a New Service Request that an Interconnection Customer who will use its generating facility to serve Co-Located Load must specify an Eligible Customer who will take transmission service on behalf of the Co-Located Load,694  (2) explaining that if an Interconnection Customer wants to serve Co-Located Load but not identify an Eligible Customer, then it may take steps to terminate its generating facility's interconnection and serve the Co-Located Load fully islanded from PJM's transmission system,695  (3) explaining that these requirements apply to all Interconnection Customers requesting to interconnect generating facilities to serve Co-Located Load,696  (4) creating a new schedule in the pro forma GIA in the form of a placeholder to specify operational procedures or data exchange requirements as may be required,697  and (5) revising the pro forma GIA to reflect the requirement to specify an Eligible Customer that will take transmission service on behalf of the Co-Located Load.698

295.
In addition, PJM states that it complies with the requirement to add a transition mechanism for existing customers that wish to add Co-Located Load by including the transition mechanism in (1) the definition of Co-Located Generating Facility in Part I of the Tariff, (2) Part III (NITS), and (3) the definition of Co-Located Generating Facility699

694  Id. at 28 (citing PJM, Proposed Tariff, pt. VIII, subpt. B, § 403 (4.0.0), § 403(1)(r)).
695  Id. at 29 (citing PJM, Proposed Tariff, pt. VIII, subpt. B, § 403 (4.0.0), § 403 (1)(r); Proposed Tariff, Part III (NITS) (4.0.0)).
696 Id. (citing PJM, Proposed Tariff, pt. VIII, subpt. B, § 403 (4.0.0), § 403(1)(r); Proposed Tariff, Part III (NITS) (4.0.0)).
697  Id. (citing PJM, Proposed Tariff, pt. IX.B (GIA), (0.0.0), Schedule O).
698  Id. (citing PJM, Proposed Tariff, pt. IX.B (GIA), (0.0.0), Schedule O).
699  PJM proposes the following definition of a Co-Located Generating Facility: "an existing or planned Generating Facility that is physically connected to a Co-Located Load. Any Generation Project Developer with an effective Service Agreement that plans to use a Generating Facility to serve Co-Located Load must provide PJM and the Transmission Owner with advance written notice to begin the Necessary Studies process provided in Tariff, § VIII.A 401(H)(3)(b). If such a Generation Project Developer has an effective Interconnection Service Agreement pursuant to Tariff, Part VI or a Generation Interconnection Agreement pursuant to Tariff, Part VII, such agreement must be 303 of 515

PDF page 13

Document AccessigIP; 22q-Aqq18 _3P9cUrnerlt:FlAd rPa g9:A-0,/18/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 147 -
in Part VIII, Subpart A, section 400 of the Tariff. PJM asserts that these proposed revisions to the Tariff are "superior to or consistent with the Commission's directive because it promotes tariff readability and usability."700

c. Definition of Non-Retail BTMG
296.
PJM states that it is also seeking to avoid any inadvertent changes to the substantive rules pertaining to Non-Retail BTMG.701  For this reason, PJM proposes to add clarifying language in Tariff, Part III, section 34.3 providing that "The daily load of a Network Customer does not include load served by operating Non-Retail Behind The Meter Generation."702  PJM states that this insertion preserves the status quo on this issue for Non-Retail BTMG.

3. Pleadings
a. Definition of Co-Located Load
297.
Constellation urges the Commission to reject PJM's proposal to replace the term "Point of Interconnection" in the definition of Co-Located Load with the "Point of Change in Ownership."703  Constellation argues that changing the specific definition of Co-Located Load already approved by the Commission in the December Order is outside the scope of compliance. Constellation asserts that Point of Change in Ownership is not a defined physical point and may lead to delays or discrimination against certain Co-Location Arrangements. Constellation states that, alternatively, if the Commission accepts PJM's proposed definition of Co-Located Load, it should (1) direct PJM to revise its Tariff to provide that PJM will determine the Point of Change in Ownership if parties cannot agree; (2) establish deadlines for parties to mutually agree to, or for PJM to determine, the location for Point of Change in Ownership; (3) ensure that the location selected for the Point of Change in Ownership does not eliminate the load from being Co-Located Load unless the Project Developer and Co-Located Load desire it; and superseded by a Generation Interconnection Agreement pursuant to Tariff, Part VIII and the pro forma GIA in Part IX, Subpart B." PJM, Proposed Tariff, § VII.A 300 (Definitions C) (4.0.0); § VIII.A 400, Definitions C (4.0.0).

700 Compliance Transmittal at 29-30. "1  Id at 16.
702 Id
703 Constellation Protest and Comments on Compliance Filing at 2. 304 of 515

PDF page 14

Document AccessigPSA 2AAZI.8-3Wcument:Flild rpaqgp: APA812PAe Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 148 -
(4) not tolerate any discrimination or delay and use its enforcement authority or other mechanisms to ensure non-discriminatory open access.704

298.
Constellation asserts that recent experience has borne out the concern raised in its initial protest that PJM's deviation from the Commission's definition of Co-Located Load will allow transmission owners to effectively block Co-Location Arrangements.7°5 Constellation states that a transmission owner recently notified Constellation that it would not study Constellation's proposed design for a Co-Location Arrangement unless Constellation agreed to transfer ownership of certain facilities to the transmission owner, which would mean that the load would no longer be on the generator's side of the Point of Change in Ownership.706  Constellation argues that, by conditioning the load's interconnection on the transmission owner's ownership of those facilities, the transmission owner would prohibit Constellation's ability to host Co-Located Load at the site and limit the ability of the Co-Located Load to access the transmission services adopted in the December Order.

299.
Vistra requests that the Commission reject PJM's use of "Point of Change in Ownership" in its proposed definition of Co-Located Load.707  Vistra argues that PJM's proposed revision to the definition of Co-Located Load creates uncertainty and an opportunity for transmission owners to unduly discriminate against certain customers. Vistra requests that, if the Commission accepts PJM's proposed definition, then the Commission should direct further compliance to prevent undue discrimination.708 300.

Energy Artisans oppose PJM's definition of Co-Located Load and its use of Point of Change in Ownership rather than Point of Interconnection as arbitrary and a pretext for cost shifting.709  Energy Artisans allege that the definition "is strategically designed to shrink the legal definition of the facility boundary, thereby capturing more load for grid-service billing and excluding it from the BTMG actual use category."71° 7°4  Id. at 3-5, 7-8.

7°5  Constellation Supplemental Protest of Compliance Filing at 2.
7°6  Id. at 3.
7°7  Vistra Protest of Compliance Filing at 17.
708  Id. at 18-19. 7°9  Energy Artisans Protest of Compliance Filing at 2. 71°  Id. 305 of 515

PDF page 15

Document Accessig#Pr; -q-230,A18-3P.9.cument:Flild rpa'qg:(360A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 149 -
b. Generation Interconnection Procedures, pro forma GIA,
and Common Service Provisions
301.
Invenergy argues that PJM proposes to continue operating a bifurcated study process in which there is no requirement for generator interconnection and transmission service request studies to be conducted in concert, on similar time frames, or using similar study assumptions. As a result, Invenergy contends that distinct studies may identify duplicative or unnecessary Network Upgrades. Invenergy requests that the Commission and PJM clarify how the definition of Eligible Customer applies to co-located generators and co-located loads.7Il

302.
Constellation urges the Commission to direct PJM to revise its proposed definition of Co-Located Generating Facility to clarify that the definition only applies to the portion of the facility serving and physically connected to the Co-Located Load."' c. Definition of Non-Retail BTMG

303. AMP argues that PJM's proposed revision to the definition of Non-Retail BTMG could be construed as preventing generating units that are merely eligible for application of the Non-Retail BTMG rules from participating in Co-Located Load configurations. Specifically, AMP asserts that the use of the word "qualifies" in the proposed definition of Non-Retail BTMG may exclude generation from participating in Co-Located Load configurations even if the generator is not engaged in netting. AMP argues that this apparently unintentional exclusion would restrict Co-Located Load from accessing service from a broad set of PJM generators. AMP avers that revising the Non-Retail BTMG definition is unnecessary and outside the scope of the Commission's compliance directives. AMP urges the Commission to reject the proposed definition of Non-Retail BTMG or, alternatively, revise the definition to specify that the exclusion applies to generators both qualifying as Non-Retail BTMG and being used for netting under the Tariff.713

d. Timing with Planned Reliability Backstop Auction
304. The Maryland OPC urges the Commission to defer action on PJM's proposed revisions until PJM announces details regarding its planned reliability backstop auction, including specifics on how the reliability backstop auction will interact with Co-Location Arrangements to ensure that new Co-Located Loads pay the costs of any new capacity. 711  Invenergy Comments on Compliance Filing at 3, 6.

712  Constellation Protest and Comments on Compliance Filing at 17.
713  AMP Limited Protest of Compliance Filing at 3, 5-8. 306 of 515

PDF page 16

Document Accessig@SA:  2AAFR18-3Q9cument:Flild ja@g: A0A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 150 -
The Maryland OPC argues that the proposed Tariff revisions fail to explain how increased capacity costs of allowing existing generators to serve Co-Located Load, as opposed to new generators, will be paid by Co-Located Load and not by existing ratepayers.714

4. Answers
305.
In response to Invenergy, Indicated TOs argue that the Commission should not mandate a combined interconnection and transmission study process for Co-Located Loads and Co-Located Generators. Indicated TOs contend this goes beyond the issues the Commission set for hearing, as well as the compliance directed, in the December Order. Indicated TOs argue that PJM's proposed coordinated study approach is just and reasonable.715

306.
Exelon argues that Constellation's motion for supplemental protest should be denied because it suggests that Constellation's experience with one transmission owner implies a universal policy. Exelon states that it is not attempting to prevent large loads, co-located or otherwise, and their load serving entities from receiving transmission service in Exelon's territories. Exelon also argues that whether a transmission owner owns certain equipment does not necessarily inform where the Project Developer's interconnection facilities connect to the transmission owner's interconnection facilities.'"

5. Determination
a. Definition of Co-Located Load
307. As in the Commission's order addressing PJM's first compliance filing with the December Order, we reject PJM's proposed change to the definition of Co-Located Load.717  We note that no party, including PJM, sought rehearing or clarification of this directive, let alone the definition, in response to the December Order. Even here, PJM does not allege that the definition of Co-Located Load set out in the December Order is unjust and unreasonable. Rather, PJM proposes to deviate from this definition by replacing the term "Point of Interconnection" with "Point of Change in Ownership"

714  Maryland OPC Protest of Compliance Filing at 10-11.
715  Indicated TOs April 24 Answer at 4-5. 716  Exelon Answer at 1, 5-6.
717  PJM Interconnection, L.L.C., 195 FERC ¶ 61,030; PJM, Proposed Tariff, § I.1 Definitions C-D (Co-Located Load) (46.0.0); § VII.A 300, Definitions C (Co-Located Load) (4.0.0); § VIII.A 400, Definitions C (Co-Located Load) (4.0.0). 307 of 515

PDF page 17

Dodument Acce„igPg 2:41
8 - 3P9.9Unlent:FlAd LPA99: A0A.8 / 2 pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 151 -
without sufficient explanation as to how this proposed deviation complies with the Commission's directive in the December Order.718

308.
Accordingly, we direct PJM to file, within 60 days of the date of issuance of this order, a compliance filing that revises the Tariff's definition of Co-Located Load to use "Point of Interconnection" instead of "Point of Change in Ownership," consistent with the Commission's directive in the December Order.

b. Generation Interconnection Procedures, pro forma GIA,
and Common Service Provisions
309.
We accept the following of PJM's proposed revisions to establish rules for Interconnection Customers serving Co-Located Load as complying with the December Order: (1) adding to the list of requirements for a New Service Request that an Interconnection Customer who will use its generator to serve Co-Located Load must specify an Eligible Customer who will take transmission service on behalf of the Co-Located Load;719  (2) establishing a new schedule in the pro forma GIA that serves as a placeholder for specifying any operational procedures or data exchange requirements that PJM deems necessary for Co-Location Arrangements;72°  (3) applying these requirements to all Interconnection Customers requesting to interconnect their generators to the transmission system and seeking to use those facilities to serve Co-Located Load;721  (4) clarifying that to the extent that an Interconnection Customer wishes to serve Co-Located Load using its generator but not identify an Eligible Customer, then the Interconnection Customer may take steps to terminate its generator's interconnection to the PJM transmission system and serve the Co-Located Load fully islanded from PJM's

718  See, e.g., PJM Interconnection LLC, 119 FERC ¶ 61,179 at P 12 ("The purpose of a compliance filing is to make the directed changes and the Commission's focus in reviewing them is whether they comply with the Commission's previously stated directives.") (citing AES Huntington Beach, LLC, 111 FERC ¶ 61,079 at P 60 & n.25).
719  See December Order, 193 FERC ¶ 61,217 at P 188; PJM, Proposed Tariff, pt. VIII, subpt. B, 403 (4.0.0), § 403(1)(r). 728  See December Order, 193 FERC ¶ 61,217 at P 188; PJM, Proposed Tariff, Part IX.B, Schedule O (0.0.0). PJM explains that it proposes to add a new schedule in the pro forma GIA in the form of a placeholder for such information as the case may require. Compliance Transmittal at 29. We also accept conforming changes to Tariff, Part IX.B, GIA Appendices and Schedules.
721  See December Order, 193 FERC ¶ 61,217 at P 189; PJM, Proposed Tariff, pt. VIII, subpt.B, 403 (4.0.0), § 403(1)(r). 308 of 515

PDF page 18

Document Accessigt?Sg 22Q12-V;g18-349c ument:FlAdriApA
8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 152 -
transmission system;722  and (5) revising the pro forma GIA to specify that an Interconnection Customer that will use its generator to serve Co-Located Load must specify an Eligible Customer that will take transmission service on behalf of the Co-Located Load.723

310. However, we reject PJM's proposed revisions to comply with the Commission's directive in the December Order to require Interconnection Customers with ISAs or GIAs executed (or requested to be filed unexecuted) prior to the effective date of the revised generation interconnection procedures and pro forma GIA directed in that order that wish to add Co-Located Load or are currently serving Co-Located Load to publicly notify PJM of that addition and identify the Eligible Customer that will take transmission service on behalf of that Co-Located Load.724  Consistent with our discussion above in Part V.C.4, we agree with protesters that PJM's proposed revisions here go beyond the directives in the December Order by requiring Interconnection Customers with existing ISAs or GIAs that are currently serving Co-Located Load or wish to add Co-Located Load (and have executed Necessary Study Agreements) to initiate a new Necessary Study process and enter into a new GIA—which the December Order did not require.725  Therefore, while we appreciate PJM's intent to promote Tariff readability and usability, we find that PJM's language in the definition of Co-Located Generating Facility does not comply with the December Order, consistent with our findings regarding the same language in Part III of the Tariff.726  We further find that PJM has failed to include a general provision in the Tariff to comply with the Commission's directive in the December Order to require Interconnection Customers with ISAs or GIAs executed (or requested to be filed unexecuted) prior to the effective date of the revised generation interconnection procedures and pro forma GIA directed in that order that wish to add Co-Located Load or are currently serving Co-Located Load to publicly notify PJM of that addition and

722  See December Order, 193 FERC ¶ 61,217 at P 189; PJM, Proposed Tariff, pt. VIII, subpt. B, § 403 (4.0.0), § 403(1)(r).
723  See December Order, 193 FERC ¶ 61,217 at P 190; PJM, Proposed Tariff, pt. IX (GIA), subpt. B, Schedule O (0.0.0).
724  See December Order, 193 FERC ¶ 61,217 at P 191; PJM, Part III (NITS) (4.0.0); § VII.A 300, Definitions C (Co-Located Generating Facility) (4.0.0); § VIII.A 400, Definitions C (Co-Located Generating Facility) (4.0.0). We note that the definition of Co-Located Generating Facility in § I.1 Definitions C-D does not include the language that we are rejecting here.
725  See, e.g., Vistra Protest of Compliance Filing at 4, 14.
726  See supra Part V.C.4. 309 of 515

PDF page 19

Dodument Acceb6ig:PSA: q§-2Yaq18-31--28.cument:FlAd
A1/0.8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 153 -
identify the Eligible Customer that will take transmission service on behalf of that Co-Located Load, separate from the Necessary Study process.

311.
Therefore, we direct PJM to submit a compliance filing within 60 days of the date of issuance of this order to: (1) revise the definition of Co-Located Generating Facility to remove the following requirement: "If such a Generation Project Developer has an effective Interconnection Service Agreement pursuant to Tariff, Part VI or a Generation Interconnection Agreement pursuant to Tariff, Part VII, such agreement must be superseded by a Generation Interconnection Agreement pursuant to Tariff, Part VIII and the pro forma GIA in Part IX, Subpart B," and (2) add to Part III a requirement that Interconnection Customers with ISAs or GIAs executed (or requested to be filed unexecuted) prior to the effective date of the revised generation interconnection procedures and pro forma GIA directed in December Order that wish to add Co-Located Load or are currently serving Co-Located Load publicly notify PJM of that addition and identify the Eligible Customer that will take transmission service on behalf of that Co-Located Load.

312.
We disagree with Constellation that PJM's proposed definition of Co-Located Generating Facility should only apply to the portion of the facility that is serving Co-Located Load. Constellation claims that the definition does not recognize that the entire facility may not serve the Co-Located Load, but Constellation has not identified any substantive concern with that outcome. We find the proposed definition is broad enough to capture both scenarios. Further, PJM's proposed Tariff language recognizes this possibility elsewhere, such as, for example, Part IX, Subpart A Form of Application and Studies Agreement, section 2, which leaves a space for the Interconnection Customer to list both the Co-Located Load and any requested CIRs.

313.
With respect to Invenergy's request that PJM perform generator interconnection and transmission service request studies in concert, we note that the December Order did not direct PJM to create such a new study process. Thus, we find that Invenergy's request is beyond the scope of this proceeding.

c. Definition of Non-Retail BTMG
314.
We agree with AMP that PJM's proposed revisions to the definition of Non-Retail BTMG may inadvertently prevent generators that could merely qualify as Non-Retail BTMG from participating in Co-Location Arrangements, regardless of whether the generator is being used to net. As PJM recognizes, the December Order "did not direct any changes to Non-Retail BTMG rules."727  PJM did not provide any justification for its proposed changes to the definition of Non-Retail BTMG, nor did the Commission direct

727  Compliance Transmittal at 7. 310 of 515

PDF page 20

Document AccessicIPW 12-Vg18_ 31:AlcUment:FlAd  ifa@gp: A1A 8 /2-Ate F i I ed 10/16/2026 Docket No. EL25-49-002, et al.

- 154 -
any changes to PJM's rules for Non-Retail BTMG in the December Order.728  Therefore, we reject PJM's proposed revisions to the definition of Non-Retail BTMG and direct PJM to file, within 60 days of the date of issuance of this order, a compliance filing to revise its Tariff to remove the proposed changes, consistent with the December Order's determination. 729

d. Timing with Planned Reliability Backstop Auction
315. As discussed below, we decline Maryland OPC's request that the Commission defer action.73°  We find that Maryland OPC's concerns about PJM's capacity market are beyond the scope of this compliance proceeding, which pertains solely to PJM's compliance with the Commission's directives in the December Order.

E. Effective Date
1. PJM Compliance Filing
316. PJM requests a placeholder effective date of 12/31/9998 because PJM cannot implement the Tariff changes until the Commission sets the terms and conditions of the new transmission services in the paper hearing.731  PJM states that it will submit a clean-up filing proposing an effective date after the Commission issues an order on the paper hearing.732

2. Effective Date Pleadings
317. Though Vistra says it will address PJM's proposed June 1, 2029 effective date in its paper hearing brief, Vistra argues in its protest of the compliance filing that PJM has not shown that its proposed effective date is just and reasonable.733  Vistra alleges that the three-year forward capacity market schedule cannot justify a delay in the provision of

728  December Order, 193 FERC ¶ 61,217 at P 222 ("We clarify we do not direct PJM to change its rules for non-retail BTMG."). 729  PJM, Proposed Tariff, § I.1 Definitions L-M-N (Non-Retail Behind The Meter Generation) (52.0.0). 73°  See supra Part VI.K.2.
731  Compliance Transmittal at 35.
732  Id. at 35-36.
733  Vistra Protest of Compliance Filing at 7. 311 of 515

PDF page 21

Dodument AcceesigiPA: gq-2-TZA18-3R9ument:Flil d rpaqg:A1A.812 pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 155 -
non-capacity-backed transmission service. Vistra also contends that the forecasts for the 2027/2028 and 2028/2029 Base Residual Auctions (BRA) include the new large loads likely to come online in that timeframe, undermining PJM's position that the capacity market schedule should delay the provision of firm transmission service. Vistra also argues that PJM has not explained why it will take until 2029 to update its software to accommodate the new curtailment logic.

318.
DCC argues that PJM's effective date should be earlier than June 1, 2029.734  DCC argues that PJM should work with stakeholders to implement workable solutions in a timely manner that ensures the transmission services can meet the immediate need within the PJM region.

3. Determination
319.
As discussed below in Part VI.J, we direct PJM to submit, within 60 days of the date of issuance of this order, a further compliance filing providing additional information on the effective date.

VI. Paper Hearing
320.
The Commission directed PJM to modify its Tariff to require that the Eligible Customer taking transmission service on behalf of a Co-Located Load takes one of three transmission services: (1) NITS or Interim NITS, (2) FCD transmission service, or

(3) NFCD transmission service.735  With respect to the new transmission services that the Commission required, the Commission established paper hearing procedures to determine the appropriate rates, terms, and conditions of those transmission services.736  PJM did not file tariff revisions in eTariff, but rather, chose to submit illustrative tariff revisions that mirror the arguments PJM filed in its initial brief as part of that brief. The illustrative tariff is not filed as a rate with the Commission, but we consider it as part of the record in response to the paper hearing as we establish the replacement rate set forth below. As discussed in detail below, as the replacement rate, we direct PJM to submit within 60 days of the date of issuance of this order, a compliance filing revising its Tariff to include rates, terms, and conditions for the new transmission services consistent with our findings in the below sections.

734  DCC Comments on Compliance Filing at 7.
735  December Order, 193 FERC ¶ 61,217 at P 193.
736  Id. PP 194, 203, 207, 219. 312 of 515

PDF page 22

Document Accessig@SA:  A2118-349curnent:FlAd rf)a@g:A1,48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 156 -
A. Rates, Terms, and Conditions for Firm and Non-Firm Contract
Demand Transmission Service
1. December Order
321.
With respect to FCD transmission service and NFCD transmission service, the Commission found in the December Order that these transmission services should be permanent transmission services available to Eligible Customers taking transmission service on behalf of Co-Located Load.737  The Commission further stated that for the Eligible Customer taking transmission service on behalf of a Co-Located Load to be eligible for these new transmission services, the Co-Located Load must be able and willing to prevent or limit its energy withdrawals and must be separately metered from the associated generator.738  The Commission also stated that Eligible Customers taking transmission service on behalf of Co-Located Loads may take a combination of FCD transmission service and NFCD transmission service, but that Eligible Customers taking transmission service on behalf of Co-Located Loads that will not withdraw energy from the transmission system must take NFCD transmission service at 0 MW.739  The Commission also found that Eligible Customers taking either transmission service on behalf of Co-Located Loads would be charged for regulation and black start services based on gross demand, rather than the reserved amount of transmission service.740 322.

The Commission found that FCD transmission service should have the same reservation and curtailment priority as existing firm transmission services at the level of the contract demand and be charged for transmission, ancillary services, and capacity based on the contract demand, with the exception of regulation and black start services."' With respect to NFCD transmission service, the Commission found that the service should be available during normal operations and curtailed during emergency operations, similar to existing non-firm transmission service options.742

737  Id. P 206.
738  Id.
739  Id.
740 Id. PP 209, 216. 741  Id. PP 208-209.
742 1d P 215. 313 of 515

PDF page 23

Document AccessigiSA: 22Wcp,A18 _ 39pcument:FlAd rFa'qg9: A1A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 157 -
2. Nature of FCD and NFCD Transmission Services
a. Initial Briefs
323.
PJM proposes to define FCD transmission service as the transfer of capacity and energy for an Eligible Customer on behalf of a designated Co-Located Load, up to a defined, pre-determined MW level of transmission service as requested by the Eligible Customer and confirmed by PJM, using capacity and energy procured by PJM.743  PJM proposes to define NFCD transmission service as a service offering the transmission of energy for an Eligible Customer on behalf of a designated Co-Located Load, on an as-available basis, up to a defined, pre-determined MW level of transmission service as requested by the Eligible Customer and confirmed by PJM, using energy procured by PJM 744

324.
PJM states that it has conceptualized the FCD and NFCD transmission services based on two key principles: (1) the services are designed to serve loads willing and able to control their withdrawals from the transmission system, and (2) the services are designed to allow PJM to maintain system reliability.745  PJM explains that, to maintain reliability, any portion of the gross demand of the Co-Located Load not served by the Co-Located Generator must be covered by FCD transmission service. PJM also states that, to ensure reliability, PJM's studies of the transmission service requests for the Co-Located Load must capture the effects of any unscheduled energy withdrawals and validate that such events would not jeopardize system reliability.746  PJM then asserts that, if the Co-Located Load's gross demand is not covered by FCD transmission service, then the Eligible Customer must cover the remaining gross demand by applying for NFCD transmission service. PJM further states that an Eligible Customer taking service on behalf of a Co-Located Load must request NFCD transmission service equal to the MW level of the Co-Located Generating Facility dedicated to serving the Co-Located Load, so that the customer is eligible to obtain NFCD transmission service if the Co-Located Generating Facility is on outage.747  PJM states that it anticipates that, in practice, requests for NFCD transmission service will be at the MW level that the Co-Located Generating Facility has dedicated to serving the Co-Located Load. PJM states that the Eligible Customer may then, on any given day, reserve NFCD transmission

743  PJM Initial Brief at 13. 744  Id at 30.
745  Id. at 6.
746  Id at 6-7.
747  Id. at 9, 16. 314 of 515

PDF page 24

Document Accessig@SA 2,4-2-VA18-34Kument:Flil d  MiLe:A1A8/2pAte Fled: 10/16/2026 Docket No. EL25-49-002, et al.

- 158 -
service up to the amount specified in the Service Agreement, but only when PJM has determined there is available transmission capacity. If there is not sufficient capacity to grant the request for NFCD transmission service, PJM explains the Eligible Customer may apply for FCD transmission service for the necessary amount, or NITS to serve the entire Co-Located Load.748  PJM maintains that its approach provides flexibility, allowing Eligible Customers to mix and match FCD and NFCD transmission services, so long as the combination of the two services covers the entire gross demand of the Co-Located Load.749

325.
PJM argues that, to prevent FCD and NFCD transmission services from adversely impacting system reliability, it is crucial for the Eligible Customer to show and prove its ability to limit withdrawals from the system. PJM maintains that, for FCD transmission service to properly function, it is essential that any NFCD transmission service for the same Co-Located Load has in place necessary control technologies and/or protective systems approved by PJM and that can effectively limit withdrawals from the transmission system that serve the Co-Located Load.75°  PJM proposes to require Eligible Customers taking NFCD transmission service to work with PJM and the affected Transmission Owners to establish necessary control technologies and protection systems for each Service Agreement to ensure reliability.751

326.
PJM explains that FCD transmission service will have priority over NFCD transmission service and equal priority, at the level of the contract demand, with other firm transmission services, including NITS. PJM proposes that NFCD transmission service be curtailed before FCD transmission service and NITS, as discussed further below, and proposes to curtail NFCD transmission service prior to dispatching Pre- Emergency Load Response Program resources or in response to a transfer capability shortage.752

748  Id at 32-33.
749  Id. at 11. 758  Id. at 15, 31.
751  Id. at 34-35.
752  Id at 15, 34. 315 of 515

PDF page 25

Document AccessigPit; 22q2 06A18 _3PWUMent:FlAd  diaN: 0361A8/2PAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 159 -
b. Response Briefs
327.
Indicated TOs support PJM's proposal to require Eligible Customers taking service on behalf of Co-Located Load to take a combination of FCD and NFCD transmission services equivalent to the entire gross demand of the Co-Located Load.753 328.

However, a number of parties protest PJM's proposed requirement that NFCD transmission service be available only when the Co-Located Generating Facility is on an outage.754  Parties argue that the December Order does not impose such a limit on this transmission service and that PJM provides no justification for the change.755  AEU/SEIA contend that the December Order required that NFCD transmission service be available "as needed during normal, non-emergency system operating conditions," and that, while it cited the use of NFCD transmission service during an outage as one potential use case, the December Order did not impose the limitation described in PJM's proposed Tariff revisions.756  AEU/SEIA claim that the practical consequences of this limitation are significant, particularly for Co-Located Loads served by resources with variable or intermittent output profiles, which may require supplemental grid withdrawals during any period in which the Co-Located Generator's output is constrained, reduced, or otherwise insufficient to meet the full gross demand of the Co-Located Load. AEU/SEIA argue that this gap in the availability of NFCD transmission service will force many transmission customers to take NITS.

329.
AEU/SEIA contend that PJM attempts to justify this restriction on operational and planning complexity grounds, but argues that the Commission considered these objections before the December Order and nonetheless required PJM to provide NFCD transmission service.757  AEU/SEIA also contend that this restriction cannot be justified on resource adequacy or reliability grounds, because NFCD transmission service is

753  Indicated TOs Response Brief at 4; Industrials/Amtrak Response Brief at 24.
754  Joint Co-Location Developers Response Brief at 6-13; AEU/SEIA Response Brief at 5; Vistra Response Brief at 25; DCC Response Brief at 4; Constellation Response Brief at 10.
755  Vistra Response Brief at 26; AEU/SEIA Response Brief at 5-6; Joint Co-Location Developers Response Brief at 7; DCC Response Brief at 5; Constellation Response Brief at 10.
756  AEU/SEIA Response Brief at 6-8 (citing December Order, 193 FERC ¶ 61,217 at PP 214-215); Joint Co-Location Developers Response Brief at 6-7.
757  AEU/SEIA Response Brief at 8-10 (citing PJM March 24, 2025 Response at 13-15). 316 of 515

PDF page 26

Document Accessigi?Sg 2A-2-VA18-3Q8Cument:Flitd rpa@p: A1/3.8/2  pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 160 -
designed to be curtailed before firm transmission services and is available only when transmission capacity exists. AEU/SEIA therefore request that the Commission direct PJM to revise and file Tariff revisions that remove the outage-only limitation and allow for the use of NFCD transmission service on an as-available basis during normal, non-emergency system operating conditions and subject to available transmission capacity and appropriate curtailment priority.

330.
Joint Co-Location Developers argue that PJM's proposal undermines economic efficiency, restricts competition, may threaten reliability for other customers, and is unclear as applied to partial outages.758  Joint Co-Location Developers maintain that PJM's proposal is inconsistent with its other transmission service offerings, such as PTPS, which is not designed based on whether generation is on an outage. Joint Co-Location Developers add that PJM's Interim NITS proposal shows PJM's ability to offer non-firm service during normal conditions without the need to request a reservation. 331.

DCC argues that PJM's proposal effectively confines NFCD transmission service to a narrow, outage-only function and prohibits its use to address foreseeable and manageable transmission constraints. DCC argues that PJM has not demonstrated why NFCD transmission service that is (a) requested in advance, (b) subject to PJM approval,

(c) fully curtailable, and (d) supported by required protection and control mechanisms, may appropriately be used to address generator outages but may not be used to address temporary transmission constraints.759

332.
Constellation also criticizes PJM's view that this proposal is needed to avoid overuse and responds that the Commission indicated that penalty charges should solve that concern.'"

333.
Constellation also protests PJM's proposal to require FCD transmission service for any portion of the Co-Located Load not served by the Co-Located Generating Facility. Constellation argues that the Commission established no such requirement, nor did the Commission require that Eligible Customers take FCD transmission service along with NFCD transmission service.'"

758  Joint Co-Location Developers Response Brief at 8-11.
759  DCC Response Brief at 5. 760  Constellation Response Brief at 11-12. 761  Id. at 10, 12. 317 of 515

PDF page 27

Document AcceseigiStg,4-q-A6, 318 _31-.29cUrnellt Flild EPa g9:A-1A8/2 pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 161 -
334.
DCC argues that PJM's proposal does not provide a workable pathway for phased development or load ramping.762  DCC argues that PJM's proposal requires that gross load and generation configurations be specified upfront and treats material changes in those configurations as requiring new applications and studies while prohibiting the mixing of NITS and Contract Demand transmission services for the same load. DCC argues that, while PJM has acknowledged limited flexibility in certain circumstances, it does not provide a clear or workable pathway for customers to (a) ramp load over time,

(b) transition between service constructs, or (c) seek to align transmission service with phased project development. DCC argues that the absence of a defined ramping framework introduces uncertainty, increases the risk of delay, and may require repeated study cycles that are not aligned with project timelines. DCC argues that the Commission should require PJM to establish clear rules and processes that enable incremental load additions without triggering unnecessary re-study or requiring customers to fundamentally restructure their service arrangements.763

335.
Market Monitor argues that the assumption underlying NFCD transmission service, that load pays for transmission only when it needs transmission, is untenable.764 Market Monitor states that although NFCD transmission service can only be a standby service, the equivalent availability factor of generators in PJM demonstrates that NFCD transmission service would have to be used regularly. Market Monitor argues that if all or a significant part of data center users wanted to use NFCD transmission service, the system would become unmanageable and the service would not be available consistently, making it meaningless. Market Monitor asserts that there can be no such service as NFCD transmission service that is fully consistent with maintaining a reliable PJM transmission system, and all transmission customers should pay for full NITS service. c. Reply Briefs

336.
PJM argues that its proposal to limit NFCD transmission service to circumstances where the Co-Located Generator is on outage is just and reasonable, consistent with the December Order, and otherwise appropriate. PJM argues that, if customers could take unlimited NFCD transmission service, that would be tantamount to offering Interim NITS permanently.765  PJM next argues that the Commission stated in the December Order that NFCD transmission service would be available "as needed" for customers able to limit withdrawals, which suggests the Commission did not intend for this service to be used on

762  DCC Response Brief at 6.
763  Id. at 6-7.
764  Market Monitor Response Brief at 5-6.
765  PJM Reply Brief at 6-7. 318 of 515

PDF page 28

Document Accessigi
2442-YRA1 8 - 3R9 I-Irnent:Flita Eaq99: A1/48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 162 -
an everyday basis.766  Moreover, PJM argues, its proposal is appropriate given the inherent risks to the transmission system and operational complexities associated with providing this service continuously, given the limited time period the non-firm service will be required. PJM asserts that the transmission system is not planned and designed to accommodate these non-firm services under North American Electric Reliability Corporation (NERC) reliability standards.

337.
PJM maintains that several aspects of NFCD transmission service are challenging from a reliability perspective, given the range of requirements of NERC reliability standards. PJM alleges that the nature of NFCD transmission service dictates that PJM will not include this service in PJM's long-term transmission planning and the system will not be evaluated for potential Corrective Action Plans, nor will PJM have procured capacity to serve this load.767  PJM also claims that, because NFCD transmission service relies on transmission capacity that is not currently used, PJM is unlikely to be in a position to provide this service during peaks or other times when the system is operating under stressed conditions. PJM argues that, from a transmission planning perspective, NFCD transmission service increases the operational risk of System Operating Limit and Interconnection Reliability Operating Limit (SOL/IROL) exceedances by operating the system with a reduced margin for contingency to accommodate high-volume loads.768 PJM contends that this operation increases the risk of an emergency occurring if unexpected conditions occur. PJM argues that providing NFCD transmission service will almost inevitably require significant adjustments to PJM's Operating Plan to mitigate exceedances of SOLs/IROLs each time service is provided due to the nature of the service. PJM maintains that, by definition, NFCD transmission service involves a customer drawing large quantities of power over transmission facilities that were not designed to serve that load and thus will almost certainly necessitate flowing power over various facilities near system limits.769

338.
Indicated TOs support PJM's proposals to restrict the use of NFCD transmission service to periods when on-site generation is on outage and claim that the Commission did not intend for this service to be a substitute for FCD transmission service or NITS for the portion of on-site load that will not be served by on-site generation. Indicated TOs argue that there is no compelling reason for NFCD transmission service to be available

766  Id at 7 (quoting December Order, 193 FERC ¶ 61,217 at P 215).
767  Id at 9-10.
768  Id at 11-12.
769  Id at 12-13. 319 of 515

PDF page 29

Document AccessigPsP; qq-Aqq-1.8-31;28curnent:Fhla 'PAP: cZq.812psIte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 163 -
during non-outage conditions.77°  Indicated TOs claim that limiting the use of NFCD transmission service is necessary to ensure the reliable operation of the PJM transmission system, particularly because of the increasing use of special protection schemes, remedial action schemes, and other control technologies and protective systems. Indicated TOs recommend that PJM clarify in the Tariff that an "outage" for these purposes is limited to periods where a generator is offline due to a breakdown or maintenance issues and does not cover other instances when a generator is not operating.771

339.
Joint Co-Location Developers urge the Commission to reject PJM's attempt to limit the availability of NFCD transmission service and require PJM to establish a NFCD transmission service product available during normal system conditions as required by the December Order.772  Joint Co-Location Developers contend that the workable non-firm transmission service offerings that are broadly available are fully consistent with reliable system operation, as demonstrated in other regions that are rapidly moving to implement non-firm transmission service offerings.773  Joint Co-Location Developers argue that limiting the scope of NFCD transmission service scheduling to generator outages, as PJM proposes, will increase reliance on simple withdrawal-limiting protection systems rather than decrease it because it will increase the frequency with which a customer will not be authorized to withdraw.774  Joint Co-Location Developers explain that this is because withdrawal-limiting protection systems are only active when the customer cannot withdraw, i.e., because no transmission service has been scheduled. Joint Co-Location Developers argue that PJM should limit the arming of remedial action schemes, or avoid installing them in the first place, and instead maximize use of pre-contingency NFCD transmission service curtailment through scheduling, which is similar to how Southwest Power Pool, Inc. (SPP) and Electric Reliability Council of Texas (ERCOT) envision curtailment under the non-firm transmission services that they are developing.775

340.
In response to DCC's concerns about phasing in Co-Located Load, PJM maintains that its proposal provides a workable pathway for phased development or load 77°  Indicated TOs Reply Brief at 3-4.

771  Id. at 5-6.
772  Joint Co-Location Developers Reply Brief at 10-11.
773  Id. at 1.
774  Id. at 7.
775  Id. at 8. 320 of 515

PDF page 30

Document AccessigOA 2Q2o18-31:2@ Urnent:FiAd M99: Ag118/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 164 -
ramping.776  PJM argues that the obvious path for Co-Located Load that increases over time is NITS, a transmission service designed to accommodate load growth. If an Eligible Customer elects Contract Demand transmission service, any change to the contracted amount would require a new service request. PJM adds that the Eligible Customer could elect to request Interim NITS or FCD transmission service for their full load amount ahead of time and use that capacity as their demand increases up to the applied for service level. PJM explains that the Commission directed PJM to offer FCD and NFCD transmission services as an alternative to NITS; thus, it is reasonable for this new service to not accommodate load growth as NITS does.

d. Answer
341.
Geronimo Power asserts that PJM's proposed restrictions on NFCD transmission service are inconsistent with the December Order and should be rejected.777  In response to PJM's and Indicated TOs' concerns with making this service more broadly available, Geronimo Power argues that PJM does not need to expand its transmission system or otherwise change its operations to accommodate this load; rather, it merely needs to allow such load to take transmission service when it is available.778  Geronimo Power argues that the effect of PJM's proposal will be to severely limit co-location opportunities in PJM, because large loads will need to either co-locate with a resource that can be called upon at all times or to take NITS or FCD transmission service that will result in the same inefficient and costly grid buildout that the December Order sought to avoid.779 e. Determination

342.
As discussed below, we find that PJM's proposal does not comply with the Commission's directives in the December Order and would fundamentally alter the nature of the FCD and NFCD transmission services that the Commission directed PJM to develop. PJM proposes to require that the Eligible Customer taking transmission service on behalf of a Co-Located Load must take sufficient transmission service to account for the entire gross demand of the Co-Located Load.78°  PJM states that an Eligible Customer taking service on behalf of a Co-Located Load must request NFCD transmission service equal to the MW level of the Co-Located Generator dedicated to serving the Co-Located

776  PJM Reply Brief at 37-38.
777  Geronimo Power May 21 Answer at 4.
778  Id. at 6.
779  Id. at 7. 78°  PJM Initial Brief at 6, 9. 321 of 515

PDF page 31

Document A„e6§-3:gi Sg qq-AqA1 - 31:299Urnent:Filtd Iraqg9:W.A8 / 2 pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 165 -
Load, so that the customer is eligible to obtain NFCD transmission service if the Co-Located Generator is on outage.781  PJM also explains that any portion of the gross demand of the Co-Located Load not served by the Co-Located Generator must be covered by FCD transmission service.782  This proposal would tie the amount of FCD and NFCD transmission services that an Eligible Customer can request to the size of the Co-Located Generator, rather than allowing the Eligible Customer to select any amount, including 0 MW for NFCD transmission service, as the Commission directed. Specifically, the December Order stated that Eligible Customers on behalf of Co-Located Loads would be able to take a combination of FCD and NFCD transmission services, but that "Eligible Customers taking transmission service on behalf of Co-Located Loads that will not withdraw energy from the transmission system must take [NFCD] transmission service at 0 MW."783  PJM's proposal would do the opposite. An Eligible Customer taking transmission service on behalf of a Co-Located Load that wished to be served entirely by the Co-Located Generator, and not withdraw any energy from the transmission system, would be required under PJM's proposal to request NFCD transmission service at a level of contract demand equal to the Co-Located Load's gross load.784  Moreover, contrary to PJM's proposal, nothing in the December Order would require an Eligible Customer taking transmission service on behalf of a Co-Located Load to take FCD transmission service at a level of contract demand that reflects the amount of load not served by the Co-Located Generator (or, for that matter, to take FCD transmission service at all). In short, the December Order does not link the level of contract demand for either FCD or NFCD transmission service that an Eligible Customer may take on behalf of a Co-Located Load to the size of the Co-Located Generator or the size of the Co-Located Load.

343. Taken together, PJM's proposed new conditions on FCD and NFCD transmission services mean that if PJM determines as a result of studies that it cannot accommodate a request for NFCD transmission service, the Eligible Customer will be required to request and take a firm transmission service (FCD transmission service or NITS) on behalf of the Co-Located Load instead. In the December Order, the Commission directed PJM to implement FCD and NFCD transmission services in response to a finding that the Tariff is unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking service on behalf of Co-Located Loads that are willing and able to limit their energy withdrawals from the transmission system under certain 7811d at 9, 16.

782  Id at 6-7.
783  December Order, 193 FERC 1161,217 at P 206.
784  PJM Initial Brief at 9. 322 of 515

PDF page 32

Document Accessigf?Sg 2k2-W518-34@Cument:Flil d rpAg:Ag,48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 166 -
conditions.785  PJM's proposal does not address this finding and proposes to create FCD and NFCD transmission services that continue to fail to recognize this flexibility. Moreover, requiring an Eligible Customer seeking to take transmission service on behalf of a Co-Located Load to take FCD transmission service or NITS instead of NFCD transmission service when it does not seek to take firm transmission service would be inconsistent with the Commission's finding in the December Order that the lack of the required new transmission services could result in unnecessary, costly, and inefficient Network Upgrades, increasing Network Upgrade costs.786  While we recognize that PJM may determine that there is insufficient available transmission capacity to fulfill a request for NFCD transmission service,787  in that scenario, the Eligible Customer seeking to take that service on behalf of a Co-Located Load should then be able to decide whether it would prefer to request FCD transmission service or NITS to serve the load — in which case it may be responsible for Network Upgrade costs — or to take 0 MW of NFCD transmission service and thus have no contractual right to withdraw power from the transmission system.

344. PJM's proposal is also inconsistent with the December Order in that PJM proposes to limit the amount of NFCD transmission service that may be reserved by an Eligible Customer to a MW level equivalent to the amount of the Co-Located Generator that is on outage.788  The December Order did not require such a restriction and instead contemplated that NFCD transmission service would be available during "normal" operations when there is sufficient available transmission capacity,789  providing Eligible Customers seeking to take transmission service on behalf of Co-Located Loads the

785  December Order, 193 FERC ¶ 61,217 at P 193.
786  See id. P 177 ("[F]or Eligible Customers taking service on behalf of Co-Located Loads that do not reserve transmission or take energy from the transmission system but which receive only regulation and black start services, or that otherwise are willing and able to limit their energy withdrawals from the transmission system, requiring such Eligible Customers to take NITS on behalf of these Co-Located Loads may in some circumstances result in costly and inefficient transmission system buildout that may not be necessary if such Eligible Customers are willing and able to take a transmission service that requires fewer Network Upgrades to provide, and therefore may result in lower Network Upgrade costs, than would NITS.").
787  See id. P 215 (stating that reservations for NFCD transmission service "would be available only when there is available transmission capacity, similar to existing non-firm transmission service options in the Tariff').
788  PJM Initial Brief at 32.
789  December Order, 193 FERC ¶ 61,217 at PP 214-215. 323 of 515

PDF page 33

Document Accessig
2AAgg-18 _ 3Qacument:Flil d  gage:
L8/2
 to Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 167 -
flexibility to request to reserve any amount of NFCD transmission service, regardless of whether the Co-Located Generator was on outage. The Commission's reference to NFCD transmission service and generator outages was an example and not a threshold requirement for an Eligible Customer to use this service.790  Regardless, because the Commission contemplated that the service would be available during normal operations when there is sufficient available transmission capacity, Eligible Customers seeking to take NFCD transmission service on behalf of Co-Located Loads must be permitted to request such service on an everyday basis. Further, contrary to the December Order, PJM's proposal to allow Eligible Customers taking transmission service on behalf of Co-Located Loads to take NFCD transmission service only when the Co-Located Generator is on outage fails to reflect Eligible Customers taking transmission service on behalf of Co-Located Loads that are willing and able to limit their energy withdrawals from the transmission system under certain conditions because it removes the option to take NFCD transmission service instead of FCD transmission service for portions of the Co-Located Load that are not served by the Co-Located Generator.

345. PJM argues that these changes to NFCD transmission service are necessary for reliability, to ensure all load is studied. We disagree. Co-Located Load is, as defined in the December Order, behind the Point of Interconnection of an interconnected generator, and PJM would already know the size of the generator and any Co-Located Load from the interconnection process (or Necessary Study), and possibly the transmission service application process. While the portion of load for which the Eligible Customer does not request transmission service would not be modeled by PJM in a transmission service request as withdrawing energy from the transmission system, this outcome is appropriate because the Eligible Customer is not intending to withdraw energy from the transmission system. However, the potential impact of the Co-Located Load on the reliability of the transmission system will still be studied as part of the Necessary Study process for the generator interconnection modification, or as part of a New Service Request. PJM already conducts dynamic studies for Co-Located Load, which evaluate all applicable NERC, PJM, and transmission owner-specific contingencies and criteria, consistent with PJM's responsibilities to ensure system reliability.791  These studies utilize a composite load model that includes power electronics, cooling, and lighting loads, and the impact of the facility during this study is dependent on the physical parameters of the facility and

790 See id P 214 ("Eligible Customers taking service on behalf of such loads may, however, still seek to withdraw energy from the transmission system from time to time when transmission capacity is available and not needed by firm customers. For example, an Eligible Customer could seek a transmission reservation for a Co-Located Load in advance for the duration of an expected outage of the associated generator.") (emphasis added).
791  PJM March 24, 2025 Response at 53. 324 of 515

PDF page 34

Document AccessigPV; 2A2-Vg18-349cument:FiAd rEqv: ,vA812pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 168 -
its control behavior, not the level or type of transmission service taken.792  This model is a complete model of the facility.793  As such, PJM, as it currently does, will know the full impact of factors unrelated to the contract demand of the Co-Located Load, including impacts on stability margins, short circuit limits, power quality and harmonic distortion, voltage flicker, interaction of active power electronic controls with the system (e.g., mitigation of oscillatory behavior), impact of STATCOMs or other reactive compensation devices, and cyclical demand ramps in the sub-synchronous frequency range. PJM provides no explanation why this data already available to them is insufficient to fully study a Co-Located Load absent changes to NFCD transmission service.

346.
PJM also argues that providing NFCD transmission service will require adjustments to PJM's Operating Plan to mitigate exceedances of SOLs/IROLs each time service is provided due to the nature of the service. While serving load using NFCD transmission service may reduce operating margins on the transmission system, PJM has presented no evidence that changes to PJM's Operating Plan will be regularly needed. However, should PJM find, based on operating experience in implementing the NFCD transmission service, that significant and frequent manual adjustments are necessary, PJM may consider filing an FPA section 205 filing to adjust the curtailment priority of NFCD transmission service.

347.
PJM also argues that, by definition, NFCD transmission service involves a customer drawing large quantities of power over transmission facilities that were not designed to serve that load and thus will almost certainly necessitate flowing power over various facilities near system limits. While we acknowledge that NFCD transmission service is designed to use available transmission capacity that is not needed by firm transmission customers, we find that PJM's assertion that providing such service will necessitate flowing power over various transmission facilities near system limits is speculative. In any case, as the Commission stated in the December Order, "[r]eservations under this service would be available only where there is available transmission capacity, similar to existing non-firm transmission service options in the

792  Id. We note that NERC has recommended use of the Power Electronic Reconnecting and Ceasing (PERC1) model, which is a different model than the current model PJM utilizes. However, the general principles are the same. See NERC, Essential Action to Industry: Computational Load Modeling, Studies, Instrumentation, Commissioning, Operations, Protection, and Control at 3 (2026), https://www.nerc.com/globalassets/programs/bpsa/alerts/level-3-computational-load- alert.pdf.
793  See, e.g., PJM, PJM Dynamic Model Development Guidelines for Interconnection Analysis § 6, PJM Dynamic Model Development Guidelines. 325 of 515

PDF page 35

Document AcceeeigPSP:  qC)gis-3RPcument:FliLd YAP: AA.812pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 169 -
Tariff."794  And consistent with the Commission's findings in establishing non-firm transmission service under its pro forma Open Access Transmission Tariff, providing non-firm transmission service increases efficiency by allowing customers to use lumpy transmission investment on an as-available basis and may reduce the costs for firm transmission service customers by allowing NFCD transmission service customers to offset the costs of that investment.795  However, we note that if PJM determines that there may be increased operational risks associated with providing NFCD transmission service, it may address those risks by increasing the transmission reliability margin that it uses when studying and determining whether to grant requests for NFCD transmission service. 348.

