Petition for Review filed in the U.S. Court of Appeals for the Third Circuit of Exelon Corp., et al. re 12/18/2025, 02/20/2026, 06/18/2026, and 08/20/2026…
Text extracted from the eLibrary original (SHA-256 c9366937e16f1b34…). Download the original from the official source.
Contents · 22 sections
- C. Necessary Studies
- D. Other
- E. Effective Date
- VI. Paper Hearing
- A. Rates, Terms, and Conditions for Firm and Non-Firm Contract
- B. Additional Charge for Eligible Customers Taking FCD and/or NFCD
- C. Interconnection Requirements and Operational Practices for
- D. Penalty Charge or Other Remedial Action for New Transmission
- E. Anti-Toggling Mechanisms for Firm Contract Demand Transmission
- F. Communications, Alarm, SCADA, or Other Requirements
- G. Curtailment Procedures for Interim NITS and Non-Firm Contract
- H. Rates, Terms, and Conditions for Interim NITS
- Attachment F-3A. Last, Indicated TOs request that PJM add a placeholder section for
- I. Annual Report on New Transmission Services
- ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0)
- ATTACHMENT F-4, OATT ATTACHMENT F-4 (0.0.0)
- ATTACHMENT D
- ATTACHMENT E
- F. Alvin Taylor
- F. Alvin Taylor
- F. Alvin Taylor
- F. Alvin Taylor
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
Document Accessig-P SP; 2QI:236-18 - 3g Wu men t:Filla EPAg9: g69,48/2pge Filed: 10/16/2026 Docket No.Read this passage
C. Necessary Studies
printed heading · Topic match: Connecting load and generation
The Commission directed PJM to revise the Tariff to clarify that an existing Interconnection Customer seeking to modify its ISA or GIA to allow its generator to serve Co-Located Load, including to reflect any reduction in its CIRs, must follow the Necessary Study process to effectuate such…Read this passage Filed comments: Connecting load and generation
D. Other
printed heading · Topic match: Connecting load and generation
However, we reject PJM's proposed revisions to comply with the Commission's directive in the December Order to require Interconnection Customers with ISAs or GIAs executed (or requested to be filed unexecuted) prior to the effective date of the revised generation interconnection procedures and pro…Read this passage Filed comments: Connecting load and generation
E. Effective Date
printed heading · Topic match: Reliability and curtailment
PJM requests a placeholder effective date of 12/31/9998 because PJM cannot implement the Tariff changes until the Commission sets the terms and conditions of the new transmission services in the paper hearing.731 PJM states that it will submit a clean-up filing proposing an effective date after the…Read this passage Filed comments: Reliability and curtailment
VI. Paper Hearing
printed heading · Topic match: Connecting load and generation
The Commission directed PJM to modify its Tariff to require that the Eligible Customer taking transmission service on behalf of a Co-Located Load takes one of three transmission services: (1) NITS or Interim NITS, (2) FCD transmission service, or (3) NFCD transmission service.735 With respect to…Read this passage Filed comments: Connecting load and generation
A. Rates, Terms, and Conditions for Firm and Non-Firm Contract
printed heading · Topic match: Connecting load and generation
We therefore direct PJM to submit a compliance filing within 60 days of the issuance of this order proposing Tariff revisions to permit Eligible Customers to elect to take FCD transmission service or NFCD transmission service without the limitations that PJM proposes (i.e., (1) the requirement that…Read this passage Filed comments: Connecting load and generation
B. Additional Charge for Eligible Customers Taking FCD and/or NFCD
printed heading · Topic match: Connecting load and generation
Constellation contends that Indicated TOs' proposed Grid Reliance Charge rests on an unsound methodology that violates cost causation principles.934 Constellation requests that the charge be recalculated based on the "minimum system" method.Read this passage Filed comments: Connecting load and generation
C. Interconnection Requirements and Operational Practices for
printed heading · Topic match: Connecting load and generation
More specifically, Constellation supports, subject to clarification, Indicated TOs' recommendations that: (1) all special protection schemes and remedial action schemes be fully redundant; (2) customers should pay for PJM and transmission owner-administered studies to ensure any special protection…Read this passage Filed comments: Connecting load and generation
D. Penalty Charge or Other Remedial Action for New Transmission
printed heading · Topic match: Reliability and curtailment
However, we reject PJM's proposal not to apply such a penalty to Eligible Customers taking FCD transmission service on behalf of Co-Located Load, consistent with our findings above that Eligible Customers taking FCD transmission service on behalf of Co-Located Load must also have necessary control…Read this passage Filed comments: Reliability and curtailment
E. Anti-Toggling Mechanisms for Firm Contract Demand Transmission
printed heading · Topic match: Connecting load and generation
PJM proposes an anti-toggling mechanism to prevent transmission customers from switching between FCD and NFCD transmission services by providing that the portion of the Co-Located Load served by FCD transmission service is not eligible to be served by NFCD transmission service for five years…Read this passage Filed comments: Connecting load and generation
F. Communications, Alarm, SCADA, or Other Requirements
printed heading · Topic match: Connecting load and generation
PJM proposes to develop telemetry requirements for Co-Located Load so that PJM can monitor the status of demand placed on PJM's transmission system, including unreserved use, to ensure reliability.1068 PJM states that it still determining the scope of the tools and requirements necessary to limit…Read this passage Filed comments: Connecting load and generation
G. Curtailment Procedures for Interim NITS and Non-Firm Contract
printed heading · Topic match: Reliability and curtailment
Joint Co-Location Developers argue that PJM fails to adequately clarify when and