We recognize that the new FCD and NFCD transmission services represent a significant change in how transmission service has been historically offered in PJM. We also recognize that significant changes to PJM's software may be necessary to integrate the FCD and NFCD transmission services, including to potentially automate some processes that are currently handled manually by operators with respect to curtailing non-firm transmission services. However, the Commission directed the new FCD and NFCD transmission services as the replacement rate after finding PJM's existing Tariff unjust and unreasonable. We therefore direct PJM to submit a compliance filing within 60 days of the issuance of this order proposing Tariff revisions to permit Eligible Customers to elect to take FCD transmission service or NFCD transmission service without the limitations that PJM proposes (i.e., (1) the requirement that the Eligible Customer taking transmission service on behalf of a Co-Located Load must take sufficient transmission service to account for the entire gross demand of the Co-Located Load, (2) the requirement for an Eligible Customer taking transmission service on behalf of a Co-Located Load to take FCD transmission service at a level of contract demand that reflects the amount of load not served by the Co-Located Generator, (3) the requirement that an Eligible Customer taking service on behalf of a Co-Located Load must request NFCD transmission service equal to the MW level of the Co-Located Generating Facility dedicated to serving the Co-Located Load if that portion of the Co-Located Load is not covered by FCD transmission service, and (4) the restriction on the use of NFCD transmission service to only those circumstances where the Co-Located Generator is on outage). Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the

794  December Order, 193 FERC ¶ 61,217 at P 215.
795  Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,272 (finding "non-firm transmission prices should reflect the interruptibility of the service and should promote efficient use of the transmission system"). 326 of 515

PDF page 36

Document Accessig@Sg 2r218-34f6
urnent:FiAd. EPAP: a I.8/2ce Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 170 -
transmission system under certain conditions, we further direct PJM to reflect this change in its compliance filing.

349.
With respect to DCC's argument that PJM's proposal does not provide a workable pathway for phased development or load ramping,796  we disagree. Because FCD transmission service is based on a reserved amount of contract demand and does not account for load growth in the way that NITS does, Eligible Customers seeking to increase the amount of load for which they are taking transmission service over time should be required to submit new transmission service requests for any increases in contract demand. As an alternative, they may request a level of contract demand in their initial transmission service request that reflects their planned total load, even though they may not need the full level of contract demand immediately. To the extent that neither of these options work for a particular Eligible Customer taking transmission service on behalf of a Co-Located Load, that Eligible Customer should consider taking NITS, which accommodates load growth over time, as PJM suggests.797

350.
DCC also argues that PJM prohibits the mixing of NITS and FCD or NFCD transmission service for the same load.798  However, in the December Order, the Commission explicitly stated that NITS cannot be combined with any of the new transmission services.799  As such, we find that DCC's argument is an untimely request for rehearing of the December Order and dismiss it.8°°

351.
With respect to DCC's argument that Eligible Customers serving Co-Located Load should be able to transition between transmission services,801  we note that Eligible Customers taking transmission service on behalf of Co-Located Load that wish to transition from one transmission service to another may do so through the same process

796  DCC Response Brief at 6.
797  PJM Reply Brief at 37-38.
798  DCC Response Brief at 6.
799  December Order, 193 FERC 1161,217 at P 195 n.408 ("Eligible Customers taking NITS on behalf of Co-Located Load may not combine NITS with any of the other transmission services discussed herein."). 888  See, e.g., ISO New Eng. Inc., 132 FERC ¶ 61,098 at P 12 ("The Commission has held that requests to alter a compliance filing in a manner that differs from the order requiring the compliance filing constitute a collateral attack on the order requiring the compliance filing.").
801 DCC Response Brief at 6. 327 of 515

PDF page 37

Doaum„t AccesigPfr; 4q'Aggl.i3 -349curnent:Flild rEq99: c3E2818/ 2  pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 171 -
as any other party requesting new transmission service, with the exception of the anti-toggling procedures discussed below in Part VI.E.

352.
Finally, with respect to Market Monitor's argument that NFCD transmission service is untenable, we dismiss this argument as an untimely request for rehearing of the December Order. We disagree that NFCD transmission service is untenable if it is not available constantly; to the contrary, NFCD transmission service is designed to be non-firm and as-available, meaning that it will sometimes be unavailable or curtailed. It is possible that if, for example, a significant number of Eligible Customers taking transmission service on behalf of Co-Located Loads were to switch to NFCD transmission service, it would be frequently curtailed, but that is the nature of non-firm, as opposed to firm, transmission service. Eligible Customers taking transmission service on behalf of Co-Located Loads that do not wish to be curtailed should consider requesting a firm transmission service instead.

3. Study Process
a. Initial Briefs
353.
PJM states that it will coordinate with the affected transmission owner to complete studies, obtain relevant data, and identify any necessary enhancements to the transmission system to accommodate the requested level of service.802  PJM also states that, during the study period, it may perform other studies.

354.
PJM proposes that it notify the affected transmission owner of an application for FCD transmission service to allow for coordination to study the potential impacts of providing this service on the transmission owner's system.803  PJM states that it will determine any necessary studies to provide the requested transmission service. If studies are needed, PJM explains, it will provide an application and studies agreement to the Eligible Customer in which the Eligible Customer will agree to reimburse PJM for study costs. PJM also states that it will consider the results of any transmission owner studies. 355.

PJM proposes that, upon receiving a service request, it will coordinate with the affected transmission owner to complete necessary studies to determine whether, and at what level, NFCD transmission service can be reliably provided.804  PJM proposes that it and the affected transmission owner will determine whether additional studies are required to assess the NFCD transmission service request, and if so, which studies are

802 PJM Initial Brief at 17-18.
803 Id. at 24. 8°4  Id. at 32-33. 328 of 515

PDF page 38

Document Accessig@Sg 2218-34Kument:Flild EFas@v: (43,48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 178 -
would address many of the concerns in the record because it would ensure Eligible Customers have more detail, transparency, and certainty regarding the study process, which is the primary concern of the protesters.833  Thus, we direct PJM to submit a compliance filing within 60 days of the date of issuance of this order to revise its Tariff to provide that it will study FCD transmission service requests using its existing process for studying firm transmission service requests. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we further direct PJM to reflect this change in its compliance filing.

373. With respect to NFCD transmission service, we agree with parties arguing that PJM's proposal lacks specificity. PJM argues that "the study approach could differ widely for each request, given the different nature of the risks involved, as the system would be operated on an as-conditions-permit basis."834  The lack of detail creates a level of discretion that is not just and reasonable; while some amount of discretion is likely necessary to ensure PJM is able to perform any additional studies necessary to maintain reliability, Eligible Customers must have some understanding of the study process PJM will use to evaluate transmission service requests. Therefore, we direct PJM to submit a compliance filing within 60 days of the date of issuance of this order that revises its Tariff to include study procedures for NFCD transmission service requests. We note that the Tariff includes detailed procedures for the study of Non-Firm PTPS, which serve as a useful reference. In particular, the Tariff provides that, following receipt of a tendered schedule, PJM will make a determination on a non-discriminatory basis of available transfer capability for PTPS requests, based on a specific methodology detailed in Tariff, Attachment C.835  No party has shown why a similar process should not apply for NFCD transmission service, and PJM has not demonstrated that having so little detail in the Tariff regarding the process for studying requests for NFCD transmission service is just and reasonable. PJM's compliance filing must also include details about the term length of NFCD transmission service, including the minimum term. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that

833  See PJM, Intra-PJM Tariffs, pt. VIII, § 404 (1.0.0) (providing overview of system impact studies, including scope of studies).
834  PJM Reply Brief at 26. 835  See PJM, Intra-PJM Tariffs, OATT, §§ 11.18.4; id attach. C (Methodology to Assess Available Transfer Capability). 335 of 515

PDF page 39

Document AccessigPA:  22q-2-Vt4318-31:29ument:Flild d'Ap:*9_8
 pa_te Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 172 -
appropriate. PJM proposes that it will provide a written explanation if it determines that none or only a portion of the requested service can be reliably provided. b. Response Briefs

356.
Indicated TOs support PJM's proposed study processes for FCD transmission service and state that it appropriately recognizes the role of transmission owners in evaluating load interconnection requests.805  Indicated TOs argue, however, that the Tariff should specify that load integration studies should be completed first and inform the determination of whether additional studies are necessary for purposes of an Eligible Customer's request for transmission service on behalf of a Co-Located Load and the interconnection of any on-site generation. Indicated TOs contend that this requirement would maximize the speed and efficiency of the overall process and avoid potential duplication of effort and expense as between PJM and the PJM transmission owners. 357.

Indicated TOs state that PJM appears to contemplate that an Eligible Customer's initial application for NFCD transmission service would serve as a "holding" request and that the actual reservation and use of the service would require the Eligible Customer to make a request and PJM to determine whether or not the requested amount of service is available.806  Indicated TOs further state that the available amount of NFCD transmission service presumably would serve as the basis for determining the relevant charge to the Eligible Customer. Indicated TOs request that PJM confirm these understandings and add appropriate Tariff language. Indicated TOs also request that PJM clarify whether the study process set forth in section 710.3 of the illustrative tariff provisions is intended to cover only the initial service study or also subsequent determinations as to specific reservation requests. Generally, Indicated TOs argue that more detail should be provided as to the process for evaluating and granting requests for NFCD transmission service, including the timelines associated with such requests, particularly with respect to forced rather than planned outages.807  Indicated TOs also contend that PJM should specify in Tariff language that NFCD transmission service will be available for periods from one month to one hour in duration.

358.
Several parties argue that PJM's proposed study process is unjust and
unreasonable.808  Constellation argues that PJM fails to sufficiently describe its proposed study procedures for the three new services. Vistra similarly argues that PJM's study 8°5  Indicated TOs Response Brief at 5-7.

806 Id. at 4.
807  Id. at 4-5. 8°8  Vistra Response Brief at 31, 33-35; Constellation Response Brief at 14-15. 329 of 515

PDF page 40

Doctunerit A„e„igP.V;
qQrAgg-18-3R89urnent:Filla rgq99:A3A8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 173 -
process provides too much discretion to PJM and transmission owners to determine whether studies are required, which studies to conduct, the timeline for doing so, and how to prioritize different requests. First, Vistra asserts that PJM does not propose a mechanism to assign customers a queue position based on the submission of a complete application. Vistra also charges that PJM reserves to itself full discretion to determine whether studies must be conducted and what analyses those studies will involve, and alleges that the proposed tariff does not appear to limit the results of PJM's analysis of transmission service requests to the results of duly conducted studies because it states that PJM will "consider" the results of the study procedures.809  Vistra and Constellation also argue that PJM provides no timelines or deadlines for processing transmission service requests. Vistra also argues that PJM provides itself total discretion to set study fees with no parameters for setting those fees. Vistra and Constellation express concern that the discretion in PJM's proposal creates a risk of undue discrimination. Vistra and Constellation argue that PJM's proposal violates the Commission's rule of reason policy because the information missing from the tariff proposal significantly affects rates, is readily susceptible of specification, and is not so readily understood as to render recitation superfluous.81°  Vistra also contends that PJM's proposal is unclear on what it means to ensure that non-firm transmission service can be provided "reliably," and requests that PJM articulate the standard."'

c. Reply Briefs
359.
PJM maintains that its illustrative tariff contains an appropriate amount of detail on the study process and states that it will work with stakeholders to develop implementation details to be set forth in the PJM manuals.812  PJM avers that the illustrative tariff provides more than enough detail to satisfy the Commission's rule of reason policy. PJM alleges that its proposal builds on its existing processes for studying requests for new transmission service requests. PJM contends that its evaluation of firm transmission service requests will require and follow similar study procedures to what is now required for NITS. For non-firm transmission service requests, PJM asserts that the study approach could differ widely for each request and will depend on a number of factors.

360.
PJM explains that, currently, the transmission owners study in the first instance all requests to connect new load to the transmission system. PJM states that, for each zone,

809 Vistra Response Brief at 33-34 (citing PJM, Initial Brief, attach. A § 702.3). 810 Id. at 36-37, 53; Constellation Response Brief at 15-18. 811  Vistra Response Brief at 39.
812  PJM Reply Brief at 22-23, 26, 32. 330 of 515

PDF page 41

Document .Accessigl
2Cr2VA18_3Q9cUMent:FlAdda
A3A812pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 174 -
the transmission owner studies the integration of the requested load and identifies upgrades. PJM says that it then performs a "do no harm" analysis of how those transmission owner-identified upgrades would affect the regional transmission system. PJM notes that NITS can then be provided consistent with the in-service date of the identified upgrades.813  PJM contends that the allocation of responsibilities between the transmission owners and PJM in the current study process follows the division of rights recently affirmed by the Commission and courts, i.e., transmission owners' reservation of rights over local transmission planning and PJM's responsibility for the regional transmission system.814  PJM claims that it maintains this division of rights in the illustrative tariff provisions.

361.
PJM also rejects protesters' arguments that its proposal affords PJM and the transmission owners inappropriate discretion. PJM argues that it seeks no more discretion than it currently has under its existing study processes. PJM argues that its evaluation of the transmission system to determine whether it can reliably provide the requested transmission service requires an exercise of engineering judgment, which inherently entails a reasonable exercise of discretion.815

362.
PJM argues that reliability reviews inherently require PJM to make judgment calls as the transmission provider and a NERC-designated Reliability Coordinator, and the flexibility to determine whether new transmission facilities are reasonably likely to be in-service fits squarely within PJM's expertise. PJM asserts that protesters' concerns about the level of detail generally concern the transmission owner's load integration studies, which PJM argues does not inherently implicate the Commission's jurisdiction under the FPA.816  In response to concerns about study timelines, PJM contends that its evaluation of any transmission service request is dependent on the load integration studies performed by the applicable transmission owner.817  PJM asserts that it does not

813  Id at 24.
814  Id. at 24 & n.68 (citing PJM Interconnection, L.L.C., 172 FERC ¶ 61,136, order on reh'g, 173 FERC ¶ 61,225, at P 19 (2020), aff'd sub nom. Am. Mun. Power, Inc.
v. FERC, 86 F.4th 922 (D.C. Cir. 2023); PJM Interconnection, L.L.C., 173 FERC ¶ 61,242 (2020), order on reh'g, 176 FERC ¶ 61,053 (2021), aff'd sub nom. Am. Mun. Power, Inc., 86 F.4th 922; Monongahela Power Co., 164 FERC ¶ 61,217, at P 14 (2018); Appalachian Power Co., 170 FERC ¶ 61,196, at P 59 (2020)).

815  Id. at 25-26.
816  Id. at 34.
817  Id at 28. 331 of 515

PDF page 42

Documerft AceessigiqSA 4q-Aeg-18_3cpp_Iment:Flitd doge: A3),48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 175 -
have authority to dictate timelines to transmission owners to complete their studies, given that load integration studies are a matter of local transmission planning. 363.

PJM also alleges that concerns that PJM will reject transmission service requests without basis are unfounded.818  PJM maintains that it will generally grant requests for NITS and FCD transmission service, and PJM will grant Interim NITS requests consistent with the results of any study/studies. As to NFCD transmission service, PJM explains that, if it denies a request in whole or in part, PJM will provide a written explanation to the customer of PJM's reasoning for the denial, which could form the basis for any complaint to the Commission.

364.
Moreover, PJM argues that the illustrative tariff puts all parties on sufficient notice as to how PJM will determine whether it can provide the requested transmission service and the study procedures to arrive at that determination.819  PJM asserts that the illustrative tariff provides the standard to which PJM will evaluate the requests—whether the requested level of service can be provided reliably.

365.
Indicated TOs concede that more detail regarding the study processes for the new transmission services could be helpful, but they argue that commenters' concerns as to the potential for delays and undue discrimination are overstated. Indicated TOs contend that it is appropriate and consistent with the Commission's rule of reason to reference the need to incorporate each transmission owner's technical requirements in the Tariff while omitting the details. Indicated TOs do not oppose making explicit in the Tariff that the studies referred to are those that the transmission owners will conduct to integrate large load facilities. Indicated TOs reject claims that they will use their role in the study process to delay or deny Co-Location Arrangements or discriminate against Co-Located Load.82°

366.
Constellation requests that the Commission deter delays and potential disputes by
(1) establishing deadlines for studies and other transmission owner approvals or consultation requirements, and (2) require PJM's and transmission owners' standards, requirements, guidance, and practices on Co-Location Arrangements to be on file with the Commission on a standalone basis or reflected in the Tariff.821

818  Id
819  Id. at 30. 82°  Indicated TOs Reply Brief at 9-11.
821  Constellation Reply Brief at 11-12. 332 of 515

PDF page 43

Document - Acces-sigl?Sg 242-YRI. 8 - 3I?
ument:FlAd  ?age: A33/41.8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 176 -
367. PJM argues that Vistra oversimplifies the provision of non-firm transmission service.822  PJM states that it is not the case that the transmission system has significantly underutilized capacity to provide the envisioned services. PJM alleges that it needs to carefully identify and manage operational risk instead of spontaneously managing non-firm load under an increasingly stressed system. Constellation also argues that PJM should clarify how it will determine the future and real-time availability of NFCD transmission service, which should be based on when transmission capacity is available and not needed by firm customers, consistent with the December Order.823 d. Answers

368. Constellation argues that the Commission has jurisdiction to regulate load integration studies in connection with jurisdictional transmission service.824 Constellation contends that the Commission should exercise jurisdiction over the load integration studies needed to provide jurisdictional transmission service and direct that these studies be on file, including study deadlines and violations to be studied.825 369. Indicated TOs argue that transmission owner processes for studying the integration of new retail loads do not implicate the Commission's jurisdiction, even though such studies will be used as an input in PJM's process for studying applications for the new transmission services.826  Indicated TOs point out that, even as to studies for Commission-jurisdictional services, the Commission does not require transmission providers to file studies.827  Indicated TOs maintain that, if an Eligible Customer disputes the outcome of PJM's study process for the new transmission services, the customer can seek redress through the Commission.

e. Determination
370. We find that PJM's proposal regarding study procedures for FCD and NFCD transmission services is not sufficiently detailed to be just and reasonable, and we direct

822  PJM Reply Brief at 35-36.
823  Constellation Reply Brief at 18 (citing December Order, 193 FERC ¶ 61,217 at P 214).
824  Id. at 6.
825  Id. at 7.
826  Indicated TOs May 28 Answer at 8.
827  Id at 9. 333 of 515

PDF page 44

Documerit Accessig
 qq2-%gg18-3P9c ument:Flil d  ]j g9: A)3/18/2 pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 177 -
PJM to file, as the replacement rate, more detailed study procedures that mirror the existing study procedures for transmission service on compliance.828  First, with respect to FCD transmission service, we agree with parties on briefing that PJM's proposal is vague and unclear. We direct PJM to file Tariff revisions on compliance to study requests for FCD transmission service using the same process PJM uses for new service requests for NITS, i.e., the cluster study process.829  This requirement is just and reasonable because it will treat new firm transmission service requests similarly. 371.

PJM contends that its proposal "has built on its existing processes for studying requests for new transmission services . . . with additional processes necessary to study the novel aspects of Interim NITS and [FCD and NFCD] Transmission Services."830 PJM also states that "[e]valuation of firm service requests will require and follow similar study procedures to what is now required for NITS."831  However, PJM's proposal is lacking in detail. It is not clear whether PJM proposes to study requests for FCD transmission service serially or through its existing cluster study process.832 372.

Regardless, we find that it is just and reasonable to study requests for FCD transmission service through PJM's existing cluster study process, and we direct PJM to file Tariff revisions on compliance consistent with this directive. We find a serial study process for new FCD transmission service requests, rather than a cluster study as for new NITS requests, would provide disparate treatment to FCD transmission service requests. PJM also does not address a timeline for its study process, meaning FCD transmission service requests could be studied more quickly or more slowly than requests in the new services queue. PJM does not provide a reason for this difference or any explanation as to why such requests should not be studied in the normal cluster process for new service requests. Further, studying such requests as part of the established cluster study process

828  We discuss PJM's proposed study procedures for Interim NITS below in Part VI.H.
829 PJM, Intra-PJM Tariffs, OATT, § III.32.3 Initial Study Procedures (3.0.0) ("A request for service for which a Phase I System Impact Study is required is subject to the System Impact Study Procedures, as set forth in Tariff, Part VII or Tariff, Part VIII, as applicable.").
830  PJM Reply Brief at 23.
831  Id. at 26.
832  See PJM, Initial Brief, attach. A, § 712.1 ("After receiving the Application for Firm Contract Demand Transmission Service, the Transmission Provider shall determine, in accordance with the PJM Manuals, any necessary studies for reliably providing the requested Firm Contract Demand Transmission Service."). 334 of 515

PDF page 45

Docurnen't AccessigPsP; 2A-Agg18 _ 3pwument:FlAd rpo.g: c ,33/6.8/ p-Ate Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 179 -
are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we further direct PJM to reflect this change in its compliance filing. 374.

Indicated TOs request that the Tariff specify that transmission owner load integration studies will be completed first and thereby inform what additional studies are necessary. However, it is not clear from the record what these studies entail, as these studies are not defined in either the Tariff or any of PJM's manuals, or how transmission owners will study the load. For example, the record indicates that Indicated TOs view a load integration study for Co-Located Load as potentially analyzing "(i) what, if any, upgrades are needed to accommodate the physical gross load amount behind the point of interconnection."836  To the extent PJM intends to permit transmission owners to study Co-Located Load as if it were native load with NITS, that would not be just and reasonable for FCD and NFCD transmission services. We therefore direct PJM to specify in a compliance filing, which it must submit within 60 days of the date of issuance of this order, how transmission owners shall participate in PJM's study process for Eligible Loads for FCD and NFCD transmission services and specify in detail the related roles and responsibilities of PJM and the transmission owners in such studies. We decline at this time to adopt Indicated TOs' requests to incorporate further revisions to the Tariff related to load integration studies.837

4. Rates and Charges
a. Initial Briefs
375.
Indicated TOs propose that the rate for the FCD transmission service be based on the zonal NITS rates and underlying NITS revenue requirements.838  Indicated TOs argue that Eligible Customers taking FCD transmission service on behalf of Co-Located Load and Network Customers should be charged the same rate because the level of service provided to both is the same for all relevant purposes. For example, Indicated TOs argue that both services are firm transmission services for which PJM procures capacity for the customers. Indicated TOs argue that it would be unjust and unreasonable and unduly discriminatory to charge FCD transmission service customers a rate lower than the NITS rate as it would subsidize FCD transmission service customers at the expense of Network Customers. Indicated TOs contend that it is appropriate to use the single peak coincident demand to calculate the FCD transmission service rate because it is an annual service.

836  Indicated TOs Initial Brief at 25-26 (emphasis added).
837  Indicated TOs Response Brief at 13, 16, 19.
838  Indicated TOs Initial Brief at 6, 8-9. 336 of 515

PDF page 46

Document Accessig@A 2ArACZ18-3Q@curnent:FiAd rPaqii9: A33 A8/zee Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 180 -
376.
Indicated TOs propose that NFCD transmission service pay a charge for the reserved contract demand amount multiplied by a zonal NFCD transmission service rate determined based on the specific term of service.839  Indicated TOs propose to use the same FCD transmission service rate for purposes of establishing the maximum rate for NFCD transmission service. Indicated TOs argue that it is just and reasonable to use the same maximum rate for FCD and NFCD transmission services, because the Commission has permitted pricing Non-Firm PTPS at the rate used for Firm PTPS and because the Commission provides flexibility to arrange and schedule NFCD transmission service. Indicated TOs allege that NFCD transmission service is superior to Non-Firm PTPS because PJM will re-dispatch generation prior to curtailing NFCD transmission service. Indicated TOs propose to consider on a going-forward basis whether a discount is appropriate for NFCD transmission service based on system conditions and use patterns. 377.

In addition to these charges, PJM proposes to assess, for FCD transmission service: (1) administrative service charges, (2) ancillary service charges, (3) black start service charges based on gross demand, (4) regulation charges based on gross demand, and (5) any redispatch costs. PJM contends that these are standard charges associated with use of the transmission system above transmission service rates.84°  For NFCD transmission service, PJM also proposes to assess certain charges within its authority:

(1) administrative charges, (2) ancillary services charges, (3) any redispatch costs,
(4) regulation charges based on gross demand, and (5) black start service charges based on gross demand.841

b. Response Briefs
378.
Several parties argue that it is just and reasonable to charge the same rate for FCD transmission service and NITS.842  NOVEC explains that Eligible Customers are receiving a service commensurate with NITS and should therefore pay a cost commensurate with NITS in recognition of the Commission's cost causation principles. Market Monitor asserts that if customers have the option to convert from FCD transmission service to NITS in the future, and given the long timelines in transmission planning and the extreme lumpiness of transmission investments, PJM must plan as if all

839  Id. at 10, 11-13. 840  PJM Initial Brief at 27.
841  Id. at 36-37.
842  ODEC Response Brief at 8; NOVEC Response Brief at 6-7; Market Monitor Response Brief at 3-4. 337 of 515

PDF page 47

Document AcceesigiSt9; qq-2 -ogg-18  _pgcument:FlAd rpaN: X303,818/2
to Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 181 -
Eligible Customers taking the new contract demand transmission services are Network Customers.

379.
Some parties also agree that it is just and reasonable to use the FCD transmission service rate as the maximum rate for NFCD transmission service.843  NOVEC argues that NFCD transmission service is a network-type service that bears a resemblance to NITS. NOVEC notes that because an Eligible Customer only purchases NFCD transmission service when reserved, transmission costs for an Eligible Customer are lower than firm rates.

380.
Other parties disagree that the proposed rate for NFCD transmission service is just and reasonable.844  Vistra alleges that Indicated TOs fail to justify not offering a discounted rate for NFCD transmission service when such a discount exists for Non-Firm PTPS. Vistra contends that the benefit of re-dispatching generation prior to curtailment does not justify charging a substantially higher rate for a service that is otherwise inferior. Vistra also argues that Indicated TOs' proposal is unjust and unreasonable and unduly discriminatory because it would create cost shifts between classes of transmission customers, where Eligible Customers taking NFCD transmission service on behalf of Co-Located Load shoulder the cost of firm transmission service, despite taking non-firm transmission service.

381.
Joint Co-Location Developers argue that pricing NFCD transmission service at the same rate as FCD transmission service is not consistent with cost causation principles or the Commission's purpose in establishing the NFCD transmission service to avoid inefficient system buildout. Joint Co-Location Developers maintain that, as compared to FCD transmission service, the rate for NFCD transmission service should reflect the lesser costs caused by and lesser benefits received by customers taking this service.845 Joint Co-Location Developers claim that, in Order No. 888-A, the Commission explained that, while in some circumstances non-firm transmission rates may be set at the firm transmission rate level, the Commission expects that non-firm transmission rates would, in most instances, be priced below the price cap.846

382.
Geronimo Power states that, combined with PJM's proposed requirement that an Eligible Customer take NFCD transmission service for the portion of its load served by a

843  ODEC Response Brief at 8; NOVEC Response Brief at 7.
844  Vistra Response Brief at 16-17, 23-24; Joint Co-Location Developers Response Brief at 20; Geronimo Power Response Brief at 4.
845  Joint Co-Location Developers Response Brief at 20-21.
846  Id at 22 (citing Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,272). 338 of 515

PDF page 48

Document Ac„„igPSg i21.8-34@cument:Flild J=Ag?:A33/48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 182 -
Co-Located Generator, the implication of the Indicated Transmission Owners' proposal appears to be that an Eligible Customer taking NFCD transmission service would be required to pay a transmission charge equivalent to the rate paid by transmission customers taking firm transmission service.847  Geronimo Power argues that charging transmission customers taking NFCD transmission service the same amount as a transmission customer taking FCD transmission service is unjust and unreasonable and inconsistent with cost causation principles because these loads will be required to pay a rate equivalent to customers receiving a higher level of service. Geronimo Power asserts that non-firm transmission service should be, and often is, priced lower than firm transmission service, such as in PJM where Non-Firm PTPS customers receive a discount as compared to Firm PTPS customers. Geronimo Power adds that the proposed rate would undermine the incentive for large load customers to reduce their reliance on the grid and therefore would fail to offer a rate that would encourage the efficient use of the transmission system, contrary to the December Order. Further, Geronimo Power states that Indicated TOs should not set an unjust and unreasonable rate based on superior services while they wait until they gather more data to determine the extent to which such unjust and unreasonable rate should be reduced when charging for an inferior service. 383.

ODEC agrees that it is reasonable for PJM to charge FCD and NFCD transmission service customers for applicable PJM administrative charges consistent with PJM's charges to existing transmission customers.848

384.
ODEC urges the Commission to direct further compliance filings in order to ensure that rates for the new FCD transmission service are just and reasonable by requiring the individual transmission owners to either confirm that their formula or stated rates and metrics reporting enable direct crediting by PJM, or provide whatever revisions are necessary in order to do so.849  ODEC states that this is important so that ODEC and other Network Customers are not subject to paying duplicative charges for the same revenue requirement amount. ODEC adds that it is also important because Indicated TOs state that load-serving entities will submit metrics to PJM used to calculate transmission, capacity, and energy charges, but such metrics may not be consistent among Indicated TOs. ODEC explains that, while it is a load-serving entity, as a transmission customer the metrics are provided to PJM by the transmission owners for the zones where ODEC takes transmission service.

385.
Constellation seeks clarification that Indicated TOs' proposed rate for FCD transmission service is equal to the applicable transmission owners' NITS rate calculated

847  Geronimo Power Response Brief at 4, 6, 7-9.
848  ODEC Response Brief at 8; see also NOVEC Response Brief at 8.
849  ODEC Response Brief at 8-9. 339 of 515

PDF page 49

Document Access
;Pr; 22qZl 8 - 3P 9c ument:Flit d rEg9:c3,0/(18/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 183 -
using that transmission owners' coincident peak methodology, given that different transmission owners use different methods.85°

386.
Industrials/Amtrak argue that the Commission must ensure that transmission owners' calculation of individual customer and zonal transmission cost allocation is transparent, whether through an Attachment M-2 filing or another publicly transparent and accountable method.851  Industrials/Amtrak also contend that the Commission must provide direction on how the revenue and the billing determinants for FCD and NFCD transmission services and Interim NITS would be incorporated into existing transmission formula rates. Similarly, Geronimo Power states that the Commission should at a minimum require the Indicated Transmission Owners to clarify the nature of the rates and billing determinants that they are proposing, including whether they intend to charge the NFCD transmission service charge on a MWh basis, which would be inconsistent both with how transmission reservation charges are historically structured and the Tariff.852 387.

Industrials/Amtrak argue that neither FCD nor NFCD transmission service provide a cost-based back-up service for cogeneration QFs and similarly-situated retail customers.853  Industrials/Amtrak contend that, because it would require payment for service based on the contracted amount, FCD transmission service inherently assumes that forced outages or other reductions in electric output by all QFs will occur simultaneously, or during the system peak, or both, without any factual data to support that assumption.854  Industrials/Amtrak aver that this is not a realistic assumption for cogeneration QFs. Industrials/Amtrak further argue that it would not comport with cost causation principles to require a FCD transmission service reservation for occasional back-up power needs, particularly where the history and risk of the individual unit is well-established or has met outside standards. Industrials/Amtrak further argue that NFCD transmission service also falls short because it requires pre-scheduling with and approval by PJM, which is inconsistent with back-up power's use in the event of forced outages, and because it is an as-available product that is subject to interruption.855 Industrials/Amtrak argue that, if the existing netting construct is no longer available, then a firm transmission service must be available for QFs to meet the requirements of 850 Constellation Response Brief at 31.

851  Industrials/Amtrak Response Brief at 25-26.
852  Geronimo Power Response Brief at 5 n.13.
853  Industrials/Amtrak Response Brief at 16-19.
854  Id. at 17 (citing Dauphinais Aff. ¶ 44).
855  Id at 18. 340 of 515

PDF page 50

Document AccessigRSg 2q-'21.8-3Q9c ument:FlAd rFa'qp: A4A8/2PAte Filed: 10116/2026 Docket No. EL25-49-002, et al.

- 184 -
PURPA based on actual use. Industrials/Amtrak contend that there must be a transmission service that applies cost causation standards to occasional, unplanned use of the transmission system.

388.
Industrials/Amtrak argue that cost causation principles dictate that the Commission should authorize cost-based back-up service for all transmission customers, not only QFs.856  Industrials/Amtrak explain that there are a number of facilities that operate on similar principles to QFs but do not maintain QF status for a variety of reasons. Industrials/Amtrak argue that these facilities, too, must occasionally draw from the grid, including for occasional unscheduled outages. Industrials/Amtrak argue that it cannot be just and reasonable or comport with cost causation principles to require facilities requiring only occasional back-up service to pay rates that are the same as FCD transmission service or gross-based NITS. Industrials/Amtrak argue that transmission customers should be charged based on actual use on an hourly basis and should not be charged a standby fee.

389.
Industrials/Amtrak explain that QFs are entitled to supplementary power, back-up power, maintenance power, and interruptible power pursuant to Commission regulations857  and that the rates for back-up power "[s]hall not be based upon an assumption (unless supported by factual data) that forced outages or other reductions in electric output by all [QFs] on an electric utility's system will occur simultaneously, or during the system peak, or both."858  Industrials/Amtrak argue the NITS BTMG netting construct meets the requirements of PURPA's enacting regulations.

c. Reply Briefs
390.
In response to Constellation's request for clarification, Indicated TOs clarify that the zonal FCD transmission service rate will be calculated using that transmission owner's specific methodology applicable to Network Customers.859

391.
NOVEC explains that because under PJM's proposal a transmission customer would only take and pay for NFCD transmission service when the generator was experiencing an outage, the same rate does not equate to the same cost to the customer.86° 856  Id at 20-22, 24.

857  Industrials/Amtrak Response Brief at 14-16 (citing 18 C.F.R. § 292.305(b)).
858  Id. at 15 (citing 18 C.F.R. § 292.305(c)(1)).
859  Indicated TOs Reply Brief at 18 (citing Constellation Response Brief at 31). 860 NOVEC Reply Brief at 10-13. 341 of 515

PDF page 51

DocumenE Accessig#SP; 22qAqA18 _31).pcument:Flild jag9: A4,A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 185 -
NOVEC argues that NFCD transmission service does not impose fewer costs on the transmission system than NITS, just "imposes costs differently" and contends that the Commission needs to be cautious to avoid providing "co-located generators a subsidized low cost option to use the system whenever they need backup."861  NOVEC argues that Co-Located Load in areas where PJM can accommodate a large amount of NFCD transmission service could end up with the best of both worlds, where they are very rarely curtailed but pay a subsidized rate for transmission service, with the option to switch from FCD transmission service or NITS if PJM can no longer accommodate the required level of NFCD transmission service.

392.
In response to arguments from Joint Co-Location Developers and Geronimo Power about whether it is appropriate to establish NFCD transmission service rates based on FCD transmission service rates, Indicated TOs argue that transmission owners need to gather data on how NFCD transmission service customers are using the service and the effect of that utilization on the transmission system.S62  Indicated TOs argue that it is not clear whether NFCD transmission service customers will cause the need for fewer Network Upgrades, and that further analysis is needed to determine whether discounts are appropriate. Finally, Indicated TOs contend that Joint Co-Location Developers' concerns that the proposed NFCD transmission service rate will discourage industrial development are exaggerated and misplaced. NOVEC similarly argues that it is not the Commission's place to subsidize certain industries at the expense of customers.863

393.
In response to Vistra's arguments about applying the rate for zonal Non-Firm PTPS to NFCD transmission service, Indicated TOs argue that doing so would be unreasonable because transmission customers have used Non-Firm PTPS exclusively to facilitate the delivery of specific generation to the PJM border—not for internal use.864 NOVEC also rejects Vistra's argument that NFCD transmission service should receive the same rate as Non-Firm PTPS, arguing that it would not be appropriate to allow NFCD transmission service the same discount as Non-Firm PTPS because the two products fundamentally differ. Indicated TOs further argue that the discounted Non-Firm PTPS rate reflects historical use and was neither intended nor appropriate for NFCD transmission service because NFCD transmission service is intended to be a limited, supplemental service within PJM and does not facilitate the delivery of specific generation to specific load over a contract path. Indicated TOs also contend that NFCD

861  Id. at 12 (citing Market Monitor Response Brief at 6). 862  Indicated TOs Reply Brief at 19-21.
863  NOVEC Reply Brief at 14.
864  Indicated TOs Reply Brief at 13, 18-19. 342 of 515

PDF page 52

Document AccessigiPA 242-16A18-31?@cument:Flit d  rpa@g9: A4/48/2PAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 186 -
transmission service is superior to Non-Firm PTPS because it has a superior curtailment priority.

394.
Indicated TOs reject Vistra's argument that Indicated TOs' proposal to credit the revenues associated with NFCD transmission service to customers taking NITS and FCD transmission service will create unjustified cost shifts among customer classes.865 Indicated TOs argue that these revenue credits are not subsidies but offsets that reduce the amount paid by firm transmission service customers, which is appropriate because transmission rates are designed to recover the fixed costs of building and maintaining the transmission system to provide service to such customers. In the absence of such credits, Indicated TOs argue that the transmission owners would over-recover their revenue requirements. Indicated TOs further argue that the revenue crediting mechanism is fully consistent with previously approved mechanisms such as section 27A, which credits Non-Firm PTPS revenue to Network and Firm PTPS customers.

395.
Industrials/Amtrak argue that NFCD transmission service cannot provide back-up power because it cannot be accessed during a BTMG generation facility outage until a request for it is submitted to and approved by PJM.866  Industrials/Amtrak further argue that NFCD transmission service is also only available on an as-available basis and is subject to both operational and automated interruption.867  Industrials/Amtrak explain that, during a forced outage, a retail customer would be required to automatically curtail load until it submits a NFCD transmission service request and PJM approves that request. 396.

Industrials/Amtrak also argue that FCD transmission service can provide maintenance power on a firm basis, but like back-up power, cannot do so at a cost lower than gross load NITS because it implicitly assumes BTMG maintenance outages cannot be scheduled to avoid peak periods.868

d. Answer
397.
Geronimo Power argues that Indicated TOs' proposed rate for NFCD transmission service is unjust and unreasonable, will disincentivize Co-Located Loads from relying on NFCD transmission service, and lead to less efficient use of the transmission system.869

865  Id. at 31-32 (citing Vistra Response Brief at 23-25).
866  Industrials/Amtrak Reply Brief at 8.
867  Id at 8 n.13.
868  Id at 9 n.16.
869  Geronimo Power May 21 Answer at 8. 343 of 515

PDF page 53

D'ocunient-AccessigSp qq,236,g-18 _3RpumentAil d rfal@g: A4A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 187 -
Geronimo Power asserts that Indicated TOs offer no meaningful response to the question of what is a just and reasonable rate for NFCD transmission service. Geronimo Power argues that the mere fact that Commission policy allows PJM transmission owners to charge up to the firm rate in some cases does not mean that doing so here is just and reasonable.87°  Geronimo Power avers that there should be little doubt that some form of discount must be applied as to NFCD transmission service.

e. Determination
398.
We agree with Indicated TOs that it is just and reasonable to base the rate for FCD transmission service on the zonal NITS rates and underlying NITS revenue requirements871  and direct the PJM transmission owners, as the replacement rate, to submit a compliance filing within 60 days of the date of issuance of this order that includes Tariff revisions to effectuate this proposal. Both FCD transmission service and NITS will provide a similar level of firm transmission service, and PJM will plan the transmission system to ensure that it is able to provide both transmission services on a firm basis .872

399.
We find unjust and unreasonable PJM's proposal to charge Eligible Customers taking FCD or NFCD transmission services on behalf of Co-Located Loads for all ancillary services other than regulation and black start based on total quantity of MWhs of energy delivered to the Co-Located Load.873  In the December Order, the Commission found that Eligible Customers taking the new FCD transmission service on behalf of Co-Located Loads must be charged for ancillary services based on the contract demand, with the exception of regulation and black start services.874  Similarly, the Commission found that Eligible Customers taking the NFCD transmission service on behalf of Co-Located Loads must be charged for ancillary services on an as-reserved contract demand basis, based on the reserved contract demand amount of transmission service, with the exception of regulation and black start services."'

870  Id at 9.
871  Indicated TOs Initial Brief at 6. 872  Id at 8-9; December Order, 193 FERC ¶ 61,217 at PP 195, 208.
873  PJM, Initial Brief, attach. A, Subpart B, §§ 714.5 & 715.4.
874  December Order, 193 FERC ¶ 61,217 at P 209. 875  Id P 216. 344 of 515

PDF page 54

Document Accessig@Sg 2qACItql8-3P9cUrnent:FlAd rg@g9: A4A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 188 -
400.
However, we find just and reasonable PJM's proposal to charge Eligible Customers taking FCD and NFCD transmission services on behalf of Co-Located Loads for regulation and black start services based on gross demand, which is consistent with the Commission's findings in the December Order. The Commission found in the December Order that "Eligible Customers that take the Firm Contract Demand transmission service on behalf of Co-Located Loads must be charged for regulation and black start services based on a gross demand basis, rather than the contract demand" because all Co-Located Loads rely on regulation and black start services to be served regardless of whether they are withdrawing energy from the transmission system.876 Likewise, the Commission found in the December Order that "Eligible Customers that take the Non-Firm Contract Demand transmission service on behalf of Co-Located Loads use and therefore should be charged for regulation and black start services based on a gross demand basis, rather than the reserved amount of transmission service."877 Therefore, and consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we direct PJM to submit a compliance filing within 60 days of the date of issuance of this order that revises its Tariff to: (1) charge Eligible Customers taking FCD and/or NFCD transmission services on behalf of Eligible Loads for all ancillary services other than regulation and black start services based on their contract demand; and (2) charge Eligible Customers taking FCD and/or NFCD transmission services on behalf of Eligible Loads for regulation and black start services based on their gross load.

401.
We also find just and reasonable PJM's proposal to charge Eligible Customers taking FCD and/or NFCD transmission services certain administrative charges. As PJM explains, these are standard charges associated with use of the transmission system above transmission service rates.S78  For the same reason, we find just and reasonable PJM's proposal to charge Eligible Customers taking FCD and/or NFCD transmission services redispatch costs to cover congestion-related costs, given that both of these services will be pool-scheduled and can be served by generators redispatched to mitigate congested transmission paths. We thus direct PJM to submit a compliance filing, within 60 days of the date of issuance of this order, that revises its Tariff to implement these charges. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission

876  Id P 209.
877 M. P 216. 878  PJM Initial Brief at 27. 345 of 515

PDF page 55

Document AccessigPsg 22q-20qA-18 _3q@cument:Flil d rpaN9: ALIA812 PAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 189 -
system under certain conditions, we further direct PJM to reflect this change in its compliance filing.

402.
However, we are not persuaded that Indicated TOs' proposal to set the maximum rate for NFCD transmission service equal to the rate for FCD transmission service is just and reasonable. In the December Order, the Commission was clear that NFCD transmission service would "provide an option for Eligible Customers seeking to use the transmission system on behalf of a Co-Located Load in this more limited manner."879 Further, NFCD transmission service is non-firm and curtailed prior to FCD transmission service and NITS.88°  NFCD transmission service is therefore an inferior service to FCD transmission service and NITS, and we find that the just and reasonable replacement rate here should not charge the same maximum rate for these transmission services. We acknowledge NOVEC's argument that under PJM's proposal, an Eligible Customer would only take and pay for NFCD transmission service when the generator serving it is experiencing an outage, so the same rate does not equate to the same cost to the Eligible Customer.881  However, the same rate could apply to Eligible Customers taking the same amount of FCD and NFCD transmission services.

403.
We also find that charging the same maximum rate for both FCD and NFCD transmission services can undermine the benefits of the new NFCD transmission service for other transmission customers. Specifically, discounting non-firm transmission services encourages transmission customers to use such services, which benefits all transmission customers by maximizing use of the existing transmission system. These benefits accrue to other transmission customers in two ways. First, the revenues related to NFCD transmission service will become a credit to, and thus offset, the transmission revenue requirement, which is the basis for the rates that firm transmission customers are charged. Moreover, utilizing NFCD transmission service can avoid unnecessary Network Upgrades, the costs of which would likely be allocated to all firm transmission service customers.

404.
Further, pricing NFCD transmission service at the same rate as FCD transmission service is not consistent with cost causation principles or the December Order's findings. Specifically, the Commission found that requiring an Eligible Customer taking transmission service on behalf of Co-Located Load to take NITS on a gross demand basis would be inefficient, and could necessitate costly transmission buildout and costs paid by transmission customers that may not be necessary if Eligible Customers taking transmission service on behalf of Co-Located Loads are willing and able to limit their

879  December Order, 193 FERC ¶ 61,217 at P 214 (emphasis added). 88°  See infra Part VI.G.
881  NOVEC Reply Brief at 10. 346 of 515

PDF page 56

Document Acce„igRSg 21Ag67.8-349curnent:FlAd rPA99:
A8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 190 -
energy withdrawals from the transmission system under certain conditions and take a transmission service that requires fewer or less costly Network Upgrades to provide.882 As noted above, the Commission directed the creation of NFCD transmission service, finding that it would provide an option for Eligible Customers taking service on behalf of Co-Located Loads that seek to use the transmission system in a more limited manner.883 The December Order further found that Eligible Customers taking service on behalf of Co-Located Loads should be allowed to choose the transmission service that aligns with their use of the transmission system and therefore aligns the charges for service with the benefits received.884  Indicated TOs' proposal fails to comply with the directive in the December Order by charging the same rate for FCD and NFCD transmission services; the proposal does not align the charges for transmission service with the benefits received. 405.

Our finding here is also consistent with Commission precedent. In Order No. 888, the Commission determined that the rate for Non-Firm PTPS "is capped at the firm rate."S85  In response to Order No. 888, Duquesne sought clarification that the phrase "the non-firm rate is capped at the firm rate" does not mean the Commission is deviating from its principles that non-firm transmission service must be priced in a manner that reflects the interruptibility of the service and is economically efficient.886  The Commission clarified that the Firm PTPS transmission rate represents a maximum price for non-firm transmission service and emphasized that "non-firm transmission prices should reflect the interruptibility of the service and should promote efficient use of the transmission system, subject to this price cap."887  The Commission concluded that, "while in some circumstances non-firm transmission rates may be set at a firm transmission rate level, the Commission expects that non-firm transmission rates would, in most instances, be priced below the cap."888

406.
Thus, while the Commission recognized that the Firm PTPS transmission rate could be a ceiling for the Non-Firm PTPS rate, the Commission also recognized that the rates should vary based on the quality of the transmission service. Our finding here is S82  December Order, 193 FERC ¶ 61,217 at P 199.

883  Id. P 214.
884 1d. P  199. 885  Order No. 888, FERC Stats. & Regs. ¶ 31,036 at 31,743.
886  Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,272.
887 Id.
888 Id. 347 of 515

PDF page 57

Document AcceeeigPSK q.A6,18- 312@cUrnent:Flita rf)A9: 0,_8/2PAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 191 -
consistent with Order No. 888 (i.e., that non-firm transmission service rates should generally be priced below firm transmission service rates). Indicated TOs propose making the exception the rule and thus fail to justify that deviation. Indicated TOs argue that NFCD transmission service is a superior level of service compared to Non-Firm PTPS. But, even assuming that statement is correct, it does not follow that NFCD transmission service is therefore a similar level of service as FCD transmission service or NITS.

407.
We recognize that Indicated TOs state that they will consider offering discounts for NFCD transmission service after an initial assessment period to determine whether a discount would encourage efficient use of the transmission system. However, Indicated TOs miss the point of not only aligning the rate with the quality of the service provided, but also designing a rate that incentivizes efficient non-firm uses of the transmission system. It is counterintuitive to expect charging the full rate to inform an analysis of what discounts may be appropriate. Therefore, we find that the possibility of offering discounts at some undefined time in the future is not sufficient to remedy our concerns with their proposal. Under that proposal, Indicated TOs would have no obligation to lower rates in the future and offer no transparency as to how or when that decision would be made; moreover, they provide no compelling explanation as to why it would be just and reasonable to charge for NFCD transmission service at the FCD transmission service rate in the interim.

408.
We further disagree with NOVEC's characterization of a lower rate for NFCD transmission service as subsidized; as discussed in the body of this order, we find that a lower rate for NFCD transmission service is just and reasonable and consistent with cost causation. A lower rate for NFCD, as compared to FCD, transmission service will also, as NOVEC points out, incentivize transmission customers to use the service in areas where PJM can accommodate a large amount of NFCD transmission service. This is exactly the point—Eligible Customers taking transmission service on behalf of Eligible Loads will be incentivized to take NFCD transmission service in areas where there is excess transmission capacity, and the charges recouped from those customers will offset the rates paid by firm transmission customers that funded the excess transmission capacity. Otherwise, this transmission capacity would remain unused and firm transmission customers would pay more.

409.
NOVEC also argues that in areas where PJM can accommodate a large amount of NFCD transmission service, Co-Located Load could end up with the best of both worlds, where they are rarely curtailed but Eligible Customers taking transmission service on their behalf pay a subsidized rate for transmission service, with the option to switch to FCD transmission service or NITS if PJM can no longer accommodate the required level 348 of 515

PDF page 58

Document AccesSigi@"7F': 2fir2-
1.8- 34@cument:Flil d
A4,4 8  / 2  pAte Filed: 10;16/2026
Docket No. EL25-49-002, et al.
- 192 -
of NFCD transmission service.889  We disagree that Eligible Customers could "simply switch" to FCD transmission service or NITS if PJM can no longer accommodate the requested level of NFCD transmission service.89°  The process to request NITS remains unchanged, and we address the process to request FCD transmission service above. But in either case, provision of firm transmission service will be studied, granted to the extent it can be done so reliably, and only available following construction of any required Network Upgrades.

410.
With respect to Industrials/Amtrak's argument that neither FCD nor NFCD
transmission services provide a cost-based back-up service for cogeneration QFs and similarly-situated retail customers,891  this argument is substantively similar to the argument the same parties raised on compliance, which is addressed supra."' Industrials/Amtrak contend that, because it would require payment for service based on the contracted amount, FCD transmission service inherently assumes that forced outages or other reductions in electric output by all QFs will occur simultaneously, or during the system peak, or both, without any factual data to support that assumption.893  However, as noted above, this argument appears to conflate rates for sales of back-up power and rates for transmission service, rendering Industrials'/Amtrak's concerns misplaced. 411.

Industrials/Amtrak further argue that it would not comport with cost causation principles to require a FCD transmission service reservation for occasional back-up power needs and that NFCD transmission service will not be useful for back-up power because it must be requested in advance.894  Again, Industrials/Amtrak appear to conflate back-up power for QFs under PURPA with the subject of this proceeding, which is transmission service taken by Eligible Customers serving Eligible Loads. Further, Industrials/Amtrak state that their concerns are for "whether retail customers can access cost-based . . . back-up service"895  but, with the exception of Eligible Customers that are retail customers taking unbundled transmission service, service available to retail customers is neither the subject of this proceeding nor within the Commission's

889  NOVEC Reply Brief at 12-13. 898  Id.
891  Industrials/Amtrak Response Brief at 16-17. 892  See supra Part V.A.3.
893  Industrials/Amtrak Response Brief at 17 (citing Dauphinais Aff. ¶ 44).
894  Id at 18.
895  Id. at 11 (emphasis added). 349 of 515

PDF page 59

Dodinnerit Acce-sa-igiSA: Z-q-Ag-18_3cp9ument:FlAd rj=)Ag: A5/0.8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 193 -
jurisdiction. However, to the extent Industrials/Amtrak refer to jurisdictional wholesale transmission service when arguing that "examples exist of bespoke arrangements for industrial and institutional customers that may require firm back-up needs,"S96  we continue to find it just and reasonable that Eligible Customers taking NITS be charged on a gross demand basis as explained in the December Order, with limited exceptions.897 Network Load has the right to be served from the transmission system at any time, and PJM and the transmission owners incorporate Network Load into their transmission planning to ensure that they can fulfill their obligation to provide such service. Thus, regardless of whether certain transmission customers that elect NITS to be able to take transmission service on demand choose to only take such service occasionally, the system will be planned to accommodate them at all times. We therefore continue to find that the benefits of NITS align with charging for NITS based on gross demand. We further reiterate that, as discussed in this order, we have set aside, in part, the December Order to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions.898 412.

Therefore, we direct the PJM transmission owners to submit, within 60 days of the date of issuance of this order, a compliance filing with the Tariff charges for NFCD transmission service in accordance with this order. Specifically, the PJM transmission owners must propose a lower maximum rate or non-discriminatory discounts for the NFCD transmission service rate. Moreover, the PJM transmission owners must ensure that their proposed Tariff revisions are transparent as to how charges will be calculated for an individual transmission customer. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we further direct the PJM transmission owners to reflect this change in their compliance filing.

5. Other
a. Initial Briefs
413.
PJM states that any request for FCD and/or NFCD transmission service must comply with Commission regulations for new service requests, and include several items specific to these transmission services, such as a description of the supply characteristics 896  Id at 12.

897  December Order, 193 FERC ¶ 61,217 at PP 186, 195.
898  See supra Part IV.C.1.b.i. 350 of 515

PDF page 60

Document Accessig@Sg 2A"2-1C7418-3Q9cUMent:Filtd IPV: A15 A8/ 2 pate Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 194 -
of the Co-Located Generator and the demand characteristics of the Co-Located Load.899 Upon receiving an application, PJM will evaluate whether the requested level of Contract Demand transmission service can be reliably provided. PJM then explains that the Eligible Customer must meet several conditions precedent, such as certifying that it is willing and able to limit withdrawals from the transmission system when requested by PJM and providing PJM with an authorization or certification from its Relevant Electric Retail Regulatory Authority (RERRA) affirming that the Eligible Customer is authorized to provide energy to the Co-Located Load. PJM also proposes to require that certain facilities and necessary technical arrangements must be completed prior to commencement of requested service.

414.
PJM next explains that, under the Service Agreement for Contract Demand transmission service, service is presumed to continue without expiration, and that there are several bases for termination.900  For example, PJM explains that service can terminate on 42 months' notice prior to the commencement of a delivery year, and PJM argues that this is appropriate because the contract demand level under FCD transmission service will be accounted for in PJM's capacity market. PJM proposes circumstances whereby PJM may terminate service for cause: (1) the Eligible Customer breaches its obligations, such as materially changing the Co-Location Arrangement without PJM studying it; or (2) the Eligible Customer is disqualified by failing to follow an operating instruction to curtail or shed load, or after the misoperation, on more than one occasion, of any necessary control technologies or required protection systems (described further below).

415.
PJM next proposes that the Eligible Customer designate the Co-Located Load and the Co-Located Generator and provide the MW level of energy from the Co-Located Generator dedicated to serving the Co-Located Load.901  For reliability purposes, PJM states, the Eligible Customer must provide PJM with timely written or electronic notice of material changes in the demand characteristics of the Co-Located Load or the supply characteristics of the Co-Located Generator. PJM maintains that necessary control technologies and protection systems for NFCD transmission service will be designed based on the specific circumstances of each Co-Location Arrangement, and PJM's ability to reliably operate the system could be impaired by any material changes to the control technologies or protection systems. PJM proposes to prohibit an Eligible Customer from using FCD transmission service for the sale of either capacity or energy to loads other

899  PJM Initial Brief at 17-19.
900  Id. at 20-22. 981  Id. at 22-24. 351 of 515

PDF page 61

Document Ac„s igi@SP; Q -16A-1.8-3F-A;Cument:Flild ]Egg A5A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 195 -
than the Co-Located Load designated in its Service Agreement or the transmission service to third parties.

b. Response Briefs
416.
ODEC requests clarification regarding how PJM's requirement that an Eligible Customer taking transmission service on behalf of a Co-Located Load provide PJM with an authorization or certification from its RERRA which affirms that the Eligible Customer is authorized to provide energy to the Co-Located Load would apply to a generation and transmission electric cooperative like ODEC.902  ODEC states that it is unclear whether PJM intends that ODEC, as an Eligible Customer, would need to provide certification that ODEC' s member distribution cooperatives (which are the RERRA in Maryland and Delaware) have authorized ODEC to provide energy to the Co-Located Load. ODEC adds that, where the state regulatory agency is the RERRA, ODEC is unaware of a procedure whereby it would obtain authorization from the Virginia State Corporation Commission to provide energy to Co-Located Loads.

417.
Constellation opposes PJM's proposal that the Eligible Customer must submit an authorization or certification from the RERRA affirming that the Eligible Customer is authorized to provide energy to the Co-Located Load.903  Constellation argues that, if the generator is the Eligible Customer, it is unreasonable to require that generator to go to the state commission for a special approval if the load is in a retail competition state. Constellation maintains that the Eligible Customer need only show that the load will be served by a transmission owner or licensed competitive retail supplier. 418.

Industrials/Amtrak argue that Co-Located Load on whose behalf an Eligible Customer takes NFCD transmission service should have firm natural gas capacity or other adequate alternatives to be able to utilize the service. Industrials/Amtrak argue this requirement will prevent "misuse" of NFCD transmission service "by generators who have the ability to operate but may want to rely on the grid when it appears to be more economical for that generator."9°4  Industrials/Amtrak explain that, from a resource adequacy perspective, policies surrounding NFCD transmission service should encourage loads to bring their own generation.

419.
Indicated TOs request that PJM add to section 710.1 of PJM's illustrative tariff provisions, as a condition precedent for receiving FCD or NFCD transmission service, a requirement that the Eligible Customer satisfy any load-connection related requirements 9°2  ODEC Response Brief at 6-7.

903 Constellation Response Brief at 29. 9°4  Industrials/Amtrak Response Brief at 24. 352 of 515

PDF page 62

Document A„„sig±Plf;
-filgoq18-34Pcurnent:Flita
@g9: A5A8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 196 -
imposed by the applicable PJM transmission owner.905  Indicated TOs argue that PJM should add language to the list of information in section 710.2 of PJM's illustrative tariff provisions to be provided in an application for FCD and/or NFCD transmission service to the effect that the customer has met applicable load interconnection study obligations. Indicated TOs request that PJM add a placeholder section for listing required control technologies or protection systems to section 5.0 of PJM's proposed Attachment F-4.906 420.

Indicated TOs request that PJM clarify whether the use of "Delivery Point" in section 710.2 subsection (iii) and subclause (i) of section 710.5 is appropriate in light of PJM's proposed definition of Co-Located Load, which is based on facilities located on the same side of the Point of Change in Ownership."'

421.
Indicated TOs contend that PJM should clarify in section 711.3 of PJM's illustrative tariff provisions or in PJM's manuals what constitutes "material changes" for purposes of the annual information updates to be provided by Eligible Customers.908 Indicated TOs argue that PJM should revise section 712.2 of PJM's illustrative tariff provisions to require PJM to notify the affected PJM transmission owner(s) of any request for NFCD transmission service. Indicated TOs argue that PJM should revise section 713 of PJM's illustrative tariff provisions to require that notice of any curtailment be provided not only to the Eligible Customer but also to the affected PJM transmission owner or Electric Distribution Company.

422.
Constellation recommends that, for Eligible Customers requesting transmission service on behalf of Co-Located Load, if the customer facilities include an existing generator, a certification be required that the existing generator supports the transmission service request.909  Constellation argues that this requirement would ensure the Co-Located Load is physically connected to the facilities of the existing or planned Customer Facility. Alliance promotes their framework for looking at how to responsibly enable large-load integration while preserving reliability, cost causation, and affordability.910

905 Indicated TOs Response Brief at 18. 906 Id. at 19, 24. 907  Id. at 18-19 n.41. 9°8  Id. at 20-22.
909 Constellation Response Brief at 30. 91°  Alliance Response Brief at 2. 353 of 515

PDF page 63

Document AccessigPIr; 2kAqq-18 _3g99urnent:FiA, rpAg9: 835/18/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 197 -
c. Reply Briefs
423.
In response to parties' comments, particularly those of Indicated TOs, PJM proposes certain revisions to its illustrative tariff language for FCD and NFCD transmission services.911  Specifically, PJM notes that it proposes revisions to section 711.3 to provide that the applicable transmission owner will be notified of material changes to Co-Located Arrangements, as well as a reference to the PJM manuals for further description of what would constitute a material change. PJM further proposes changes to section 713.1 to provide that PJM will notify the applicable transmission owners of any instruction to curtail Co-Located Load.

424.
Constellation urges the Commission to deny Indicated TO.,; proposal to replace "Delivery Point" with "Point of Change in Ownership" in PJM's requirements for applications for FCD and NFCD transmission services because it would risk uncertainty or delays for parties in Co-Location Arrangements.912  Constellation asserts that the Tariff should use "Point of Interconnection," consistent with the definition of Co-Located Load. 425.

Since filing its initial brief, PJM states that it has determined that changes to Auction Revenue Rights rules must be modified to recognize that FCD transmission service customers will contribute towards enhancing and maintaining the transmission system and should have the right to request Auction Revenue Rights.913  To effectuate this modification, PJM proposes a revision to Operating Agreement, Schedule 1, section 7.4.2(d) and includes a new Operating Agreement, Schedule 1, section 7.4.2(1) to detail the Auction Revenue Rights rules specific to Eligible Customers taking FCD transmission service.914

d. Determination
426.
We disagree with PJM that it is just and reasonable for the replacement rate to require Eligible Customers requesting FCD or NFCD transmission service to provide an authorization or certification from its RERRA affirming that the Eligible Customer is authorized to provide energy to the Co-Located Load."' PJM does not provide any explanation or context for proposing this requirement, and it is not clear why an Eligible

911  PJM Reply Brief at 62-63.
912  Constellation Reply Brief at 9 (citing Indicated TOs Response Brief at 19).
913  PJM Reply Brief at 65.
914  Id. at 65-66. 915  PJM Initial Brief at 18-19. 354 of 515

PDF page 64

Document AccessigP.
qq2.4_,18 _3L29cument:Flil d  &qv: A5A8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 198 -
Customer would need to go through this extra step under the Tariff to prove it is authorized to serve load. If an Eligible Customer that is not authorized to provide energy to load attempts to do so, that would be a matter for the RERRA's enforcement mechanisms.

427.
We similarly disagree with Constellation that it is necessary to require Eligible Customers requesting FCD or NFCD transmission service on behalf of Co-Located Load to include a certification from the Co-Located Generator, if it is an existing generator, to ensure that the Co-Located Load is physically connected to the generator's facilities. The Commission already made clear that Co-Located Load must be "physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer's side of the Point of Interconnection to the PJM Transmission System."916  If an Eligible Customer attempts to request FCD or NFCD transmission service on behalf of a load that did not meet the definition of Co-Located Load, that should be referred to the Commission's Office of Enforcement and Regulatory Accounting.

428.
Industrials/Amtrak argue that Co-Located Load on whose behalf an Eligible Customer takes NFCD transmission service should have firm natural gas capacity or other adequate alternatives to be able to utilize the service.917  Industrials/Amtrak explain that such a requirement would "avoid misuse of the [NFCD transmission] service by generators who have the ability to operate but may want to rely on the grid when it appears to be more economical for that generator." The December Order contained no such limitation and Industrials/Amtrak have failed to justify adding it here. Specifically, the December Order stated that NFCD transmission service would reflect Eligible Customers taking service on behalf of Co-Located Loads that may not "necessarily plan to withdraw energy from the transmission system on a regular basis" but "still seek to withdraw energy from the transmission system from time to time when transmission capacity is available and not needed by firm customers."918  The December Order thus contemplates that NFCD transmission service would be an option for Eligible Customers taking transmission service on behalf of Co-Located Load, not a mandate. 429.

Indicated TOs request that the Commission direct as part of the replacement rate requirements related to Eligible Customers satisfying requirements related to load interconnections.919  Indicated TOs have not explained why these requirements are

916  December Order, 193 FERC 1161,217 at P 1 & n.3; February Order, 190 FERC IT 61,115 at P3 & n.4.
917  Industrials/Amtrak Response Brief at 24.
918  December Order, 193 FERC ¶ 61,217 at P 214.
919  Indicated TOs Response Brief at 18-19. 355 of 515

PDF page 65

Document A.c.„sigP#::
LPAW: °A812 pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 199 -
necessary, and so we decline to make them a part of the replacement rate at this time. However, we agree with Indicated TOs' request that PJM add a placeholder section for listing necessary control technologies and/or protection systems to section 5.0 of PJM's proposed Attachment F-4.

430.
We also find PJM's proposal to allow FCD transmission service customers to request Auction Revenue Rights in stage 2 of the allocation process to be just and reasonable. Given the underlying design of the FCD transmission service, we find the presumption that FCD transmission service customers contribute towards enhancing and maintaining the transmission system on par with other Firm PTPS transmission customers to be reasonable. PJM's proposal provides FCD transmission service customers an equivalent opportunity to request Auction Revenue Rights. We direct PJM to submit a compliance filing within 60 days of the date of issuance of this order to revise its Tariff consistent with this replacement rate. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we further direct PJM to reflect this change in its compliance filing.

B. Additional Charge for Eligible Customers Taking FCD and/or NFCD
Transmission Service
1. December Order
431.
As part of the paper hearing, the Commission asked the parties:
Should the rate paid by an Eligible Customer on behalf of a
Co-Located Load taking only the new Non-Firm Contract
Demand transmission service that elects to not reserve any
amount of that service for a period of time (e.g., one month)
reflect not only charges for regulation and black start
services, but also an additional charge given that regulation
and black start services could not be provided without the
transmission system? If so, how should that additional charge
be determined?
432.
In addition, the Commission asked:
Should the rate paid by an Eligible Customer on behalf of a
Co-Located Load taking only a de minimis amount of the new
Firm or Non-Firm Contract Demand transmission services
reflect not only (i) charges for regulation and black start
service and (ii) the transmission service charges for that
de minimis amount of service, but also an additional charge
356 of 515

PDF page 66

Document AccessigPV; -2521q4518-31:2E6ument:Flild rpa'qg.e: A5A8/2pate Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 200 -
reflecting that the Co-Location Arrangement is physically
connected and synchronized to the PJM transmission system?
If so, how should that additional charge be determined?
2. Initial Briefs
433.
Indicated TOs propose to charge a Grid Reliance Charge to Eligible Customers taking FCD or NFCD transmission service based on the difference between either the contract amount of FCD transmission service, or the reserved amount of NFCD transmission service, and the customer's gross on-site load.920  Indicated TOs explain that the Grid Reliance Charge is designed to reflect the costs of using the transmission system to deliver black start and regulation services, as well as the inherent benefit that all customers receive through their synchronization to and reliance on the transmission system. Indicated TOs state that the Grid Reliance Charge also recognizes the costs associated with the operations, maintenance, and other activities that Indicated TOs will need to perform for the transmission system and to accommodate the increased number of protection schemes required for Co-Location Arrangements. Indicated TOs propose to calculate this charge for each zone based on an average fixed percentage of the portion of transmission depreciation and operations and maintenance expense associated with providing grid reliance services, and to apply that percentage to each transmission owner's annual revenue requirement.921  Indicated TOs argue that it is appropriate to use annual depreciation and operations and maintenance expenses because these expenses best capture the portions of a transmission owner's revenue requirement relating to the ongoing reliable operation of the transmission system. Indicated TOs propose an initial percentage of 25.8%, subject to adjustment every five years.

434.
In further justifying the Grid Reliance Charge, Indicated TOs assert that Co-Located Load and its associated Co-Located Generator benefit from the existence and reliable operation of the transmission system because they are electrically connected to the transmission system, and should contribute to paying the costs of continuing to reliably operate the system regardless of the amount of energy withdrawn. Indicated TOs contend that a large Co-Location Arrangement with zero MW of FCD or NFCD transmission service still depends on the grid for the delivery of various ancillary services and a suite of synchronization support services, such as stable frequency, inertia, stability services, fault current capability, and ride-through and protection coordination. Indicated TOs argue that the Commission has long recognized that an integrated transmission

920  Indicated TOs Initial Brief at 14.
921  Id. at 14-16. 357 of 515

PDF page 67

Docufnelit AccessigPV: 2.2q-Argbq-1 8 _3P9cUrnerlt:Flild rpAp: A5/48/2 p-Ate Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 201 -
system provides broad reliability benefits to all customers of the system, and this recognition has guided Commission decisions on ratemaking and cost allocation.922 435.

Indicated TOs maintain that their proposed methodology for the Grid Reliance Charge is a just and reasonable way to estimate with an appropriate level of precision the benefits to Co-Located Load from relying on the grid while ensuring this charge can be fairly and efficiently implemented.923  Indicated TOs state that they have included detailed testimony on the proposed methodology, and they highlight that the allocator is based on costs included in transmission plant and transmission operations and maintenance FERC accounts.924  Indicated TOs contend that their proposal is conservative in a number of respects, for example, they exclude amortization and general plant depreciation, as well as administrative and general expenses. Indicated TOs explain that the allocator will be multiplied by each transmission owner's rate for NITS and FCD transmission service, resulting in an "unadjusted" Grid Reliance Charge rate. Indicated TOs further explain that they propose to multiply this unadjusted rate by a ratio that accounts for the difference between the demand used to account for the NITS and FCD transmission service rate and the gross load for Eligible Customers on behalf of Co-Located Load, resulting in the final Grid Reliance Charge for each zone. Indicated TOs propose to update the allocation percentage every five years to ensure rate stability and avoid the allocators becoming stale. Indicated TOs propose to apply the revenues from the Grid Reliance Charge as credits to NITS and FCD transmission service customers in the relevant zone to avoid double recovery or inappropriate cost shifts.

3. Response Briefs
a. Basis for an Additional Charge
436.
ODEC and NOVEC support Indicated TOs' proposal for a Grid Reliance Charge to be applied to customers taking FCD and NFCD transmission service.925  ODEC argues such a charge ensures that Co-Located Loads pay their "fair share" of costs that are commensurate with the benefits Co-Located Loads receive from the transmission system, including the costs associated with delivery of black start and regulation services. NOVEC similarly asserts that Co-Located Load depends on the transmission system to deliver black start and regulation services, the charges for which a delivery component is

922  Id at 15-16 (citing W. Mass. Elec. Co. v. FERC, 165 F.3d 922, 927 (D.C. Cir. 1999)).
923  Id at 16.
924  Id. at 16-18.
925  ODEC Response Brief at 10; NOVEC Response Brief at 9. 358 of 515

PDF page 68

Document Accessig@A 2A-2.36 18 _3Q9cument:Fl il d  Ipp:
8, 2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 202 -
not included. NOVEC argues that without the Grid Reliance Charge, a Co-Located Load that reserved no FCD or NFCD transmission service would be a free rider, as it would benefit from the payments of existing transmission customers to maintain the transmission system without making any contribution towards it.

437.
Geronimo Power argues that Indicated TOs have not demonstrated that their proposed Grid Reliance Charge reflects Co-Located Loads' actual impact on or benefits from interconnection with the transmission system and is consistent with cost causation principles.926  Further, Geronimo Power states that Indicated TOs have failed to demonstrate that there is a separate delivery component to black start and regulation services and that, if there were such a component, Indicated TOs have not explained why it would not be unduly discriminatory to apply it only to Co-Located Loads. 438.

Vistra argues that Indicated TOs fail to address the nuances in the Commission's paper hearing questions on additional charges or the actual ways that NFCD transmission service customers might rely on the grid.927  Vistra asserts that the Commission's questions illustrate that customers could use NFCD transmission service in different ways but transmission owners would impose the same charge regardless. Vistra maintains that, while Indicated TOs argue that Co-Located Loads are all synchronized to the grid, synchronization is not, itself, a service. Vistra alleges that, in contrast to the Commission's long-standing policy that transmission providers offer and price ancillary services separately, Indicated TOs create a new service for what appears to be an undefined ancillary service (i.e., grid reliance) to cover a suite of synchronization support services. Vistra argues that it is not consistent with cost causation principles to impose the same grid reliance charge for very different types of grid reliance. Vistra contends that the Commission did not prejudge whether or when a grid reliance charge is necessary and that the Commission could conclude no such charge is necessary for customers taking zero MWs or a de minimis amount of the new transmission services. 439.

Industrials/Amtrak argue that, as an as-available service, there should be no standby fee charging NFCD transmission service customers for access to the transmission system that is not guaranteed. Instead, Industrials/Amtrak contend that customers should be charged based on actual use on an hourly basis.928

926 Geronimo Power Response Brief at 10-11, 13-14.
927  Vistra Response Brief at 19-21.
928  Industrials/Amtrak Response Brief at 24. 359 of 515

PDF page 69

Document A„e6sigiPg 2q-Agg11.8-3g9cUMent:Filtd rPA99: A6A8/2PAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 203 -
b. Methodology for Determining Additional Charge
440.
NOVEC states that the proposed Grid Reliance Charge is just and reasonable because it is limited to depreciation and operations and maintenance, and conservatively excludes a return on rate base and associated income taxes.929  NOVEC also notes that because revenues earned from the Grid Reliance Charge are returned to NITS and FCD transmission service customers as a revenue credit, the structure avoids any risk of double recovery.

441.
Alliance argues that the additional charge question is important and should be resolved in a way that protects other customers from unjustified cost shifts.93°  Alliance takes no position on a specific dollar figure; instead, it recommends that any additional charge reflect the contributions of load that have efficient operations or verified load flexibility through reductions in their cost obligations.

442.
Regarding Indicated TOs' argument that the Grid Reliance Charge will also cover costs associated with the protection schemes for Co-Located Load, Geronimo Power argues there is no reason to believe transmission owners will bear any such costs that could not be addressed in interconnection agreements.93'

443.
Vistra argues that, even if some charge is appropriate, Indicated TOs have not justified their proposed rate.932  Vistra contends that it is unreasonable to propose that a customer that never takes transmission service receives benefits approximating 25.8% of the transmission owners' revenue requirement. Vistra highlights that only 0.5% of PJM's monthly total billings are related to black start and regulation charges and that, to the extent an NFCD transmission service customer never reserves transmission service relies on the transmission system, that reliance is for the sole purpose of receiving black start and regulation service. As such, Vistra argues, the percentage of PJM's total monthly billings that relates to black start and regulation charges is a reasonable proxy for the amount of transmission system costs that are associated with use of the grid to deliver black start and regulation service.

444.
Vistra also contends that Indicated TOs' proposal conflicts with the Commission's transmission pricing policy because it disincentivizes efficiency and focuses on reallocating a large share of sunk costs. Moreover, Vistra contends, Indicated TOs'

929  NOVEC Response Brief at 10. 930 Alliance Response Brief at 4. 931  Geronimo Power Response Brief at 14.
932  Vistra Response Brief at 21-23. 360 of 515

PDF page 70

Document AccessigSg 'Q''Aq418-34@cument:Flild rpa'gg:A6/1812pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 204 -
proposal would create significant and unjustified cost shifts between NFCD transmission service customers and Network Customers."' Vistra suggests it is not clear what transmission owners, which are major Network Customers, will do with the bill credits and that it is not a foregone conclusion that they will pass savings onto retail customers. 445.

Constellation contends that Indicated TOs' proposed Grid Reliance Charge rests on an unsound methodology that violates cost causation principles.934  Constellation requests that the charge be recalculated based on the "minimum system" method. Constellation asserts that Indicated TOs both exclude reasonable costs and include unreasonable costs in the grid reliance capability operations and maintenance and provide very little justification for their proposal. Moreover, Constellation argues that Indicated TOs inappropriately include full depreciation costs for a variety of transmission components that are sized to meet actual peak demand requirements of the PJM system, even though customers paying the Grid Reliance Charge do not withdraw energy from the PJM system. In support of the minimum system method, Constellation argues it is designed to calculate the set of costs that a Co-Located Load that benefits from the existence of wires but imposes no demand on the grid should share. Constellation explains that its method involves determining the minimum size of all electricity system components that could be used by the utility to recreate its system and connect each customer to the grid, and then applying this fraction to each transmission owners' NITS rate.

4. Reply Briefs
a. Basis for an Additional Charge
446.
Indicated TOs contend that being connected to the grid provides obvious benefits in terms of the ability to access resources that are not co-located with load.935  Indicated TOs further argue that being connected to the grid includes benefits like delivering ancillary services and essential reliability services, such as frequency support, inertia, voltage stability, fault current capability, ride-through and protections coordination, and providing sufficient short-circuit capability. Indicated TOs state that they are unaware of any existing or proposed Co-Located Load customers that are choosing to island their load and on-site generation, and they infer from that fact that Co-Located Loads should 933  Id. at 23-25.

934  Constellation Response Brief at 25-28.
935  Indicated TOs Reply Brief at 22 (citing Joint Blazunas/Schafer/Hammer Rebuttal Test. at 16); see also Joint Blazunas/Schafer/Hammer Rebuttal Test. at 31. 361 of 515

PDF page 71

Document A„essigPSA: qc1"2-%Qq1 8 -.349 urnent:Flita rEN9:4,48/2 pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 205 -
share in the basic costs of operating and maintaining the grid upon which they rely.936 Indicated TOs further argue that an additional charge is appropriate because ancillary services such as black start and regulation provide no value without the ability to access the transmission system to obtain them.937

b. Methodology for Determining Additional Charge
447.
Indicated TOs defend their proposed methodology, arguing that it produces a more conservative result focused on recovery of the costs necessary to support the ongoing reliable operation of the transmission system, rather than a return on investment.938 Indicated TOs criticize Constellation's proposal to use the "minimum system" method, arguing that it is not used at the transmission level and lacks any correlation between the benefits Co-Located Load receives and the electrical connection of customers. Indicated TOs also reject Vistra's proposed methodology, arguing that Vistra draws no connection between the percentage of billed revenue for regulation and black start and the costs of the transmission system to deliver those services and the benefits associated with grid connection.

448.
NOVEC argues that Constellation's minimum system proposal is not cost-aligned with the use of black start service or regulation service because black start service relies on the existence and durability of the transmission system in a way that Constellation's minimum system methodology does not capture.939  NOVEC further argues that the ratio method advanced by Vistra arbitrarily confuses the cost of black start and regulation services with the cost of the transmission infrastructure necessary for customers to receive them.

449.
Joint Co-Location Developers argue that the proposed Grid Reliance Charge is derived from an unsound methodology that violates cost causation principles.940  Joint Co-Location Developers argue that the Commission should direct the PJM transmission

936  Indicated TOs Reply Brief at 22.
937  Id. at 22-23.
938  Id. at 24, 26-27, 29.
939  NOVEC Reply Brief at 23, 26. 94°  Joint Co-Location Developers Reply Brief at 3 (citing Constellation Response Brief at 25; Geronimo Power Response Brief at 9-15; Vistra Response Brief at 18-23). 362 of 515

PDF page 72

Document AccessigPSg 2A72-YRI. 8 - 3QiNument:Fl it d rfal@g: A6/48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 206 -
owners to adopt the alternate cost calculation framework proposed by Constellation, which follows the Commission's cost causation principles."'

450.
Industrials/Amtrak argue that the proposed Grid Reliance Charge fails to reflect how different customers actually rely on the transmission system and would result in customers that take little or no energy from the grid subsidizing traditional network customers, violating cost causation principles.942  Industrials/Amtrak argue that NFCD transmission service should not be charged a standby fee such as the Grid Reliance Charge, as NFCD transmission service does not provide any guaranteed availability.

5. Answers
451.
Constellation contends that Indicated TOs' proposal would force customers that do not impose demand on the transmission system to pay for transmission components sized to serve peak load, while also arbitrarily excluding costs related to rate of return and taxes.943  Constellation defends its proposed minimum system methodology. 452.

Geronimo Power asserts that, while it does not oppose the concept of a grid reliance charge, Indicated TOs continue to fail to show that it is necessary and reflects Co-Located Loads' actual grid impact or the transmission service they will receive.944 Geronimo Power argues that Indicated TOs' proposal to assess a charge for the delivery of black start and regulation service when other customers are not required to pay a separate delivery charge is unjust, unreasonable, and unduly discriminatory or preferential.945  Geronimo Power maintains that Indicated TOs have not demonstrated that the purported synchronization benefits will accrue to the same degree for Co-Located Load that is being primarily supplied by on-site generation.946

453.
Indicated TOs respond to Constellation's argument that the Indicated TOs' proposed charge is based on the cost of the transmission system to serve peak demand rather than to delivery ancillary services, arguing that the purpose of the Grid Reliance 941  Id. at 4 (citing Constellation Response Brief, attach. 1, (Testimony of Zachary Ming), at 14-15).

942  Industrials/Amtrak Reply Brief at 11-12, 14.
943  Constellation May 11 Answer at 11-12.
944  Geronimo Power May 21 Answer at 10.
945  Id. at 11.
946 1d. at 12. 363 of 515

PDF page 73

Document AccessigiSP: 22q-A-,1 8  _3pwument:FlAd rp,Ag9: A6A 8/2  pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 207 -
Charge is not only to recover costs to deliver ancillary services, but to ensure Co-Located Load customers pay their fair share of the transmission system as it exists and the associated benefits that it provides to all interconnected customers, including essential reliability services.94' Indicated TOs maintain that their proposed charge does so by calculating the annual depreciation and operations and maintenance expenses that constitute a reasonable proxy for the costs of providing those benefits. Indicated TOs assert that Constellation's minimum system method is only appropriate for and applicable to distribution level service.

6. Determination
454.
In the December Order, the Commission sought briefing on whether the
Commission should establish an additional charge for Eligible Customers on behalf of a Co-Located Load that elects to not reserve any amount of transmission service or only a de minimis amount of transmission service.948  In response, parties submitted briefs addressing a range of issues, including, among others: (1) what potential benefits Eligible Customers that are synchronized to the transmission system might receive when not drawing energy from the transmission system; (2) whether those potential benefits warrant an additional charge or are adequately addressed through any transmission service charges that the Eligible Customer is already responsible for; and (3) proposed rates for such a charge and whether those proposed rates are consistent with cost causation principles.

455.
We have considered that record and conclude that it does not adequately substantiate the need for an additional charge at this time or how such a charge should be calculated and assessed. In particular, the record contains insufficient description of the potential nature or magnitude of the cited benefits or the potential costs that transmission providers or owners may incur when providing these benefits to Eligible Customers on behalf of Co-Located Loads. For example, Indicated TOs state that, even where an Eligible Customer has requested FCD or NFCD transmission service for 0 MW, a large Co-Location Arrangement will still depend on the transmission system for a suite of synchronization support services, such as stable frequency, inertia, stability services (damping, angle stability), fault current capability, and ride-through and protection coordination.9" However, beyond briefly listing such benefits, the record lacks specificity regarding what these services are, what costs they involve, and how they 947  Indicated TOs May 28 Answer at 11.

948  December Order, 193 FERC ¶ 61,217 at P 219, questions 3 and 4. 949  Indicated TOs Initial Brief at 15. 364 of 515

PDF page 74

Document AccessigPSA:  22Q-2-YRI.8-3QPc ument FlAd
AK8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 208 -
benefit Eligible Customers on behalf of Co-Located Loads. Accordingly, we decline to establish an additional charge at this time.

456.
Nonetheless, we recognize that the new transmission services created in this proceeding could raise novel questions regarding application of cost causation principles, particularly if, in practice, many Eligible Customers taking the new transmission services on behalf of Eligible Load elect to take a de minimis or not reserve any amount of transmission service. We believe that experience with the actual use of these new transmission services will improve our understanding of any potential issues and inform whether future action is needed. To the extent parties identify such issues resulting from how Eligible Customers on behalf of Eligible Load use the new transmission services, they may submit filings under FPA section 205 or complaints under FPA section 206, as appropriate, and the Commission will consider the records before us at that time.

C. Interconnection Requirements and Operational Practices for
Necessary Control Technologies and/or Protection Systems
1. Initial Briefs
457.
PJM states that NERC has established reliability standard requirements for the various forms of control technologies that may be relied upon for grid stability to which Eligible Customers are expected to adhere.95°  PJM explains that the PJM manuals and, as applicable, NERC reliability standards will contain the interconnection requirements and operational practices needed for necessary control technologies and protection systems to maintain system reliability if a Co-Located Load or Co-Located Generator trips offline. PJM asserts that the NERC reliability standards form baseline interconnection requirements and operational practices, and the PJM manuals provide additional details and, at times, more stringent standards for remedial action schemes. PJM describes an illustrative list of interconnection requirements and operational practices in its brief, including NERC Reliability Standards PRC-012-2 and PRC-017-1, PJM Manual 3, section 1.8, and PJM Manual 7, section 17.2.951

458.
Indicated TOs do not offer a specific proposal at this time, but they highlight concerns and key elements relating to interconnection, planning, and operational practices for the new transmission services.952  Indicated TOs assert that it is novel to use multiple special protection schemes/remedial action schemes to protect the grid from large amounts of on-site load exceeding their contractual withdrawal limitations. 95°  PJM Initial Brief at 56-57.

951  Id. at 57-58.
952  Indicated TOs Initial Brief at 22-26. 365 of 515

PDF page 75

Document Accessig
qPiAgg-1.8-348cument:Flild EpAg:A6A8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 209 -
Indicated TOs recommend that all special protection schemes and remedial action schemes be fully redundant to protect against the failures of protection schemes. Indicated TOs recommend that the Eligible Customer taking FCD transmission service, NFCD transmission service, or Interim NITS on behalf of Co-Located Load pay for PJM- and transmission owner-administered studies to ensure any special protection schemes or remedial action schemes can mitigate the risks of potential failure modes. Indicated TOs request the option to review and agree to curtailment procedures and operational control mechanisms. Indicated TOs argue that all special protection schemes and remedial action schemes must meet PJM and transmission owner technical criteria. 459.

Indicated TOs state that the Commission should consider requiring more frequent testing of special protection schemes and remedial action schemes than is currently required by NERC reliability standards. Indicated TOs argue that they and PJM should receive test results of protection schemes and that any inadequate special protection schemes or remedial action schemes should be updated accordingly. Indicated TOs argue that they and PJM should be permitted to implement and enforce reasonable limits on the total amount of load that can be covered by special protection schemes or remedial action schemes. Indicated TOs request that the Commission direct NERC to establish requirements so that Eligible Customers taking FCD transmission service, NFCD transmission service, or Interim NITS on behalf of Co-Located Loads would be responsible for meeting relevant NERC reliability standards. Indicated TOs contend that the Commission must strictly enforce compliance with NERC Reliability Standard PRC-012-2 (Remedial Action Schemes), which includes nine requirements to address all aspects of remedial action schemes. Indicated TOs also emphasize that they will need to perform load integration studies for any Co-Located Load, as they currently do for large load customers, which could involve analysis of whether upgrades are needed to accommodate the physical gross load behind the Point of Interconnection.

2. Response Briefs
460.
Vistra opposes Indicated TOs' request to implement and enforce limits on the amount of load that can be covered by special protection schemes, including in certain areas.953  Vistra expresses concern that this limit could lead to undue discrimination, and argues that if the Commission permits such limits, the Commission must ensure standardized and transparent guidelines are in place. Vistra contends that Indicated TOs' proposal would violate the comparability requirement because PJM's existing procedures do not include location-based restrictions for remedial action schemes. Vistra also opposes Indicated TOs' proposal to own special protection schemes, arguing that it would needlessly raise the cost of transmission service.

953  Vistra Response Brief at 27-28, 31. 366 of 515

PDF page 76

Document AccessigPSK 2A-AA18 -31?Pcument:FlA d  rpAgp:A6A8/2p,,aje Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 210 -
461.
NOVEC states that at a minimum, PJM's proposal to incorporate NERC reliability standards is just and reasonable.954  NOVEC also states that the Commission should direct NERC to establish registration requirements for Co-Located Loads so that they can be responsible for meeting NERC reliability standards.

462.
NOVEC states that special protection schemes should be fully redundant and that the applicable transmission owner should be able to establish technical criteria for the interconnection of Co-Located Load.955  NOVEC argues that transmission owners are familiar with the operating characteristics of their own systems, and any criteria should be flexible enough to include reasonable requirements the transmission owners believe are necessary to protect the transmission system.

463.
Industrials/Amtrak argue that, to the extent that special protective schemes are required by the Commission for access to NFCD transmission service, the requirements should account for realistic on-site constraints, such as certain load/generation configurations that allow only a limited amount of draw from the transmission system.956 464.

In response to PJM's Initial Brief, Indicated TOs argue that any Eligible Customer taking any of the new transmission services (including FCD transmission service) ought to comply with requirements to implement necessary control technologies and protection systems to ensure that a Co-Located Load does not exceed its specified level of service.957  Indicated TOs therefore request that PJM add language to section 708(c) of PJM's illustrative tariff provisions making clear that Interim NITS, FCD transmission service, and NFCD transmission service are contingent on the implementation of necessary control technologies and protection systems, where applicable. Relatedly, Indicated TOs propose to strike the phrase "only in the case of Non-Firm Contract Demand Transmission Service" from subclause (ii) of section 710.5 of PJM's illustrative tariff provisions.958  Similarly, Indicated TOs contend that PJM should revise section 713.6 of PJM's illustrative tariff provisions so as to not limit the requirement to establish necessary control technologies and protection systems to NFCD transmission service.

954  NOVEC Response Brief at 16-17.
955  Id. at 17.
956  Industrials/Amtrak Response Brief at 25.
957  Indicated TOs Response Brief at 7-8, 17-18.
958  Id. at 19-20, 22. 367 of 515

PDF page 77

Document Accessigi?:  qq"23oql 8 - 3ggcLIMent:FlAd LPag9:A6A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 211 -
465.
Indicated TOs argue that PJM should include language in the Tariff making clear that necessary control technologies and protection systems may be required on both the customer's and the transmission owner's side of the Point of Interconnection, including in section 710.5 of PJM's illustrative tariff provisions.959

466.
Indicated TOs argue that it is important for PJM to work with the PJM transmission owners and other stakeholders to develop details on the requirements associated with control technologies and protection systems necessary to ensure that Co-Located Loads do not exceed their relevant withdrawal limitations.96° 467.

Constellation seeks clarification that PJM only intends to apply existing requirements in Manual 3 to Co-Location Arrangements, not to establish new requirements solely for such arrangements.961  Constellation also seeks clarification that PJM does not intend to restrict the use of permanent system protection schemes. 468.

Constellation supports Indicated TOs' first four recommendations, subject to clarification to avoid delay and discrimination.962  For example, while Constellation supports requiring full redundancy for special protection schemes and remedial action schemes, Constellation argues that it is not clear what full redundancy means. Constellation opposes the Indicated TOs' remaining recommendations as unsupported and discriminatory.

3. Reply Briefs
469.
Indicated TOs state that they agree that the transmission owner and customer each may own the circuit breaker(s) and protection systems at their respective facilities and, in response to Constellation, state that the number of breakers will be determined by the transmission owner's and customer's design practices and budgets, as well as the

959  Id. at 8-9, 20. 96°  Id at 9.
961  Constellation Response Brief at 21.
962  Id. at 22-25. More specifically, Constellation supports, subject to clarification, Indicated TOs' recommendations that: (1) all special protection schemes and remedial action schemes be fully redundant; (2) customers should pay for PJM and transmission owner-administered studies to ensure any special protection schemes and remedial action schemes can effectively mitigate the risks of potential failure modes; (3) transmission owners have the option to review and agree to any customer load curtailment procedures or operational control mechanisms; and (4) all special protection schemes and remedial action schemes must fully meet PJM and transmission owner technical criteria. Id. 368 of 515

PDF page 78

Document AccessigPW 2A-Aqq1.8-34Pcument:Flild Ifaiqp:A6)21.8/2pate Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 212 -
transmission owner's technical criteria. Indicated TOs disagree with Constellation's assertion that new technical criteria specific to Co-Located Load need not be added to PJM Manual 3. Indicated TOs argue that such revisions or additions may be unavoidable due to the technical characteristics of Co-Located Load and contend that PJM and the PJM transmission owners should not be restricted from developing and implementing criteria applicable to Co-Located Load as a class if warranted by reasonable technical differences.963

470.
Indicated TOs argue that Constellation's request for the Commission to reject certain recommendations made by Indicated TOs is without merit. Indicated TOs reject Constellation's claim that these recommendations treat Co-Located Loads differently without legitimate basis and explain that certain transmission owners already require protection on their facilities in certain circumstances.964

471.
Indicated TOs argue that Vistra provides no convincing reason for the Commission to reject Indicated TOs' recommendation for reasonable limits on the amount of load covered by special protection schemes/remedial action schemes in specific geographic areas. Indicated TOs acknowledge, however, that implementing such limitations would require the development of further details and guidelines.965 472.

Joint Co-Location Developers argue that PJM and Market Monitor ignore the distinction between simple withdrawal-limiting protection systems that are required by PJM for sites taking non-firm transmission service and standard remedial action schemes.966  Joint Co-Location Developers explain that unlike standard remedial action schemes, which monitor and control components across the grid, simple withdrawal-limiting protection systems monitor and control only facility-internal components, monitoring flows, adjusting consumption or generation at the site level, and disconnecting from the grid if necessary. Joint Co-Location Developers argue that simple withdrawal-limiting protection systems can be relied upon much more extensively than standard remedial action schemes without creating the same complexities and interdependencies.

963  Indicated TOs Reply Brief at 11-13.
964  Id. at 13-14.
965  Id at 14.
966  Joint Co-Location Developers Reply Brief at 6-7. 369 of 515

PDF page 79

Document AccessigPir; Z2-%q1q71 - 312€6ument:FlAd rpAg:A7/ 812 pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 213 -
473.
Joint Co-Location Developers agree with Indicated TOs that all special protection schemes and remedial action schemes should be fully redundant.967

474.
Constellation argues that Indicated TOs' recommendation that PJM impose necessary control technologies and protection systems on both the customer's side and the transmission owner's side of the Point of Interconnection for Co-Located Loads as a default requirement is unsupported and unduly discriminatory.968  Constellation asserts that always requiring double special protection schemes is not good utility practice and would likely be appropriate only in rare situations.969

475.
Constellation contends that system studies of unauthorized use should be standardized, transparent, and based on reasonable assumptions set ahead of time to avoid disparate treatment.97°  Constellation states that PJM can use the standardized study processes and established reliability tests in its existing generator interconnection process and RTEP process to determine whether a special protection scheme is needed. 476.

Constellation argues that criteria for special protection schemes should leverage current RTEP planning criteria to develop specific criteria for Co-Located Load risks that are reasonable and transparent.97I

477.
Constellation asserts that the special protection scheme that PJM requires an Eligible Customer to implement should be commensurate with the risks identified in the studies. Constellation argues that special protection schemes are not appropriate for every situation, and PJM only requires them when studies identify actual overloads and conditions that could cause cascading failures that PJM cannot mitigate through normal operations.972  Constellation contends that double special protection schemes should not be employed when other measures can maintain system reliability and real-time monitoring can address any unexpected reliability issue.973

967  Id. at 7 n.23 (citing Indicated TOs Initial Brief at 23).
968  Constellation Reply Brief at 13-14 (citing Indicated TOs Response Brief at 8).
969  Id at 14 (citing Kormos Aff. ¶¶ 7, 11). 97°  Id at 15. 971  Id at 15-16.
972  Id at 16 (citing Kormos Aff. ¶¶ 5-6).
973  Id at 18. 370 of 515

PDF page 80

Document Accessig@A 2qXR18-399cument:Flild IFAgp: A7A8/ - pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 214 -
4. Answer
478. In response to Constellation, Indicated TOs argue that, in order for an Eligible Customer to take one of the new transmission services, it is necessary and just and reasonable to require an Eligible Customer to include appropriate protection systems.974 Indicated TOs further assert that special protection schemes on the Co-Located Load customer's and the transmission owner's side of the point of interconnection should not be limited to what Constellation claims are higher-risk situations.975  Indicated TOs claim that, without protection system redundancy, the transmission system is at risk.976 Indicated TOs reject Constellation's assertion that PJM should use a PJM-driven study process to evaluate special protection schemes, arguing that special protection schemes and remedial action schemes are within the purview of the transmission owners, and PJM is not equipped to perform these studies. Indicated TOs also allege that the cost to implement protection systems is extremely low compared to other costs to develop and interconnect Co-Located Load and would not be a deterrent.977

5. Determination
479.
We decline to direct PJM's proposal as part of the replacement rate because it does not require Eligible Customers taking FCD transmission service to have necessary control technologies and/or protection systems to limit their energy withdrawals from the transmission system to their contract demand level. We find that PJM's proposal is inconsistent with the directives in the December Order. In the December Order, the Commission found that an Eligible Customer that is willing and able to limit its energy withdrawals from the transmission system under certain conditions should be able to take transmission services on behalf of Co-Located Load that reflect their ability to limit withdrawals.978  The Commission stated that where a Co-Location Arrangement includes special protection schemes that limit its energy withdrawals, it is a just and reasonable replacement rate to allow an Eligible Customer taking transmission service on behalf of such load to take these transmission services.979  We clarify, however, that the December

974  Indicated TOs May 28 Answer at 4.
975  Id. at 5.
976  Id at 6.
977  Id. at 7.
978  December Order, 193 FERC ¶ 61,217 at PP 159-160.
979  Id. PP 204-205. 371 of 515

PDF page 81

Document AccessiggSg
44-20Eg18-3P9c ument:Fl il d
A7;?38/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 215 -
Order did not limit eligibility to take the new transmission services only to Co-Location Arrangements that include a special protection scheme.98°

480.
Based on the record here, we find it just and reasonable that, in order for an Eligible Customer to take Interim NITS, FCD, and/or NFCD transmission services on behalf of any Eligible Load, an Eligible Customer must have necessary control technologies and/or protection systems, which may include a special protection scheme, to limit its energy withdrawals to its contract demand leve1.981  This replacement rate is consistent with prior Commission precedent for interconnection service, which recognizes that these necessary control technologies and/or protection systems are essential to enforce physical limits and ensure system reliability where an Interconnection Customer has requested a level of service below its maximum capacity.982  Further, consistent with the Commission's determination in Order No. 845, nothing prevents an Eligible Customer taking Interim NITS, FCD, and/or NFCD transmission service on behalf of Eligible Load from proposing its own necessary control technologies and/or protection systems for consideration, which may include a special protection scheme.983 481.

PJM's proposal falls short because it does not require Eligible Customers taking FCD transmission service to have necessary control technologies and/or protection systems to limit their energy withdrawals from the transmission system to their contract demand level. As such, PJM would have to rely on penalties that disqualify an Eligible Customer from taking FCD transmission service if the Eligible Customer fails to follow established load shedding and curtailment procedures, and financial penalties for unreserved use of the PJM transmission system, to discourage excess energy withdrawals. However, load shedding and curtailment events for a transmission service that will be treated as the equivalent of NITS for purposes of curtailment will be rare; and PJM itself has stated concerns that financial penalties alone are insufficient to deter 980  Id. P 205 ("For these reasons, in these instances where the Co-Location Arrangement includes special protection schemes that limit its energy withdrawals, we find that it is a just and reasonable replacement rate to allow an Eligible Customer taking transmission service on behalf of such load to take and be charged for new types of transmission service that are alternatives, and not equivalent, to NITS."). 981  While we will continue to use the term "special protection scheme" in this proceeding, we reiterate that this term is equivalent to "remedial action scheme." Id P 204.

982  Reform of Generator Interconnection Procs. & Agreements, Order No. 845, 163 FERC ¶ 61,043, at P 367 (2018), order on reh'g, Order No. 845-A, 166 FERC ¶ 61,137, order on reh'g, Order No. 845-B, 168 FERC ¶ 61,092 (2019).
983  Id P 372. 372 of 515

PDF page 82

Document Accessigi
2A-Ag18-349cument:lild  L'qp:A57/48/2DAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 216 -
unreserved use.984  Accordingly, and consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we direct PJM to file, within 60 days of the date of issuance of this order, a compliance filing with Tariff revisions that require Eligible Customers taking Interim NITS, FCD, and/or NFCD transmission service on behalf of Eligible Loads, to have necessary control technologies and/or protection systems.

482.
We find it just and reasonable for PJM to include the interconnection requirements and operational practices needed for necessary control technologies and/or protection systems in the PJM manuals and, as applicable, to rely on relevant NERC reliability standards, consistent with PJM's current practices. Further, we find it appropriate for PJM to develop new interconnection requirements and operational practices that recognize the unique nature of Co-Location Arrangements and the new transmission services. However, PJM has not, to date, actually proposed any interconnection requirements and operational practices specific to Co-Location Arrangements, nor does PJM indicate which of its existing interconnection requirements and operational practices it will apply to Co-Location Arrangements. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we direct PJM to submit, as part of its compliance filing due within 60 days of the date of issuance of this order, an explanation of what new and existing interconnection requirements and operational practices it will apply to Eligible Customers taking Interim NITS, FCD, and/or NFCD transmission services on behalf of Eligible Load. We agree with Indicated TOs that it is important for PJM to work with the transmission owners to develop specificity regarding the requirements associated with necessary control technologies and/or protection systems necessary to ensure that Eligible Customers do not withdraw energy from the transmission system in excess of their contract demand. 483.

We do not agree that all parties' recommendations to clarify PJM's proposal are just and reasonable, or even within the scope of this proceeding. However, we agree that some guidance on the study and implementation of necessary control technologies and/or protection systems would be of value. Therefore, and consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we explain several principles that PJM's compliance filing should consider.

984  PJM Initial Brief at 50. 373 of 515

PDF page 83

Document Accessiggsp: A-AQ2-,18 _3cpcument:FlAd ripa g9: (3-JA8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 217 -
484.
First, Eligible Customers shall pay for PJM and transmission owner-administered studies to evaluate and design necessary control technologies and/or protection systems, consistent with their responsibilities for the costs of other studies performed as part of the evaluation of their transmission service request. However, the scope of these studies should be defined in the Tariff, consistent with the level of detail for other transmission services, as discussed in Part VI.A.3.985  Furthermore, we reiterate our finding above that an Eligible Customer taking transmission service on behalf of an Eligible Load may propose its own necessary control technologies and/or protection systems for consideration as part of this study, which may include a special protection scheme, although PJM and the transmission owners retain their existing discretion regarding the determination of what is necessary to ensure the reliability of the transmission system. 485.

Second, if a special protection scheme is employed as necessary control technologies and/or protection systems, then such special protection schemes implemented must be, at minimum, fully redundant. Given questions by commenters regarding what "redundant" specifically means, we clarify that such special protection schemes must be able to withstand removal of part or all of one scheme due to a failure, or to allow for maintenance on a scheme, while providing full scheme capability with a functionally equivalent and separate scheme.986

486.
Third, all necessary control technologies and/or protection systems, which may include a special protection scheme, must fully meet PJM and transmission owner technical criteria, as well as any applicable NERC reliability standards. 487.

Fourth and finally, both PJM and the transmission owners shall have the option to review and agree to the implementation of the Eligible Customer's necessary control technologies and/or protection systems as defined in the service agreement, to ensure that it meets both PJM and transmission owner technical criteria, and is capable of limiting withdrawals from the transmission system.

488.
We disagree with Indicated TOs that PJM should include language in the Tariff making clear that necessary control technologies and/or protection systems may be required on both the Interconnection Customer's and the transmission owner's side of the Point of Interconnection. PJM and the transmission owners will, as noted in the principles above, be responsible for evaluating and designing necessary control technologies and/or protection systems for each Co-Location Arrangement. The location or number of devices required should be based on the engineering judgment of PJM and 985  See supra Part VI.A.3.

986  See, e.g., WECC, Remedial Action Scheme Design Guide, § 4.10 (July 2022), https://www.wecc.org/sites/default/files/documents/meeting/2024/WECC%20RAS%20D esign%20Guide%202022.pdf. 374 of 515

PDF page 84

Document AccessiggSP; 22Q-2-18-3QPcument:Fht d  yalq99:,k7/5is
 Date Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 218 -
the transmission owners.987  Similarly, we find that questions of ownership of these facilities, or the potential to earn a rate of return on said facilities, are outside the scope of this proceeding.

489.
In response to Indicated TOs, we find that there is insufficient information in this record to justify allowing them or PJM to implement and enforce limits on the total amount of load that can be covered by a special protection scheme. If PJM or its transmission owners wish to impose a specific limit, they may submit a new filing under FPA section 205 with a sufficient showing, based on experience gained once Eligible Customers begin taking Interim NITS, FCD, and/or NFCD transmission service on behalf of Eligible Load. However, implementation of a special protection scheme should not be universally required as a condition of taking these transmission services; rather, only necessary control technologies and/or protection systems are required. If PJM or its transmission owners wish to limit the use of special protection schemes on their system, they can also design necessary control technologies and/or protection systems for Eligible Customers that do not have a special protection scheme.

490.
We decline to address NOVEC's request that the Commission direct NERC to establish registration requirements for Co-Located Loads. Whereas NOVEC's request may be availing in the context of a FPA section 215 proceeding, the instant case arises under FPA section 206. In addition, NERC is already considering registration requirements for large loads, including potentially Co-Located Loads, as part of its Large Load Action Plan.988

D. Penalty Charge or Other Remedial Action for New Transmission
Services
1. Initial Briefs
491.
PJM proposes different penalties where an Eligible Customer: (1) fails to follow established load shedding and curtailment procedures; (2) relies on necessary control

987  Cf. RWE Clean Energy, LLC v. PJM Interconnection, L.L.C., 194 FERC ¶ 61,212, at P 42 (2026) ("The Commission generally allows transmission providers to exercise their engineering judgment when conducting interconnection studies, including deferring to transmission providers' discretion regarding how to maintain a reliable transmission system."); Order No. 1920-A, 189 FERC ¶ 61,126 at P 450 ("Finally, we clarify that the Commission generally provides transmission providers with the discretion to use engineering judgment in designing and conducting transmission planning studies, and we therefore decline to address Dominion's hypothetical in the abstract.").
988  See NERC, Large Loads Action Plan, https://www.nerc.com/initiatives/large- loads-action-plan (last visited May 15, 2026). 375 of 515

PDF page 85

Document Accessigi
2z -2q:§1.8 - 348c ument:Fl il d 13a.N:A-7/6.8/2Me Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 219 -
technologies or protection systems that fail more than once; and (3) makes unreserved use of the transmission system.989  PJM argues that, where an Eligible Customer fails once to respond to established load shedding and curtailment pfocedures, the customer is disqualified automatically because of the significant reliability risk. PJM asserts that its proposal is just and reasonable and consistent with the key principles that (1) Eligible Customers are willing and able to control their withdrawals from the transmission system and (2) the services are designed to allow PJM to maintain system reliability. PJM proposes that, if the Eligible Customer is taking FCD or NFCD transmission service and is disqualified, such customer may still take NITS or Interim NITS. PJM proposes that, if the Eligible Customer is taking Interim NITS and is disqualified, such customer may take NITS.99°

492. PJM argues that when a control technology or protection scheme misoperates there can be serious consequences.991  PJM proposes that, after one instance of misoperation, the Eligible Customer will be prohibited from taking transmission service or otherwise withdrawing energy from the transmission system for a period of up to 120 days from misoperation to allow for an analysis of the necessary control technology or protection system scheme's operational performance. PJM asserts that this proposed pause is consistent with NERC requirements for an investigation into the operation of a remedial action scheme992  and will allow PJM time to investigate, identify, and implement fixes to better protect the transmission system.993  PJM proposes that, after two instances of misoperation, the Eligible Customer will be automatically disqualified from taking the relevant new transmission service because of the significant reliability risks. PJM asserts that this rule properly balances the need to protect reliability against the desire of an Eligible Customer taking service on behalf of a Co-Located Loads to take a transmission service lesser than NITS because the Co-Located Loads are willing and able to limit their energy withdrawals. PJM maintains that a second instance of a misoperation makes it evident that the necessary control technology or protection system cannot adequately protect the system from the Co-Located Load's unreserved energy withdrawals. PJM explains that an Eligible Customer disqualified from taking FCD or

989  PJM Initial Brief at 40. 990  Id. at 41-43.
991  Id. at 43-44. Misoperation, as contemplated by PJM, relies on and incorporates the term as defined by NERC (e.g., PRC-004-6). See, e.g., NERC, PRC-004-6 — Protection System Misoperation Identification & Correction (June 12, 2025), https://www.nerc. c om/gl ob al as s ets/standards/rel iability-standards/prc/prc-0 04-6.p df.
992  Reliability Standard PRC-004-6.
993  PJM Initial Brief at 45. 376 of 515

PDF page 86

Document AccessigisA: 2A-2-VA18 - 3RPcument:Flild
A57A8/2.pe Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 220 -
NFCD transmission service on this ground may either take NITS or Interim NITS, and that an Eligible Customer disqualified from taking Interim NITS on this ground may take NITS. PJM supports its proposal to permit an Eligible Customer disqualified from taking the new transmission services to take NITS by reasoning that NITS, in and of itself, addresses curtailment, load shed, and control technology or protection scheme misoperation risk.994

493.
PJM states that it supports a penalty for unreserved use in addition to the operational penalties and intends to work with the transmission owners to explore a financial penalty.995  PJM argues that financial penalties alone are insufficient to incentivize Eligible Customers to comply with load shed, curtailment, and control technology and protection system obligations. PJM asserts that many, if not most, Eligible Customers taking service on behalf of a Co-Located Load could elect to absorb financial penalties for unreserved use rather than follow curtailment or load shed procedures or avoid misoperation of the protective technology or system. 494.

Indicated TOs assert that any penalty regime should rely on both operational consequences and complementary financial penalties.996  Indicated TOs allege that it is of the utmost importance that Co-Located Loads respect contractual limits because Co-Location Arrangements involve substantial amounts of load connected to the grid and failure to respect these limits could pose severe reliability consequences for the system. 495.

Indicated TOs support PJM's proposal but argue that additional details must be developed as to how operational consequences would be applied.997  Indicated TOs also state that financial penalties could be valuable where the Eligible Customer exceeds its contract demand, even if such deviations are mitigated by a special protection scheme.

2. Response Briefs
496.
ODEC supports PJM's proposed penalty structure, including operational penalties.998  NOVEC states that disqualification for failure to follow load shedding or

994  Id. at 45-50.
995  Id at 50.
996  Indicated TOs Initial Brief at 19.
997  Id at 20.
998  ODEC Response Brief at 11. 377 of 515

PDF page 87

Documett AccessigPA qq"2-1§A18-31;26)9LIMent:FlAd LFlaqg
4/41812 PAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 227 -
513. Indicated TOs propose to distribute daily, weekly, and monthly penalty revenues on a monthly basis to Eligible Customers taking NITS or FCD transmission service that have not been penalized during the month, as pro rata bill credits. Indicated TOs further propose to distribute annual penalty charges on an annual basis to Eligible Customers taking NITS and FCD transmission service that have not been penalized during the year as pro rata bill credits.1025

4. Answer
514. Constellation alleges that PJM's reliability arguments are not persuasive, because PJM's example involves grid-connected load, not Co-Located Load.102G  Constellation argues that PJM fails to explain how resource adequacy concerns justify its proposed penalty scheme, and points out that PJM has proposed no such penalties for Connect and Manage.1027  Constellation next argues that a four-month suspension is not consistent with NERC requirements, as PJM claims.1028

5. Determination
515.
We find that it is just and reasonable to impose operational and financial penalties on Eligible Customers taking the three new transmission services as part of the replacement rate, given that these services are designed for Eligible Customers taking transmission service on behalf of Eligible Loads that are willing and able to limit their withdrawals from the transmission system under certain conditions, and there are significant reliability risks if Eligible Customers fail to do so. However, we decline to adopt PJM's proposed replacement rate. First, we disagree that it is just and reasonable to disqualify an Eligible Customer from taking any of the new transmission services after the first instance of failing to follow a curtailment or load shedding directive, as discussed below. We instead find that it is just and reasonable to establish an operational penalty whereby, after the second instance of failing to follow a curtailment or load shedding directive, PJM will terminate the transmission service agreement with the Eligible Customer taking Interim NITS, FCD, or NFCD transmission service on behalf of the Eligible Load. We agree with PJM that there are significant reliability risks associated with failing to follow a curtailment or load shedding directive, but we find that PJM's one strike proposal is unnecessarily strict. We direct PJM to file, within 60 days 1°25  Id. at 15-16.

1026  Constellation May 11 Answer at 8-9.
1°27  Id at 9.
1°28  Id at 9-10.
384 of 515

PDF page 88

Document Accessigisne;
ArR g--1. 8  _ 31:2@c ument:FlAd rgqg9:
8.8i2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 221 -
curtailment procedures is necessary to protect the integrity of the transmission system.999 Indicated TOs request that Tariff language be included requiring that the relevant transmission owner's approval be obtained before service to an Eligible Customer is reinstated following a control technology/protection system misoperation. 497.

Constellation opposes the proposal to suspend or disqualify an Eligible Customer, arguing it is excessive and applies regardless of fault and does not apply to Non-Firm PTPS customers.'°°° Constellation urges the Commission to follow SPP's proposal for Conditional High Impact Large Load Service (CHILLS) and align treatment of -

unreserved use for the new services with its treatment of Non-Firm PTPS. DCC expresses concern about PJM's operational penalties in light of the lack of clarity around PJM's curtailment procedures for the new transmission services.1°°1  Vistra similarly argues that PJM's proposed operational penalties diverge from the Commission's directives and violate the comparability principle because the December Order does not contemplate disqualification and, more generally, such a penalty structure exceeds what the Commission has allowed for unreserved use of the transmission system.'°°2  Vistra contends that PJM's proposal is excessively punitive and may be unduly discriminatory in comparison to customers that take PTPS. Vistra also alleges that PJM's proposal also violates the comparability requirement because it treats Co-Location Arrangements using special protection schemes differently from any other entities using such schemes. Vistra also points out that, if the Commission accepts transmission owners' proposal to own special protection schemes, then misoperation of such schemes must attach to the transmission owner, not the Eligible Customer.

498.
Joint Co-Location Developers argue that PJM's proposed penalty provisions are unjust and unreasonable because they are not "narrowly designed to balance the need to deter conduct that is harmful to the system with the need to limit excessive and unnecessary costs."1°°3  Joint Co-Location Developers express concern that PJM's proposed disqualification rules will dissuade Eligible Customers from taking the new transmission services because of the risk of stranding or undermining investments in the

999  NOVEC Response Brief at 11-12. nu  Constellation Response Brief at 19-20. See also Joint Co-Location Developers Response Brief at 25. 1001  DCC Response Brief at 7. 1002  Vistra Response Brief at 29-31. 1003 Joint Co-Location Developers Response Brief at 23 (quoting Mirant Kendall, LLC, 110 FERC ¶ 61,272, at P 17 (2005)). 378 of 515

PDF page 89

Document A„eseigPV; -qAq,448-31?@cument:Filtd rEq99:AR812pAte Filed: 10116/2026 Docket No. EL25-49-002, et al.

- 222 -
new services.1004  Joint Co-Location Developers propose that PJM adopt financial penalties sufficient to deter gaming of transmission service subscription. Joint Co-Location Developers contend that a disqualification-based penalty is not necessary because transmission owners can manually disconnect a facility in case of potential severe reliability risk. Joint Co-Location Developers assert that failure to respond to curtailment would have a similar impact from a resource adequacy perspective to a capacity resource failing to perform during emergency events, in which case only a non-performance charge is assessed. Joint Co-Location Developers urge that, if the Commission adopts disqualification as a penalty, the Commission should adopt intent (or at least fault), materiality, and repetition elements prior to disqualification to ensure disqualification sends an actionable signal.'°°5  Joint Co-Location Developers suggest that that an operational penalty is excessive for misoperation of control technologies or protection systems because misoperation without withdrawal does not risk system harm 1°°6

499.
Indicated TOs propose a financial penalty charge structure with two components:
(1) a base penalty charge; and (2) a penalty ratchet.1°°7  The base penalty charge would be assessed for any hour in which at least one five-minute interval occurs during which a customer's metered load at the Point of Interconnection exceeds its reserved transmission service. The penalty ratchet would apply additional daily penalties if exceedances occurred in more than one hour during a day, additional weekly penalties if exceedances occurred on more than one day during a week, and additional monthly penalties if exceedances occurred in more than one week during a month. Further, each of these penalties would entail escalating financial liabilities for repeated penalties, which Indicated TOs argue would reinforce the expectation that Co-Located Load customers manage their load in a manner consistent with their reserved transmission service. 500.

NOVEC states that a penalty for unreserved use in addition to disqualification and pause-in-service rules is appropriate, as this penalty would be an additional deterrent that would help make the market or other ratepayer whole if a Co-Located Load customer exceeds its contract demand.'°°8  NOVEC suggests that any financial penalty should compensate other customers for any harm caused by the Eligible Customer's departure Imm  Id at 24-25.

1005  Id at 26 (citing PJM Interconnection, L.L.C., 178 FERC ¶ 61,104, at PP 60-61 (2022)).

1006  Id at 26.
1" 7  Indicated TOs Response Brief at 12-13.
1008 NOVEC Response Brief at 13 (citing Indicated TOs Initial Brief at 20). 379 of 515

PDF page 90

Document Accessigtr:4q-2-30QA18-3[2@cument:Flitd
( ,)8/C18/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 223 -
from Co-Location requirements or, if there is no harm, be set at a level sufficient to encourage compliance with the Tariffs scheduling requirements.

501.
ODEC suggests that the Commission also consider whether any protections are needed for local utilities or transmission owners should they need to take the extraordinary measure of disconnecting an Eligible Customer taking service on behalf of Co-Located Loads, if the Eligible Customer's use of the transmission system exceeds contract demand or is called upon for load shedding and curtailment.10°9  ODEC states that, in such instance, the local utility or transmission owner should not be liable for legal, financial, or other damages that might be experienced by an Eligible Customer. NOVEC asserts that PJM's penalty language should be revised to specify that when an Eligible Customer serves multiple Co-Located Loads, only the culpable Co-Located Load is disqualified rather than the Eligible Customer as a whole.'°'°

3. Reply Briefs
502.
PJM argues that monetary penalties, in place of non-monetary penalties, would undermine the value of reliability and hand it to a single site or a class of load that may decide to pay the penalty in place of operating as agreed to ensuring overall system reliability.1011 PJM alleges that non-monetary operational penalties are essential to the responsible integration of large loads. PJM maintains that its non-monetary operational penalties represent a measured approach that balances significant reliability concerns with the interest in integrating large loads quickly. However, PJM notes that, in response to protesters' concerns, PJM proposes revisions to its illustrative tariff language to add discretion to the strict application of non-monetary operational penalties. 503.

PJM argues that the Commission did not foreclose non-monetary penalties because the December Order "also direct[s] parties to brief . . . any other remedial action that PJM should take to address withdrawals in excess of the contract demand."1" 2  PJM also claims that financial penalties alone are insufficient to support reliability in light of the volume of load that is anticipated to come online in short order and the nature of how these new loads will seek to connect through co-location with potentially critical generators. PJM rejects Vistra's contention that non-monetary penalties are a departure from Commission precedent, and responds that the Commission has long held that where monetary penalties do not incentivize actions consistent with reliability, it may be 1009 ODEC Response Brief at 11-12.

1°1°  NOVEC Response Brief at 14-15.
1011  PJM Reply Brief at 40-43.
1°12  Id. at 49-50 (quoting December Order, 193 FERC ¶ 61,217 at P 212). 380 of 515

PDF page 91

Document AccessigPSP; 2q"21
.1.8-3419curnent:Flild rEq99: APA8/2pate Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 224 -
necessary to implement "a range of non-monetary and monetary penalties" to promote behavior that supports and improves the reliability of the bulk power system.1013  PJM rejects Joint Co-Location Developers' suggestion that PJM adopt financial penalties sufficient to deter gaming, and responds that PJM's proposed penalty structure is not intended to address gaming but to support reliability. In response to Joint Co-Location Developers' suggestion that disqualification is unnecessary because transmission owners can manually disconnect a facility, PJM argues that it is inconsistent with reliable operation of the transmission system to shift responsibility away from the Eligible Customer. PJM also alleges that it and the transmission owner will become aware of an improperly set-up protection scheme only after the misoperation incident, which will expose the PJM system to risk. PJM adds that when a transmission owner manually cuts load suddenly, without proper coordination, it can have disastrous and dangerous cascading system effects.'°14

504.
Nevertheless, PJM proposes revisions to its illustrative tariff language to permit, where appropriate, PJM to exercise discretion in determining when disqualification penalties are appropriate based on PJM's assessment of factors including the reliability impact of the failure to curtail or shed load or the misoperation of control technologies or protection system schemes. PJM adds that, with these revisions, the Eligible Customer taking transmission service on behalf of Co-Located Load will not be held liable for the actions of others. 1015

505.
Several parties agree that financial penalties are insufficient to ensure reliability.1016 ODEC asserts that it does not agree that PJM's proposed suspension and disqualification measures are unfairly imposed regardless of fault and will make the services unduly risky for many loads. Earthjustice argues that PJM's operational penalties are proportionate to the prospective harm associated with a customer's failure to follow curtailment orders. Earthjustice argues that, while opposing commenters note that PJM's proposed penalties are stricter than the penalties it has levied in other circumstances, those comments fail to acknowledge that the stakes here are higher. 1013 Id at 51 (quoting Rules Concerning Certification of the Elec. Reliability Org.; and Procs. for the Establishment, Approval, and Enf't of Elec. Reliability Standards, Order No. 672, 114 FERC ¶ 61,104, at PP 49, 455, order on reh'g, Order No. 672-A, 114 FERC ¶ 61,328 (2006)).

'°14 Id at 52-53.
1015  Id. at 54.
1016 ODEC Reply Brief at 4-5; Earthjustice Reply Brief at 2-3, 5, 8; Indicated TOs Reply Brief at 14-15 (citing Joint Blazunas/Schafer/Hammer Rebuttal Test. at 4). 381 of 515

PDF page 92

Document AccessigP#: qq-266A18-349cument:Fht d  yaN9: A8;21812 p1Ate Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 225 -
Earthjustice argues that PJM's penalty proposal is appropriately designed to protect system reliability, rather than assign fault.

506.
Industrials/Amtrak urge the Commission to exercise caution in overly harsh operational penalties, especially for existing retail customers who may be forced to move from retail BTMG arrangements to Co-Location Arrangements. Industrials/Amtrak argue that it is reasonable to pay financial penalties, but a retail customer should not be banned from NFCD transmission service for a lone violation.1017

507.
PJM rejects Vistra's contention that its non-monetary penalties for misoperation of necessary control technologies or protection systems are unduly discriminatory. PJM alleges that NERC, Market Monitor, and PJM's 2026 load forecast each demonstrate that the new large loads integrating into PJM's transmission system are not similarly situated to traditional loads. PJM adds that disqualification penalties do not foreclose Eligible Customers from taking transmission service entirely, and that, where Eligible Customers demonstrate that they cannot (or are unwilling to) limit withdrawals, it is appropriate for those Eligible Customers to take NITS.1°18

508.
Indicated TOs reject Constellation's argument that PJM should simply adopt financial penalties as is the case with SPP's High Impact Large Load (HILL) process.1°19 Indicated TOs argue that SPP's HILL process is different in that, under PJM's proposal, Co-Located Load customers may be in the position of installing and operating their own control technologies and protection systems. Indicated TOs further argue that PJM and SPP are different regions with different characteristics, including topology and proliferation of large loads. Indicated TOs also dismiss DCC's and Vistra's concerns regarding Co-Located Load's liability for penalties associated with control technologies and protection systems operated by other parties, including transmission owners. Indicated TOs argue that installation of redundant protection facilities by transmission owners should not serve as an excuse for the failure of customers to properly maintain and operate their own equipment.

509.
NOVEC states that it generally supports Indicated TOs' proposed financial penalty charge structure, subject to Indicated TOs providing further information.1020  ODEC supports financial penalties but states that PJM's implementation of its penalties must not subject ODEC or its member distribution cooperatives to service interruptions or 1017 Industrials/Amtrak Reply Brief at 17-18.

1018 PJM Reply Brief at 43, 45, 47.
1019 Indicated TOs Reply Brief at 15-16.
1°2°  NOVEC Reply Brief at 26-27.
382 of 515

PDF page 93

Document AccessiggSg Z-P12-1§)?i18-3Q9ument:FlAd
Ag812pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 226 -
disqualification, or financial penalties, as a result of requiring ODEC to serve as the Eligible Customer.1°21

510.
Indicated TOs further explain their financial penalty proposal, explaining that when a Co-Located Load exceeds its reserved transmission service limit, which includes any reductions based on curtailments directed by PJM, the base penalty charge will be assessed for any hour (Exceedance Hour) in which at least one five-minute interval (Exceedance Interval) occurs during which a customer's metered load at the point of delivery exceeds its reserved transmission service. Indicated TOs state that the base penalty charge will apply to each Exceedance Hour.1°22

511.
Indicated TOs state that the base penalty charge will be calculated as the product of the Hourly Exceedance MW, the Equivalent Hourly FCD transmission service rate, and the number of Exceedance Intervals within the hour, where the Hourly Exceedance MW is equal to the maximum telemetered load during the hour less the reserved transmission service limit for the hour and where the Equivalent Hourly FCD transmission service rate is equal to the FCD transmission service rate divided by 8,760 hours.1023  Indicated TOs explain that the FCD transmission service rate is used as the basis for assessing the penalty because, when a customer exceeds its reserved transmission service limit without authorization, the excess usage effectively imposes firm-level demand on the system.

512.
Indicated TOs state that the penalty ratchet applies escalating FCD-equivalent transmission service rates as the frequency of unreserved transmission use increases. Indicated TOs explain that the penalty ratchet applies daily, weekly, monthly, or annual penalty charges depending on whether exceedances occur within the same calendar day, week, month, or year, and that these penalty charges are equal to the Daily FCD-Equivalent Rate, Weekly FCD-Equivalent Rate, Monthly FCD-Equivalent Rate, and FCD Annual Rate, respectively.1°24  Indicated TOs further explain that, where a daily penalty charge is assessed, it is in addition to the base penalty charge applicable to each individual Exceedance Hour; where a weekly penalty charge is assessed, it is in addition to the base penalty charges and daily penalty charges; and so on.

1021  ODEC Reply Brief at 4.
1°22  Indicated TOs Reply Brief at 16-17.
1°23  Indicated TOs Reply Brief, Joint Blazunas/Schafer/Hammer Rebuttal Test. at 8-9.

1°24  Id. at 10-14.
383 of 515

PDF page 94

Document Acc„sigi@SP; 2AAZ18-3Q@cument:Flitd  p@g9: A8/48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 228 -
of the date of issuance of this order, a compliance filing to revise its Tariff consistent with these findings.

516.
Second, we find that it is just and reasonable to establish an operational penalty of suspension in service for a period of up to 120 days for an Eligible Customer taking Interim NITS, FCD, and/or NFCD transmission service after the first misoperation of necessary control technologies and/or protection systems given the reliability risks associated with such misoperation. However, as above, we disagree with PJM's proposal regarding disqualification, and we instead find that it is just and reasonable to establish an operational penalty whereby, after the second misoperation of necessary control technologies and/or protection systems, PJM will terminate the transmission service agreement with the Eligible Customer taking Interim NITS, FCD, and/or NFCD transmission service on behalf of Eligible Load. We direct PJM to file, within 60 days of the date of issuance of this order, a compliance filing to revise its Tariff consistent with these findings.

517.
Third, we find that it is just and reasonable to subject an Eligible Customer taking any of the three new transmission services on behalf of Eligible Load to financial penalties in any circumstance where the transmission customer uses transmission service that it has not reserved. We thus direct the PJM transmission owners to file, within 60 days of the date of issuance of this order, a compliance filing that effectuates Indicated TOs' proposed framework for financial penalties for Eligible Customers taking one of the three new transmission services that withdraw from the transmission system in excess of their contract demand level (i.e., for unreserved use).

518.
Before addressing each topic in turn, as an initial matter, we disagree with protesters that operational penalties, either for failure to follow a curtailment or load shedding directive, or for misoperation of necessary control technologies and/or protection systems, "diverg[e] from" or were "not contemplated" in the December Order.1°29  The financial penalties that the Commission required only apply to Eligible Customers' unreserved use of the transmission system and are consistent with the Commission's directives in the December Order.'°3°  The Commission has previously found that transmission customers should be subject to unreserved use penalties in circumstances where a transmission customer uses transmission service in excess of its 1029 Constellation Response Brief at 19; Vistra Response Brief at 29.

1030 December Order, 193 FERC 1161,217 at P 212 (directing a penalty rate for excess withdrawals of energy from the transmission system by an Eligible Customer taking FCD transmission service on behalf of a Co-Located Load); id. P 217 (directing same as to excess withdrawals by an Eligible Customer taking NFCD transmission service on behalf of a Co-Located Load).

385 of 515

PDF page 95

Document Accessigir; qq"2306,A18-3r-.28curnent:Flil d rPa gp: A8/6.8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 229 -
reserved capacity or if it uses transmission service where it does not have a reservation, and as discussed further below, we find it just and reasonable that an Eligible Customer taking any of the three new transmission services on behalf of Eligible Load incur a financial penalty for unreserved use of the transmission system.1031  But the Commission also directed briefing broadly on the rates, terms, and conditions of the new transmission services, including "other remedial action[s]" in addition to financial penalties, as pertinent to this question.'°32  We find that an operational penalty for Eligible Customers taking Interim NITS, FCD transmission service, and/or NFCD transmission service on behalf of Eligible Load for misoperation of necessary control technologies and/or protection systems is consistent with the December Order's finding that Eligible Customers may take Interim NITS, FCD transmission service, and/or NFCD transmission service because it is the use of necessary control technologies and/or protection systems that effectively limits their energy withdrawals from the transmission system.1°33  The Commission in the December Order also broadly sought briefing on the appropriate procedures to govern circumstances under which PJM curtails an Eligible Customer taking any of the three new transmission services, and we find that an operational penalty for an Eligible Customer taking the new transmission services on behalf of Eligible Load failing to follow a curtailment or load shedding directive is within the scope of provisions that we can consider as part of establishing curtailment procedures for the three new transmission services.

a. Failure to Follow Curtailment or Load Shedding Directive
519.
We find that it is just and reasonable to establish an operational penalty for an Eligible Customer taking any of the new transmission services on behalf of Eligible Load after the second instance of failing to follow a curtailment or load shedding directive. Specifically, we find that it is just and reasonable for PJM to terminate the transmission service agreement with the Eligible Customer taking Interim NITS, FCD transmission service, or NFCD transmission service on behalf of Eligible Load after the second instance of failing to follow a curtailment or load shedding directive. We direct PJM to file, within 60 days of the date of issuance of this order, a compliance filing to revise its Tariff consistent with this finding. PJM persuasively argues that there are significant reliability risks associated with failure to curtail, and "financial penalties, alone, are not sufficient to incentivize Eligible Customers to comply with Load Shed and Curtailment."1034  However, we agree with concerns raised in the record that PJM's 1031 Order No. 890, 118 FERC ¶ 61,119 at P 834.

1032  December Order, 193 FERC ¶ 61,217 at P 219.
1033  Id. P 205; see supra Part VI.C.
1034 PJM Initial Brief at 41-42, 45, 50.
386 of 515

PDF page 96

Document AccessiciPc; 2YAC618-3R@P-Irnent:Filld S'AV: (4A8/2pAte Filed: 10116/2026 Docket No. EL25-49-002, et al.

- 230 -
proposal to disqualify an Eligible Customer taking one of the three new transmission services on behalf of Eligible Load from continuing to take any of those services is unnecessarily strict. When considering the need to ensure reliability is preserved, as well as to allow Eligible Customers taking transmission service on behalf of Eligible Load to adapt to a new transmission service paradigm, we find that, on balance, complete disqualification is excessive because it would impose penalties on the Eligible Customer that apply to all of its transmission service agreements, even those for which it has followed all curtailment or load shedding directives. However, we agree with PJM that a strict operational penalty will deter conduct contrary to the fundamental principle upon which the new transmission services required by the December Order were based, which is that Eligible Customers taking service on behalf of Co-Located Loads are willing and able to limit their energy withdrawals from the transmission system under certain conditions.1035  We therefore find, as part of the just and reasonable replacement rate, that the transmission service agreement with the Eligible Customer taking Interim NITS, FCD transmission service, or NFCD transmission service on behalf of Eligible Load should be terminated on the second instance of failing to follow a curtailment or load shedding directive. The Eligible Customer will remain eligible to take the three new transmission services on behalf of other Eligible Loads through its other transmission service agreements. NITS remains an option for an Eligible Customer disqualified from taking one of the new transmission services; however, such Eligible Customer may not begin taking NITS until all necessary Network Upgrades are completed.1°36

520. Recognizing that we are not adopting the exact penalty framework for failing to follow a curtailment or load shedding directive that PJM proposes, we nevertheless disagree with many of protesters' arguments on this matter. Joint Co-Location Developers, for example, argue that disqualification is not necessary because transmission owners can manually disconnect a facility. This argument supports PJM's premise that a financial penalty alone cannot deter the Eligible Customer taking one of the three new transmission services on behalf of Co-Located Load from failing to control unauthorized withdrawals; instead, it unreasonably and unnecessarily shifts the responsibility to manage complying with the Tariff and the terms of the transmission service from the Eligible Customer to the transmission owners. Joint Co-Location 1035 December Order, 193 FERC ¶ 61,217 at P 177 ("we also find that PJM's Tariff is unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking service on behalf of Co-Located Loads that are willing and able to limit their energy withdrawals from the transmission system under certain conditions.").

1036  See PJM Initial Brief at 43 ("Importantly, however, such an Eligible Customer may take NITS, which would begin after all necessary upgrades are placed into service.").

387 of 515

PDF page 97

Document AccessigPSA: 4q-AQA18-3R9cument:Fhld
X3,818/2
 to Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 231 -
Developers also claim that disqualification is disproportionate and may not send an actionable signal without "fault or materiality elements." This argument is misplaced, as PJM's requirements for the new transmission services make the Eligible Customer's responsibilities clear and actionable: prior to commencement of service, the Eligible Customer must demonstrate to PJM's satisfaction that it can fully comply with load shedding and curtailment procedures. Lastly, Joint Co-Location Developers suggest that, the Commission's approval of a non-performance charge rate for capacity resources that fail to perform in emergency events means that an Eligible Customer that fails to follow a curtailment or load shedding directive can be sufficiently penalized through a similar charge. Joint Co-Location Developers allege that failure to respond or perform in both these circumstances is similar from a resource adequacy perspective. We disagree that the two are comparable. Capacity resources are purchased to meet the needs of transmission customers taking existing firm service, such as NITS. As PJM explains in its initial brief, the choice to take NITS decreases the likelihood of significant issues arising from failure to curtail.1037  By contrast, the Commission created the three new transmission services to reflect that Eligible Customers taking transmission service on behalf of Co-Located Load are willing and able to limit their energy withdrawals from the transmission system under certain conditions that are different than those under which Network Customers take NITS.1038  For these reasons, we find that it is just and reasonable to subject Eligible Customers on behalf of such loads to a stricter penalty regime.

521.
We also disagree with Constellation's suggestion that the Commission should adopt SPP's approach for CHILLS, which contains only penalties for exceeding the transmission customer's reserved capacity.1039  The Commission has permitted regional 1037  Id. at 48-49.

1°38  December Order, 193 FERC 1161,217 at P 2; see, e.g., id. P 208
(distinguishing an Eligible Customer's rights under FCD transmission service in contrast to NITS).

1039  Sw. Power Pool, Inc., 195 FERC ¶ 61,196, at 98 (2026).
388 of 515

PDF page 98

Document Acc„sigPSg 2-ArArCg18-34Pcument:Flild
e:
Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 232 -
variation among RTOs/ISOs'°4°  and need only explain its choice and how it has chosen a just and reasonable rate.'°4'

522. We also find that ODEC has not demonstrated a need, nor does the record developed in this paper hearing otherwise reflect a need, to establish protections for transmission owners if the Eligible Customer may experience damages as a result of the transmission owner disconnecting the Eligible Customer. Lastly, with respect to Joint Co-Location Developers' concern that PJM's proposed disqualification rules will dissuade Eligible Customers from taking the new transmission services because of the risk of stranding or undermining investments in the new transmission services, we note that an Eligible Customer is not required to take the new transmission services and may elect to take NITS if that transmission service option better reflects the Eligible Customer's use of the transmission system and risk profile.'°42

1040 See, e.g., Reg 'l Transmission Orgs., Order No. 2000, FERC Stats. & Regs. 1131,089, at 31,073 (1999) (cross-referenced at 89 FERC ¶ 61,285), order on reh'g, Order No. 2000-A, FERC Stats. & Regs. ¶ 31,092 (2000) (cross-referenced at 90 FERC ¶ 61,201), aff'd sub nom. Pub. Util. Dist. No. 1 of Snohomish Cnty. v. FERC, 272 F.3d 607 (D.C. Cir. 2001) (stating there is no "one size fits all" approach to RTO governance); Offer Caps in Mkts. Operated by Reg'l Transmission Orgs. & Indep. Sys. Operators, Order No. 831, 157 FERC ¶ 61,115, at P 147 (2016), order on reh'g & clarification, Order No. 831-A, 161 FERC ¶ 61,156 (2017) (permitting regional variation for treatment of incremental energy offers above $1,000/MWh that the RTO/ISO or Marketing Monitoring Unit cannot verify prior to the start of the market clearing process); Wholesale Competition in Regions with Organized Elec. Mkts., Order No. 719, 125 FERC ¶ 61,071, at P 62 (2008), order on reh'g, Order No. 719-A, 128 FERC 1161,059, order on reh'g, Order No. 719-B, 129 FERC ¶ 61,252 (2009) (permitting regional variation for RTOs/ISOs developing requirements for demand response resources participating in ancillary service markets).

1041 See ExxonMobil Oil Corp. v. FERC, 487 F.3d 945, 955 (D.C. Cir. 2007) ("We need not decide whether the Commission has adopted the best possible policy as long as the agency has acted within the scope of its discretion and reasonably explained its actions."); Cities of Batavia v. FERC, 672 F.2d 64, 84 (D.C. Cir. 1982) ("[T]he billing design need only be reasonable, not theoretically perfect.").

1042 See PJM Reply Brief at 47 (arguing that disqualification penalties reflect that Eligible Customers take the level of transmission service that aligns with their demonstrated use of the transmission system).

389 of 515

PDF page 99

Document AccessigP SA qq-Aq-18_,RwurnentAlt d EpAg9: ANB/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 233 -
b. Misoperation of Necessary Control Technologies and/or
Protection Systems
523.
We find that it is just and reasonable to establish an operational penalty of suspension in service for a period of up to 120 days for an Eligible Customer taking Interim NITS, FCD, and/or NFCD transmission service on behalf of Eligible Load after the first misoperation of necessary control technologies and/or protection systems. However, as noted above, we disagree with PJM's proposal regarding disqualification, and we instead find that it is just and reasonable to establish an operational penalty whereby, after the second misoperation of necessary control technologies and/or protection systems, PJM will terminate the transmission service agreement with the Eligible Customer taking Interim NITS, FCD transmission service, or NFCD transmission service on behalf of Eligible Load. We direct PJM to file, within 60 days of the date of issuance of this order, a compliance filing to revise its Tariff consistent with these findings.

524.
We agree with PJM that there are significant reliability risks associated with misoperation of special protection schemes, and that "financial penalties, alone, are not sufficient to incentivize Eligible Customers to comply with . . . control technology and protection system obligations."1043  We find that this replacement rate serves to deter conduct contrary to the fundamental principle around which the new transmission services created by the Commission were based, i.e., that Eligible Customers taking service on behalf of Co-Located Loads are willing and able to limit their energy withdrawals from the transmission system under certain conditions.1044  Moreover, we agree with PJM that, after the first misoperation of necessary control technologies and/or protection systems, suspension of service for a period of up to 120 days is reasonable to allow for an analysis by PJM, and the affected transmission owner(s) as necessary, of the operational performance of the necessary control technologies and/or protection systems. 1043 PJM Initial Brief at 41-42, 45, 50.

1044 December Order, 193 FERC ¶ 61,217 at P 177 ("we also find that PJM's Tariff is unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking service on behalf of Co-Located Loads that are willing and able to limit their energy withdrawals from the transmission system under certain conditions."); see id. P 205 ("We note that, in general, special protection schemes allow Eligible Customers on behalf of Co-Located Load to effectively limit their withdrawals from the transmission system. For these reasons, in these instances where the Co-Location Arrangement includes special protection schemes that limit its energy withdrawals, we find that it is a just and reasonable replacement rate to allow an Eligible Customer taking transmission service on behalf of such load to take and be charged for new types of transmission service that are alternatives, and not equivalent, to NITS."). 390 of 515

PDF page 100

Document AccessigPSA:  2kgits418-3QPcument:Flild rpaN9: A39/118/2p2ate Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 234 -
In response to the Indicated TOs, we find that it is reasonable that the Tariff provide that service may resume following PJM's approval, as well as the relevant transmission owner's approval of the necessary control technologies and/or protection systems for consistency with the transmission owner's technical standards.

525. However, we reject PJM's proposal not to apply such a penalty to Eligible Customers taking FCD transmission service on behalf of Co-Located Load, consistent with our findings above that Eligible Customers taking FCD transmission service on behalf of Co-Located Load must also have necessary control technologies and/or protection systems to limit their energy withdrawals from the transmission system to their contract demand level.1045  We also disagree with protesters' arguments opposing PJM's proposal to establish an operational penalty for misoperation of necessary control technologies and/or protection systems. Vistra suggests that PJM's proposal unduly discriminates against Co-Location Arrangements as compared to other entities using special protection schemes, but this penalty proposal (which Vistra mistakenly alleges applies only to special protection schemes) is not relevant to existing transmission services in PJM.1046  By contrast, as discussed above, correct operation of necessary control technologies and/or protection systems is foundational to the new transmission services. Vistra's separate claim that PJM's proposal is unduly discriminatory "insofar as it treats unreserved use of the transmission system by point-to-point customers differently from unreserved use by customers taking these new transmission services" is misplaced. In contrast to Eligible Customers taking Interim NITS, FCD transmission service, and/or NFCD transmission service on behalf of Eligible Load, PTPS customers are not required to establish necessary control technologies and/or protection systems in order to take PIPS .1047  We also find unpersuasive Joint Co-Location Developers' allegation that this operational penalty is even more excessive, as compared to a penalty for failure to follow curtailment or load shedding directives, because misoperation without withdrawal does not risk system harm.'°48  We agree with PJM that "[w]hen a control technology or protection scheme misoperates, there can be serious consequences.i1049  Where PJM 1°45  See supra Part VI.C.

1046  See PJM Initial Brief at 47 (justifying its proposal to allow that an Eligible Customer disqualified from the new transmission services may take NITS because "NITS, in and of itself, addresses Curtailment, Load Shed, and control technology or protection scheme misoperation risk").

1047 Id. at 50 ("PJM supports a penalty for unreserved use in addition to the disqualification and pause-in-rules discussed above."); see id. at 41 (Table 1 (Penalties)). 1048 Joint Co-Location Developers Response Brief at 26.

1049  PJM Initial Brief at 43, 45; PJM Reply Brief at 52-53.
391 of 515

PDF page 101

Document Acc„sig SK qq-Aqq-18-34PcurnentFhla EPa.@9: Ap/48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 235 -
plans and operates the system around an assumption that necessary control technologies and/or protection systems will work, unexpected system behavior due to misoperation risks system reliability regardless of whether withdrawals occur, and we find that it is reasonable not to rely only on financial penalties to mitigate these risks. 526.

We disagree with Constellation's suggestion that the Commission should adopt SPP's approach from CHILLS, which contains only penalties for exceeding the transmission customer's reserved capacity,'°5°  but not suspension or disqualification, for the same reasons discussed above.

527.
We agree with NOVEC that PJM's proposed penalty language to disqualify the Eligible Customer as a whole from taking the relevant transmission service is not just and reasonable. Instead, we direct PJM to propose on compliance Tariff provisions providing that, after the second misoperation of necessary control technologies and/or protection systems pertaining to a transmission service agreement governing an Eligible Customer taking Interim NITS, FCD transmission service, and/or NFCD transmission service on behalf of Eligible Load, PJM will terminate the transmission service agreement. The Eligible Customer could still take transmission service, including Interim NITS, FCD transmission service, and NFCD transmission service, on behalf of other loads through other transmission service agreements.

528.
ODEC asserts that PJM's implementation of its penalties must not subject ODEC or its member distribution cooperatives to service interruptions or disqualification, or financial penalties, as a result of requiring ODEC to serve as the Eligible Customer. The Commission set a replacement rate in the December Order applicable to Eligible Customers taking transmission service on behalf of Co-Located Load. The operational (and financial) penalties we establish in this order apply to Eligible Customers who elect to take the new transmission services on behalf of Eligible Load and who do not comply with the terms and conditions of the new transmission services, including misoperation of necessary control technologies and/or protection systems. The December Order does not require that Eligible Customers on behalf of Co-Located Load take one of the new transmission services and they may choose to take NITS instead. The Co-Located Load cannot force an Eligible Customer to take a type of transmission service it does not wish to take. As the Commission explained in the December Order, NITS remains a just and reasonable transmission service option that an Eligible Customer on behalf of a Co-Located Load may choose.1051

1050 Sw. Power Pool, Inc., 195 FERC ¶ 61,196 at 98.
1051  December Order, 193 FERC ¶ 61,217 at P 195.
392 of 515

PDF page 102

Document AccessigPA 2A2-V;tg18-3PSc ument:Flil d  d:),,age. 7,93
Date Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 236 -
c. Unreserved Use of the Transmission System
529. We find that it is just and reasonable to impose a financial penalty on an Eligible Customer taking any of the new transmission services on behalf of Eligible Load for unreserved use of the transmission system. We find that it is just and reasonable to use Indicated TOs' two-part penalty framework and to apply, within that framework, a penalty rate that is twice the rate we establish in this order for FCD transmission service.'052  Indicated TOs propose a base penalty charge for each hour in which the Eligible Customer's reserved service limit is exceeded at the Point of Interconnection during at least one five-minute interval (Exceedance Hour) and a penalty ratchet when exceedances occur repeatedly.1°53  Specifically, Indicated TOs propose that, if more than one Exceedance Hour occurs on the same day, then an additional daily penalty applies; if exceedances occur on multiple days within the same week, an additional weekly penalty applies; if exceedances occur in multiple weeks within the same month, then an additional monthly penalty applies; and if exceedances occur in multiple months within the same year, then an additional annual penalty applies.'054  We agree with Indicated TOs that progressively increasing the consequences of repeated penalties encourages Eligible Customers to manage their usage consistent with their reserved transmission service limit.1°55  We note that Indicated TOs submit testimony indicating that they propose to distribute revenues collected from financial penalty charges on a monthly basis to Eligible Customers taking NITS and FCD transmission service. However, we find that unreserved use penalties should be distributed to all non-offending transmission 1052 See Order No. 890, 118 FERC ¶ 61,119 at P 848 ("As a result, we establish a rebuttable presumption that unreserved use penalties no greater than twice the firm point-to-point rate for the penalty period defined above are just and reasonable."); id. P 846 (basing penalty charges on the period of unreserved use and determining that, as a general rule, more than one assessment for a given duration will increase the penalty period to the next longest duration).

1053 Indicated TOs Response Brief at 12 ("When a Co-Located Load exceeds its reserved transmission service limit, the base penalty charge will be assessed for any hour in which at least one five-minute interval occurs during which a customer's metered load at the point of interconnection exceeds its reserved transmission service."); Indicated TOs Reply Brief at 16.

1054 Indicated TOs Reply Brief at 16; Indicated TOs Reply Brief, Ex.
No. PTO-0005 at 7.
1°55  Indicated TOs Response Brief at 12-13; Indicated TOs Reply Brief at 17. 393 of 515

PDF page 103

Documerit A„„sigi
SP; Z-Q-2(qA-1.8-3[29curnent:Flita rPA09:A918/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 237 -
customers consistent with Order No. 890.1056 We direct the PJM transmission owners to file, within 60 days of the date of issuance of this order, a compliance filing consistent with these findings.

E. Anti-Toggling Mechanisms for Firm Contract Demand Transmission
Service
530.
In the December Order, the Commission found that FCD transmission service should have a minimum term of one year, but that PJM should propose an anti-toggling mechanism for Eligible Customers switching between FCD and NFCD transmission service.1057

1. Initial Briefs
531.
PJM proposes an anti-toggling mechanism to prevent transmission customers from switching between FCD and NFCD transmission services by providing that the portion of the Co-Located Load served by FCD transmission service is not eligible to be served by NFCD transmission service for five years following the effective date of the Service Agreement. Conversely, PJM explains, it does not bar Co-Located Load served by NFCD transmission service from being served by FCD transmission service in future years. However, PJM proposes an exception if there is a physical change to the Co-Located Generator that would materially alter the MW level dedicated to the load or to the Co-Located Load that would materially alter the MW level of its gross demand.105s PJM argues this exception is necessary to ensure that, if an Eligible Customer materially changes either the generation capacity or the load on a gross demand basis, the Tariff provides flexibility to determine whether FCD or NFCD transmission service should be taken for the new incremental portion.

532.
PJM also maintains that its proposed 42-month notice of termination acts as an anti-toggling device in a manner similar to the five-year commitment period applicable to the Fixed Resource Requirement alternative in the PJM capacity market. PJM explains that its notice period recognizes that PJM incorporates these loads in the capacity market, 1056  See Order No. 890, 118 FERC ¶ 61,119 at P 860 ("Unreserved use penalties are assessed against transmission customers and should, therefore, be distributed to all non-offending transmission customers, whether affiliated with the transmission provider or not.").

1057 December Order, 193 FERC ¶ 61,217 at P 213.
1058 PJM Initial Brief at 53-54.
394 of 515

PDF page 104

Document AccessigPA:  22q-2-lebZ1.8-3R9cument:FlAd rpAv: A9A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 238 -
and it would unreasonably shift costs to other loads if Co-Located Loads could avoid capacity charges incurred on their behalf by terminating service prematurely.10s9 533. Indicated TOs propose a five-year minimum commitment period for FCD transmission service, arguing that doing so is necessary to ensure that FCD transmission service customers cannot trigger Network Upgrades and then cease taking service, thereby potentially shifting costs to other transmission customers, and because it mirrors the commitment period for loads seeking to procure their own capacity.1060 Indicated TOs argue that, where Network Upgrades are attributable to FCD transmission service customers, separate payment guarantees may be required to prevent Network Customers from being left "holding the bag" if an FCD transmission service customer exits the system before the costs of the Network Upgrades are fully paid.1061  Finally, Indicated TOs recommend that the Commission adopt the same requirements for FCD transmission service that apply to notices of termination for NITS, including the 42-month notice period.1062

2. Response Briefs
534. NOVEC states that it supports PJM's five-year minimum service commitment and 42-month notice requirement. NOVEC asserts that the minimum service commitment sends timely price signals to the capacity market, enhances market stability, and minimizes upgrade-related risks if a Co-Located Load withdraws. NOVEC notes that the notice-of-termination period is identical to the requirements for termination of NITS and prevents Co-Located Loads from avoiding capacity charges by prematurely terminating their agreement.1063

3. Determination
535. Except as noted below, we find PJM's proposed anti-toggling mechanism to be a just and reasonable replacement rate. In particular, we find that PJM's proposal to prohibit, for a period of five years, Eligible Customers taking transmission service on behalf of a Co-Located Load from taking NFCD transmission service for any portion of 1059 Id at 54-55.

1060 Indicated TOs Initial Brief at 21 (citing December Order, 193 FERC 1161,217 at P 213).

1061  Id. at 21 n.50.
1°62  Id at 21 & n.52.
1063 NOVEC Response Brief at 15-16.
395 of 515

PDF page 105

Document Acceseigi SA qW§A18-31--299ument:Flald ipaN9: Aqq8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 239 -
Co-Located Load served by FCD transmission service will ensure that such Eligible Customers do not attempt such a switch based on expected capacity market conditions, consistent with the December Order.'°64  We further find that PJM's proposed 42-month notice of termination provision applicable to FCD transmission service customers mirrors that applicable to Network Customers and recognizes that PJM has procured capacity on their behalf. We direct PJM to file, within 60 days of the date of issuance of this order, a compliance filing to revise its Tariff consistent with these findings. 536.

However, we find PJM's proposed exceptions regarding changes to the
Co-Located Generator or Co-Located Load are not just and reasonable to the extent they would permit Eligible Customers to decrease the level of contract demand for FCD transmission service they take on behalf of an Eligible Load, and increase the level of contract demand for NFCD transmission service, without being subject to the anti-toggling provision. The Commission found that the anti-toggling mechanism should ensure Eligible Customers taking transmission service on behalf of Co-Located Loads cannot switch from FCD to NFCD transmission service based on expected capacity market conditions.1°65  As such, PJM's proposal is not consistent with the December Order, and we direct PJM to propose an anti-toggling mechanism without an exception for Eligible Customers taking FCD transmission service on behalf of Eligible Load in a compliance filing within 60 days of the date of issuance of this order. 537.

We also reject Indicated TOs' proposal for a five-year minimum commitment period. As Indicated TOs acknowledge, the Commission required in the December Order that the minimum term for FCD transmission service should be one year.1°66  As such, we find that Indicated TOs' arguments in support of its proposal are an untimely request for rehearing of the December Order.1067

1064 December Order, 193 FERC ¶ 61,217 at P 213.
1065 Id
1066 Id
1067  See, e.g., ISO New Eng. Inc., 132 FERC ¶ 61,098 at P 12 ("The Commission has held that requests to alter a compliance filing in a manner that differs from the order requiring the compliance filing constitute a collateral attack on the order requiring the compliance filing.").

396 of 515

PDF page 106

Document AccessigtPg 2A-ACCR18-3Q9cument:Flild rgq99:A9/718/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 240 -
F. Communications, Alarm, SCADA, or Other Requirements
1. Initial Briefs
538.
PJM proposes to develop telemetry requirements for Co-Located Load so that PJM can monitor the status of demand placed on PJM's transmission system, including unreserved use, to ensure reliability.1068  PJM states that it still determining the scope of the tools and requirements necessary to limit withdrawals that exceed reserved use. PJM also proposes to develop data exchange and metering requirements for Co-Located Load that may be similar to those applicable to generation. PJM proposes to develop the capability to differentiate more granularly between the transmission services available to Eligible Customers on behalf of Co-Located Load because they are prioritized differently. PJM maintains that Eligible Customers would need to take these different forms of transmission service on different feeders, or cables leaving substations, to ultimately serve the Co-Located Load.

539.
PJM next proposes to develop requirements and identify any relevant NERC rules to ensure that relay settings are consistent with the design of the necessary control technologies and/or protection systems, as set forth in each Service Agreement.1069  PJM asserts that transmission owners must be heavily involved in ensuring that necessary control technology and/or protection systems are properly designed. PJM explains that it proposes technical requirements that must be in place prior to commencement of service because there are significant risks introduced by the necessary control technology and protection systems. PJM also proposes to make changes to core Markets and Operations systems to incorporate the information provided by Eligible Customers and Co-Located Load to ensure reliability of the PJM transmission system.

2. Response Briefs
540. Indicated TOs support PJM's proposal in its initial brief to develop telemetry requirements and require Co-Located Load to meet such requirements in order to monitor Co-Located Loads' use of the transmission system.107°

3. Determination
541. We decline to direct PJM's proposed telemetry, data exchange, metering, and relay setting requirements as the replacement rate because PJM has not provided 1°68  PJM Initial Brief at 59-61.

1°69  Id at 60-61.
1070 Indicated TOs Response Brief at 10-11.
397 of 515

PDF page 107

Document AccessigsP; Z-q-2-VA-18-31-29Curnent:FlAd rraN9: A9,818/2 pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 241 -
sufficient detail to find they are just and reasonable. PJM by its own admission has not finished determining the scope of what might be necessary to limit energy withdrawals from the transmission system. Accordingly, and consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we direct PJM to file, within 60 days of the date of issuance of this order, a compliance filing with Tariff revisions it deems necessary for PJM to be able to ensure that an Eligible Customer has adequate telemetry, data exchange, and metering requirements such that PJM may monitor the Eligible Load's use of the transmission system, limit withdrawals, and ensure relay settings are consistent with necessary control technologies and/or protection systems.

G. Curtailment Procedures for Interim NITS and Non-Firm Contract
Demand Transmission Service
1. Initial Briefs
542.
PJM proposes that Interim NITS and NFCD transmission service will be curtailed before FCD transmission service and NITS.1071  PJM also proposes that it may curtail Interim NITS or NFCD transmission service prior to dispatching the Pre-Emergency Load Response Program or in response to a transfer capability shortage as a result of system reliability conditions. PJM proposes that FCD transmission service be treated equal to NITS for purposes of curtailment.1072  PJM states that it reserves the right to curtail the three new transmission services on a non-discriminatory basis for the purpose of making necessary adjustments to, changes in, or repairs on its lines, substations, and facilities, and in cases where continuation of service would endanger persons or property. PJM proposes that the Eligible Customer must shed load in accordance with previously established procedures under the relevant Service Agreement.

543.
PJM acknowledges that its system does not differentiate between different types of transmission service because all load within PJM is currently served by NITS.1°73  Thus, PJM explains, core systems would need to be implemented to enable sufficient granularity when shedding an Eligible Customer's Co-Located Load being served by two different levels of transmission service, i.e., both FCD and NFCD transmission services. PEW clarifies that, assuming these core system design changes can be implemented, Eligible Customers taking transmission service on behalf of Co-Located Load would 1071 PJM Initial Brief at 63.

1°72  Id at 64.
1°73  Id. at 65-66.
398 of 515

PDF page 108

Document Acc„sigPSA:  2Q121R18-34@cument:Flild )fal@ii19: Asg8, 2pAte Filed' 10/16/2026 Docket No. EL25-49-002, et al.

- 242 -
need to take different forms of transmission service on different feeders, or cables leaving substations, to ultimately serve Co-Located Load.

2. Response Briefs
544.
Joint Co-Location Developers argue that PJM fails to adequately clarify when and how NFCD transmission service and Interim NITS shall be curtailed, in particular the curtailment trigger.1074  Joint Co-Location Developers maintain that the curtailment trigger significantly affects rates and service and is realistically susceptible of specification and should be included in the tariff. Joint Co-Location Developers assert that PJM does not clarify whether and how it will determine curtailment priority among its different classes of non-firm service, including Non-Firm PTPS, NFCD transmission service, and Interim NITS.

545.
Constellation argues that it is discriminatory to require different feeders and would unnecessarily delay Co-Location Arrangements.'°7s  At minimum, Constellation asserts that such a requirement should not apply in the case of Interim NITS since the Co-Located Load is not taking both firm and non-firm service.

546.
AEU/SEIA explain that the December Order established a curtailment hierarchy in accordance with which Interim NITS and NFCD transmission service will be curtailed before NITS and FCD transmission service and before pre-emergency demand response resources are dispatched.1076  AEU/SEIA claim that PJM's implementation of this hierarchy is contradictory because PJM states that it "may" curtail Interim NITS and NFCD transmission service prior to dispatching the Pre-Emergency Load Response Program and that it "will" curtail Interim NITS and NFCD transmission service before demand response resources are called upon to reduce load.1077  AEU/SEIA argue that this inconsistency must be resolved because a customer considering whether to take Interim NITS or NFCD transmission service needs to know whether curtailment before pre-emergency demand response is a certainty or a possibility.

547.
AEU/SEIA contend that PJM has provided no information about the conditions that would actually trigger curtailment of Interim NITS or NFCD transmission service in practice and that, because these are novel services, no historical curtailment data 1074 Joint Co-Location Developers Response Brief at 17.

1075 Constellation Response Brief at 29-30.
1076 AEU/SETA Response Brief at 11.
1077 Id. (citing PJM Initial Brief at 63-64).
399 of 515

PDF page 109

Document Accessig.PSier; 2218-3Q9c
urnent:Fhld PA99:6460A812Me Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 243 -
exists.1078  AEU/SETA further argue that modeling of expected curtailment frequency and duration or examples of how curtailment would operate for a hypothetical Co-Location Arrangement must be provided in order for customers to make informed business decisions on the transmission service that best serves their needs. If it is not, AEU/SEIA argue that prospective customers will default to taking NITS. AEU/SEIA request that the Commission require PJM to develop and publish historical analysis and forward-looking modeling of curtailment frequency and duration for Interim NITS and NFCD transmission service, as informed by historical system conditions in PJM and broken down by zone. AEU/SEIA also argue that PJM should set out in its reply brief how it intends to operationalize curtailment for NFCD transmission service, including the sequence in which Co-Located Loads will be curtailed relative to other non-firm services and the mechanism by which curtailment instructions will be communicated and enforced. Without this sequence, AEU/SEIA claim that neither the Commission nor affected parties can evaluate whether PJM's proposed curtailment framework is consistent with the December Order's requirement that NFCD transmission service be available "as needed during normal, non-emergency system operating conditions."1°79

3. Reply Briefs
548.
Earthjustice argues that the Commission should require PJM to clarify how and when PJM will enforce its curtailment procedures, including: (1) how PJM will communicate its curtailment directives; (2) how and when transmission providers will determine that load shed is necessary, which loads will be curtailed first, and at what stage curtailments will occur; and (3) how a data center will be disqualified and the timeline for that disqualification.1°8°

549.
Industrials/Amtrak argue that many traditional large loads cannot shut off immediately if their on-site generation trips.1°81

1°78  Id. at 12-14.
1°79  Id. at 14 (quoting December Order, 193 FERC ¶ 61,217 at P 215). 1080 Earthjustice Reply Brief at 14, 16.

1°81  Industrials/Amtrak Reply Brief at 6.
400 of 515

PDF page 110

Document AccessigiqSA 22Q2VA18_34Kurnent:Flild rPaN:6160A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 244 -
4. Answers
550. Constellation argues that PJM inappropriately attempts in its reply brief to reinstate a curtailment criterion of a capacity/reserve shortage and that the Commission rejected this element of PJM's proposed Option 7 in the December Order.1°82

5. Determination
551. We find PJM's proposed curtailment hierarchy for Interim NITS, FCD transmission service, and NFCD transmission service to be just and reasonable. PJM's proposal to treat FCD transmission service as comparable to NITS is consistent with the December Order,1°83  as is PJM's proposal to curtail Interim NITS and NFCD transmission service prior to firm transmission services.1°84  In addition, we find PJM's proposal to curtail Interim NITS and NFCD transmission service prior to deployment of its Pre-Emergency Load Response Program, or in response to a transfer capability shortage as a result of system reliability conditions, to be just and reasonable because it is consistent with how Non-Firm PTPS is curtailed.1°85  We disagree with Constellation that PJM's proposal to curtail Interim NITS during capacity or reserve shortages is inconsistent with the Commission's findings in the December Order that PJM's proposed construct for an interim transmission service was too broad and not sufficiently detailed to direct as a replacement rate.1°86  Constellation misunderstands the December Order, which found it was not reasonable to allow the transitional period for Interim NITS to continue until any resource adequacy challenges associated with the addition of the Co-Located Load were addressed, and instead limited the transitional period to the time 1082  Constellation May 11 Answer at 13 (citing December Order, 193 FERC ¶ 61,217 at P 202).

1083 See, e.g., December Order, 193 FERC ¶ 61,217 at P 208 (stating that FCD transmission service will have the same curtailment priority as existing firm transmission services).

1084  See, e.g., id. P 201 (stating that Interim NITS "will be curtailed before existing firm transmission services and the new Firm Contract Demand Transmission Service"); id. P 215 (stating same with respect to NCFD transmission service).

1085  See PJM, Intra-PJM Tariffs, OATT, § II, § 14.7 (Curtailment or Interruption of Service) (0.0.0) (describing PJM's curtailment procedures for Non-Firm PTPS); RIM Manual 13: Emergency Operations, Rev. 97 (eff. November 20, 2025), § 2.3.2. 1086  Constellation May 11 Answer at 13 (citing December Order, 193 FERC ¶ 61,217 at P 202).

401 of 515

PDF page 111

Document Acc„sigiqP-; Z-C)72VA18-3ci@cUrnent:FlAd IgN9:6460/48/ 2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 245 -
needed to complete any Network Upgrades identified in the study process.1087  The Commission did not find, as Constellation alleges, that Interim NITS could not be curtailed as a result of capacity or reserve shortages. Here, we find that PJM's proposal to curtail Interim NITS during capacity or reserve shortages is just and reasonable and consistent with both the nature of the transmission service as a non-firm transmission service for which Eligible Customers do not pay generation capacity charges, and the need to maintain reliability.

552.
We disagree with commenters that PJM must provide specific details in its Tariff, such as the trigger and procedures for curtailment of Interim NITS and FCD or NFCD transmission services, or how PJM will enforce its curtailment procedures. We find that requiring PJM to specify the curtailment priority of these new transmission services in its Tariff, while leaving specific implementation details in its manuals and individual service agreements, provides transmission customers sufficient certainty as to their priority relative to other transmission services and ensures that PJM has sufficient flexibility to preserve system reliability in varying operating conditions.1088  We find that it is just and reasonable and important to protect transmission system reliability to provide PJM with sufficient operational flexibility during emergency procedures to curtail transmission customers as needed to preserve reliability.1089

553.
However, we find that PJM does not adequately explain its curtailment hierarchy amongst non-firm transmission services. For example, while PJM states that it will curtail Interim NITS and NFCD transmission service prior to deployment of its Pre-Emergency Load Response Program, it does not detail if these transmission services will be curtailed before or after Non-Firm PTPS, or if curtailment priority within NFCD transmission service will be based on duration, as are curtailments for Non-Firm pips .1090

1087 December Order, 193 FERC ¶ 61,217 at P 202.
1088 See rum,
r
Intra-PJM Tariffs, OATT, § II.14.7 Curtailment or Interruption of
Service (0.0.0) (describing PJM's curtailment procedures for Non-Firm PTPS). 1089 See Order No. 890-A, 121 FERC ¶ 61,297 at P 566 ("If the [conditional firm transmission] customer selects the annual hourly cap option, the transmission provider will have the flexibility to conditionally curtail the customer for any reliability reason during those hours, including but not limited to, the system condition(s) identified in the system impact study.").

1090 PJM, Intra-PJM Tariffs, OATT, § II.14.7 Curtailment or Interruption of Service (0.0.0).

402 of 515

PDF page 112

Document Acc„sigiqW 2q-AQq18-346)cument:Flild IEN9:64EpA8/2pAte Filed 10/16/2026 Docket No. EL25-49-002, et al.

- 246 -
554.
We also find that PJM has not justified its assertion that an Eligible Customer taking different forms of transmission service on behalf of Co-Located Load would need to take those services on different feeders. PJM states that this requirement is based on the need for core systems to be implemented to enable sufficient granularity when shedding an Eligible Customer's Co-Located Load being served by two different levels of transmission service.1091  While we recognize that core systems will need to be implemented, PJM provides no explanation as to why these systems could not be sufficiently flexible as to accommodate a single feeder with two different levels of transmission service on it. 1092

555.
Accordingly, we direct PJM to submit, within 60 days of the date of issuance of this order, a compliance filing to revise the Tariff to include the curtailment priorities for Interim NITS, FCD transmission service, and NFCD transmission service consistent with our findings above. This language must specify that FCD transmission service shall be treated the same as NITS for the purposes of curtailment, and that Interim NITS and NFCD transmission service will be curtailed prior to deployment of PJM's Pre- Emergency Load Response Program, or in response to a transfer capability shortage as a result of system reliability conditions. PJM's submittal must also detail the curtailment priorities between Non-Firm PTPS, Interim NITS, and NFCD transmission service, including how or if PJM will prioritize transmission customers for curtailment based on duration of service. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we further direct PJM to reflect this change in its compliance filing.

H. Rates, Terms, and Conditions for Interim NITS
1. Initial Briefs
556.
PJM proposes to model the non-rate terms and conditions for Interim NITS on NITS.1093  PJM proposes that an Eligible Customer may take Interim NITS on behalf of Co-Located Load until Network Upgrades are complete, and then the customer will automatically convert to a Network Customer. PJM states that an Eligible Customer receiving Interim NITS on behalf of Co-Located Load will receive non-firm transmission 1091 PJM Initial Brief at 66.

1092 For example, this system could assume that load on a feeder is firm up until the Eligible Customer's Firm Contract Demand withdrawal limit, and non-firm above that contract demand amount.

1093 PJM Initial Brief at 67-70.
403 of 515

PDF page 113

Document AccessigPSg AAgg-18-3PFicurnent:Fiald rFaINP:A0A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 247 -
service for the delivery of energy to Co-Located Load. PJM proposes that, upon receipt of request, PJM will determine the amount of Interim NITS that can be reliably provided based on the results of appropriate studies and in consultation with the affected transmission owner. PJM proposes that, for Interim NITS, the Eligible Customer must meet certain conditions and appropriate technical requirements. PJM proposes that the Eligible Customer have an ongoing obligation to notify PJM of material changes in the demand characteristics of the Co-Located Load and the supply characteristics of the Co- Located Generator. PJM explains that the Co-Location Arrangement cannot change during the term of the Interim NITS without discussion and possible further studies by PJM.

557.
PJM proposes load shedding and curtailment provisions applicable to Interim NITS, including that prior to commencement of service, the Eligible Customer must demonstrate its ability to comply with PJM's load shedding and curtailment procedures.1094  PJM proposes to require Eligible Customers taking Interim NITS to work with PJM and the affected transmission owners to establish necessary control technologies and/or protection systems. PJM proposes that Eligible Customers will be assessed certain non-transmission-related rates, including: (1) administrative service charges, (2) ancillary services charges except for regulation, (3) black start service charges based on gross demand, and (4) any redispatch costs. PJM proposes a single Service Agreement specific to Eligible Customers serving Co-Located Load via Interim NITS or NITS. Indicated TOs propose to apply the NITS rate to Eligible Customers taking Interim NITS.1095

2. Response Briefs
558.
Indicated TOs propose several clarifications to PJM's illustrative Tariff provisions.1096  First, Indicated TOs propose revisions to section 702.4 to require an Eligible Customer to satisfy any applicable technical requirements imposed by the relevant transmission owner. Second, Indicated TOs propose revisions to section 703.2 to clarify that both new and increased Co-Located Loads will be studied pursuant to a new application for transmission service. Third, Indicated TOs contend that PJM should provide additional information as to what would constitute a "material change" in the demand characteristics of a Co-Located Load for purposes of an Eligible Customer's notice obligations under section 703.3. Fourth, Indicated TOs recommend that PJM establish load shedding practice guidelines applicable to Co-Location Arrangements for purposes of load shedding conducted under section 705.3 of PJM's illustrative tariff 1094 Id at 71-75.

1095 Indicated TOs Initial Brief at 5 n.13.
1096 Indicated TOs Response Brief at 13-17, 23.
404 of 515

PDF page 114

Document AccessigPsf;
349Cument:Flit d rpaN: A0A8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 248 -
provisions. Indicated TOs explain that they are particularly concerned with automatic load shedding schemes because of the possibility that unintentional activation of these schemes may result in unwanted shedding of nearby customer loads in addition to the Co-Located Load. Fifth, Indicated TOs propose revisions to section 705.5 to require that the necessary control technologies and/or protection systems that must be approved by PJM are also approved by and developed in accordance with the transmission owners' interconnection standards, guidelines, and practices. Sixth, Indicated TOs assert that the reference to the transmission owner's cost responsibility for redispatch costs in section 706.2 of PJM's illustrative tariff provisions is incorrect and request that PJM remove such reference from the filed Tariff records. Seventh, Indicated TOs propose to correct a typo to the conditions of Part XI of the Tariff in section 2.0 of PJM's proposed Attachment F-3A. Last, Indicated TOs request that PJM add a placeholder section for listing required control technologies and/or protection systems to section 4.0 of PJM's proposed Attachment F-3A.

559.
Vistra argues that PJM's study process is flawed because it provides too much discretion to PJM and transmission owners to determine whether studies are required, which studies to conduct, the timeline for doing so, and how to prioritize different requests.'°97  Also, Vistra contends that PJM's proposal is unclear on what it means to ensure that non-firm transmission service can be provided reliably, and that it is critical customers seeking non-firm service not be held to some higher standard. Constellation similarly argues that PJM's proposed study procedures lack sufficient detail to prevent delay and discrimination by transmission owners."'" Constellation argues that PJM must spell out the studies it will perform in the tariff, as well as the timetable for completing the studies.

560.
Market Monitor argues that Interim NITS is not consistent with PJM's planning process and poses potentially significant reliability risks due to the complexity introduced by the necessary control technology and protection systems. Market Monitor states that these risks mean there is not an unlimited amount of Interim NITS that can be provided, which raises questions about which customers would be allowed to take Interim NITS if demand exceeds supply.1°99

561.
Several parties oppose any restriction on Co-Located Loads accessing on-site generation while using Interim NITS and being curtailed, noting that PJM's initial brief is not clear on whether such a requirement is being proposed. Parties argue that such a requirement would be in violation of the December Order and significantly degrade the 1097 Vistra Response Brief at 31, 39.

1098 Constellation Response Brief at 14-15.
1099 Market Monitor Response Brief at 6-7.
405 of 515

PDF page 115

Document -AccessigPg q%2qq-18 _39pcument:FlAd  rjpaN:A0A812 pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 249 -
value of Interim NITS."°°  DCC argues that allowing customers to be curtailed despite bringing their own generation does not align with the Commission's objective to enable more flexible and timely service arrangements for Co-Located Load. "°' DCC argues that PJM's proposal does not recognize an intermediate operational state in which Co-Located Generators can operate in parallel with the grid on a limited, non-exporting or non-market-participating basis while completing interconnection requirements. Enchanted Rock argues that because this limitation during curtailment conditions is a practice that affects rates and service significantly, that is reasonably susceptible of specification, and that is not so generally understood in any contractual arrangement as to render recitation superfluous, it must be included within the Tariff in order to be effectuated.11°2

562.
AEU/SEIA request that the Commission direct PJM to revise its Interim NITS proposal to explicitly allow Eligible Customers to use on-site generation to serve load continuously, provided that the generator is new and that the Co-Located Load does not simultaneously withdraw energy from the transmission system.11°3  Joint Co-Location Developers assert that, as long as Co-Located Generators are not capacity resources, they should be free to serve Co-Located Loads during curtailment conditions.1104 563.

Constellation asks the Commission to direct PJM to include a transitional mechanism for pending large load NITS applicants so that this new service is not unnecessarily limited to new applicants.1105

1100 See AEU/SEIA Response Brief at 20 (citing December Order, 193 FERC ¶ 61,217 at P 201); Enchanted Rock Response Brief at 7; Joint Co-Location Developers Response Brief at 18.

1101 DCC Response Brief at 3-4.
1102 Enchanted Rock Response Brief at 7.
1103 AEU/SEIA Response Brief at 21.
1104 Joint Co-Location Developers Response Brief at 19.
1105 Constellation Response Brief at 14.
406 of 515

PDF page 116

Document Acc„sigPSA:  2C5-
1.8-3Q1Scument:FiAd rPa@g: A8/2
e Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 250 -
3. Reply Briefs
564.
In consideration of parties' comments, particularly those of Indicated TOs, PJM proposes certain revisions to the illustrative tariff provisions for Interim NITS and NITS, and the Service Agreement for Interim NITS.11°6

565.
PJM articulates several reasons why Interim NITS customers should not be allowed to access the Co-Located Generator when PJM curtails the Co-Located Load.11°7 First, PJM states that Interim NITS will be curtailed when the system cannot support it in real time, whether with sufficient generation or transmission capacity. Second, PJM argues that Interim NITS must be designed to allow PJM to maintain system reliability, both from a transmission and capacity perspective, and that allowing an interruptible customer to preclude PJM from accessing a generation resource during times of system stress would be contrary to that objective. PJM maintains that, if the Co-Located Generator is a capacity resource, then PJM has the first call on such resource's energy to meet the region's needs. Third, PJM explains that Interim NITS is a type of NITS and is served by the pool of resources and not any one dedicated resource. PJM asserts that allowing an Interim NITS customer to take energy from the Co-Located Generator during curtailment would effectively transform this service into something akin to FCD or NFCD transmission service, where the Co-Located Generator dedicates a MW level of output to the Co-Located Load. Lastly, PJM argues that Interim NITS is predicated on the Co-Located Load's willingness to curtail, and allowing an Interim NITS customer access to the Co-Located Generator during times of system stress is contrary to this foundational element of the December Order.11°8  PJM also asserts that providing a right to an Interim NITS customer to access the Co-Located Generator during times of system stress is illogical when such right is not available to full Network Customers. NOVEC urges the Commission to accept PJM's proposal and argues that if prospective customers find that Interim NITS is not desirable, they have the flexibility to pursue a combination of FCD and NFCD transmission services.11°9

566.
PJM defends its process for Interim NITS to determine whether "additional studies are needed" by arguing that the NITS study could provide sufficient information for PJM to determine if Interim NITS can be reliably provided.111°  PJM maintains that it should 11°6  PJM Reply Brief at 60-64.

11°7  Id. at 16-20.
II" Id. at 21 (citing December Order, 193 FERC ¶ 61,217 at P 201).
11°9  NOVEC Reply Brief at 16.
11°  PJM Reply Brief at 27.
407 of 515

PDF page 117

Document AccessigaS
 2A-AQA18-3489ument:FlAd rpaqg9: 6460,q8/24Ate  Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 251 -
not be required to provide as much detail for Interim NITS determinations as for FCD and NFCD transmission services given that Interim NITS is derivative of the customer's existing NITS request and associated studies, although the illustrative tariff authorizes NM to perform additional studies if needed."

567.
Joint Co-Location Developers argues that the Interim NITS proposal undermines PJM's reliability rationale for NFCD transmission service outage restrictions because PJM has proposed to make it broadly available during normal operating conditions, and PJM has not claimed that doing so will compromise reliability.1112

568.
Constellation avers that PJM's omission of any detail with respect to this study process does not comply with the Commission's directive to provide additional record evidence to set the appropriate replacement rates, terms, and conditions for Interim NITS and urges the Commission to direct PJM to file its study process for Interim NITS within 30 days.1113

4. Answers
569.
Constellation asks the Commission to direct PJM to revise its illustrative tariff to clarify that large loads with pending NITS applications shall be studied for Interim NITS at the request of the load without having to submit a separate application.1114 570.

Enchanted Rock reiterates that PJM's implementation of Interim NITS is fundamentally flawed because, while an Eligible Customer takes Interim NITS on behalf of a Co-Located Load, PJM proposes not to allow that Co-Located Load to receive any capacity or energy from a Co-Located Generator and instead to treat the Co-Located Generator as a capacity resource.1115  Enchanted Rock disagrees with PJM that this limitation accords with the principles of the December Order that the new transmission services are designed to serve loads that are willing and able to control their withdrawals from the transmission system and to allow PJM to maintain system reliability. Enchanted Rock avers to the contrary that allowing a Co-Located Load to take capacity and energy from a Co-Located Generator enables that Co-Located Load to control its withdrawals 1111  Id. at 31-32.

1112  Joint Co-Location Developers Reply Brief at 9-10.
1113  Constellation Reply Brief at 12.
1114  Constellation May 11 Answer at 14.
1115  Enchanted Rock May 7 Answer at 2-3.
408 of 515

PDF page 118

Document AccessiggSg 4g1"2-1§A18-3Q6)cument:Flild rg@iii:610)48/2p-Ate Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 252 -
from the transmission system.116  Enchanted Rock also contends that PJM is mistaken in its argument that the PJM region has first call on the output of a Co-Located Generator before the Co-Located Generator has completed PJM's interconnection study process and received a GIA, because until that point, the Co-Located Generator is not eligible to be a capacity resource. Enchanted Rock argues that forcing the Co-Located Generator to be dispatched under emergency conditions during this period would be unduly discriminatory by imposing on these Co-Located Generators obligations that are not imposed on similarly situated generators.1117  Finally, Enchanted Rock argues that it would be illogical that an Interim NITS customer not be allowed to rely on its non-firm Co-Located Generator in order to remain online during emergencies when it is taking non-firm transmission service. Enchanted Rock further contends that it would be unjust and unreasonable for a Co-Located Load to bear the full capital and development risk of bringing a Co-Located Generator online only for PJM to dispatch the Co-Located Generator to serve firm Network Customers during emergencies—precisely when PJM is serving firm Network Customers but curtailing Interim NITS customers.1118

5. Determination
571.
We find PJM's proposal for Interim NITS to be just and reasonable, subject to the clarifications directed below, and direct PJM to file, as the replacement rate, rates, terms, and conditions for Interim NITS as detailed below on compliance. We generally agree with PJM that the non-rate terms and conditions for Interim NITS reflect those applied to NITS, with necessary modifications to reflect the interim and non-firm nature of this new transmission service. We find that PJM's proposals that an Eligible Customer taking Interim NITS will receive non-firm transmission service for the delivery of energy to Co-Located Load and convert automatically to a Network Customer when Network Upgrades are complete to be consistent with the directives in the December Order.1119 We direct PJM to file, within 60 days of the date of issuance of this order, a compliance filing revising its Tariff consistent with these findings. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able 1116  M at 5-6.

1"7  Id. at 6-8.
1118  Id. at 8-9.
"18  December Order, 193 FERC ¶ 61,217 at P 200 (stating that Interim NITS "can be interrupted until the Network Upgrades necessary to provide NITS are complete and the Co-Located Load can be designated as Network Load").

409 of 515

PDF page 119

Document AccessigPc 22Q-A-1 8  _3I?pument:Flil d rj'Ag9: A110.8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 253 -
to limit their energy withdrawals from the transmission system under certain conditions, we further direct PJM to reflect this change in its compliance filing. 572.

We find that Indicated TOs' proposal to apply the NITS rate to Eligible Customers taking Interim NITS on behalf of Co-Located Load is just and reasonable and consistent with the December Order.112°  Therefore, and consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we direct the PJM transmission owners to submit, within 60 days of the date of issuance of this order, a compliance filing to apply the NITS rate to Eligible Customers taking transmission service on behalf of Eligible Loads.

573.
Consistent with our findings in Part VI.A.4, we also find just and reasonable PJM's proposal to charge Eligible Customers taking Interim NITS on behalf of Co-Located Load certain administrative and ancillary services charges, and to assess charges based on gross demand for regulation and black start service. We find PJM's proposal consistent with the December Order.1121 Moreover, we find it is just and reasonable to charge Interim NITS customers redispatch costs to cover congestion-related costs, given that Interim NITS will be pool-scheduled and can be served by generators redispatched to mitigate congested transmission paths. Accordingly, and consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we direct PJM to submit, within 60 days of the date of issuance of this order, a compliance filing to incorporate in the Tariff revisions to assess to Eligible Customers taking transmission service on behalf of Eligible Loads: (1) administrative service charges, (2) ancillary service charges, (3) black start service charges,

(4) regulation charges, and (5) any redispatch costs.
574.
We note that only curtailment procedures were explicitly included in the paper hearing, and Tariff provisions governing other terms and conditions for Interim NITS, including the study process, should be filed on compliance.1122  That said, we find it is just and reasonable to allow PJM greater discretion as to how it studies Interim NITS 1120  Id. (stating that Interim NITS customers would pay the NITS rate). 1121

7.

la (stating that Interim NITS customers would pay ancillary service charges and charges for black start service).

"22 m P 219.
410 of 515

PDF page 120

Document AccessigPSP; 2A-Aggl.8-3R@cument:Flild rpAgp: ,A1A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 254 -
requests, in comparison to requests for FCD transmission service.1123  We disagree with Vistra that PJM's proposed study process provides too much discretion to PJM and transmission owners. We reiterate that Interim NITS is only "available to the extent PJM determines that it can provide some level of interim service reliably,"1124  and therefore we find that it is just and reasonable to limit this service to situations in which PJM, in consultation with transmission owners, grants such service based on the results of appropriate studies. The Commission generally defers to transmission providers' discretion regarding how to maintain a reliable transmission system.1125 575. We further find that Interim NITS is distinguishable from FCD and NFCD transmission services, for which we direct PJM to provide additional detail in the Tariff regarding the study process as discussed Part VI.A.3, because Interim NITS is a temporary service akin to provisional interconnection service in that both services are intended to allow a customer to temporarily use an amount of a service that can be provided reliably until such customer may begin taking the full requested service. In both cases, the Commission requires the transmission provider to determine if the requested service could be provided reliably.1126 Similar to provisional interconnection 1123  See PJM, Intra-PJM Tariffs, OATT, § VIII.L 439 Provisional Interconnection Service (0.0.0) (providing that PJM "may grant such service at its discretion based upon an evaluation that will consider the results of available studies"); Order No. 890, 118 FERC ¶ 61,119 at P 957 (in the case that a request for long-term Firm PTPS cannot be satisfied out of existing capacity, the transmission provider is required to identify options for providing service but has discretion to study and offer a mix of planning redispatch and conditional firm options for a single service request). 1124  December Order, 193 FERC ¶ 61,217 at P 200.

1125  RWE Clean Energy, LLC, 194 FERC ¶ 61,212 at P 42 ("The Commission generally allows transmission providers to exercise their engineering judgment when conducting interconnection studies, including deferring to transmission providers' discretion regarding how to maintain a reliable transmission system."). 1126  December Order, 193 FERC ¶ 61,217 at P 200 ("Moreover, this new service would be optional for an Eligible Customer seeking NITS on behalf of a Co-Located Load and would only be available to the extent PJM determines that it can provide some level of interim service reliably."); Order No. 845, 163 FERC ¶ 61,043 at P 440 ("In response to CAISO, we clarify that `a certain amount of capacity already studied' refers to situations where, for example, available studies or additional studies as necessary indicate that there is a certain amount of interconnection service available without the need for additional network upgrades and the transmission provider can reliably accommodate the interconnection service.").

411 of 515

PDF page 121

Document Acc„sigPSier; 4q
218-3P8curnent:Filla rPaqg9:64613.812pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 255 -
service, we find that it is just and reasonable, in the case of this new interim transmission service, to afford PJM greater discretion as to how it decides to study Interim NITS requests, in comparison to requests for FCD and NFCD transmission services, and thus we decline to direct PJM to provide more detail in its Tariff on the process for studying requests for Interim NITS.1127  We also disagree with Constellation that it is necessary for PJM to study requests for Interim NITS as part of the NITS process, rather than pursuant to a separate application. On compliance, we direct PJM to file Tariff provisions to effectuate a study process for Interim NITS, as discussed herein. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we further direct PJM to reflect this change in its compliance filing. 576. Regarding requests from parties that Interim NITS customers be allowed access to the Co-Located Generator during curtailments, we find that it is just and reasonable to prohibit the Eligible Customer taking Interim NITS on behalf of Co-Located Load from drawing energy from the Co-Located Generator when the Eligible Customer is curtailed, if the Co-Located Generator is a capacity resource. As PJM explains, capacity resources have an obligation to serve Network Load, and this obligation is particularly important during emergency or pre-emergency conditions when PJM needs all resources at its disposal to maintain reliability.1128  However, in response to parties, we clarify that such a restriction would not be applicable to an Eligible Customer taking Interim NITS on behalf of Co-Located Load if the associated Co-Located Generator does not yet have any interconnection service or has only provisional interconnection service. Further, this restriction applicable to an Eligible Customer taking Interim NITS on behalf of Co-Located Load would not be applicable if the associated Co-Located Generator is seeking capacity resource status, but not yet obtained such status, because that Co- Located Generator would not yet have any obligation to provide capacity under the 1127  See PJM, Intra-PJM Tariffs, OATT, § VIII.L 439 Provisional Interconnection Service (0.0.0) (providing that PJM "may grant such service at its discretion based upon an evaluation that will consider the results of available studies"); RWE Clean Energy v. PJM Interconnection, L.L.C., 194 FERC ¶ 61,212 at P 42 ("The Commission generally allows transmission providers to exercise their engineering judgment when conducting interconnection studies, including deferring to transmission providers' discretion regarding how to maintain a reliable transmission system."); Order No. 890, 118 FERC 1161,119 at P 957 (in the case that a request for long-term Firm PTPS cannot be satisfied out of existing capacity, the transmission provider is required to identify options for providing service but has discretion to study and offer a mix of planning redispatch and conditional firm options for a single service request).

1128 PJM Reply Brief at 18.
412 of 515

PDF page 122

Document Acce„igP SA 2A -21Qq18-349cument:Flitd. EPAg:61/41A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 256 -
Tariff. We therefore direct PJM to submit, within 60 days, a compliance filing to incorporate the rates, terms, and conditions for Interim NITS that includes clarifications to specify that (1) an Eligible Customer taking Interim NITS on behalf of Co-Located Load may be served by a Co-Located Generator that is seeking capacity resource status during a curtailment condition to the extent that Co-Located Generator has yet to obtain interconnection service or has only provisional interconnection service, and (2) an Eligible Customer on behalf of Co-Located Load cannot expect to be served by a Co-Located Generator that is a capacity resource during a curtailment condition. Consistent with our determination above to extend the three new transmission services set forth in the December Order to Eligible Customers taking service on behalf of load with BTMG that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, we further direct PJM to reflect this change in its compliance filing.

577.
We disagree with Market Monitor's arguments that Interim NITS is not consistent with PJM's transmission planning process and poses potentially significant reliability risks. As discussed above, we adopt PJM's proposal for application and studies for Interim NITS, which limits the amount of Interim NITS available to an Eligible Customer seeking to take Interim NITS on behalf of a Co-Located Load to the amount that PJM, in consultation with the affected transmission owner(s), determines can be provided reliably to that customer while maintaining the reliability of the transmission system. 578.

We decline to adopt Constellation's proposal to include a transitional mechanism for pending NITS applications. PJM's proposal does not prohibit any NITS applicant from also applying for Interim NITS, provided the applicant pays the additional study fee and is subject to the technical requirements for Interim NITS. Therefore, we find such a transitional mechanism not to be necessary.

I. Annual Report on New Transmission Services
579.
Having addressed the rates, terms, and conditions for each of the new transmission services (subject to additional compliance), we now turn to our ongoing oversight of the implementation and use of these new transmission services. As discussed in the December Order and reiterated today, we expect that these new transmission services will facilitate more efficient use of the existing transmission system and limit unnecessary transmission system buildout. However, we also recognize that the new transmission services represent new developments in the provision of transmission service in the PJM region. These developments require effective oversight and monitoring to help ensure the transmission services are working as intended and do not create reliability issues or raise novel questions regarding application of cost causation principles. Transparent information on the use of the new transmission services is also important for prospective Eligible Customers on behalf of Eligible Loads to assess which transmission service to request and where on the transmission system to make such requests. We conclude that 413 of 515

PDF page 123

Document Acceseiggtr; Z--216318-3[28.curnent:Flita rPaq99: A1A8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 257 -
the Commission, states, PJM market participants, and stakeholders would benefit from additional transparency about these new transmission services, and we therefore direct PJM to prepare an annual report, posted to its website, containing information about the demand for and use of these new transmission services. Accordingly, we direct PJM to submit, as part of its compliance filing within 60 days of the date of issuance of this order, proposed Tariff provisions requiring such a report and a proposal for the information to be included in that annual report.

580. As PJM considers the scope and content of that annual report, we propose that the following information could aid the Commission, states, PJM market participants, and stakeholders in assessing the impact of the new transmission services:

1) Data regarding each transmission service request seeking each of the new services by transmission zone, including:1129

a. Peak gross load of the Eligible Load
b. Category of the Eligible Load
c. Type and MW of transmission service being requested
d. Type and MW of transmission service granted
e. Dates of reservation and usage (for non-firm services)
2) Total MW of each type of transmission service taken each year by transmission zone, including:

a. Total amount of FCD transmission service taken relative to peak gross load at the meter receiving FCD transmission service

b. Total amount of NFCD transmission service taken relative to peak gross load at the meter receiving NFCD transmission service

c. Total amount of Interim NITS relative to peak gross load at the meter receiving Interim NITS

1129  Some of the information we identify here is likely to be available on PJM's Open Access Same-Time Information System. PJM may account for that availability in designing its proposal and addressing the potential burden associated with preparing the annual report.

414 of 515

PDF page 124

Document AccessigRag 42 -VAI.13-349cument:Filla rPaqi19: 6161A 8/2PAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 258 -
3) Information about transmission revenues paid by Eligible Customers on behalf of Eligible Loads for each transmission service by transmission zone, including: a. Total revenues paid by Eligible Customers taking each service per transmission zone

b. Percentage of each transmission owner's total revenue requirement paid via revenues from each new service

c. MWs of each new transmission service taken by Eligible Customers
serving Eligible Loads as a percentage of peak gross load for each
transmission owner
4) Frequency and magnitude of curtailment from the reservation of NFCD transmission service and Interim NITS by transmission zone

5) Frequency and magnitude of denials of NFCD transmission service reservation requests by transmission zone

J.
Proposed Effective Date
1. Initial Briefs
581.
PJM proposes an effective date of June 1, 2029, for the three new transmission services. PJM advances two rationales for its proposal: (1) integration of the new transmission services into PJM's capacity market so that PJM can procure capacity for Eligible Customers taking FCD transmission service on behalf of Co-Located Loads cannot occur until 2029; and (2) necessary modifications to the PJM core markets and operations software will take time.113°  PJM also argues that this effective date will not be a limiting factor because Eligible Customers taking the new transmission services on behalf of Co-Located Load and their Co-Located Generators likely will not be online before June 1, 2029, given interconnection requirements, supply chain issues, procurement challenges, and capacity auction timelines.1131

582.
As to the capacity market, PJM argues that demand associated with Co-Located Loads will significantly affect PJM's load forecast and thus have significant implications for the capacity market. PJM explains, however, that while the BRA for the 2028/2029 delivery year (beginning June 1, 2028) has not taken place, the load forecast and eligible 1130  PJM states this includes Real-Time Security Constrained Economic Dispatch, Day-Ahead Market, and dispatch software. PJM Initial Brief, Horger Aff. ¶ 16. 1131  PJM Initial Brief at 79-82.

415 of 515

PDF page 125

Document Access igiPP:: 22q-AgA18 _3Q@cument:Fl it d IpAg9:6451/6.8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 259 -
capacity have already been determined, and it is no longer possible to implement changes before the BRA is conducted. Therefore, according to PJM, the 2029/2030 delivery year (beginning June 1, 2029) is the first BRA in which the effects of the new transmission services can be considered and PJM can procure capacity for Eligible Customers taking FCD transmission service on behalf of Co-Located Loads.1132

583.
As to the technical implementation issues, PJM argues that implementing the proposed curtailment priorities applicable to Interim NITS and NFCD transmission service will require modifying PJM's economic dispatch software and dispatch tools in order to incorporate system automation that will avoid undesirable outcomes. PJM further contends that work cannot begin until the rates, terms, and conditions of these new transmission services are finalized, and that changes to these systems will be dependent on vendor availability, the speed with which systems changes can be designed, and interaction with other software changes. 1133

2. Response Briefs
584.
Some parties support PJM's proposed effective date. Market Monitor argues that all load in PJM currently is served by NITS, and that PJM has demonstrated that it must significantly modify core systems to address curtailing load where an Eligible Customer takes more than one kind of transmission service on behalf of Co-Located Load.1134 NOVEC contends that entities other than PJM must also prepare for these new transmission services by making operational adjustments and regulatory and billing changes to ensure costs reflect cost causation principles.1135

585.
Constellation, DCC, Joint Co-Location Developers, and Vistra oppose PJM's proposed effective date, and make a variety of arguments against PJM's rationales for it or in favor of alternative proposals for faster implementation.1136  As to arguments PJM makes about the capacity market, Vistra contends that resource adequacy considerations 1132  Id at 79-80 (citing Horger Aff. ¶¶ 11-13). PJM also argues that inclusion of these services in Incremental Auctions would be inappropriate because they are conducted to procure replacement resources and generally result in small adjustments. Id at 80-81 (citing Horger Aff. ¶ 15).

1133  Id. at 81; Horger Aff. ¶ 16.
1134  Market Monitor Response Brief at 8.
1135  NOVEC Response Brief at 17-18.
1136  Constellation Response Brief at 7; Joint Co-Location Developers Response Brief at 28; Vistra Response Brief at 8-9.

416 of 515

PDF page 126

Document Accessig! iQ2Vg18-3Q9cument:Flild ,ja~ge: NA 8 12  PAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 260 -
are beyond the scope of a transmission provider's obligation to serve and that the Commission requires transmission providers to make transmission service decisions based on available transfer capacity.1137  Constellation, Joint Co-Location Developers, and Vistra each criticize PJM on the basis that Interim NITS and NFCD transmission service are not capacity-backed services such that PJM need not procure capacity on their behalf. Joint Co-Location Developers contend that PJM does not explain why a customer taking NITS would be reflected in capacity market demand forecast but a customer taking FCD transmission service would not. Similarly, Vistra argues that large loads were already included in the load forecasts for the 2027/2028 and 2028/2029 BRAs and that some of the new large loads in the forecasts may take the new transmission services. Joint Co-Location Developers argue that, if PJM's concerns stem from a planning need associated with existing capacity resources de-registering, then PJM should propose a delayed implementation limited to particular use cases.

586.
As to PJM's technical implementation issues, Vistra and Joint Co-Location Developers criticize PJM for failing to offer any specificity.1138 Vistra alleges that previous experience, such as in PJM's implementation of Order No. 841, suggests that PJM should be able to implement software changes much more quickly. Vistra further charges that the Commission should demand more support to justify delaying implementation than PJM has provided here, as it did in prior cases such as MISO's implementation of Order No. 2222. Similarly, Joint Co-Location Developers argue that curtailable products can be implemented on much faster timelines, pointing in particular to SPP's CHILLS and PJM's planned Connect and Manage proposal. Vistra also argues that PJM's systems should already be capable of curtailing because its Tariff provides Non-Firm PTPS. Joint Co-Location Developers assert that PJM does not explain why additional software must be developed for FCD transmission service, which is similar to NITS. Lastly, Joint Co-Location Developers state that their attached testimony notes that leveraging price responsive demand modifications to security constrained economic dispatch could allow PJM to implement faster any security constrained economic dispatch changes for non-firm loads.

587.
Several parties disagree with PJM that Co-Located Generators will not be online before June 1, 2029."39  Joint Co-Location Developers argue that there are likely to be projects already in development that may opt to use these new transmission services. 1137  Vistra Response Brief at 7 (citing, e.g., Order No. 890, 118 FERC ¶ 61,119 at P 2).

1138  Id. at 10-12; Joint Co-Location Developers Response Brief at 29-30. 1139  Joint Co-Location Developers Response Brief at 30; Vistra Response Brief at 9-10; Constellation Response Brief at 8.

417 of 515

PDF page 127

Document AccessigOA:  4§.72-W_8-396)9 ument:FlAd tpa p: A1A8/2pge Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 261 -
Vistra adds that some generators are not capacity resources, are already in the process of de-listing, or could enter into a bilateral agreement with another generator to cover its capacity obligation. Constellation points out that load co-locating with existing generation could take Interim NITS.

588.
Several parties request that the Commission make all or certain of the new transmission services available earlier.114°  DCC argues that PJM has not demonstrated that all elements of the proposed services must be deferred for several years, nor has it identified opportunities for phased or interim implementation. DCC argues that the Commission should consider whether certain components of the framework can be implemented on an accelerated or staged basis to provide near-term benefits while longer-term systems are developed. Joint Co-Location Developers ask the Commission to require that FCD transmission service be available within six months of an order accepting PJM's filing and NFCD transmission service and Interim NITS be available at the earliest date technically feasible.

589.
Constellation urges the Commission to establish a separate track to approve rates and terms for Interim NITS and make them effective no later than October 1, 2026.1141 Constellation argues that PJM offers no legitimate reason for proposing a three-and-a-half-year delay and argues that it should not be difficult to adopt as soon as possible. Constellation maintains that, if the Commission separates and implements Interim NITS on a fast track, potential logistical challenges will not risk delay. Constellation suggests that the Commission review FCD and NFCD transmission services on a separate track and urges the Commission not to delay them until June 2029. Vistra proposes that, even if the Commission accepts PJM's software-based justifications, the Commission should require PJM to immediately accommodate Co-Location Arrangements for which software changes are irrelevant, such as where the Eligible Customer does not reserve any amount of NFCD transmission service on behalf of Co-Located Load.1142  Vistra asserts that, whereas PJM contends that it needs software upgrades to apply appropriate curtailment priorities, a customer that reserves zero MWs of transmission service has no service to curtail. Vistra contends that it is not just and reasonable to prevent service on the basis of a software upgrade that is, at best, nominally relevant to that service. Vistra maintains that delaying service to customers that pull no energy from the grid is inconsistent with the December Order's goal to remedy PJM's 1140 DCC Response Brief at 9; Joint Co-Location Developers Response Brief at 27-28.

1141  Constellation Response Brief at 6-9.
1142  Vistra Response Brief at 12-14.
418 of 515

PDF page 128

Document AccessigPSA: 2A-2-Ytg518 - 34pcument.Filld rpAp:6161/48/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 262 -
failure to provide transmission service reflecting a Co-Located Load's willingness and ability to limit withdrawals.

3. Reply Briefs
590.
PJM asserts that NFCD transmission service is not easy to implement from an operations perspective, particularly at scale, and in addition to exposing the system to higher reliability risks, will also require PJM to modify key systems.1143  PJM explains that changes to Energy Management Systems are needed to ensure that PJM's systems are able to properly account for the provision of energy to Co-Located Load in the day-ahead and real-time market. PJM contends that its Energy Management System does not currently distinguish between different types of load, and that feature must be added. PJM argues that it must determine how to properly model and reflect NFCD transmission service and Co-Located Load in the different systems given that NFCD transmission service requires the transmission system to operate on reduced contingency margins. PJM maintains that significant modifications to the market clearing engines used in both the day-ahead and real-time markets will be required because PJM must be able to curtail NFCD transmission service with little to no advanced notification to respond to significant SOL/IROL exceedances.

591.
Separate from systems updates, PJM argues that it will still be challenging from an operational perspective to provide NFCD transmission service.1144  PJM explains that its systems must not only accurately reflect how this new service affects the transmission system, but PJM must also account for this service in the Operating Plans and then implement those plans manually when needed in real time. PJM argues that, because the transmission system is not designed to accommodate NFCD transmission service, it will likely trigger many more SOL/IROL exceedances for PJM to mitigate in the Operating Plan and require operations at or near operating limits, rendering the system less flexible to respond to unexpected changes during operations. PJM contends that it will be imperative that loads taking NFCD transmission service can be removed from the system as soon as possible when needed.

592.
PJM claims it will need additional tariff language and manuals to operationalize requests for service.1145  PJM asserts that it reserves the right to further supplement the record in this proceeding if and when it develops such tariff language. 1143  PJM Reply Brief at 13-14.

1144  /Ci. at 14-15.
1145  Id. at 16.
419 of 515

PDF page 129

Documerit AccesSigisp;
ument:F~l~d1j
Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 263 -
593.
PJM clarifies that June 1, 2029, is the effective date for providing the new transmission services and that, once the Commission establishes the terms and conditions for these new services, PJM is willing to start accepting service requests and processing service applications.1146  PJM states its intent to get a headstart on establishing the details as to how it would implement the illustrative tariff by soon commencing discussions with stakeholders regarding implementation details, to be stated in PJM manuals, for these new transmission services. PJM contends that, with these clarifications, there is no need to establish a transition mechanism for pending NITS applications, as Constellation suggests. In response to concerns that PJM failed to provide a specific timeline for software development, PJM contends that it cannot determine a more exact development schedule at this time because these are new transmission services.

594.
Some commenters continue to support PJM's proposed effective date.1147  Other commenters continue to criticize PJM's proposed effective date. Joint Co-Location Developers argue that it is unclear why PJM must delay implementation until 2029, given that ERCOT has committed to implementation of controllable load as soon as 2027.1148 Joint Co-Location Developers further argue that PJM has provided no reason why its system uniquely requires a longer implementation process compared to other RTOs, and that PJM is well placed to implement changes to its security constrained economic dispatch given the existing capability of its nodal Price Responsive Demand implementation.

595.
Constellation argues that PJM's proposed effective date would impose a three- to five-year moratorium on Co-Location Arrangements and undermines the December Order by allowing rates found to be unjust and unreasonable to remain in place for years.1' 49  Constellation asserts that PJM has devoted significant resources to such changes and has the tools to implement new rules quickly. Constellation urges the Commission to promptly approve the rates and terms for Interim NITS, including the study process, by no later than October 1, 2026.

1146  Id at 55-57.
1147  NOVEC Reply Brief at 27; Earthjustice Reply Brief at 19.
1148  Joint Co-Location Developers Reply Brief, Supp. Aff. of Andrew Levitt and Aniruddh Mohan at 10 (citing ERCOT Large Load Interconnection Batch Study Workshop #7 at 25 (April 9, 2026), ERCOT-Large-Load-Batch-Study-Workshop7- 20260409 v03.pptx).

"
Constellation Reply Brief at 3-5.
420 of 515

PDF page 130

Document Accessigt@Sg 2A-Ags18-34@cument:FlA d IFAv: g/118/2L Ate Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 264 -
4. Answer
596. Constellation opposes PJM's requested effective date and points out that PJM seeks to begin Connect and Manage July 1, 2027, to allow the interconnection of non-capacity-backed loads that are potentially interruptible during capacity shortages, unless the load brings its own generation.11" Constellation contends that it is not credible that PJM will take more than three years to implement Interim NITS, but less than one year to commence Connect and Manage.1151  Constellation asks the Commission to make Interim NITS effective no later than October 1, 2026, so that service can begin no later than June 1, 2027.

5. Determination
597.
We find that PJM has not provided sufficient information for the Commission to find that its proposed June 1, 2029, effective date is just and reasonable. We are concerned that the proposed June 1, 2029, effective date unduly delays the availability of the new transmission services, particularly those where PJM does not procure generation capacity for Eligible Customers taking the transmission service on behalf of Eligible Load, i.e., Interim NITS and NFCD transmission service. As discussed above, while PJM will procure generation capacity in forward capacity auctions to serve Eligible Customers taking FCD transmission service based on the contract demand level, PJM will not consider Interim NITS or NFCD transmission service in its resource adequacy planning. Further, we agree with Vistra and Joint Co-Location Developers that PJM's proposal lacks specificity. In particular, we find that the implementation details for the software updates necessary for PJM's economic dispatch software and dispatch tools lack specificity. Though PJM states that it cannot determine "a more exact development schedule" for software development,1152  the Commission generally requires more support for the timeliness of a proposed effective date.1153  We believe that the instant order provides PJM further clarity. We note that June 1, 2029, is approximately three years from now, and the issues raised by this proceeding, including those pertaining to Co-Located Load, are urgent in nature and, therefore, merit serious consideration of an earlier effective date. Therefore, we direct PJM to reconsider its proposed effective date of June 1, 2029. Moreover, we direct PJM to make a compliance filing, due within 60 days of the date of issuance of this order, in which PJM must explain whether it can 1150 Constellation May 11 Answer at 2.

1151 Id. at 3.
1152 PJM Reply Brief at 57.
1153  See, e.g., Midcontinent Indep. Sys. Operator, Inc., 190 FERC 1161,031, at P 163 & n.302 (2025).

421 of 515

PDF page 131

Dobument Accessigf Sie,:: 22Woftql8-3R99PMent:Filtd IPA9:616-7q8/2P-Ae Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 265 -
make the new transmission services available on different effective dates. In the compliance filing, PJM should specifically discuss whether Interim NITS and NFCD transmission service can be made effective at an earlier date for Eligible Customers taking transmission service on behalf of Eligible Loads.

K.
Additional Arguments
1. Behind the Meter Generation
a. Reply Briefs
598.
Industrials/Amtrak argue that the Commission should take the following actions:
(1) set a realistic retail BTMG threshold to focus new Co-Located Load rules on "gridbusting" growth above 200-300 MW, not on existing industrial customers (e.g., consumer goods manufacturers, steel mills, chemical manufacturers, paper mills, and pharmaceutical factories); (2) qualify all QFs for retail BTMG treatment without a date limit, consistent with PURPA regulations; (3) set clear grandfathering rules to enable existing, established users to avoid intensive PJM study queues, study deposits, and processes for operations that continue to function properly.1154

599.
PJM argues that certain parties raise issues beyond the scope of this proceeding. PJM contends that Industrials/Amtrak improperly ask the Commission to examine BTMG.1155

b. Determination
600. Industrials/Amtrak raise issues with respect to PJM's retail BTMG netting rules that we address in PJM's second compliance filing above.1156

2. Reliability Backstop Auction
a. Reply Briefs
601. Maryland OPC asserts that PJM's proposed terms and conditions do not explain how existing capacity resources that shift to Co-Location Arrangements with new data centers would be treated relative to the PJM's proposed reliability backstop procurement (RBP). For example, Maryland OPC states that it is unclear whether capacity from 1154  Industrials/Amtrak Reply Brief at 15.

1155 PJM Reply Brief at 58-59.
1156  See supra Part V.A.
422 of 515

PDF page 132

Document AccesSi
2-Ag1.8-39@cument:Fi il d  aqii:61g4812ppe Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 266 -
existing generators that remove themselves from the capacity market and enter Co-Location Arrangements with new data center load would need to be replaced with new capacity through the RBP or in the regular BRA, and whether new data center load that co-locates with an existing generator will be included in the cost allocation of the RBP 115'  Maryland OPC states that if the capacity of existing generation that shifts to serve new co-located data center load is added to the BRA, ratepayers would be saddled with enormous costs that should be assigned to the Co-Located Load, in contravention of the White House and PJM Governors' Statement of Principles and the White House's Ratepayer Protection Pledge. Maryland OPC requests that the Commission at minimum require PJM demonstrate how its proposal meets ratepayer protection standards set forth in the Statement of Principles and Ratepayer Protection Pledge and defer action on the proposed revisions until after PJM proposes tariff revisions to implement its RBP. Maryland OPC also raises concern that PJM's initial brief suggests PJM does not intend for existing load to be eligible for the new transmission services.I158 b. Determination

602. As an initial matter, we clarify that, contrary to Maryland OPC's concern, PJM's paper hearing proposal does not restrict Eligible Customers on behalf of existing Co-Located Load from taking the new transmission services. We decline Maryland OPC's request to defer action. Maryland OPC expresses concern that PJM's paper hearing proposal does not address how existing capacity resources that seek to serve Co-Located Loads would be treated relative to a potential future filing by PJM to address its reliability backstop mechanism. We find that Maryland OPC's concerns about PJM's capacity market are beyond the scope of this paper hearing, which addresses the rates, terms, and conditions for new transmission services for Eligible Customers to take on behalf of Eligible Loads.1159

1157  Maryland OPC Reply Brief at 9-11.
1158  Id. at 8 (noting PJM's explanation that it is unlikely that new generation will be operational before its proposed June 1, 2029 effective date).

1159  In recognition of the goal to prevent unfair cost shifts, we also note that as part of the President's Ratepayer Protection Pledge, a number of computational loads have committed to paying for "all new power delivery infrastructure upgrades to service their data centers." Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026). 423 of 515

PDF page 133

Document Accessig SA 2A-g64-,1 8  _ 3Q gg ument :F
d rpaN9: gfli8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 267 -
3. Eligible Customer Requirements
a. Response Briefs
603. Invenergy requests that the Commission and PJM clarify how the definition of Eligible Customer applies to Co-Located Generators and Co-Located Loads.116° Invenergy explains that, where a state retail choice program results in unbundled retail access, customers may take transmission service as an Eligible Customer, and that therefore, Invenergy believes that a Co-Located Load could qualify as an Eligible Customer in a retail choice jurisdiction.1161  Invenergy seeks clarity as to whether, in the context of a Co-Location Arrangement, a Co-Located Generator qualifies as an Eligible Customer on behalf of the Co-Located Load, and whether that Co-Located Generator's status as an Eligible Customer depends on whether the Co-Location Arrangement is in a retail choice jurisdiction.

b. Reply Briefs
604.
NOVEC argues that the Commission should consider a more definitive delineation of who may be an Eligible Customer as well as the scope of the Eligible Customer's obligations. Specifically, NOVEC seeks confirmation that it cannot be required to serve as an Eligible Customer serving Co-Located Load unless it agrees to do so.1162 605.

NOVEC argues that the Commission cannot require LSEs to modify their retail rates to accommodate these new services and undertake the administrative burden of being an Eligible Customer for a Co-Located Load unless the LSE chooses to do so. Further, NOVEC contends that it should not be subject to potential liability for the transmission costs, much less penalties for non-compliance with the Tariff's requirements, if a Co-Located Load for which NOVEC is serving as Eligible Customer fails to meet or comply with all applicable provisions.1163

606.
Indicated TOs express support for PJM's decision to retain the existing definition of Eligible Customer. In response to Invenergy's request for clarification as to how that definition applies to Co-Located Generators and Co-Located Loads, Indicated TOs argue that it will depend on an individual Co-Located Generator's specific factual circumstances. Indicated TOs contend that a Co-Located Generator is unlikely to meet " 6°  Invenergy Comments at 6.

1161 Id. (citing Order No. 888, FERC Stats. & Regs. ¶ 31,036 at 31,689). 1162  NOVEC Reply Brief at 5.

1163  Id. at 7.
424 of 515

PDF page 134

Document AccessigPA 12.16R-18-3499ument:FlAd rFaIN9:61A8/2psite Filed: 10/16/2025 Docket No. EL25-49-002, et al.

- 268 -
the definition of an Eligible Customer for purposes of obtaining FCD or NFCD transmission service because it is more likely to sell its output directly to the on-site load at retail. Indicated TOs further contend that the ability of Co-Located Load or an entity representing the load to qualify as an Eligible Customer would necessarily depend on whether its host jurisdiction has adopted retail choice.1164

c. Determination
607.
With respect to Invenergy's request, we note the Tariff defines an Eligible Customer as (1) any electric utility or any person generating electric energy for sale for resale, but with respect to transmission service that the Commission is prohibited from ordering by section 212(h) of the FPA, such entity is eligible only if the service is provided pursuant to a state requirement that the Transmission Provider or Transmission Owner offer the unbundled transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner or (2) any retail customer taking unbundled transmission service pursuant to a state requirement that the Transmission Provider or a Transmission Owner offer the transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner.1165  A Co-Located Generator may serve as an Eligible Customer if it meets the requirements of this definition of Eligible Customer. 608.

We also clarify that nothing in this order or the December Order requires LSEs to modify their retail rates to accommodate the new transmission services. We require PJM, as the transmission provider, to offer these services, but we do not require LSEs to offer them to their retail customers. In other words, we do not require any LSE to become an Eligible Customer taking one of the new transmission services on behalf of an Eligible Load.

4. Demand Side Pathways
a. Response Briefs
609.
Alliance supports converting Options 7 and 8 from PJM's March 2025 Answer into enforceable tariff language. Alliance supports strong measurement and verification of load reductions from demand response and energy efficiency in order to implement Options 7 and 8.1166

1164  Indicated TOs Reply Brief at 6-7.
1165  PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions — E-F (41.0.0).
1166  Alliance Response Brief at 5-6.
425 of 515

PDF page 135

Document AccessigiV: 2gl'Agg18-31:29.curnent:Fhld rPA99: _
8/2pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 269 -
b. Determination
610. Alliance's comments are essentially an untimely request for rehearing of the December Order. Alliance overlooks that the December Order required PJM to create a new interim non-firm transmission service similar to PJM's Option 7. As part of our determinations with respect to the rates, terms, and conditions for Interim NITS, we are directing PJM to submit a compliance filing to revise its Tariff to implement this new transmission service. As for PJM's Option 8, wherein Co-Located Load that is Network Load may participate as a demand response resource, the Commission in the December Order did not direct any changes to PJM's demand response rules. We reiterate, as the Commission explained in the December Order, there is not sufficient evidence to conclude that the existing Tariff is not just and reasonable as it relates to the existing demand response rules.1167  Co-Located Loads that elect to be Network Load may participate as a demand response resource under PJM's existing Tariff to the extent that they meet the requirements to participate as such.

5. Interconnection
a. Response Briefs
611. AEU/SEIA claim that PJM proposes to require all co-located generators to undergo full interconnection studies, including those that have no intention of exporting power to the transmission system.I168  AEU/SEIA argue that PJM indisputably requires sufficient information about proposed co-located generators to reliably plan and operate the transmission system, but that subjecting non-exporting facilities to full interconnection studies will impose costs, delays, and administrative burden that are disproportionate to the reliability benefits that are achieved. AEU/SEIA further argue that this would further strain the interconnection queue to the detriment of the PJM region and its customers.

b. Reply Briefs
612. PJM argues that AEU/SEIA improperly assert that PJM should not study all interconnecting generators.""

1167  December Order, 193 FERC ¶ 61,217 at P 242.
1168  AEU/SEIA Response Brief at 15-16 (citing PJM Initial Brief at 82). 1169  PJM Reply Brief at 58.

426 of 515

PDF page 136

Document AccessigPV; 2A-A418-3Q6cument:Flita
g 6W8/2 ?Ate Filed: 10/16/2026
Docket No. EL25-49-002, et al.
- 270 -
c. Determination
613.
We find that AEU/SEIA's concerns about interconnection studies for Co-Located Generators are beyond the scope of this paper hearing, which concerns the rates, terms, and conditions of new transmission services that Eligible Customers may take on behalf of Eligible Loads. However, we note that the Commission has approved PJM's proposal to comply with the directives of the December Order that, for Interconnection Customers seeking to use new generators to serve Co-Located Load: PJM will consider requests for interconnection service below the full generating capability of the generator, and such Interconnection Customers may use existing procedures to accelerate a new service request if they satisfy the criteria of the Tariff.1170

6. Co-Location Arrangement with Electric Storage Resource
a. Response Brief
614.
Joint Co-Location Developers ask that PJM clarify that its transmission service requirements for electric storage charging apply to storage co-located with load, and exempt customers from the Maximum Facility Output where the customer's load shape and characteristics are inherently flexible.1171  Joint Co-Location Developers state that PJM does not require electric storage resources to take transmission service for charging, except where the storage charges during the zonal peak hour without being dispatched. Joint Co-Location Developers claim that, in the context of PJM's proposal to limit NFCD transmission service to 100% of the Maximum Facility Output of the Co-Located Generator, PJM appears to allow the relevant Co-Located Load to take service while the co-located electric storage resource charges. Joint Co-Location Developers maintain that PJM should clarify this point in its Tariff to avoid any implication that this activity is prohibited. Joint Co-Location Developers request that PJM clarify that co-located charging loads, like standalone electric storage resources, do not require transmission service unless they charge during the zonal peak hour without being dispatched, and that any withdrawals for electric storage charging at the Point of Interconnection for which transmission service is not required do not count toward the Maximum Facility Output. Joint Co-Location Developers request, in the alternative, that PJM remove the Maximum Facility Output limit for loads co-located with electric storage resources. 117°  PJM Interconnection, L.L.C., 195 FERC ¶ 61,030 at P 25.

1171  Joint Co-Location Developers Response Brief at 13-14.
427 of 515

PDF page 137

Document AccessigIir; A-2-YCZZ18-3R9c ument:Fht d ripAg: 64(gEi8/2pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 271 -
b. Reply Brief
615. PJM argues Joint Co-Location Developers improperly ask the Commission to examine transmission service for charging electric storage resources.1172 c. Determination

616. To the extent Joint Co-Location Developers ask the Commission to address transmission service for electric storage resources, such request is beyond the scope of this paper hearing, which concerns the rates, terms, and conditions of new transmission services for Eligible Customers on behalf of Eligible Loads. However, insofar as Joint Co-Location Developers raise concerns about PJM's proposed requirement that an Eligible Customer electing to take NFCD transmission service "must apply for [NFCD transmission service] equivalent to the megawatt level of the Co-Located Generating Facility dedicated to serving the Co-Located Load," which Joint Co-Location Developers refer to as the Maximum Facility Output limit, we reject PJM's proposal above.1173 The Commission orders:

(A)
In response to the requests for rehearing, the December Order is hereby modified and set aside, in part, as discussed in the body of this order. (B)

The clarification requests are hereby denied in part and granted in part, as discussed in the body of this order.

(C)
PJM is hereby directed to submit, within 60 days of the date of issuance of this order, a compliance filing with revisions to its Tariff as described in Part IV.B.3. (D)

PJM is hereby directed to submit, within 60 days of the date of issuance of this order, a compliance filing with revisions to its Tariff as described in Part IV.C.1.b.i. (E)

PJM is hereby directed to submit, within 60 days of the date of issuance of this order, a compliance filing with revisions to its Tariff as described in Part IV.C.1.c.i. (F)

PJM is hereby directed to submit, within 60 days of the date of issuance of this order, a compliance filing as described in Part V.

(G)
PJM is hereby directed to submit, within 60 days of the date of issuance of this order, a compliance filing as described in Part VI.

1172 PJM Reply Brief at 59.
1173  See supra Part VI.A.2.
428 of 515

PDF page 138

Document AccessigPsA: 2.2q-Agiq18 _31?gument:Flit d rpAg: Agq. 81, pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 272 -
(H)
PJM transmission owners are hereby directed to submit, within 60 days of the date of issuance of this order, a compliance filing as described in Part VI. By the Commission. Commissioner Chang is concurring with a separate statement attached.

(SEAL)
Debbie-Anne A. Reese,
Secretary.
429 of 515

PDF page 139

Document AccessigPSA: 2AActg-18  _ 3Q9cu men tFl it d rpAg9: d163/C1812 pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 273 -
Appendix — Tariff Record[s]
PJM Interconnection, L.L.C.
Intra-PJM Tariffs
•
A-B, OATT Definitions -- A - B (24.0.0)
•
L-M-N, OATT Definitions -- L
M - N (52.0.0)
•
28.1. OATT 28.1 Scope of Service: (2.0.0)
•
29.1, OATT 29.1 Condition Precedent for Receiving Service (4.0.0) •

29.2, OATT 29.2 Application Procedures: (4.0.0)
•
31.6. OATT 31.6 Annual Load and Resource Information Updates: (4.0.0) •

34.2, OATT 34.2 Netting of Behind the Meter Generation. (1.0.0) •

34.3, GATT 34.3 Netting of Non-Retail Behind The Meter Generation (2.0.0) •

300 B, OATT 300 Definitions B (2.0.0)
•
300 N, OATT 300 Definitions N (3.0.0)
•
400 B, OATT 400 Definitions B (2.0.0)
•
400 N, OATT 400 Definitions N (4.0.0)
•
401, OATT Part VIII.A 401 Applications for Cycle Process Intro (5.0.0) •

403, OATT Part VIILB 403 Application Rules (4.0.0)
•
IX Subpart A, OATT Part IX Subpart A FORM OF APPLICATION AND STUDIES AGRMT (4.0.0)

•
IX.B GIA Appx-Sched, OATT Part IX.B GIA Appendices and Schedules (5.0.0) •

IX.B GIA Schedule O. OATT Part IX.B GIA Schedule O (0.0.0) •

IX Subpart G, OATT Part IX Subpart G FORM OF NECESSARY STUDIES AGREEMENT (3.0.0)

430 of 515

PDF page 140

Document AccessigRW 2A1§A18-3Q9cLIMent:Filtd A3,11.s/2pAte Filed: 10/16/2026

Docket No. EL25-49-002, et al.
- 274 -
•
XL OATT XI. TRANSMISSION SERVICES FOR CO LOCATED LOADS (0.0.0)

•
ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0) •

ATTACHMENT F-4, OATT ATTACHMENT F-4 (0.0.0)
431 of 515

PDF page 141

Doaufnerit Accessigi SP 2Q12-YZA18-3Q0cUMent:Filtd Dijag9:6t3/4812pAte Filed: 10/16/2026 UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket Nos. EL25-49-002
Allegheny Electric Cooperative, Inc.
EL25-49-000
American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc.
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company
Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company

AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.

AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
432 of 515

PDF page 142

Document AccessigPsA: 2.2q-AqA18 _31:?@cument:Fhl d  d'g9:A3A812pAte Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 2
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
AD24-11-001
Constellation Energy Generation, LLC
EL25-20-001
(consolidated)
v. PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
ER26-1479-000
(Issued June 18, 2026)
CHANG, Commissioner, concurring:
1. In today's order, the Commission addresses rehearing requests and the paper hearing and compliance record regarding the rates, terms, and conditions through which Co-Located Loads may take transmission service from the PJM Interconnection, L.L.C. (PJM) system. I write separately to address the Commission's resolution of the "minimum charge" issue raised in my concurrence to the December Order,' which I believe provides a reasonable path forward based on the record before us.

2. In its December Order, the Commission asked two briefing questions regarding establishing an additional charge for Eligible Customers on behalf of a Co-Located Load that elects not to take any amount of transmission service or only a de minimis amount of 1  PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (December Order) (Comm'r Chang, concurring).

433 of 515

PDF page 143

Dod-ument Accessicir; qq-236CZA18_ 3RWUMerlt:Flitd EPAg9:61e3A8/2Me Filed: 10/16/2026 Docket No. EL25-49-002, et al.

- 3
transmission service.2  At that time, I wrote separately to emphasize my concern that the implementation of our rules around the new transmission services could risk cost shifting if those loads take little or no transmission service and thereby do not contribute to paying for the transmission system costs. Broadly, I remain vigilant about the impacts on consumers as the Commission continues to respond to new challenges from large and Co- Located Loads.

3. In today's order, the Commission concludes that the record does not adequately support either the need for an additional charge at this time, or how such a charge should be calculated and assessed. In so doing, the Commission acknowledges the complexity of (1) documenting the benefits that accrue to Co-Located Loads paying little or no transmission service from the grid, and (2) designing a charge that corresponds to those benefits.

4. As explained in my concurrence to the December Order, because the Commission does not require a Co-Located Load to take any specific amount of the new transmission services, it creates the possibility that the load could pay little or nothing towards the costs of the transmission system, notwithstanding potential benefits it receives from that system. If this fact pattern occurs, particularly on any significant scale, it may result in problematic cost shifts to other transmission customers. However, if Co-Located Loads do, in fact, take meaningful transmission service via an existing service or one or both of the new contract demand services, they would pay transmission charges that contribute to the recovery of the transmission system's capital and operations and maintenance costs. Therefore, whether underlying concerns around cost shifting actually manifest will ultimately depend on how the new transmission services will be used.

5. So, today's order reasonably concludes that insights from concrete experience with the use of these new transmission services will help inform whether further action would be needed to address cost shifting issues. Given the challenges demonstrated in the record with articulating or documenting the specific benefits associated with being synchronized to the PEW system, and designing a rate (including conditions under which and the parties to whom it will be charged) that is commensurate with those benefits, I am persuaded that continued monitoring of this issue is appropriate.

6. Furthermore, as part of a broader recognition that implementing the new transmission services represents a significant development in PJM, the Commission directs PJM to prepare an annual report that includes critical information about how these services are being requested and used, as well as how loads using the services contribute toward transmission owners' revenue requirements.3  The annual reports will provide

2  December Order, 193 FERC ¶ 61,217 at P 219, questions 3 and 4.
3  PJM Interconnection, L.L. C., 195 FERC ¶ 61,209, at PP 580-81 (2026). 434 of 515

PDF page 144

,Document AccessigP.
c Z-§)-AgAls 3Q9cu me nt:Fl
rpal@g9 : 6163A812pAte Filed: 10/16/2026
Docket No. EL25-49-002, et al.
4
information that helps the Commission, the states, market participants, and stakeholders monitor the impacts of these new transmission services, including assessing whether the potential cost shift concern discussed above and in my prior concurrence actually occurs. If it does, I stand ready to consider Federal Power Act section 205 filings or section 206 complaints (including sua sponte action by the Commission) to address those cost shifts. For these reasons, I respectfully concur.

Judy W. Chang
Commissioner
435 of 515

PDF page 145

Dodziinent-  Acce6eigitr; 2S)16q18-3489unient:Flild. rFa'q99: Mq8/2Me Filed: 10/16/2026 Document Content(s)

EL25-49-002.docx
1
436 of 515

PDF page 146

Case: 26-3621
Document: 1-1
Page: 437
Date Filed: 10/16/2026
ATTACHMENT D
PJM Interconnection, L.L.C. et al.; Notice of Denial of Rehearing By Operation of Law and Providing for Further Consideration, 196 FERC ¶ 62,089 (Aug. 20, 2026).

437 of 515

PDF page 147

Document AccessigiA 22q-Aq1 _ Apgument:FlAd rpa@g: 6183A012pAte Filed: 10/16/2026 196 FERC ¶ 62,089

UNTIED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc.
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company
Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company

AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.

AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Docket Nos. EL25-49-003
438 of 515

PDF page 148

Document Accessigi
22qAqlo _Apcurnent:Flil d ripAg:616.3A 012 p-Ate Filed: 10/16/2026
Docket No. EL25-49-003, et al.
-2-
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
AD24-11-002
Constellation Energy Generation, LLC
EL25-20-002
(consolidated)
v. PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
ER26-1479-001
NOTICE OF DENIAL OF REHEARING BY OPERATION OF LAW AND
PROVIDING FOR FURTHER CONSIDERATION
(August 20, 2026)
Rehearing has been timely requested of the Commission's order issued on June 18, 2026, in this proceeding. PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026). In the absence of Commission action on a request for rehearing within 30 days from the date it is filed, the request for rehearing may be deemed to have been denied. 16 U.S.C. § 8251(a); 18 C.F.R. § 385.713 (2025); Allegheny Def. Project v. FERC, 964 F.3d 1 (D.C. Cir. 2020) (en bans).

As provided in 16 U.S.C. § 8251(a), the requests for rehearing of the above-cited order filed in this proceeding will be addressed in a future order to be issued consistent with the requirements of such section. As also provided in 16 U.S.C. § 8251(a), the 439 of 515

PDF page 149

_ _ Dobumerit Accesbigf?g 22c3-AqA10 _ 31dppmentFlil d
6184A 0 12  pge Filed: 10/16/2026
Docket No. EL25-49-003, et al.
-3-
Commission may modify or set aside its above-cited order, in whole or in part, in such manner as it shall deem proper.

Debbie-Anne A. Reese,
Secretary.
440 of 515

PDF page 150

Document AccessigiS:: 2A-AA10_ 31d9gument:Flild jcpa g9:61,84/120/2pAte Filed: 10/16/2026 Document Content(s)

EL25-49-003.docx
1
441 of 515

PDF page 151

_Case: 26-3621
Document: 1-1
Page: 442
Date Filed: 10/16/2026
ATTACHMENT E
SERVICE LIST
442 of 515

PDF page 152

Andrew
Hinz
Andrew Hinz
1427 PARK AVE
BALTIMORE, MARYLAND
21217
UNITED STATES
ahinz61@outlook.com
Primary Person or Counsel
of Record to be Served
Party
Michael Haugh
Policy Director
Advanced Energy United
1010 VERMONT AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 20005
UNITED STATES
mhaugh@advancedenergyunited.or
g
Advanced
Energy
United
AEP
Appalachia
n
Transmissi
on
Company,
Inc.
Stacey Burbure
SVP, Transmission Regulatory
Engagement & Compliance
8500 Smiths Mill Road, 4th Floor
New Albany, OHIO 43054
UNITED STATES
slburbure@aep.com
Jessica A. Cano
Assoc.Gen.Counsel Regul. East
1 Riverside Plaza
Columbus, OHIO 43215-2372
jacano@aep.com
AEP
Indiana
Michigan
Transmissi
on
Company,
Inc.
Jennifer Key
1330 Connecticut Ave., N.W.
Washington, DISTRICT OF
COLUMBIA 20036
UNITED STATES
'key@steptoe.com
Jessica A. Cano
Assoc.Gen.Counsel Regul. East
1 Riverside Plaza
Columbus, OHIO 43215-2372
'acano@aep.com
AEP
Kentucky
Stacey Burbure
SVP, Transmission Regulatory
Jessica A. Cano
Assoc.Gen.Counsel Regul. East
Other Contact to be Served
- 1 -
Case: 26-3621
Document: 1-1
Page: 443
Date Filed: 10/16/2026
443 of 515

PDF page 153

Case: 26=3621
Document: 1-1
Page: 444
Date Filed: 10/16/2026
Transmissi ;
on
Company, "New
Inc.
!
Engagement & Compliance
8500 Smiths Mill Road, 4th Floor
Albany, OHIO 43054
UNITED STATES
slburbure@aep.com
1 Riverside Plaza
Columbus, OHIO 43215-2372
jacano@aep.com
- - ---
AEP Ohio i
Transmissi

on
Company,
Inc.
Jessica Cano
Assoc.Gen.Counsel Regul. East
1 Riverside Plaza
Columbus, OHIO 43215-2372
UNITED STATES
jacano aep.com
!
; :
'
Robert L Pennybaker
Regulated Pricing & Analysis M
 PO Box 201
TULSA,OHIO 74102
rlpennybaker@aep.com
;
AEP West
Virginia
'
Transmissi
on
Company,
Inc.
Stacey Burbure
SVP, Transmission Regulatory
Engagement & Compliance
8500 Smiths Mill Road, 4th Floor
New Albany, OHIO 43054
UNITED STATES
slburbure@aep.com
Jessica A. Cano
Assoc.Gen.Counsel Regul. East
1 Riverside Plaza
Columbus, OHIO 43215-2372
jacano@aep.com
AES
Corporatio
n, The
;
!
Elizabeth Savage
AES Corporation, The
4300 Wilson Blvd
Arlington, VIRGINIA 22203
UNITED STATES
elizabeth.savage@aes.com
Allegheny
Electric
Cooperativ i
e, Inc.
!
i
i
1212
Todd Sallade
VP Power Supply & Engineering
Allegheny Electric Cooperative,
Inc.
Locust Street
Harrisburg, PENNSYLVANIA
17101
todd sallade@ccsenergy.coln
Alliant
:
Energy

Corporate ;
Services,
Inc.
Mary Emerson
Corporate Counsel
Alliant Energy Corporation
801 PENNSYLVANIA AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 20004

2
444 of 515

PDF page 154

UNITED STATES
maryemerson@alliantenergy.com
Alpha
Generation,
LLC
Liam Baker
Senior Vice President Regulato
Alpha Generation, LLC
300 Atlantic Street
5th floor
Stamford, CONNECTICUT 06901
UNITED STATES
lbaker@alphagen.com
Ameren
Services
Company
on behalf
of Ameren
Illinois
Company,
Ameren
Transmissi
on
Company
of Illinois
and Union
Electric
Company
d/b/a
Ameren
Missouri
Stacey Scales
Paralegal
Ameren Services Company
1901 Chouteau
Mail Code 1310
St. Louis, MISSOURI 63103
UNITED STATES
sscales@ameren.com
Jennifer S. Moore
Senior Corporate Counsel
Ameren Services Company
1901 Chouteau Avenue
Mail Code 1310
St. Louis, MISSOURI 63103
jmoore499a@ameren.com
Brett White
Deputy General Counsel
American Clean Power Association
1299 Pennsylvania Avenue, N.W.
WASHINGTON, DISTRICT OF
COLUMBIA 20004
UNITED STATES
bwhite@cleanpower.org
American
Clean
Power
Association
American
Clean
Carrie Zalewski
VP & Markets and Transmission
Case: 26-3621
Document: 1-1
Page: 445
Date Filed: 10/16/2026
- 3 -
445 of 515

PDF page 155

Case: 26-3621
Document: 1-1
Page: 446
Date Filed: 10/16/2026
Power
,
Association
Washington, DISTRICT OF
COLUMBIA 20036
UNITED STATES
czalewski@cleanpower.org
'
American '
Council on '
Renewable
Energy
Elise Caplan
Director of Electricity Policy
American Council on Renewable
Energy
1150 CONNECTICUT AVE NW
STE 401
WASHINGTON, DISTRICT OF
COLUMBIA 20036
UNITED STATES
caplan@acore.org
American
Electric
Power
Service
Corporatio
n
Stacey Burbure
SVP, Transmission Regulatory
American Electric Power
Company
Engagement & Compliance
8500 Smiths Mill Road, 4th Floor
New Albany, OHIO 43054
slburbure@aep.com
American
Power
Service
Corporatio
n
Electric
' Kate Daley
1 Riverside Plaza
Columbus, OHIO 43215
kbdaley@aep.com
American
Electric
Power
Service
Corporatio ,
n
'
:
,
Adam Hickman
1 RIVERSIDE PLZ FL 25
COLUMBUS, OHIO 43215
ajhickman@aep.com
.
. _
American
Electric
Power
Service
,
i
LaChon Turner
AEP COMPANIES
801 PENNSYLVANIA AVE NW
STE 735

4
446 of 515

PDF page 156

American
Forest &
Paper
Association
Case: 26-3621
Document: 1-1
Page: 447
Date Filed: 10/16/2026
WASHINGTON, DISTRICT OF
COLUMBIA 20004
lturner@aep.com
Corporatio
Kenneth Stark
McNees Wallace & Nurick LLC
100 Pine Street
P.O. Box 1166
Harrisburg, PENNSYLVANIA
17108
UNITED STATES
kstark@mcneeslaw.com
Susan E. Bruce
McNees Wallace & Nurick LLC
100 Pine Street
P.O. Box 1166
Harrisburg, PENNSYLVANIA
17108
sbruce@mcneeslaw.com
American
Forest &
Paper
Association
Matthew L. Garber
McNees Wallace & Nurick LLC
100 Pine Street
P.O. Box 1166
Harrisburg, PENNSYLVANIA
17108
mgarber@mcneeslaw.com
Lisa McAlister
Deputy General Counsel - FERC/
American Municipal Power, Inc.
1111 Schrock Road
Suite 100
Columbus, OHIO 43229
UNITED STATES
lmcalister@amppartners.org
Gerit F. Hull
Deputy General Counsel - Regul
American Municipal Power, Inc.
1111 Schrock Road
Suite 100
COLUMBUS, OHIO 43229
ghull@amppartners.org
American
Municipal
Power, Inc.
John E. McCaffrey
Partner
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
WASHINGTON, DISTRICT OF
COLUMBIA 20006
*ohn.mccaffrey@stinson.com
American
Municipal
Power, Inc.
Christopher J Norton
Director of Market Regulatory
American Municipal Power, Inc.
1111 Schrock Road
American
Municipal
Power, Inc.
5
447 of 515

PDF page 157

Ca-se: 2&3621
Document: 1-1
Page: 448
Date Filed: 10/16/2026
Suite 100
Columbus, OHIO 43229
Icnorton@amppartners.org
AMERICA !
N
PETROLE '
UM
'
INSTITUT
E
'
Grace Soderberg
Senior Counsel
AMERICAN PETROLEUM
INSTITUTE
200 MASSACHUSETTS AVE
NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
soderbergg@api.org
American
Transmissi
on
Systems,
Incorporate
d
Amanda Parker
Attorney
76 South Main Street
Akron, OHIO 44308
UNITED STATES
aparker@firstenergycorp.com
Deborah L. Jacobson, ESQ
Attorney
341 WHITE POND DR
AKRON, OHIO 44320

djacobson@firstenergycorp.com
American
:
Transmissi
:
on
Systems,
Incorporate '
•
d
Amanda Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OHIO 44308
UNITED  STATES
aparker@firstenergycorp.com
Tricia S Hartzell
,
FirstEnergy Legal Specialist
FirstEnergy Service Company
i 76 S. Main Street
15th Floor
: Akron, OHIO 44308
thartzell@firstenergycorp.com ..
American

Transmissi ,
on
Systems,
I
Incorporate !
i
d
Morgan Parke
Associate General Counsel
FirstEnergy
341 White Pond Dr.
Akron, OHIO 44320
UNITED STATES
mparke@firstenergycorp.com
Americans
fora Clean :10
Energy
i
Grid
,....._,..._.
_.
,
Paige Rodrigues
Americans for a Clean Energy Grid
G St NE
Washington, DISTRICT OF
COLUMBIA 20002
-6
448 of 515

PDF page 158

UNITED STATES
paige.rodrigues@cleanenergygrid.o
rg
Lisa G McAlister
Deputy General Counsel - FERC/
1111 Schrock Road
Suite 100
Columbus, OHIO 43229
lmcalister@amppartners.org
AMP
Transmissi
on, LLC
Lisa McAlister
Deputy General Counsel - FERC/
American Municipal Power, Inc.
1111 Schrock Road
Suite 100
Columbus, OHIO 43229
UNITED STATES
Imcalister@amppartners.org
Christopher J Norton
Director of Market Regulatory
American Municipal Power, Inc.
1111 Schrock Road
Suite 100
Columbus, OHIO 43229
cnorton@amppartners.org
Jason Evans
Vice President
Antora Energy LLC
1080 W. Ewing Place - Box B10
Seattle, WASHINGTON 98119
UNITED STATES
jason.evans@tuusso.com
Noah B Long
Director, State & Regulatory P
Antora Energy LLC
200 W DE VARGAS ST STE 200
SANTA FE, NEW MEXICO
87501
noah.long@antora.com
Antora
Energy
LLC
Noah Long
Director, State & Regulatory P
Antora Energy LLC
200 W DE VARGAS ST STE 200
SANTA FE, NEW MEXICO
87501
UNITED STATES
noah.long@antora.com
Jessica Cano
Assoc.Gen.Counsel Regul. East
1 Riverside Plaza
Columbus, OHIO 43215-2372
UNITED STATES
acano@aep.com
Robert L Pennybaker
Regulated Pricing & Analysis M
PO Box 201
TULSA,OHIO 74102
rlpennybaker@aep.com
Antora
Energy
LLC
Appalachia
n Power
I Company
Case: 26-3621
Document: 1-1
Page: 449
Date Filed: 10/16/2026
7
449 of 515

PDF page 159

--Case: 26-3621
Document: 1-1
Page: 450
Date Filed: 10/16/2026
;
Appalachia ;
n Voices

Nicholas Guidi
Southern Environmental Law
Center
500 NEW JERSEY AVE NW STE
600
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
nguidi@selc.org
Katherine Rogers
€ Southern Environmental Law
Center
122 C ST NW STE 325
; WASHINGTON, DISTRICT OF
i COLUMBIA 20001
; krogers@selc.org
Arevon
'
Energy,
Inc.
'
Mike Gahimer
Arevon Energy, Inc.
14427 Salem Dr E
Carmel, INDIANA 46033
UNITED STATES
mgahimer@arevonenergy.com
Arkansas
Public
Service
io
Commi ss
n
:
Bridgette Frazier
Arkansas Public Service
Commission
1000 CENTER ST
LITTLE ROCK, ARKANSAS
72201
UNITED STATES
bridgette.frazier@arkansas.gov
,
Atlantic
City
Electric
Company
,
'
Carlos Isaac
Assistant General Counsel
Exelon Corporation
10 S. Dearborn Street
Chicago, ILLINOIS 60603
UNITED STATES
carlos.isaac@exeloncorp.com
, Stan Berman
' 3502 Fremont Ave N, #1
' Seattle, WASHINGTON 98103
stan@bermlaw.com
Avant-.d
!
, Avangrid
- 1 '
Inc.
,
Julie Morris
Compliance
Power, LLC
2701 NW VAUGHN ST STE 300 ,
PORTLAND, OREGON 97210
UNITED STATES
avangridpowerferc@avangrid.com '
Alan Trotta
United Illuminating Company,
The
157 Church Street
New Haven, CONNECTICUT
06510
alan.trotta@tlinet.cotn
__
_
8
450 of 515

PDF page 160

Diane Janicki
INDIVIDUAL
500 West Madison
Chicago, ILLINOIS 60661
Diane.Janicki@betm.com
Case: 26-3621
Document: 1-1
Page: 451
Date Filed: 10/16/2026
Avangrid,
Inc.
Baltimore
Gas and
Electric
Company
Noelle Kinsch
VP, Gen.Counsel & Corp Sec.
Avangrid Networks, Inc.
80 State Street
Albany, NEW YORK 12207
UNITED STATES
noelle.kinsch@avangrid.com
Carlos Isaac
Assistant General Counsel
Exelon Corporation
10 S. Dearborn Street
Chicago, ILLINOIS 60603
UNITED STATES
carlos.isaac@exeloncorp.com
Joel Newton
VP, Regulatory Law
Bloom Energy Corporation
6611 Dearborn Dr
Falls Church, VIRGINIA 22044
UNITED STATES
joel.newton@bloomenergy.com
Michael Blasik
Diamond Generating Corporation
1 International Place
Suite 910
Boston, MASSACHUSETTS
02110
UNITED STATES
m.blasik@dgc-us.com
Kevin Kilgallen
Director, Market Structure & P
Avangrid, Inc.
411 OAKLAND DR
DOWNINGTOWN,
PENNSYLVANIA 19335
kevin.kilgallen@avangrid.com
Stan Berman
3502 Fremont Ave N, #1
Seattle, WASHINGTON 98103
stan@bermlaw.com
Bloom
Energy
Corporatio
n
Boston
Energy
Trading
and
Marketing
LLC
Duane K. Duclaux
General Counsel
BrightNight, LLC
515 N FLAGLER DR STE P200
WEST PALM BEACH,
FLORIDA 33401
duane@brightnightpower.com
Robert C. Fallon
ENGELMAN FALLON, PLLC
BrightNigh
t Power
Marketing,
LLC
BrightNigh
t Power
9
451 of 515

PDF page 161

Case: 26-3621
Document: 1-1
Page: 452
Date Filed: 10/16/2026

  Marketing,
LLC

  1717 K St. NW
Washington, DISTRICT OF
COLUMBIA 20006
rfallon@efenergylaw.com

athalie Godard
Law Clerk
Brookfield Energy Marketing LP
41 Victoria Street
Gatineau, QUEBEC J8X2A1
CANADA
nathalie.godard@brookfieldrenewa
ble.com
 Aleksandar Mitreski
Brookfield Energy Marketing Inc.
68 Ellington St
Longmeadow,
MASSACHUSETTS 01106
aleksandar.mitreski@brookfieldre
newable.com

Brookfield
Renewable
Trading
and
Marketing
LP

Brookfield
Renewable
Trading
and
Marketing
LP

Steve Kelly
Director
Brookfield Energy Marketing LP
3261 Arters Mill Rd
Westminster, MARYLAND
21158
stephen.kelly@brookfieldrenewab
le.com

Lija Kaleps-Clark
Buckeye Power, Inc.
6677 Busch Blvd
Columbus, OHIO 43229
UNITED STATES
lkaleps@ohioec.org
Matt Barnes
Calibrant Energy
16 Gavin Cir
Andover, MASSACHUSETTS
01810
UNITED STATES
matthew.barnes@calibrantenergy.c
om
  Kurt Helfrich
Buckeye Power, Inc.
6677 Busch Boulevard
Columbus, OHIO 43229
khelfrich@ohioec.org

Buckeye
Power, Inc.

Calibrant
Energy

  California
Department
of Water
Resources
 Lisa Dowden
Senior Counsel
Spiegel & McDiarmid LLP
1818 N Street, NW
  Stephen C. Pearson
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor

- 10 -
452 of 515

PDF page 162

Case: 26-3621
Document: 1-1
Page: 453
Date Filed: 10/16/2026

State Water
Project
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
UNITED STATES
Lisa.Dowden@spiegelmcd.com

WASHINGTON, DISTRICT OF
COLUMBIA 20036
steve.pearson@spiegelmcd.com

  California
Department
of Water
Resources
State Water
Project

 Samuel B. Whillans
Spiegel & McDiarmid LLP
1818 N ST NW
8TH Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
samuel.whillans@spiegelmcd.com

 Amanda Drennen
Attorney
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
UNITED STATES
amanda.drennen@spiegelmcd.com

 Nhu Nguyen
Deputy Attorney General
California Department of Justice
1300 I Street
Sacramento, CALIFORNIA
95814
nhu.nguyen@doj.ca.gov

California
Department
of Water
Resources
State Water
Project

California
Department
of Water
Resources
State Water
Project

E Service
Spiegel & McDiarmid LLP
1818 N Street NW
8th Floor
Washington, DISTRICT OF
COLUMBIA 20036
eservice@spiegelmcd.com

  California
Department
of Water
Resources
State Water
Project

Robert S Hedrick
Office of the General Counsel
PO Box 899
SACRAMENTO,
Robert.Hedrick@water.ca.gov

California
Department
of Water
Resources

Robin M. Hennessy
Office of the General Counsel
Department of Water Resources
PO Box 899

453 of 515

PDF page 163

Case: 26-3621 _ Document: 1-1
Page: 454
Date Filed: 10/16/2026
State Water;
Project
,..
1
SACRAMENTO,
robin.hennessy water.ca.gov
California
Department
of Water
Resources !
State Water
Project
,
X95814
Regina Tochterman
Senior Legal Analyst
California Department of Justice
1300 I Street
Sacramento, CALIFORNIA
Regina.Tochterman@doj.ca.gov
California
Public
Utilities
Commissio
n
Christofer Nolan
California Public Utilities
Commission
505 Van Ness Avenue
SAN FRANCISCO,
CALIFORNIA 94102
UNITED STATES
christofer.nolan@cpuc.ca.gov
Anand Durvasula
California Public Utilities
Commission
505 VAN NESS AVE
SAN FRANCISCO,
CALIFORNIA 94102
anand.durvasula@cpuc.ca.gov

California
, Public
Utilities
Commissio
n
'
Simon T. Hurd
California Public Utilities
Commission
505 Van Ness Avenue
San Francisco, CALIFORNIA
94102
Simon.Hurd@cpuc.ca.gov
Calpine
,
Corporatio
n
Sarah Novosel
SR Vice President Gov. Affairs
Calpine Corporation
717 Texas Avenue, Suite 1000
Houston, TEXAS 77002
UNITED STATES
snovosel@calpine.com
Calpine
Corporatio
n
Rachael Marsh
V.P. and Managing Counsel
PO Box NA
Houston,TEXAS 77002
UNITED STATES
rachael.marsh@calpine.com
,
-12-
454 of 515

PDF page 164

Tom Smith
1300 Lakeside Avenue
Cleveland, OHIO 44114
tsmith@cpp.org
City of
Cleveland,
Department
of Public
Utilities,
Division of
Cleveland
Public
Power
David Scarpignato
Calpine Corporation
Calpine
717 Texas Avenue
Corporatio Suite 1000
n
Houston, TEXAS 77002
UNITED STATES
david.scarpignato@calpine.com
Howard Crystal
Senior Attorney
Center for Biological Diversity
1411 K ST NW STE 1300
WASHINGTON, DISTRICT OF
COLUMBIA 20005
UNITED STATES
hcrystal@biologicaldiversity.org
Vanessa Colon
Senior Counsel
Chevron U.S.A. Inc.
1400 SMITH ST RM 31158
HOUSTON, TEXAS 77002
UNITED STATES
vanessa.colon@chevron.com
Andrew Davitt
Chevron U.S.A. Inc.
Chevron
1400 SMITH ST RM 06076
U.S.A. Inc. HOUSTON, TEXAS 77002
UNITED STATES
andrewdavitt@chevron.com
Center for
Biological
Diversity
Chevron
U.S.A. Inc.
Case: 26-3621
Document: 1-1
Page: 455
Date Filed: 10/16/2026
-13-
455 of 515

PDF page 165

Case: 26-3621
Document: 1-1
Page: 456
Date Filed: 10/16/2026
City of
Hamilton,
Ohio
r
Michael R. Perry
Director of Electric
345 High Street
Suite 450
Hamilton, OHIO 45011
perrym@ci.hamilton.oh.us
Clean Air
'
Task Force
Shaun Goho
114 STATE ST FL 6
'
BOSTON, MASSACHUSETTS
'
02109
UNITED STATES
sgoho@catf.us
.
Ann Weeks.
Clean Air Task Force
18 Tremont St
Boston, MASSACHUSETTS
02108
aweeks@cat£us
Clean
Energy
-
Buyers
Association
Bryn Baker
Corporate Energy Buyers Associ
1501 M ST NW STE 900
WASHINGTON, DISTRICT OF
COLUMBIA 20005
UNITED STATES
bbaker@ceba.org
Clearway
'
Energy
Group LLC
Gretchen Schott
Assistant General Counsel, Reg
'
Clearway Energy Group LLC
'
1200 SMITH ST STE 600
:
HOUSTON, TEXAS 77002
:
UNITED STATES
gretchen.schott@clearwayenergy.c :
om
!imiller@ceba.9rg
John C Miller
Director, Transmission Policy
Corporate Energy Buyers
Association
1501 M ST NW STE 900
WASHINGTON, DISTRICT OF
COLUMBIA 20005
Cogentrix

Energy
Power
i
Manageme
nt, LLC
,
'
Brian Zimmet
Partner
1 THOMAS CIR NW
i
ROCK CREEK ENERGY
GROUP, LLP
WASHINGTON, DISTRICT OF
;
COLUMBIA 20005
,
UNITED STATES
;
bzimmet@rockcreekenergygroup.c
om
Marica Sharashenidze
Rock Creek Energy Group, LLP
1 Thomas Circle
Suite 700
Washington, DISTRICT OF
COLUMBIA 20005
msharashenidze@rockcreekenergy
group.com
- 14 -
456 of 515

PDF page 166

Case: 26-3621
Document: 1-1
Page: 457
Date Filed: 10/16/2026

Cogentrix
Energy
Power
Manageme
nt, LLC

George Knapp
General Counsel
13860 Ballantyne Corporate Place
Suite 300
Charlotte, NORTH CAROLINA
28277
GeorgeKnapp@cogentrix.com
Stephanie C Kueffner ESQ
Associate General Counsel
Cogentrix Energy Power
Management, LLC
13860 BALLANTYNE
CORPORATE PL STE 300
CHARLOTTE, NORTH
CAROLINA 28277
stephaniekueffner@cogentrix.com

Cogentrix
Energy
Power
Manageme
nt, LLC

Carlos Isaac
Assistant General Counsel
Exelon Corporation
10 S. Dearborn Street
Chicago, ILLINOIS 60603
UNITED STATES
carlos.isaac@exeloncorp.com

Commonw
ealth
Edison
Company

Stan Berman
3502 Fremont Ave N, #1
Seattle, WASHINGTON 98103
stan@bermlaw.com

Commonw
ealth
Edison
Company
of Indiana,
Inc.
Marianne Alvarez
Senior Analyst
101 Constitution Ave, NW
Suite 400 East
Washington, DISTRICT OF
COLUMBIA 20001
UNITED STATES
marianne.alvarez@exeloncorp.com

Amy L Blauman
Associate General Counsel
701 Ninth St. N.W.
WASHINGTON, DISTRICT OF
COLUMBIA 20001
amy.blauman@exeloncorp.com

Connecticu
t Municipal
Electric
Energy
Cooperativ
e
Scott Strauss
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036

Jeffrey A. Schwarz
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
jeffrey.schwarz@spiegelmcd.com

-15-

457 of 515

PDF page 167

-Case: 26-3621
Document: 1-1
Page: 458
Date Filed: 10/16/2026
UNITED STATES
Scott.Strauss@spiegelmcd.com
Connecticu
t Municipal '
Electric
Energy
Cooperativ
e
:
'
!
:
Dave Meisinger
Chief Executive Officer
CMEEC
30 Stott Avenue
Norwich, CONNECTICUT 06360'
dmeisinger@cmeec.org
Connecticu
t Municipal
Electric
Energy
Cooperativ
e
E Service

Spiegel & McDiarmid LLP
1818 N Street NW
8th Floor
Washington, DISTRICT OF
COLUMBIA 20036
eservice@spiegelmcd.com
Consolidate
d Edison
Company
of New
York, Inc.
and Orange
and
Rockland '
Utilities,
Inc.
Joshua Kirstein
Senior Attorney
Consolidated Edison Company of
New York, Inc.
Consolidated Edison Co. of New
York, Inc.
4 Irving Place-18th Floor
New York, NEW YORK 10003
UNITED STATES
kirsteinj@coned.com
Joshua A Kirstein
Senior Attorney
Consolidated Edison Company of
ew York, Inc.
Consolidated Edison Co. of New
York, Inc.
4 Irving Place-18th Floor
New York, NEW YORK 10003
kirsteinj@coned.com
Consolidate,
d Edison
'
Company
'
of New
York, Inc. '
and Orange
and
:
Rockland
'
Utilities,
,
Inc.
Sebrina Greene
Associate General Counsel
Consolidated Edison Company o f ,
New York, Inc.
,
i
4 Irving Place
i
New York, NEW YORK 10003
UNITED STATES
'
'
greenes@coned.com
Sebrina M. Greene
Associate General Counsel
Consolidated Edison Company of
New York, Inc.
4 Irving Place
New York, NEW YORK 10003
greenes@coned.com

Consolidate,
d Edison
Company
' NEELAM GALE-AHMAD
Paralegal
Con Edison Company of New
- 16 -
458 of 515

PDF page 168

of New
York, Inc.
and Orange
and
Rockland
Utilities,
Inc.
York
4 IRVING PL
W YORK, NEW YORK 10003
galeahmadn@coned.com
Consolidate
d Edison
Company
of New
York, Inc.
and Orange
and
Rockland
Utilities,
Inc.
Consolidate
d Edison
Company
of New
(York, Inc.
and Orange
and
Rockland
Utilities,
Inc.
Dana Lazarus
Director
Con Edison Company of New
York
4 Irving Place
New York, NEW YORK 10003
lazarusd@coned.com
David C Burns
Project Manager
Consolidated Edison Company of
New York, Inc.
Consolidated Edison Co. of New
York, Inc.
4 Irving Place-18th Floor
New York, NEW YORK 10003
burnsd@coned.com
Christopher Wilson
Director, Fed. Regulatory A
250 Massachusetts Avenue NW
Suite 760
Washington, DISTRICT OF
COLUMBIA 20001
UNITED STATES
FERCe-
filingsl@Constellation.com
Carrie I-I Allen
SVP & Deputy General Counsel
101 Constitution Ave. NW Suite
400 East
Washington, DISTRICT OF
COLUMBIA 20001
carrie.allen@constellation.com
Constellati
on Energy
Generation,
LLC
Constellati
on Energy
Paul Wight
DLA Piper LLP (US)
,Seth T. Lucia
Assistant General Counsel
- 17 -
Case: 26-3621
Document: 1-1
Page: 459
Date Filed: 10/16/2026
459 of 515

PDF page 169

Case: 26-3621. Document: 1-1
Page: 460
Date Filed: 10/16/2026
Generation,
LLC
;
I
500 Eighth St, NW
=
Washington, DISTRICT OF
#
COLUMBIA 20004
UNITED STATES
i
paul.wight@us.dlapiper.com
! ,
250 Massachusetts Avenue, NW
Suite 760
WASHINGTON, DISTRICT OF
COLUMBIA 20001
Seth.Lucia@constellation.com
Rachael Moore
Senior Attorney
Consumers ,
Energy
Consumers Energy Company
One Energy Plaza
Company
Jackson, MICHIGAN 49201
. UNITED STATES
rachael.moore@cmsenergy.com … 
...;._
Will Hild
Executive Director
Consumers' Research
Consumers' 1801 F St NW
Research
Washington, DISTRICT OF
COLUMBIA 20006
UNITED STATES
info@consumersresearch.org
Katie Guerry
SVP Regulatory Affairs
Convergent ; Convergent Energy and Power LP Energy and ! 7 TIMES SQ

Power LP ! NEW YORK, NEW YORK 10036 ; UNITED STATES

.i kg!.ierry@convergentep.com
Matthew Rudolphi
Joshua E. Adrian
Thompson Coburn LLP
Attorney
1909 K Street, N.W.
i Thompson Coburn LLP
I Cooperativ Suite 600
1909 K Street NW
e Energy
i Washington, DISTRICT OF
Suite 600
COLUMBIA 20006
WASHINGTON, DISTRICT OF
UNITED STATES
; COLUMBIA 20006
mrudolphi@thompsoncoburn.com
jadrian@thompsoncoburn.com

Cooperativ
e Energy
Nathan T Bellville
Regulatory Affairs Specialist
South Mississippi Electric Power
..._„; ..._

-18-
460 of 515

PDF page 170

Cordelio
Services
LLC
Association
PO BOX 15849
HATTIESBURG, MISSISSIPPI
39404
nbellville@cooperativeenergy.co
m
Gregory Jones
Paul Hastings LLP
1101 New York Avenue, NW
WASHINGTON, DISTRICT OF
COLUMBIA 20005
UNITED STATES
gjones@milbank.com
Lily Hunter
Milbank LLP
1101 New York Avenue, NW
Washington, DISTRICT OF
COLUMBIA 20005
lhunter@milbank.com
Sophia Faram
Paul Hastings LLP
2050 M St NW
Washington, DISTRICT OF
COLUMBIA 20036
sophiafaram@paulhastings.com
Cordelio
Services
LLC
Cordelio
Services
LLC
Luke Pangman
General Counsel
Cordelio Power
100 King St West, Suite 7000
Toronto, ONTARIO M5X 1A9
1pangman@cordeliopower.com
Cliff Sikora
Earthrise Energy, PBLLC
3033 WILSON BLVD STE 700
ARLINGTON, VIRGINIA 22201
UNITED STATES
cliff.sikora@earthriseenergy.com
Aaron Tinjum
Data Center Coalition
525-K East Market Street
#253
Leesburg, VIRGINIA 20176
UNITED STATES
aaron@datacentercoalition.org
Morgan A Sipple, ESQ
Data Center Coalition
1250 H ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20005
morgan@datacentercoalition.org
Data
Center
Coalition
Crete
Energy
Venture,
LLC
Case: 26-3621
Document: 1-1
Page: 461
Date Filed: 10/16/2026
- 19 -
461 of 515

PDF page 171

Case: 26-3621 - Document: 1-1
Page: 462
Date Filed: 10/16/2026
Data
Center
Coalition
{
-
, ,
Cy McNeill
Data Center Coalition
525 K-East Market, Street #253
1Leesburg, VIRGINIA 20175
cy@datacentercoalition.org _ _
I
Delaware
Municipal
Electric
Corporatio
n, Inc.
Thomas Rudebusch
;
Partner
Duncan, Weinberg, Genzer &
Pembroke PC
1667 K Street, NW
Suite 700
Washington, DISTRICT OF
,
COLUMBIA 20006
'
UNITED STATES
tlr@dwgp.com
Linda L. Murray-Kimball
Legal Assistant
Duncan, Weinberg, Genzer &
Pembroke PC
1667 K Street, NW
Suite 700
Washington, DISTRICT OF
COLUMBIA 20006-1654
lmk@dwgp.com
Delaware
Municipal
Electric
Corporatio
n, Inc.
Bhaveeta Mody
Duncan, Weinberg, Genzer &
Pembroke PC
1667 K Street, N.W.
Suite 700
WASHINGTON, DISTRICT OF
COLUMBIA 20006
UNITED STATES
bkm@dwgp.com
_
Kimberly Schlichting
Delaware Municipal Electric
Corporation, Inc.
22 Artisan Drive
Smyrna, DELAWARE 19977
kschlichting@demecinc.net
-
-
Delaware
Public
Service
Commissio ,
n
'
Matthew Hartigan
Delaware Public Service
Commission
861 Silver Lake Blvd.
Suite 100
Dover, DELAWARE 19904
UNITED STATES
matthew.hartigan@state.de.us
Delmarva

Power &
"
Light
Company
Carlos Isaac
Assistant General Counsel
Exelon Corporation
10 S. Dearborn Street
Chicago, ILLINOIS 60603
:
Stan Berman
3502 Fremont Ave N, #1
Seattle, WASHINGTON 98103
stan@bermlaw.com
-20-
462 of 515

PDF page 172

UNITED STATES
carlos.isaac@exeloncorp.com
Brian Caldwell
Senior Assistant Attorney Gene
Office of the Attorney General for
the District of Columbia
400 6TH ST NW FL 9
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
brian.caldwell@dc.gov
Shilpa Sadhasivam
400 6TH ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
shilpa.sadhasivam@dc.gov
DISTRICT
OF
COLUMBI
A
Wesley Walker
Senior Assistant General Couns
Dominion Companies
PO Box 25615
Richmond,VIRGINIA 23260-5615
UNITED STATES
wesley.walker@dominionenergy.c
om
Jacqulynn B. Hugee
Deputy General Counsel
Dominion Energy Services, Inc.
120 Tredegar Street
Richmond, VIRGINIA 23219
'acqulynn.b.hugee@dominionener
gy.com
Dominion
Energy
Services,
Inc.
James G Davis
Regulatory and Market Policy S
Dominion Energy & Dominion
Generation
120 TREDEGAR ST
RIVERVIEW
RICHMOND, VIRGINIA 23219
james.g.davis@dominionenergy.c
om
Dominion
Energy
Services,
Inc.
Andrea Hayden
Office of the General Counsel
DTE Electric Company
One Energy Plaza
1635 WCB
Detroit, MICHIGAN 48226
UNITED STATES
andrea.hayden@dteenergy.com
Tristin Rojeck
Regulatory Strategy Consultant
DTE Energy Company
1 ENERGY PLZ
DETROIT, MICHIGAN 48226
tristin.rojeck@dteenergy.com
DTE
Electric
Company
Duke
Energy
Leah Buchanan
Duke Energy eTariff Account
Case: 26-3621
Document: 1-1
Page: 463
Date Filed: 10/16/2026
-21-
463 of 515

PDF page 173

Case: 26-3621 _ Document: 1-1
Page: 464
Date Filed: 10/16/2026
Kentucky,
Inc.
, 550 South Tryon Street
' Charlotte, NORTH CAROLINA
128202
e-tariff@duke-energy.com
Duke
Energy
Ohio, Inc.
Sheri May
! Associate General Counsel
139 E. 4th Street, 1212-M
' Cincinnati, OHIO 45202
' sheri.may@duke-energy.com
Duquesne
Light
Company
Michael Brechlin
411 7th Ave
Pittsburgh, PENNSYLVANIA
15219
mbrechlin@duqlight.com
Duquesne
Light
Company
Tishekia Williams
Director of External Affairs a
411 Seventh Avenue
15th Floor
Pittsburgh, PENNSYLVANIA
15219
UNITED STATES
twilliams@duqlight.com
'
EARTHJU
STICE
'
Aaron Stemplewicz
Senior Attorney
EARTHJUS TICE
Clean Energy Program
1617 John F. Kennedy Blvd
Suite 2020
Philadelphia, PENNSYLVANIA
19103
UNITED STATES
astemplewicz@earthjustice.org
.
.
.
East
Kentucky
,
Power
'
Cooperativ ! ,
e, Inc.
'
Daniel Frank
Partner
Eversheds Sutherland (US) LLP
700 Sixth Street, N.W.
Suite 700
Washington, DISTRICT OF
,
' Denise R Foster Cronin
Vice President, Federal and RT
; East Kentucky Power
' Cooperative, Inc.
4775 LEXINGTON ROAD
LEXINGTON, KENTUCKY
-22-
464 of 515

PDF page 174

Case: 26-3621
Document: 1-1
Page: 465
Date Filed: 10/16/2026
COLUMBIA 20001-3980
UNITED STATES
DanielFrank@eversheds-
sutherland.corn
40392
denise.cronin@ekpc.coop
Allison Salvia
Eversheds Sutherland (US) LLP
700 Sixth Street, NW
Suite 700
Washington, DISTRICT OF
COLUMBIA 20001
UNITED STATES
AllisonSalvia@eversheds-
sutherland.corn
East
Kentucky
Power
Cooperativ
e, Inc.
Kelly Cuthbertson
Associate
Eversheds Sutherland (US) LLP
700 Sixth Street, NW
Suite 700
Washington, DISTRICT OF
COLUMBIA 20001
UNITED STATES
kellycuthbertson@eversheds-
sutherland.com
East
Kentucky
Power
Cooperativ
e, Inc.
Allison Salvia
700 Sixth Street, NW
Suite 700
Washington, DISTRICT OF
COLUMBIA 20001
UNITED STATES
AllisonSalvia@eversheds-
sutherland.com
Denise R Foster Cronin
Vice President, Federal and RT
4775 LEXINGTON ROAD
LEXINGTON, KENTUCKY
40392
denise.cronin@ekpc.coop
East
Kentucky
Power
Cooperativ
e, Inc.
F. Alvin Taylor
Attorney
McCarter & English, LLP
1301 K Street, NW
Suite 1000 West
Washington, DISTRICT OF
COLUMBIA 20005
East Texas
Electric
Cooperativ
e, Inc.
-23-
465 of 515

PDF page 175

Case: 26-3621_
Document: 1-1
Page: 466
Date Filed: 10/16/2026
UNITED STATES
ataylor@mccarter.com
......._
EDF
, :
Renewable I

s, Inc.
Linda Walsh
Husch Blackwell LLP
,
1801 Pennsylvania Ave. NW, Suite
1000
Washington, DISTRICT OF
COLUMBIA 20006
UNITED STATES
linda.walsh@huschblackwell.com
Corban A. Coffman

in Gump Strauss Hauer & Feld i
LLP
2001 K Street N.W.
 Washington, DISTRICT OF
COLUMBIA 20006
ccoffman@akingump.com … 
EDF
Renewable
s, Inc.
.
Michael Blackwell
Attorney
Husch Blackwell LLP
10700 VALLEY DR
CARMEL, INDIANA 46280
michael.blackwell@huschblackwe
ll.com
EDF
Renewable ,
s, Inc.
'
Emma Simon
Director, Transmission Policy
EDF Renewables Development,
Inc.
15445 Innovation Dr
San Diego, CALIFORNIA 92128
emmanix.simon@edf-re.com
EDF
Renewable !
s, Inc.
Temujin J Roach
Senior Director - Transmission
EDF Renewables, Inc.
400
3600 American Blvd., W, Suite
Minneapolis, MINNESOTA
55413
temujin.roach@edf-re.corn
____ _...._.. _ _ .... ___ ..___.
EDF
Renewable ;
s, Inc.
Anton Ptak
Director, Transmission and Int
EDF Renewables, Inc.
3600 AMERICAN BLVD W STE
400
BLOOMINGTON, MINNESOTA
-24-
466 of 515

PDF page 176

Case: 26-3621
Document: 1-1
Page: 467
Date Filed: 10/16/2026
55431
anton.ptak@edf-re.com
Kevin Huyler
Managing Director, Edison Elec
Edison Electric Institute
701 PENNSYLVANIA AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 20004
UNITED STATES
khuyler@eei.org
Christopher M Randall
Edison Electric Institute
Edison Electric Institute
701 Pennsylvania Avenue, NW
Washington, DISTRICT OF
COLUMBIA 20004
crandall@eei.org
Edison
Electric
Institute
Nancy Bagot
Senior Vice President
Electric Power Supply Association
1401 New York Avenue, NW
Suite 950
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
NancyB@epsa.org
Nancy Bagot
1401 NEW YORK AVE NW STE
950
WASHINGTON, DISTRICT OF
COLUMBIA 20005
UNITED STATES
nbagot@epsa.org
Electric
Power
Supply
Association
Electric
Power
Supply
Association
Karen Onaran
Vice President
ELCON
1101 K Street NW
Suite 700
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
KOnaran@elcon.org
Electricity
Consumers
Resource
Council
Electricity
Consumers
Karen Onaran
Vice President
ELCON
-25-
467 of 515

PDF page 177

Case: 26-3621
Document: 1-1
Page: 468
Date Filed: 10/16/2026
Resource
:
Council
1101 K Street NW
 Suite 700
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
KOnaran@elcon.org
Enchanted
Rock, LLC
Steven Shparber
Mintz, Levin, Cohn, Ferris,
Glovsky and Popeo, P.C.
Joel Yu
Director of Regulatory & Legis
Enchanted Rock, LLC
1113 VINE ST STE 101
HOUSTON, TEXAS 77002
jyu@enchantedrock.com
555 12TH ST NW S FE 1100
WASHINGTON, DISTRICT OF
COLUMBIA 20004
UNITED STATES
sshparber@mintz.com
Enchanted
Rock, LLC
Omar Bustami
Mintz, Levin, Cohn, Ferris,
Glovsky and Popeo, P.C.
3580 Carmel Mountain Road
Suite 300
San Diego, CALIFORNIA 92130
UNITED STATES
OBustami@mintz.com
James Huang
Director, Wholesale Markets Po
1113 Vine Street
Suite 101
Houston, TEXAS 77002
jhuang@erock.com
Enerwise
Global
Technologi
es, LLC
dba
CPower
Aaron Breidenbaugh
CPower Energy Management
CPower, Inc.
64 Westview Rd
Voorheesville, NEW YORK 12186
UNITED STATES
aaron.breidenbaugh@cpowerenerg
ymanagement.com
, agement.com

Nancy Chafetz
Senior Director, Regulatory an
LS POWER CORPORATION
1001 Fleet St Unit 400
Baltimore, MARYLAND 21202
nancy.chafetz@cpowerenergyman
Enerwise
Global
Technologi
es, LLC
dba
CPower
Kenneth D Schisler
Regulatory Affairs
CPower, Inc.
7604 Cooper Point Rd
Bozman, MARYLAND 21612
Kenneth.Schisler@CPowerEnergy
Management.com
-26-
468 of 515

PDF page 178

Case: 26-3621
Document: 1-1
Page: 469
Date Filed: 10/16/2026
Sarah Bresolin Silver
Vice President
ENGIE North America Inc.
1360 Post Oak Blvd
Houston, TEXAS 77056
UNITED STATES
sarah.bresolin@engie.com
Ted Kelly
Senior Attorney
Environmental Defense Fund
1875 Connecticut Ave NW Suite
600
Washington, DISTRICT OF
COLUMBIA 20012
UNITED STATES
tekelly@edf.org
Eric Stoutenburg
Eolian, L.P.
988 Howard Ave Ste
Eolian, L.P. Burlingame, CALIFORNIA 94010 UNITED STATES

eric.stoutenburg@eolianenergy.co
m
Bruce Grabow
Sheppard Mullin Richter &
Hampton LLP
2099 Pennsylvania Avenue, NW
Eolian, LP Suite 100
Washington, DISTRICT OF
COLUMBIA 20006-6801
UNITED STATES
bgrabow@sheppard.com
ENGIE
North
America
Inc.
Environme
ntal
Defense
Fund
1
Brian Zimmet
Partner
1 THOMAS CIR NW
ROCK CREEK ENERGY
GROUP, LLP
WASHINGTON, DISTRICT OF
Marica Sharashenidze
Rock Creek Energy Group, LLP
1 Thomas Circle
Suite 700
Washington, DISTRICT OF
COLUMBIA 20005
Essential
Power
OPP, LLC
- 27 -
469 of 515

PDF page 179

Case: 26-3621
Document: 1-1
Page: 470
Date Filed: 10/16/2026
COLUMBIA 20005
;
UNITED STATES
:
bzimmet@rockcreekenergygroup.c
om
msharashenidze@rockcreekenergy
group.com
Essential
Power
OPP, LLC
'
'
George Knapp
General Counsel
13860 Ballantyne Corporate Place
Suite 300
Charlotte, NORTH CAROLINA
28277
GeorgeKnapp@cogentrix.com

Essential
Power
OPP, LLC
Stephanie C Kueffner ESQ
Associate General Counsel
Cogentrix Energy Power
Management, LLC
13860 BALLANTYNE
CORPORATE PL STE 300
CHARLOTTE, NORTH
CAROLINA 28277
stephaniekueffner@cogentrix.com
Essential
'
Power
Rock
Springs,
LLC
;om
Brian Zimmet
Partner
1 THOMAS CIR NW
,'
ROCK CREEK ENERGY
i
'
GROUP, LLP
WASHINGTON, DISTRICT OF
COLUMBIA 20005
,
UNITED STATES
bzimmet@rockcreekenergygroup.c !
George Knapp
General Counsel
13860 Ballantyne Corporate Place
Suite 300
Charlotte, NORTH CAROLINA
28277
GeorgeKnapp@cogentrix.com

:
Essential
Power
i
Rock
Springs,
LLC
!COLUMBIA
Lynn Kirshbaum
1 Thomas Circle NW
'
Suite 700
i
Washington, DISTRICT OF
20005
:
UNITED STATES
;
lkirshbaum@rockcreekenergygrou
p.com
,
Haley M. Franco
Energy Regulatory Advisor
_
1 Thomas Circle NW
Suite 700
Washington, DISTRICT OF
COLUMBIA 20005
hfranco@rockcreekenergygroup.c
om
-28-
470 of 515

PDF page 180

Case: 26-3621
Document: 1-1
Page: 471
Date Filed: 10/16/2026
Brian Zimmet
Partner
Marica Sharashenidze
Essential
1 THOMAS CIR NW
Rock Creek Energy Group, LLP
Power
ROCK CREEK ENERGY
1 Thomas Circle
Rock
Springs,
GROUP, LLP
WASHINGTON, DISTRICT OF
Suite 700
Washington, DISTRICT OF
LLC

COLUMBIA 20005
UNITED STATES
COLUMBIA 20005
msharashenidze@rockcreekenergy
bzimmet@rockcreekenergygroup.c
om
group.com
George Knapp
General Counsel
13860 Ballantyne Corporate Place
Suite 300
Charlotte, NORTH CAROLINA
28277
GeorgeKnapp@cogentrix.com
Stephanie C Kueffner ESQ
Associate General Counsel
Cogentrix Energy Power
Management, LLC
13860 BALLANTYNE
CORPORATE PL STE 300
CHARLOTTE, NORTH
CAROLINA 28277
stephaniekueffner@cogentrix.com
Essential
Power
Rock
Springs,
LLC
Essential
Power
Rock
Springs,
LLC
Max Minzner
SVP and Deputy General Counsel
Exelon BSC-Legal Regulatory
701 9TH ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
max.minzner@exeloncorp.com
Carlos Isaac
Assistant General Counsel
Exelon Corporation
10 S. Dearborn Street
Jordan Kwok
Director, Federal Regulatory A
Exelon Business Services
701 9TH ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
jordan.kwok@exeloncorp.com
Exelon
Corporatio
n
Exelon
Corporatio
n
-29-
471 of 515

PDF page 181

-Case: 26-3621
Document: 1-1
Page: 472
Date Filed: 10/16/2026
Chicago, ILLINOIS 60603
UNITED STATES
carlos.isaac@exeloncorp.com
Exelon
Corporatio
n
Alejandro Bautista
Assistant General Counsel
Exelon Business Services
Company, LLC
2301 Market Street
Philadelphia, PENNSYLVANIA
19101
alejandro.bautista@exeloncorp.co
m
FirstEnergy
Service
Company
Amanda Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OHIO 44308
Tricia S Hartzell
FirstEnergy Legal Specialist
FirstEnergy Service Company
76 S. Main Street
15th Floor
Akron, OHIO 44308
thartzell@firstenergycorp.com
UNITED STATES
aparker@firstenergycorp.com
FirstEnergy
Service
'
Company
Morgan Parke
Associate General Counsel
FirstEnergy
341 White Pond Dr.
Akron, OHIO 44320
UNITED STATES
mparke@firstenergycorp.com
I
Google
'
Energy
'
LLC
Jane Rueger
Perkins Coie LLP
,
700 13th Street, N.W.
!
Suite 800
,
Washington, DISTRICT OF
;
COLUMBIA 20005-3960
:
UNITED STATES
,
jane.rueger@ashurstperkins.com
Brian D George
Google LLC
25 MASSACHUSETTS AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
briangeorge@google.com
Google
Energy
LLC
,
,
Jacob Neeley
Attorney
Ashurst Perkins Coie US LLP
33 E Main Street
-- ----- - - -
-
-30-
472 of 515

PDF page 182

Hamilton
Liberty
LLC
Stephanie C Kueffner ESQ
Associate General Counsel
Cogentrix Energy Power
Suite 201
Madison, WISCONSIN 53703
jacob.neeley@ashurstperkins.com
Jane Rueger
Perkins Coie LLP
700 13th Street, N.W.
Suite 800
Washington, DISTRICT OF
COLUMBIA 20005-3960
UNITED STATES
jane.rueger@ashurstperkins.com
Brian D George
Google LLC
25 MASSACHUSETTS AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
briangeorge@google.com
Google
LLC
Jacob Neeley
Attorney
Ashurst Perkins Coie US LLP
33 E Main Street
Suite 201
Madison, WISCONSIN 53703
'acob.neeley@ashurstperkins.com
Google
LLC
Brian Zimmet
Partner
1 THOMAS CIR NW
ROCK CREEK ENERGY
GROUP, LLP
WASHINGTON, DISTRICT OF
COLUMBIA 20005
UNITED STATES
bzimmet@rockcreekenergygroup .c
om
Marica Sharashenidze
Rock Creek Energy Group, LLP
1 Thomas Circle
Suite 700
Washington, DISTRICT OF
COLUMBIA 20005
msharashenidze@rockcreekenergy
group.com
Hamilton
Liberty
LLC
George Knapp
General Counsel
13860 Ballantyne Corporate Place
Suite 300
Charlotte, NORTH CAROLINA
28277
GeorgeKnapp@cogentrix.com
Hamilton
Liberty
LLC
Case: 23-3621
Document: 1-1
Page: 473
Date Filed: 10/16/2026
-31-
473 of 515

PDF page 183

Case: 26-3621
Document: 1-1
Page: 474
Date Filed: 10/16/2026
Management, LLC

13860 BALLANTYNE
CORPORATE PL STE 300
CHARLOTTE, NORTH
CAROLINA 28277
stephaniekueffner@cogentrix.com
Hamilton
Patriot
LLC
Brian Zimmet
Partner
1 THOMAS CIR NW
ROCK CREEK ENERGY
GROUP, LLP
WASHINGTON, DISTRICT OF
COLUMBIA 20005
UNITED STATES
bzimmet@rockcreekenergygroup.c
om
Marica Sharashenidze
Rock Creek Energy Group, LLP
1 Thomas Circle
Suite 700
Washington, DISTRICT OF
' COLUMBIA 20005
msharashenidze@rockcreekenergy
group.com
Hamilton
Patriot
LLC
George Knapp
General Counsel
13860 Ballantyne Corporate Place
Suite 300
Charlotte, NORTH CAROLINA
28277
GeorgeKnapp@cogentrix.com
Hamilton
Patriot
LLC
Stephanie C Kueffner ESQ
Associate General Counsel
Cogentrix Energy Power
Management, LLC
. 13860 BALLANTYNE
 CORPORATE PL STE 300
CHARLOTTE, NORTH
CAROLINA 28277
stephaniekueffner@cogentrix.com '
Hudson
Transmissi
on Partners,
LLC
William Hollaway
Gibson, Dunn & Crutcher LLP
1050 Connecticut Ave NW
Washington, DISTRICT OF
COLUMBIA 20036
-32-
474 of 515

PDF page 184

Case: 26-3621
Document: 1-1
Page: 475
Date Filed: 10/16/2026
UNITED STATES
WHollaway@gibsondunn.com
Edward Stern
President and CEO
Gibson, Dunn & Crutcher LLP
501 Kings Highway East, Suite 300
Fairfield, CONNECTICUT 06825
UNITED STATES
estern@powerbridge.us
Hudson
Transmissi
on Partners,
LLC
Lisa O'Hara
Corporate Counsel
Idaho Power Company
PO Box 70
BOISE,IDAHO
UNITED STATES
lo'hara@idahopower.com
Kimberly Janas
Office of the Illinois Attorney
General
115 S LA SALLE ST
CHICAGO, ILLINOIS 60603
UNITED STATES
kimberly.janas@ilag.gov
Idaho
Power
Company
Scott Metzger
Office of the Illinois Attorney
General
115 S LA SALLE ST
25TH FLOOR
CHICAGO, ILLINOIS 60603
scott.metzger@ilag.gov
Illinois
Attorney
General's
Office
'Susan L. Satter
Chief, Public Utilities Bureau
Office of the Illinois Attorney
General
115 S LA SALLE ST
CHICAGO, ILLINOIS 60603
susan.satter@ilag.gov
Illinois
Attorney
General's
Office
Eric DeBellis
Illinois Citizens Utility Board
309 W WASHINGTON ST STE
800
CHICAGO, ILLINOIS 60606
UNITED STATES
edebellis@citizensutilityboard.org
Clara Summers
Consumers for a Better Grid Ca
Citizens Utility Board of Illinois
309 W WASHINGTON ST STE
800
CHICAGO, ILLINOIS 60606
csummers@citizensutilityboard.or
g
Illinois
Citizens
Utility
Board
- 33 -
475 of 515

PDF page 185

-Case: 26-3621
Document: 1-1
Page: 476
Date Filed: 10/16/2026
Illinois
'
Municipal
Electric
,
Agency
Troy Fodor
Vice President General Counsel
Illinois Municipal Electric Agency
3400 Conifer Drive
Springfield, ILLINOIS 62711
UNITED STATES
tfodor@imea.org
..._
Illinois
Municipal
Electric
Agency
Daniel Chung
Staff Attorney
Illinois Municipal Electric Agency
3400 Conifer Drive
Springfield, ILLINOIS 62711
UNITED STATES
dchung@imea.org
.
Indiana
Michigan
Power
Company
Stacey Burbure
SVP, Transmission Regulatory
Engagement & Compliance
8500 Smiths Mill Road, 4th Floor
New Albany, OHIO 43054
UNITED STATES
slburbure@aep.com
Jessica A. Cano
Assoc.Gen.Counsel Regul. East
1 Riverside Plaza
Columbus, OHIO 43215-2372
jacano@aep.com
Indiana
Office of
Utility
Consumer
Counselor ;
I
Arthur Iler
Deputy Consumer Counsel - Fede
Indiana Office of Utility Consumer '
Counselor
115 W Washington St
Ste 1500 South
Indianapolis INDIANA 46204
UNITED STATES
ailer oucc.in.gov
South
,
Scott Jones
Indiana Office of the Utility

Indiana Office of Utility
Consumer Counselor
115 West Washington St. Ste.1500,
Indianapolis, INDIANA 46204
sjonesl@oucc.in.gov
,
Individual
Bruce Campbell
Principal
Enerwise Global Technologies,
LLC
9204 2ND AVE
SILVER SPRING, MARYLAND
20910
-34-
476 of 515

PDF page 186

Case: 26-3621
Document: 1-1
Page: 477
Date Filed: 10/16/2026

UNITED STATES
bruce@campbellea.com

Industrial
Energy
Consumers
of America

Kenneth Stark
McNees Wallace & Nurick LLC
100 Pine Street
P.O. Box 1166
Harrisburg, PENNSYLVANIA
17108
UNITED STATES
kstark@mcneeslaw.com

Internation
al
Transmissi
on
Company

Lauren Parrottino
Associate Attorney
ITC Holdings Corp.
27175 ENERGY WAY
NOVI, MICHIGAN 48377
UNITED STATES
1parrottino@itctransco.com

  r
  Tyler O'Connor
Crowell & Moring LLP
600 5TH ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
toconnor@crowell.com
William Borders
Chief Compliance Officer
Invenergy LLC
One South Wacker Drive
Suite 1500
Chicago, ILLINOIS 60606
UNITED STATES
ferccompliance@invenergy.com

  Invenergy
Renewable
s LLC

Kathryn Douglass
Crowell & Moring LLP
1601 Wewatta Street
Ste. 815
Denver, COLORADO 80202
kdouglass@crowell.com

Invenergy
Renewable
s LLC

Nicole Luckey
Senior Vice President, Regulat
Invenergy LLC
1 S WACKER DR STE 1800
CHICAGO, ILLINOIS 60606
nluckey@invenergy.com

Invenergy
Thermal
LLC

Tyler O'Connor
Crowell & Moring LLP
600 5TH ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001

Kathryn Douglass
Crowell & Moring LLP
1601 Wewatta Street
Ste. 815
Denver, COLORADO 80202
kdouglass@crowell.com

- 35 -
477 of 515

PDF page 187

Case: 26-3621
Document: 1-1
Page: 478
Date Filed: 10/16/2026
UNITED STATES
toconnor@crowell.com
Invenergy
Thermal
LLC
'
'
William Borders
Chief Compliance Officer
Invenergy LLC
One South Wacker Drive
Suite 1500
Chicago, ILLINOIS 60606
UNITED STATES
ferccompliance@mvenergy.com
,
i
Nicole Luckey
Senior Vice President, Regulat
Invenergy LLC
 1 S WACKER DR STE 1800
CHICAGO, ILLINOIS 60606
nluckey@invenergy.com
Jersey
Central
Power &
Light
Company
Amanda Parker
Attorney
76 South Main Street
Akron, OHIO 44308
UNITED STATES
aparker@firstenergycorp.com
Tricia S Hartzell
FirstEnergy Legal Specialist
76 S. Main Street
15th Floor
Akron, OHIO 44308
thartzell@firstenergycorp.com
Jersey
Central
Power &
Light
Company
Amanda Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OHIO 44308
UNITED STATES
aparker@firstenergycorp.corn
Tricia S Hartzell
FirstEnergy Legal Specialist
FirstEnergy Service Company
76 S. Main Street
15th Floor
Akron, OHIO 44308
thartzell@firstenergycorp.com
Jersey
Central
Power &
Light
Company
Morgan Parke
Associate General Counsel
FirstEnergy
341 White Pond Dr.
Akron, OHIO 44320
UNITED STATES
mparke@firstenergycorp.com
Kentucky
Power
Company
:
'
'
,
John Crespo
Deputy General Counsel
1 Riverside Plaza
29th Floor
Columbus, OHIO 43215
UNITED STATES
jccrespo aep.com
'
,
,
Jennifer L. Key, ESQ
1330 Connecticut Ave., N.W.
Washington, DISTRICT OF
COLUMBIA 20036
jkey@steptoe.com
-36-
478 of 515

PDF page 188

Case: 26-3621
Document: 1-1
Page: 479
Date Filed: 10/16/2026

Keystone
Appalachia
n
Transmissi
on
Company

Amanda Parker
Attorney
76 South Main Street
Akron, OHIO 44308
UNITED STATES
aparker@firstenergycorp.com

Deborah L. Jacobson, ESQ
Attorney
341 WHITE POND DR
AKRON, OHIO 44320
djacobson@firstenergycorp.com

Keystone
Appalachia
n
Transmissi
on
Company
Amanda Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OHIO 44308
UNITED STATES
aparker@firstenergycorp.com

Tricia S Hartzell
FirstEnergy Legal Specialist
FirstEnergy Service Company
76 S. Main Street
15th Floor
Akron, OHIO 44308
thartzell@firstenergycorp.com

  Keystone
Appalachia
Transmissi
on
Company
 Morgan Parke
Associate General Counsel
FirstEnergy
341 White Pond Dr.
Akron, OHIO 44320
UNITED STATES
mparke@firstenergycorp.com

Kingsport
Power
Company

Renee Hawkins
Assistant Treasurer
1 Riverside Plz
Columbus, OHIO 43215
UNITED STATES
rvhawkins@aep.com
Debra Raggio
Executive Vice President, Head
Klondike Digital Infrastructure
LLC
117 ORONOCO ST
ALEXANDRIA, VIRGINIA
22314
UNITED STATES
draggio@newfortressenergy.com

William E. Johnson, ESQ
Senior Counsel
1 Riverside Plaza
23rd Floor
Columbus, OHIO 43061
wejohnson@aep.com

Klondike
Digital
Infrastructu
re LLC

Lakewood
Cogenerati
on, LP

Brian Zimmet
Partner
1 THOMAS CIR NW

Marica Sharashenidze
Rock Creek Energy Group, LLP
1 Thomas Circle

- 37 -
479 of 515

PDF page 189

Case: 26-3621
Document: 1-1
Page: 480
Date Filed: 10/16/2026
'
ROCK CREEK ENERGY
GROUP, LLP
'
WASHINGTON, DISTRICT OF
:
COLUMBIA 20005
;
UNITED STATES
'
bzimmet@rockcreekenergygroup.c
om
 Suite 700
Washington, DISTRICT OF
COLUMBIA 20005
msharashenidze@rockcreekenergy
group.com
Lakewood
Cogenerati
on, LP
George Knapp
General Counsel
13860 Ballantyne Corporate Place
Suite 300
Charlotte, NORTH CAROLINA
28277
GeorgeKnapp@cogentrix.com
Lakewood
Cogenerati
on, LP
Stephanie C Kueffner ESQ
Associate General Counsel
Cogentrix Energy Power
Management, LLC
13860 BALLANTYNE
CORPORATE PL STE 300
CHARLOTTE, NORTH
CAROLINA 28277
stephaniekueffner@cogentrix.com
Large
Public
'
Power
Council
'
Jonathan Schneider
'
Stinson LLP
'
1775 Pennsylvania Avenue NW
Suite 800
'
Washington, DISTRICT OF
COLUMBIA 20006
:
UNITED STATES
;
jonathan.schneider@stinson.com
John E. McCaffrey
Partner
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
WASHINGTON, DISTRICT OF
COLUMBIA 20006
ohn.mccaffrey@stinson.com

Large
Public
Power
Council
,
_._
M. Denyse Zosa., ESQ
Stinson Leonard Street LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DISTRICT OF
COLUMBIA 20006
denyse.zosa@stinson.com
-38-
480 of 515

PDF page 190

Case: 26-3621
Document: 1-1
Page: 481
Date Filed: 10/16/2026

Lee County
Electric
Cooperativ
e, Inc.

John Adragna
McCarter & English, LLP
1301 K Street, NW
Suite 1000 West
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
Jadragna@mccarter.com

F. Alvin Taylor
Attorney
McCarter & English, LLP
1301 K Street, NW
Suite 1000 West
Washington, DISTRICT OF
COLUMBIA 20005
ataylor@mccarter.com

Lee County
Electric
Cooperativ
e, Inc.

Clark Hawkins
Director - Electric Operations
4980 Bayline Drive
North Fort Myers, FLORIDA
33917
Clark .Hawkins @lcec.net

Sarah Bullock
Director Finance and Supply Ch
Lee County Electric Cooperative,
Inc.
4980 BAYLINE DR
NORTH FORT MYERS,
FLORIDA 33917
sarah.bullock@lcec.net

Lee County
Electric
Cooperativ
e, Inc.

Lincoln
Generating
Facility,
LLC

Cliff Sikora
Earthrise Energy, PBLLC
3033 WILSON BLVD STE 700
ARLINGTON, VIRGINIA 22201
UNITED STATES
cliff.sikora@earthriseenergy.com
Marjorie Philips
VP, Wholesale Market Policy
LS Power Associates, L.P.
250 W 55TH ST FL 31
NEW YORK, NEW YORK 10019
UNITED STATES
mphilips@Ispower.com

LS Power
Developme
nt, LLC

LS Power
Developme
nt, LLC

Tom Hoatson
1 Tower Center
East Brunswick, NEW JERSEY

-39-
481 of 515

PDF page 191

Case: 26-3621
Document: 1-1
Page: 482
Date Filed: 10/16/2026
08816
UNITED STA'L'ES
thoatson@lspower.com
:
LS Power
Developme ;
nt, LLC
Daniel Pierpont
Vice President
LS Power Development, LLC
250 W 55TH ST FL 31
NEW YORK, NEW YORK 10019
UNITED STATES
dpierpont@lspower.com
Mainspring
Energy
Brian Kauffman
Director, Wholesale Market Dev
Mainspring Energy
3601 HAVEN AVE
MENLO PARK, CALIFORNIA
94025
UNITED STATES
brian.kauffman@mainspringenergy
.com
Mainspring
Energy
Brian Kauffman
Director, Wholesale Market Dev
Mainspring Energy
3601 HAVEN AVE
MENLO PARK, CALIFORNIA
94025
UNITED STATES
brian.kauffman@mainspringenergy
.com
Maryland
Office of
'
People's

Counsel
William Fields
Deputy People's Counsel
6 SAINT PAUL ST STE 2102
BALTIMORE, MARYLAND
'
21202

UNITED STATES
william.fields@maryland.gov
Philip L Sussler
Senior Assistant People's Coun
Maryland Office of People's
Counsel
6 SAINT PAUL ST STE 2102
BALTIMORE, MARYLAND
21202
.
pluhp.sussler@maryland.gov
Maryland
Office of
i Alexis H Lewis, ESQ
Assistant People's Counsel
-40-
482 of 515

PDF page 192

Case: 26-3621
Document: 1-1
Page: 483
Date Filed: 10/16/2026
Office of People's Counsel
6 SAINT PAUL ST
BALTIMORE, MARYLAND
21202
alexis.lewis@maryland.gov
People's
Counsel
Ransom (Ted) Davis
Associate General Counsel
Maryland Public Service
Commission
6 St. Paul Street
16th Floor
BALTIMORE, MARYLAND
21202
UNITED STATES
Ransom.Davis@Maryland.gov
Miles H Mitchell
General Counsel
Maryland Public Service
Commission
6 St. Paul Street
16th Floor, William Donald
Schaefer Tower
Baltimore, MARYLAND 21202
miles.mitchell@maryland.gov
Morris Schreim
6 St. Paul Street
Baltimore, MARYLAND 21202
morris.schreim@maryland.gov
Maryland
Public
Service
Commissio
n
Maryland
Public
Service
Commissio
Scott Strauss
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
UNITED STATES
Scott.Strauss@spiegelmcd.com
Jeffrey A. Schwarz
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
jeffrey.schwarz@spiegelmcd.com
Massachus
etts
Municipal
Wholesale
Electric
Company
Matthew J. Ide
Exec. Director of Special Proj
Massachusetts Municipal
Wholesale Electric Company
327 Moody Street
P.O. Box 426
Ludlow, MASSACHUSETTS
01056
MIde@mmwec.org
Massachus
etts
Municipal
Wholesale
Electric
Company
- 41 -
483 of 515

PDF page 193

- Case: 26-3621
Document: 1-1
Page: 484
Date Filed: 10/16/2026
Massachus
efts
Municipal
Wholesale
Electric
Company
- -
-
:
Service

8th Floor

E
Spiegel & McDiarmid LLP
1818 N Street NW
Washington, DISTRICT OF
COLUMBIA 20036
eservice@spiegelmcd.com
Mid-
Atlantic
Interstate
Transmissi
on LLC
Amanda Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OHIO 44308
UNITED STATES
aparker@firstenergycorp.com
thartzell@firstenergycorp.corm
Morgan
Tricia S Hartzell
FirstEnergy Legal Specialist
FirstEnergy Service Company
76 S. Main Street
15th Floor
Akron, OHIO 44308
Mid-
Atlantic
Interstate
Transmissi
on LLC
Parke
Associate General Counsel
FirstEnergy
341 White Pond Dr.
Akron, OHIO 44320
UNITED STATES
mparke@firstenergycorp.com
Mid-
Atlantic
Interstate
Transmissi
on, LLC
. Deborah L. Jacobson, ESQ
Attorney
341 WHITE POND DR
AKRON, OHIO 44320
djacobson@firstenergycorp.com
:
Midwest

Generation,

LLC
,
Neal Fitch
Sr. Director, Regulatory Affai
NRG Energy, Inc.
804 CARNEGIE CTR
PRINCETON, NEW JERSEY
08540
UNITED STATES
neal.fitch@nrg.com
Midwest
,
Generation' '
LLC
Cortney Slager
VP & Assistant General Counsel
NRG Companies
804 Carnegie Center
.,
-42-
484 of 515

PDF page 194

Princeton, NEW JERSEY 08540
UNITED STATES
cortney.slager@nrg.com
Jennifer Hsia
Assistant General Counsel
NRG Energy
804 Carnegie Center
Princeton, NEW JERSEY 08540
UNITED STATES
Jennifer.Hsia@nrg.com
Midwest
Generation,
LLC
William Booth
Michael Best & Friedrich, LLP
1000 Maine Ave SW
Suite 400
Washington, D.C., DISTRICT OF
COLUMBIA 20024
UNITED STATES
wdbooth@michaelbest.com
Alex L. Peterson
Michael Best & Friedrich, LLP
1000 Maine Avenue, S.W.
Suite 400
Washington, DISTRICT OF
COLUMBIA 20024
alpeterson@michaelbest.com
Mississippi
Public
Service
Commissio
n
Barton Norfleet
Special Counsel for Federal En
501 N. West Street, Suite 201-A
P.O. Box 1174
JACKSON, MISSISSIPPI 39201
barton.norfleet@psc.ms.gov
Mississippi
Public
Service
Commissio
n
Jeffrey Mayes
General Counsel
Monitoring Analytics, LLC
2621 Van Buren Avenue, Suite 160
Valley Forge Corporate Center
Eagleville, PENNSYLVANIA
19403
UNITED STATES
jeffrey.mayes@monitoringanalytic
s.com
Suzette N Krausen
Executive Assistant
Monitoring Analytics, LLC
2621 Van Buren Ave Ste 160
Norristown, PENNSYLVANIA
19403
SuzetteKrausen@monitoringanal
ytics.com
Monitoring
Analytics,
LLC
Joseph Bowring
Monitoring Analytics, LLC
2621 Van Buren Avenue, Suite
160
Monitoring
Analytics,
LLC
Case: 26-3621
Document: 1-1
Page: 485
Date Filed: 10/16/2026
- 43 -
485 of 515

PDF page 195

-Case: 26-3621
Document: 1-1
Page: 486
Date Filed: 10/16/2026
Norristown, PENNSYLVANIA
19403
Joseph.Bowring@monitoringanaly
tics.com
Monongahe
la Power
Company
'
Amanda Parker
Attorney
,
76 South Main Street
Akron, OHIO 44308
UNITED STATES
a parker @firstenergycorp.com
Deborah L. Jacobson, ESQ
Attorney
341 WHITE POND DR
AKRON, OHIO 44320
djacobson@firstenergycorp.com
Monongahe,
la Power
Company
Amanda Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OHIO 44308
UNITED STATES
aparker@firstenergycorp.com
thartzell@firstenergycorp.corm
Morgan
Tricia S Hartzell
FirstEnergy Legal Specialist
FirstEnergy Service Company
76 S. Main Street
15th Floor
Akron, OHIO 44308
Monongahe
la Power
Company
Parke
Associate General Counsel
FirstEnergy
341 White Pond Dr.
Akron, OHIO 44320
UNITED STATES
mparke@firstenergycorp.com
National
Grid
,
.
Patrick Tarmey
Senior Counsel
National Grid
170 Data Drive
Waltham, MASSACHUSETTS
02451
UNITED STATES
patrick.tarmey@nationalgrid.com
National
Grid
Renewable
s
Developme
nt, LLC
Kurt Rempe
National Grid Renewables
Development, LLC
8400 NORMANDALE LAKE
BLVD S'IE 1200
BLOOMINGTON, MINNESOTA
- 44 -
486 of 515

PDF page 196

Case: 26-3621
Document: 1-1
Page: 487
Date Filed: 10/16/2026
55437
UNITED STATES
krempe@geronimopower.com
Matthew Morais
Senior Director, Federal Reg
PJM Interconnection, L.L.C.
8400 Normandale Lake Boulevard
Suite 1200
Bloomington, MINNESOTA
55437
UNITED STATES
mmorais@geronimopower.com
Connor Nelson
National Hydropower Associatio
National Hydropower Association
200 MASSACHUSETTS AVE
NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
connor@hydro.org
Michael Purdie
National Hydropower Association
601 NEW JERSEY AVE NW
STE 660
WASHINGTON, DISTRICT OF
COLUMBIA 20001
michael@hydro.org
National
Grid
Renewable
Developme
nt, LLC
National
Hydropowe
r
Association
Susan Bruce
McNees Wallace & Nurick LLC
100 Pine Street
P.O. Box 1166
Harrisburg, PENNSYLVANIA
17108
UNITED STATES
sbruce@mcneeslaw.com
Kenneth R. Stark
McNees Wallace & Nurick LLC
100 Pine Street
P.O. Box 1166
Harrisburg, PENNSYLVANIA
17108
kstark@mcneeslaw.com
National
Railroad
Passenger
Corporatio
n
("Amtrak")
Matthew L. Garber
McNees Wallace & Nurick LLC
100 Pine Street
P.O. Box 1166
Harrisburg, PENNSYLVANIA
17108
mgarber@mcneeslaw.com
National
Railroad
Passenger
Corporatio
n
("Amtrak")
National
Rural
Adrienne Clair
Thompson Coburn LLP
- 45 -
487 of 515

PDF page 197

Case: 26-3621
Document: 1-1
Page: 488
Date Filed: 10/16/2026
Electric
'
Cooperativ
e
"
Association
1
1909 K Street NW
Suite 600
Washington, DISTRICT OF
COLUMBIA 20006
UNITED STATES
aclair@thompsoncoburn.com

National
Rural
Electric
Cooperativ
e
Association
'
Mary Ann Ralls
Senior Direct, Regulatory Coun
National Rural Electric
Cooperative Association
4301 Wilson Blvd.
Arlington, VIRGINIA 22203
maryann.ralls@nreca.coop
Natural
Resource
Defense
Council
Tom Rutigliano
Sr. Advocate
NRDC/FERC Project
1124 15th St. NW
Suite 300
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
trutigliano@nrdc.org
Nebraska
Public
.
Power
District
David D'Alessandro
Attorney
Stinson LLP
1775 Pennsylvania Avenue, Suite
800
Washington, DISTRICT OF
COLUMBIA 20006
UNITED STATES
david.dalessandro@stinson.com
,
!
John McClure
Exec.VP Ext Affair/Gen Counsel
1414 15th Street
Columbus, NEBRASKA 68601
jcmcclu@nppd.com
Nebraska
Public
Power
District
,
'
Harold Hadland
Nebraska Public Power District
1414 15th Street
Columbus, NEBRASKA 68601
hlhadla@nppd.com
Neptune
Regional
'
William Hollaway
Gibson, Dunn & Crutcher LLP
-46-
488 of 515

PDF page 198

Transmissi
on System,
LLC
1050 Connecticut Ave NW
Washington, DISTRICT OF
COLUMBIA 20036
UNITED STATES
WHollaway@gibsondunn.com
Edward Stern
President and CEO
Gibson, Dunn & Crutcher LLP
501 Kings Highway East, Suite 300
Fairfield, CONNECTICUT 06825
UNITED STATES
estern@powerbridge.us
Neptune
Regional
Transmissi
on System,
LLC
Robert Glover
New Jersey Division of Rate
Counsel
PO Box 003
Trenton,NEW JERSEY 08625
UNITED STATES
rglover@rpa.nj.gov
T. David Wand
Division of Rate Counsel
New Jersey Division of Rate
Counsel
140 E. Front St.
4th Flr.
Trenton, NEW JERSEY 08625
dwand@rpa.nj.gov
New Jersey
Division of
Rate
Counsel
Debora Layugan
New Jersey Division of Rate
Counsel
PO Box 003
Trenton, 08625
dlayugan@rpa.nj.gov
New Jersey
Division of
Rate
Counsel
Brian O. Lipman
Director
New Jersey Division of Rate
Counsel
PO Box 003
Trenton, 08625
blipman@rpa.nj.gov
New Jersey
Division of
Rate
Counsel
New York
State
Reliability
Council,
L.L.C.
Amanda De Vito
Couch White, LLP
540 Broadway, Suite 7
Albany, NEW YORK 12207
Case: 26-3621
Document: 1-1
Page: 489
Date Filed: 10/16/2026
-47-
489 of 515

PDF page 199

— Case: 26-3621
Document: 1-1
Page: 490
Date Filed: 10/16/2026
UNITED STATES
adevito@couchwhite.com
NextEra
Energy
,
Transmissi
on
MidAtlanti
c Indiana,
Inc.
.
:
Travis M. Contratto
Principal Attorney
801 Pennsylvania Avenue, N.W.
Suite 220
Washington, DISTRICT OF
COLUMBIA 20004
Travis.Contratto@nee.com
North
American
Electric
Reliability
Corporatio
n
Caelyn Palmer
1325 G Street NW
Suite 600
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
caelyn.palmer@nerc.net
Candice Castaneda
Senior Counsel
North American Electric
Reliability Corporation
1325 G Street, NW
Suite 600
Washington, DISTRICT OF
COLUMBIA 20005
candice.castaneda@nerc.net
Northeast
Texas
Electric
Cooperativ
e, Inc.
F. Alvin Taylor
Attorney
McCarter & English, LLP
1301 K Street, NW
Suite 1000 West
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
ataylor@mccarter.com
Northeaster
n REMC
.
Alexandra Jones
VP & Sr. Counsel of Energy and
NORTHEASTERN REMC
6908 GEM CREEK LN
WHITESTOWN, INDIANA 46075
UNITED STATES
,
a~jones@nremc.com
Eric Jung
President/CEO
NORTHEASTERN REMC
4901 E Park 30 Drive
Columbia City, INDIANA 46725
ejung@nremc.com
Northern
Virginia
Electric
'
Alan Robbins
Partner
'
Washington Energy Law LLP
900 17TH ST NW STE 500-A
Patrick Toulme
Northern Virginia Electric
Cooperative,
10323 Lomond Drive
-48-
490 of 515

PDF page 200

Case: 26-3621
Document: 1-1
Page: 491
Date Filed: 10/16/2026
WASHINGTON, DISTRICT OF
COLUMBIA 20006
UNITED STATES
arobbins@washingtonenergylaw.co
m
Manassas, VIRGINIA 20109
ptoulme@novec.com
Cooperativ
e, Inc.
Debra Roby
Partner
Washington Energy Law LLP
900 17th Street NW
Suite 500-A
Washington, DISTRICT OF
COLUMBIA 20006
UNITED STATES
droby@washingtonenergylaw.com
Thomas Steiger
Associate
Washington Energy Law LLP
900 17th Street NW
Suite 500-A
Washington, DISTRICT OF
COLUMBIA 20006
UNITED STATES
tsteiger@washingtonenergylaw.co
m
Neal Fitch
Sr. Director, Regulatory Affai
NRG Energy, Inc.
804 CARNEGIE CTR
PRINCETON, NEW JERSEY
08540
UNITED STATES
neal.fitch@nrg.com
Cortney Slager
VP & Assistant General Counsel
NRG Companies
804 Carnegie Center
Princeton, NEW JERSEY 08540
Northern
Virginia
Electric
Cooperativ
e, Inc.
Northern
Virginia
Electric
Cooperativ
e, Inc.
G
Business
Marketing
LLC
G
Business
Marketing
LLC
-49-
491 of 515

PDF page 201

Case: 26-3621
Document: 1-1
Page: 492
Date Filed: 10/16/2026
•
UNITED STATES
cortney.slager@nrg.com
NRG
Business
,
Marketing
LLC
Jennifer Hsia
Assistant General Counsel
NRG Energy
804 Carnegie Center
Princeton, NEW JERSEY 08540
UNITED STATES
Jennifer.Hsia@nrg.com
Office of
the Ohio
Consumers'
Counsel
Denise Goulet
Partner
McCarter & English, LLP
1301 K ST NW
SUITE 1000 WEST
WASHINGTON, DISTRICT OF
COLUMBIA 20005
UNITED STATES
dgoulet@mccarter.com
Office of
,
the Ohio
,
Consumers'
Counsel
Angela O'Brien
Deputy Consumers' Counsel
Office of the Ohio Consumers'
Counsel
65 E STA IE ST STE 700
OFFICE OF THE O111O
CONSUMERS' COUNSEL
COLUMBUS, OHIO 43215
UNITED STATES
angela.obrien@occ.ohio.gov
Ohio
,
Federal
Energy
Advocate
Thomas Lindgren
Assistant Attorney General
Public Utilities Commission of
.
Ohio
30 East Broad Street
16th Floor
Columbus, OHIO 43215-3793
UNITED STATES
thomas.lindgren@ohioattomeygene
l.g
raov
Sarah Parrot
Federal Energy Advocate
Public Utilities Commission of
Ohio
180 E BROAD ST
COLUMBUS, OHIO 43215
sarah.parrot@puco.ohio.gov
-50-
492 of 515

PDF page 202

Chris Zentz
Partner
750 9th St. NW, #750
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
chris.zentz@akerman.com
Robert L Pennybaker
Regulated Pricing & Analysis M
PO Box 201
TULSA,DISTRICT OF
COLUMBIA 74102
rlpennybaker@aep.com
Ohio
Power
Company
Joe Bower
700 K Street NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
joe.bower@bakerbotts.com
Ohio
Power
Company
Scott R Cunningham
Electrical Operations Director
PO BOX 468
3932 US ROUTE 23
PIKETON, OHIO 45661
scunning@ovec.com
Ohio
Valley
Electric
Corporatio
n
Nick Privette
3932 U.S. Route 23
piketon, OHIO 47250
UNITED STATES
nprivett@ovec.com
Jecoliah Williams
555 Eleventh Street NW
Suite 1000
Washington, DISTRICT OF
COLUMBIA 20004
UNITED STATES
jecoliah.williams@lw.com
Adrienne E. Clair
1909 K Street NW
Suite 600
Washington, DISTRICT OF
COLUMBIA 20006
aclair@thompsoncoburn.com
Old
Dominion
Electric
Cooperativ
e
James Dunn
Senior Counsel
One Power Company
12385 Township Road 215
Findlay, OHIO 45840
UNITED STATES
jdunn@onepower.com
One Power
Company
Gregory Carmean
Executive Director
Organization of PJM States, Inc.
700 Barksdale Road
Suite 1
Newark, DELAWARE 19711
Organizatio
n of PJM
States, Inc.
Case: 26-3621
Document: 1-1
Page: 493
Date Filed: 10/16/2026
-51-
493 of 515

PDF page 203

= Case: 26-3621
Document: 1-1
Page: 494
Date Filed: 10/16/2026
UNITED STATES
greg@opsi.us
Pacific Gas ,
and
Electric
Company
Charles Middlekauff
Chief Counsel
Pacific Gas and Electric Company
PO Box 1018
Oakland,CALIFORNIA 94604-
1018
UNITED STATES
Charles.Middlekauff@pge.com
PECO
Energy
Company
Carlos Isaac
Assistant General Counsel
Exelon Corporation
10 S. Dearborn Street
Chicago, ILLINOIS 60603
UNITED STATES
carlos.isaac@exeloncorp.com
Stan Berman

3502 Fremont Ave N, #1

Seattle, WASHINGTON 98103

stan@bermlaw.com
Pennsylvan
is Office of
Consumer '
Advocate
Melanie El Atieh
Deputy Consumer Advocate
Pennsylvania Office of Consumer
Advocate
555 WALNUT ST
5TH FLOOR, FORUM PLACE
HARRISBURG,
PENNSYLVANIA 17101
UNITED STATES
melatieh@paoca.org
HARRISBURG,

Denell Lewis
Pennsylvania Office of Consumer
Advocate
555 WALNUT ST

PENNSYLVANIA 17101

dlewis@paoca.org
Pennsylvan
is Office of
Consumer
Advocate
'
Josiah Harmar
Assistant Consumer Advocate
Pennsylvania Office of Consumer
Advocate
555 WALNUT ST
5th Floor, Forum Place
HARRISBURG,
PENNSYLVANIA 17101
UNITED STATES
jharmar@paoca.org
- 52 -
494 of 515

PDF page 204

Case: 26-3621
Document: 1-1
Page: 495
Date Filed: 10/16/2026
Susan Bruce
McNees Wallace & Nurick LLC
100 Pine Street
P.O. Box 1166
Harrisburg, PENNSYLVANIA
17108
UNITED STATES
sbruce@mcneeslaw.com
PJM
Industrial
Customer
Coalition
Lauren Huff
Paralegal
McNees Wallace & Nurick LLC
100 Pine Street
P.O. Box 1166
Harrisburg, PENNSYLVANIA
17108
lhuff@mwn.com
iDavid S. Mabry
McNees Wallace & Nurick LLC
100 Pine Street
Harrisburg, PENNSYLVANIA
17101
dmabry@mwn.com
Craig Glazer
V.P., Federal Gov't Policy
1200 G Street, N.W.
Suite 600
Washington, DISTRICT OF
COLUMBIA 20005
craig.glazer@pjm.com
Ryan J. Collins
Attorney
1200 G Street, N.W.
Suite 600
Washington, DISTRICT OF
COLUMBIA 20005-3898
collins@wrightlaw.com
PJM
Industrial
Customer
Coalition
PJM
Industrial
Customer
Coalition
Mark Stanisz
Assistant General Counsel
PJM
2750 Monroe Blvd.
Interconnec Audubon, PENNSYLVANIA
tion L.L.C
19403
UNITED STATES
mark.stanisz@pjm.com
Andrew Swers
1200 G ST NW
PJM
Suite 600
Interconnec Washington, DISTRICT OF
tion L.L.C COLUMBIA 20005
UNITED STATES
swers@wrightlaw.com
- 53 -
495 of 515

PDF page 205

- Case: 26-3621
Document: 1-1
Page: 496
Date Filed: 10/16/2026
PJM
,
tion, L.L.C.'
Interconnec .
Mark Stanisz
:
Assistant General Counsel
'
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
.
Audubon, PENNSYLVANIA
19403
.
UNITED STATES
mark.stanisz@pjm.corn
Craig Glazer
i
V.P., Federal Gov't Policy
PJM Interconnection, L.L.C.
1200 G Street, N.W.
Suite 600
Washington, DISTRICT OF
COLUMBIA 20005
craig.glazer@pjm.com
PJM
Interconnec
tion, L.L.C.:
Arleigh Helfer
Sr. Counsel
PJM Interconnection, L.L.C.
2750 Monroe Boulevard
Audubon, PENNSYLVANIA
19403
arleigh.helfer@pjm.com
PJM Power
Providers
Group
'
Glen Thomas
101 Lindenwood Drive
Suite 225
Malvern, PENNSYLVANIA
19355
UNITED STATES
gthomas@gtpowergroup.com

Diane L Slifer
101 LINDENWOOD DR STE 225
MALVERN, PENNSYLVANIA
19355
dslifer@gtpowergroup.com
PJM Power
Providers
Group
Laura Chappelle
6688 FOREST BEACH DR
HOLLAND, MICHIGAN 49423
laurac@chappelleconsulting.net
Potomac
Electric
Power
Company
'
Gary Guy
Assistant General Counsel
Exelon Corporation
701 Ninth Street, NW
Washington, DISTRICT OF
COLUMBIA 20001
UNITED STATES
gary.guy@exeloncorp.com
PPL
Electric
:
Utilities
Steven Nadel
PPL Services Corporation
645 Hamilton Street
Suite 601

-54-
496 of 515

PDF page 206

Allentown, PENNSYLVANIA
18101
UNITED STATES
SMNadel@pplweb.com
Corporatio
n
PPL
Electric
Utilities
Corporatio
n
John Longstreth
K&L Gates LLP
1601 K Street, NW
Washington, DISTRICT OF
COLUMBIA 20006
UNITED STATES
john.longstreth@klgates.com
Donald Kaplan
K&L Gates LLP
1601 K Street, NW
Washington, DISTRICT OF
COLUMBIA 20006
UNITED STATES
don.kaplan@klgates.com
William Keyser
Steptoe LLP
1330 Connecticut Avenue NW
Washington, DISTRICT OF
COLUMBIA 20036
UNITED STATES
wkeyser@steptoe.com
PPL
Electric
Utilities
Corporatio
n
PPL
Electric
Utilities
Corporatio
n
Viet Ngo
Associate Counsel, Federal Reg
Public Service Enterprise Group
Incorporated
601 New Jersey Ave, NW
Suite 310
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
Viet.Ngo@pseg.com
Jodi Moskowitz
Deputy General Counsel and RTO
PSEG Services Corporation
Strategy Officer
80 Park Plaza, T-20
ewark, NEW JERSEY 07102
Jodi.Moskowitz@pseg.com
PSEG
Power LLC
Robert E. Gardinor
Paralegal
PSEG Services Corporation
PSEG
Power LLC
Case: 26-3621
Document: 1-1
Page: 497
Date Filed: 10/16/2026
-55-
497 of 515

PDF page 207

-Case: 26-3621
Document: 1-1
Page: 498
Date Filed: 10/16/2026
80 Park Plaza, T5
Newark, NEW JERSEY 07102
Robert.Gardinor@pseg.com
PSEG
'
Companies
Viet Ngo
Associate Counsel, Federal Reg
Public Service Enterprise Group
,
Incorporated
601 New Jersey Ave, NW
Suite 310
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
Viet.Ngo@pseg.com _
Jodi Moskowitz
Deputy General Counsel and RTO
PSEG Services Corporation
Strategy Officer
80 Park Plaza, T-20
Newark, NEW JERSEY 07102
Jodi.Moskowitz@pseg.com
.
PSEG
Companies
Robert E. Gardinor
Paralegal
PSEG Services Corporation
80 Park Plaza, T5
Newark, NEW JERSEY 07102
Robert.Gardinor@pseg.com
PSEG
Energy
Resources
& Trade
LLC
Viet Ngo
Associate Counsel, Federal Reg
Public Service Enterprise Group
Incorporated
601 New Jersey Ave, NW
Suite 310
WASHINGTON, DISTRICT OF
COLUMBIA 20001
.
UNITED STATES
Viet.Ngo@pseg.com
Jodi Moskowitz
Deputy General Counsel and RTO
PSEG Services Corporation
Strategy Officer
80 Park Plaza, T-20
Newark, NEW JERSEY 07102
Jodi.Moskowitz@pseg.com
PSEG
Energy
Resources
& Trade
LLC
'
-
- .
-
Robert E. Gardinor
Paralegal
PSEG Services Corporation
80 Park Plaza, T5
Newark, NEW JERSEY 07102
Robert.Gardinor@pseg.com
PUBLIC
CITIZEN, i
INC
Tyson Slocum
Energy Program Director
PUBLIC CITIZEN, INC

-56-
498 of 515

PDF page 208

215 PENNSYLVANIA AVE SE
WASHINGTON, DISTRICT OF
COLUMBIA 20003
UNITED STATES
tslocum@citizen.org
Public
Service
Commissio
n of West
Virginia
Jacqueline Roberts
Federal Policy Advisor, WV Pub
West Virginia Public Service
Commission
201 Brooks Street
Charleston, WEST VIRGINIA
25301
UNITED STATES
jroberts@psc.state.wv.us
Viet Ngo
Associate Counsel, Federal Reg
Public Service Enterprise Group
Incorporated
601 New Jersey Ave, NW
Suite 310
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
Viet.Ngo@pseg.com
Jodi Moskowitz
Deputy General Counsel and RTO
PSEG Services Corporation
Strategy Officer
80 Park Plaza, T-20
Newark, NEW JERSEY 07102
Jodi.Moskowitz@pseg.com
Public
Service
Electric
and Gas
Company
Robert E. Gardinor
Paralegal
PSEG Services Corporation
80 Park Plaza, T5
Newark, NEW JERSEY 07102
Robert.Gardinor@pseg.com
Public
Service
Electric
and Gas
Company
John Shepherd
Special Asst Attorney General
2200 Pennsylvania Avenue
WASHINGTON, DISTRICT OF
COLUMBIA 20037
UNITED STATES
jshepherd@hunton.com
Jodi Moskowitz
Deputy General Counsel and RTO
Strategy Officer
80 Park Plaza, T-20
Newark, NEW JERSEY 07102
Jodi.Moskowitz@pseg.com
Public
Service
Electric
and Gas
Company
Case: 26-3621
Document: 1-1
Page: 499
Date Filed: 10/16/2026
-57-
499 of 515

PDF page 209

Case: 26-3621
Document: 1-1
Page: 500
Date Filed: 10/16/2026
Public
Service
Electric
and Gas
Company
,
:
Blake Grow
2200 Pennsylvania Avenue, NW
WASHINGTON, DISTRICT OF
COLUMBIA 20037
bgrow@hunton.com
Repsol
Energy
North
America
Corporatio
n
Jordan Kirwin
Regulatory Affairs
Repsol Energy North America
Corporation
2455 Technology Forest Blvd.
The Woodlands, TEXAS 77381
UNITED STATES
jordan.kirwin@repsol.com
Rockland
Electric
Company
John Longstreth
K&L Gates LLP
1601 K Street, NW
Washington, DISTRICT OF
COLUMBIA 20006
UNITED STATES
john.longstreth@klgates.com
'
Rockland
Electric
Company
Joshua Kirstein
Senior Attorney
Consolidated Edison Company of
New York, Inc.
Consolidated Edison Co. of New
York, Inc.
4 Irving Place-18th Floor
New York, NEW YORK 10003
UNITED STATES
kirsteinj@coned.com
York, Inc.

Joshua A Kirstein
Senior Attorney
Consolidated Edison Company of
New York, Inc.
Consolidated Edison Co. of New
4 Irving Place-18th Floor
New York, NEW YORK 10003
kirsteinj@coned.com

Rockland
Electric
Company
Sebrina Greene
Associate General Counsel
Consolidated Edison Company of
New York Inc.

,
4 Irving Place
New York, NEW YORK 10003
UNITED STATES
greenes coned.com
=
:
'
Sebrina M. Greene

Associate General Counsel

Consolidated Edison Company of
New York, Inc.
4 Irving  Place
New York, NEW YORK 10003
greenes@coned.com
-58-
500 of 515

PDF page 210

Shell
Energy
North
America
(US), L.P.
ELAM GALE-AHMAD
Paralegal
Con Edison Company of New
York
4 IRVING PL
NEW YORK, NEW YORK 10003
galeahmadn@coned.com
Rockland
Electric
Company
Dana Lazarus
Director
Con Edison Company of New
York
4 Irving Place
New York, NEW YORK 10003
lazarusd@coned.com
Rockland
Electric
Company
David C Burns
Project Manager
Consolidated Edison Company of
New York, Inc.
Consolidated Edison Co. of New
York, Inc.
4 Irving Place-18th Floor
New York, NEW YORK 10003
burnsd@coned.com
Rockland
Electric
Company
Jonathan Newlander
Attorney
San Diego Gas & Electric
Company
8330 Century Park Ct
San Diego, CALIFORNIA 92123
UNITED STATES
JNewlander@sdge.com
Sean Chang
Director, Regulatory Affairs
Shell Energy North America (US),
L.P.
1000 Main Street
Level 12
Houston, TEXAS 77002
Pamela Mills
Regulatory Affairs Mgr
San Diego Gas & Electric
8330 Century Park
san diego, CALIFORNIA 92122
pmills@sdge.com
Matthew J. Picardi, ESQ
Vice President
Shell Energy North America (US),
L.P.
36 Pinewood Ave.
Saratoga Springs, NEW YORK
San Diego
Gas &
Electric
Company
Case: 26-3621
Document: 1-1
Page: 501
Date Filed: 10/16/2026
-59-
501 of 515

PDF page 211

- --Case: 26:3621
Document: 1-1
Page: 502
Date Filed: 10/16/2026
UNITED STATES
sean.chang@shell.com
12866
Matthew.Picardi@shell.com
Shell
Energy
North
' America
(US), L.P.
f
:
Shaela McNulty Collins
S. Power Policy Adv., Corp.
Shell Energy North America
(U.S.), L.P.
1050 K Street NW
Suite 700
Washington, DISTRICT OF
COLUMBIA 20001
shaela.collins@shell.com
Sierra Club
Justin Vickers
Senior Attorney
Sierra Club
Environmental Law Program
1229 W. Glenlake Ave.
Chicago, ILLINOIS 60660
UNITED STATES
justin.vickers@sierraclub.org
' Dorothy E Jaffe
Managing Attorney
50 F St NW
Washington, DISTRICT OF
COLUMBIA 20001
dori.jaffe@sierraclub.org
Silver Run ,
Electric,
LLC
'
;
Michael R. Engleman
1717 K St. NW
Washington, DISTRICT OF
COLUMBIA 20006
mengleman@efenergylaw.com
Silver Run ,
Electric,
LLC
Sharon Segner
Vice President
1001 19th Street North
Suite 1200
Arlington, VIRGINIA 22209
ssegner@lspower.com,
Solar
Energy
.
Industries
Association
Melissa Alfano
Manager of Regulatory Affairs
Solar Energy Industries
Association
1425 K Street, N.W., Suite 1000
Washington, DISTRICT OF
COLUMBIA 20005
:
Ben Norris
Manager of Federal Regulatory
 Solar Energy Industries
Association
1425 K St NW
 Washington, DISTRICT OF
COLUMBIA 20005
bnorris seia.org
-60-
502 of 515

PDF page 212

UNITED STATES
malfano@seia.org
Ellen Kenney
Southern California Edison
Company
2244 WALNUT GROVE AVE
ROSEMEAD, CALIFORNIA
91770
UNITED STATES
ellen.kenney@sce.com
Southern
California
Edison
Company
FERC Case Administration
Southern California Edison
Company
2244 WALNUT GROVE AVE
ROSEMEAD, CALIFORNIA
91770
ferccaseadmin@sce.com
John Rohrbach
ED Regulatory
4140 W 99TH ST
CARMEL, INDIANA 46032
UNITED STATES
JRohrbach@acespower.com
Mark MacDougall
Senior Vice President and Gene
PO Box 1937
Hughesville,MARYLAND 20637-
1937
UNITED STATES
mark.macdougall@smeco.coop
Damon Krieger
VP, Legal Affairs, Deputy Gen
15035 Burnt Store Road
P.O. Box 1937
Hughesville, MARYLAND
20637-1937
Damon.Krieger@SMECO.coop
Eugene Bradford
Vice President, Rates and Ener
15035 Burnt Store Rd.
Hughesville, MARYLAND 20637
Eugene.Bradford@smeco.coop
Southern
Maryland
Electric
Cooperativ
e, Inc.
Southern
Maryland
Electric
Cooperativ
e, Inc.
Damon Krieger
VP, Legal Affairs, Deputy Gen
Southern Maryland Electric
Cooperative, Inc.
15035 Burnt Store Road
P.O. Box 1937
Hughesville, MARYLAND 20637-
1937
UNITED STATES
Damon.Krieger@SMECO.coop
Southern
Maryland
Electric
Cooperativ
e, Inc.
John Rohrbach
ED Regulatory
ACES POWER MARKETING
4140 W 99TH ST
CARMEL, INDIANA 46032
JRohrbach@acespower.com
Eugene Bradford
Vice President, Rates and Ener
SOUTHERN MARYLAND
ELECTRIC COOP INC
Southern
Maryland
Electric
Case: 26-3621
Document: 1-1
Paae: 503
Date Filed: 10/16/2026
-61-
503 of 515

PDF page 213

Case: 26-3621
Document: 1-1
Page: 504
Date Filed: 10/16/2026
Cooperativ :
e, Inc.
.
15035 Burnt Store Rd.
Hughesville, MARYLAND 20637 ,
Eugene.Bradford@smeco.coop
Sustainable
FERC
Project
Tom Rutigliano
Sr. Advocate
C/FERC Project
1124 15th St. NW
Suite 300
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
trutigliano@nrdc.org
Talen
Energy
Cor poratio
n
Jennifer Mansh
Senior VP, Regulatory Counsel
Talen Energy Corporation
600 Hamilton Street
Suite 600
Allentown, PENNSYLVANIA
18101
UNITED STATES
Jennifer.Mansh@talenenergy.com
Jacqueline Fleming

Contracts and Legal Services A
Talen Energy Corporation
600 Hamilton Street, Suite 600
Allentown, PENNSYLVANIA
18101
jacqueline.fleming@talenenergy.c
0111
The Dayton
Power and
Light
Company
William M Rappolt
Assistant Gen. Counsel, FERC
4300 WILSON BLVD
ARLINGTON, VIRGINIA 22203 ,
william.rappolt@aes.com
The
Potomac
,
Edison
,
Company
'
Michael Kunselman
1301 K Street, NW Suite 500 East
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
michaelkunselman@dwt.com
Evan K Dean, ESQ
Managing Counsel, Transmission
341 WHITE POND DR # B-2
AKRON, OHIO 44320
edean@firstenergycorp.com
The
Potomac
Edison
Company
.._ .
' Bradley R. Miliauskas
1251 Avenue of the Americas
21st Floor
New York, NEW YORK 10020
bradleymiliauskas @dwt.com
-62-
504 of 515

PDF page 214

Amanda Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OHIO 44308
UNITED STATES
aparker@firstenergycorp.com
Tricia S Hartzell
FirstEnergy Legal Specialist
FirstEnergy Service Company
76 S. Main Street
15th Floor
Akron, OHIO 44308
thartzell@firstenergycorp.com
The
Potomac
Edison
Company
Morgan Parke
Associate General Counsel
FirstEnergy
341 White Pond Dr.
Akron, OHIO 44320
UNITED STATES
mparke@firstenergycorp.com
The
Potomac
Edison
Company
The Retail
Energy
Supply
Association
Elizabeth Whittle
Nixon Peabody LLP
799 9th Street NW
Suite 500
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
ewhittle@nixonpeabody.com
Evan Dean
Managing Counsel, Transmission
341 WHITE POND DR # B-2
AKRON, OHIO 44320
UNITED STATES
edean@firstenergycorp.com
Morgan E. Parke
Associate General Counsel
341 White Pond Dr.
Akron, OHIO 44320
mparke@firstenergycorp.com
Trans-
Allegheny
Interstate
Line
Company
Amanda Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OHIO 44308
UNITED STATES
aparker@firstenergycorp.com
Morgan Parke
Associate General Counsel
FirstEnergy
Tricia S Hartzell
FirstEnergy Legal Specialist
FirstEnergy Service Company
76 S. Main Street
15th Floor
Akron, OHIO 44308
thartzell@firstenergycorp.com
Trans-
Allegheny
Interstate
Line
Company
Trans-
Allegheny
Interstate
Case: 26-3621
Document: 1-1
Page: 505
Date Filed: 10/16/2026
-63-
505 of 515

PDF page 215

Case: 26-3621
Document: 1-1
Page: 506
Date Filed: 10/16/2026
Line
:
Company
341 White Pond Dr.
Akron, OHIO 44320
UNITED STATES
mparke@firstenergycorp.com
Transource , :
West
Virginia,
LLC
Stacey Burbure
SVP, Transmission Regulatory
Engagement & Compliance
8500 Smiths Mill Road, 4th Floor
New Albany, OHIO 43054
UNITED STATES
slburbure@aep.com
, Jessica A. Cano
Assoc.Gen.Counsel Regul. East
1 Riverside Plaza
Columbus, OHIO 43215-2372
jacano@aep.com
U.S.
Energy
Storage
Coalition
Noah Roberts
Executive Director
1650 Harvard St NW
Washington, DISTRICT OF
COLUMBIA 20009
UNITED STATES
noah@energystorage.org
UGI
Utilities
Inc.
Lindsay Berkstresser
Counsel — Energy & Regulatory
UGI Corporation
500 N. Gulph Road
King of Prussia,
PENNSYLVANIA 19406
UNITED STATES
berkstresserl@ugicorp.com
'
Alexandra Colaizzi
UGI Utilities, Inc.
1 UGI Drive
Denver, PENNSYLVANIA 17517
acolaizzi@ugi.com
UGI
Utilities
Inc.
i
Jesse Tyahla
Director of Energy Supply & P1
UGI Utilities Inc.
1 UGI Drive
Denver, PENNSYLVANIA 17517;
ityahla@ugi.com
_ _ _ _ .
UGI
Utilities
Inc.
i
Jamie Jowers
Senior Manager, Energy Supply
UGI Utilities Inc.
1 UGI Drive
Denver, PENNSYLVANIA 17517
jharper@ugi.com
-64-
506 of 515

PDF page 216

Case: 26-3621
Document: 1-1
Page: 507
Date Filed: 10/16/2026

UGI
Utilities,
Inc.

Richard Bonnifield
Partner
1801 PENNSYLVANIA AVE NW
STE 1000
WASHINGTON, DISTRICT OF
COLUMBIA 20006
UNITED STATES
richard.bonnifield@huschblackwell
.com

Michael Swerling
UGI Corporation
460 N Gulph Road
King of Prussia,
PENNSYLVANIA 19406
swerlingm@ugicorp.com

  Corban A. Coffman
2001 K Street N. W.
Washington, DISTRICT OF
COLUMBIA 20006
ccoffman@akingump.com

UGI
Utilities,
Inc.

 Michael Jacobs
Sr. Energy Analyst

UNION OF
CONCERN
ED
SCIENTIS
TS

UNION OF CONCERNED
SCIENTISTS
2 BRATTLE SQ
CAMBRIDGE,
MASSACHUSETTS 02138
UNITED STATES
mjacobs@ucs.org
Jason Barker
VP, Regulatory Affairs
Vitol Inc.
931 Metfield Rd
Towson, MARYLAND 21286
UNITED STATES
bja@vcrenewables.com

  Edwin Cambero
Compliance officer
2925 RICHMOND AVE
HOUSTON, TEXAS 77098
enc@vitol.com

VC
Renewable
s LLC

Vermont
Public
Power
Supply
Authority

Scott Strauss
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
UNITED STATES
Scott.Strauss@spiegelmcd.com

Jeffrey A. Schwarz
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
jeffrey.schwarz@spiegelmcd.com

-65-
507 of 515

PDF page 217

Case: 26-3621
Document: 1-1
Page: 508
Date Filed: 10/16/2026
Vermont
Public
Power
Supply
Authority
'
'
.
Kenneth A. Nolan
General Manager
Vermont Public Power Supply
Authority
P.O. Box 126
Waterbury Center, VERMONT
05677
knolan@vppsa.com . .
Vermont
Public
Power
Supply
Authority
E Service
Spiegel & McDiarmid LLP
1818 N Street NW
8th Floor
Washington, DISTRICT OF
COLUMBIA 20036
eservice@spiegelmcd.com
Verrus
LLC
Jeffrey Bladen
Verrus LLC
918 N Rengstorff Ave
Mountain View, CALIFORNIA
94043
UNITED STATES
bladen@verrusdata.com
Virginia
Electric
and Power
Company
Kathryn Gantley
Counsel
'
400 N CAPITOL ST NW STE 875
WASHINGTON, DISTRICT OF
COLUMBIA 20001
UNITED STATES
'
kathryn.gantley@dominionenergy. ,
corn
Jason B Lazos
Contracts Administrator III
201 West Blvd.
Williamston, NORTH
CAROLINA 27892
Jason.B.Lazos@dominionenergy.c
om
Virginia

State
Corporatio '
n
Commissio '
n
Frederick Ochsenhirt
Legal Advisor to the Commissio
Virginia State Corporation
Commission
1300 E MAIN ST
RICHMOND, VIRGINIA. 23219
UNITED STATES
-66-
508 of 515

PDF page 218

frederick.ochsenhirt@scc.virginia.g
ov
Nicholas Gladd
Wilson Sonsini Goodrich & Rosati,
P.C.
201 Washington St.
Suite 2000
Boston, MASSACHUSETTS
02108
UNITED STATES
ngladd@wsgr.com
J. Arnold Quinn
INDIVIDUAL
325 7th Street, N.W
Suite 520
Washington, DISTRICT OF
COLUMBIA 20004
UNITED STATES
arnie.quinn@vistracorp.com
Sarah Greenberg
Wilson Sonsini Goodrich & Rosati
1700 K ST NW FL 5
WASHINGTON, DISTRICT OF
COLUMBIA 20006
sgreenberg@wsgr.com
Andrew Weinstein
Director of ISO-NE Markets
Vistra Corp.
325 7th Street, NW
WASHINGTON, DISTRICT OF
COLUMBIA 20004
andrew.weinstein@vistracorp.com
Vistra
Corp.
Vistra
Corp.
Seth Cochran
Head of Strategic Market Polic
Vitol Inc.
2925 RICHMOND AVE
HOUSTON, TEXAS 77098
UNITED STATES
sco@vitol.com
Edwin Cambero
Compliance officer
2925 RICHMOND AVE
HOUSTON, TEXAS 77098
enc@vitol.com
Vitol Inc.
Kimaya Abreu
Voltus
Voltus, Inc.
2443 Fillmore Street
#380-3427
San Francisco, CALIFORNIA
94115
UNITED STATES
kabreu@voltus.co
Voltus, Inc.
Vote Solar
Nathan Phelps
Vote Solar
131 FARMHOLME RD
Case: 26-3621
Document: 1-1
Page: 509
Date Filed: 10/16/2026
-67-
509 of 515

PDF page 219

Case: 26-3621
Document: 1-1
Page: 510
Date Filed: 10/16/2026
- - _ - -
STONINGTON, CONNECTICUT
06378
UNITED STATES
nathan@votesolar.org
Wabash
Valley
,
Power
Association
, Inc.
John Adragna
1301 K Street, NW

,
Suite 1000 West
Washington, DISTRICT OF
COLUMBIA 20005
UNITED STATES
Jadragna@mccarter.com
Jeremy L. Fetty

6702 Intech Blvd.
Indianapolis, INDIANA 46278
JJetty@wvpa.com

Wabash
Valley
Power
Association
, Inc.
F. Alvin Taylor
Attorney
1301 K Street, NW
Suite 1000 West
Washington, DISTRICT OF
COLUMBIA 20005
Randolph Lee Elliott
1301 K Street, NW
Suite 1000 West
Washington, DISTRICT OF
COLUMBIA 20005
relliott@mccarter.com
UNITED STATES
ataylor@mccarter.com
Wabash
Valley
Power

Association'
,Inc.
Jeremy Fetty
Parr Richey Obremskey & Morton
6702 Intech Blvd.
Indianapolis, INDIANA 46278
UNITED STATES
Jjetty@wvpa.com
Wheeling
Power
,
Company
William Johnson
Senior Counsel
i
1 Riverside Plaza
23rd Floor
:
Columbus, OHIO 43061
UNITED STATES
,
wejohnson@aep.com
Julie Sherwood
1 Riverside Plaza
Floor 28
Columbus, OHIO 43215
jasherwood@aep.com
--- - -
-68-
510 of 515

PDF page 220

Case: 26-3621
Document: 1-2
Page: 1
Date Filed: 10/16/2026
26-3621 Case Caption
1
October 20, 2026 11:54 AM
Exelon Corp; American Transmission Systems, Inc.; Jersey Central Power & Light, Co.; Keystone Appalachian Transmission Co.; Mid Atlantic Interstate Transmission LLC; Monongahela Power Co.; Potomac Edison Co.; Trans Allegheny Interstate Line Co.; American Electric Power Service Corp., on behalf of its affiliates; Appalachian Power Co.; Indiana Michigan Power Co.; Kentucky Power Co.; Kingsport Power Co.; Ohio Power Co.; Wheeling Power Co.; AEP Appalachian Transmission Co., Inc.; AEP Indiana Michigan Transmission Co., Inc.; AEP Kentucky Transmission Co., Inc.; AEP Ohio Transmission Co., Inc.; AEP West Virginia Transmission Co., Inc.; Dayton Power & Light Co., DBA AES Ohio; Dominion Energy Services, Inc., on behalf of; Virginia Electric & Power Co., DBA Dominion Energy Virginia; Duquesne Light Co.; East Kentucky Power Cooperative, Inc.; PPL Electric Utilities Corp.; Rockland Electric Co., Petitioners

Federal Energy Regulatory Commission
511 of 515

PDF page 221

-- Case: 26-3621
Document: 1-3
Page: 1
Date Filed: 10/16/2026
PATRICIA S. DODSZUWEIT
CLERK
OFFICE OF THE CLERK
UNITED STATES COURT OF APPEALS
21400 UNITED STATES COURTHOUSE
601 MARKET STREET
PHILADELPHIA, PA 19106-1790
Website: www.ca3.uscourts.gov
October 20, 2026
TELEPHONE
215-597-2995

Stanley A. Berman
Stan Berman
3502 Fremont Avenue N
Suite 1
Seattle, WA 98103
Jared B. Fish
Federal Energy Regulatory Commission
888 1st Street NE
Washington, DC 20426
David M. Gossett
Davis Wright Tremaine
1301 K Street NW
Suite 500 East
Washington, DC 20005
Gary Guy
Exelon Corporation
701 Ninth Street NW
Washington, DC 20068
Michael Kunselman
Davis Wright Tremaine
1301 K Street NW
Suite 500 East
Washington, DC 20005
Steven M. Nadel
PPL Services Corp
645 Hamilton Street
Suite 601
Allentown, PA 18101
512 of 515

PDF page 222

Case: 26-3621
Document: 1-3
Page: 2
Date Filed: 10/16/2026
Morgan E. Parke
Firstenergy Service Co
341 White Pond Drive
Akron, OH 44320
Amanda P. Parker
Firstenergy Service Co
341 White Pond Drive
Akron, OH 44320
William M. Rappolt
AES US Services LLC
4300 Wilson Boulevard
Arlington, VA 22203
David Samford
East Kentucky Power Cooperative Inc
PO Box 707
Winchester, KY 40392
Robert H. Solomon
Federal Energy Regulatory Commission
888 1st Street NE
Room 9A-01
Washington, DC 20426
RE: Exelon Corp, et al v. FERC
Case Number: 26-3621
Agency Case Number: FERC No. AD24-11
Agency Case Number: FERC No. EL25-20
Agency Case Number: FERC No. EL25-49
PACER account holders are required to promptly inform the PACER Service Center of any contact information changes. In order to not delay providing notice to attorneys or pro se public filers, your information, including address, phone number and/or email address, may have been updated in the Third Circuit database. Changes at the local level will not be reflected at PACER. Public filers are encouraged to review their information on file with PACER and update if necessary.

Effective December 15, 2008, the Court implemented the Electronic Case Files System. Accordingly, attorneys are required to file all documents electronically. See 3d Cir. L.A.R. 113 (2008) and the Court's CM/ECF website at https://www.ca3.uscourts.gov/forms. 513 of 515

PDF page 223

Case: 26-3621
Document: 1-3
Page: 3
Date Filed: 10/16/2026
To All Parties:
Enclosed is the case opening information regarding the above-captioned petition for review filed by Appalachian Power Co, Virginia Electric & Power Co, Trans Allegheny Interstate Line Co., American Transmission Systems Inc, AEP Appalachian Transmission Co Inc, Potomac Edison Co, Duquesne Light Co, Mid Atlantic Interstate Transmission LLC, PPL Electric Utilities Corp, Rockland Electric Co, Dayton Power & Light Co, Keystone Appalachian Transmission Co., AEP Indiana Michigan Transmission Co Inc, Indiana Michigan Power Co, Kentucky Power Co, Wheeling Power Co, AEP Kentucky

Transmission Co Inc, Exelon Corp, Ohio Power Co, East Kentucky Power Cooperative Inc, Kingsport Power Co, American Electric Power Service Corp, Jersey Central Power & Light Co, Dominion Energy Services Inc, AEP Ohio Transmission Co Inc, Monongahela Power Co, AEP West Virginia Transmission Co Inc, docketed at No. 26-3621. The petition was received on October 16, 2026. All inquiries should be directed to your Case Manager in writing or by calling the Clerk's Office at 215-597-2995. This Court's rules, forms and case information are available on our website at http://www.ca3.uscourts.gov.

Pursuant to Fed. R. App. P. 17 (a), the agency must file the record with this Court within forty
(40) days after being served with the petition for review, unless the statute authorizing review provides otherwise.

Attached is a copy of the full caption. Please review the caption carefully and promptly advise this office in writing of any discrepancies.

The docketing fee of $600.00 was received on October 16, 2026. electronically. 10/16/2026 @ 5:18pm.

Payment made through pay.gov..
A03-69773-560.
For Immigration cases only:
The filing of this petition for review will not automatically stay removal. A separate Motion for Stay of Removal must be filed.

Counsel for Petitioner(s) must file:
1.Application for Admission (if applicable);
2. Appearance Form
3. Disclosure Statement (except governmental entities);
4. Docketing Statement.
514 of 515

PDF page 224

Case: 26-3621
Document: 1-3
Page: 4
Date Filed: 10/16/2026
These forms must be filed within 14 days of the date of this letter. Failure of Petitioner(s) to comply with any of these requirements by the deadline will result in the DISMISSAL of the case without further notice. 3rd Cir. LAR Misc. 107.2. Counsel for Respondent(s) must file:

1.Application for Admission (if applicable);
2.Appearance Form
3.Disclosure Statement (except governmental entities).
These forms must be filed within 14 days of the date of this letter. Very truly yours,

Patricia S. Dodszuweit, Clerk
By: s/ James King
Case Manager
267-299-4958
515 of 515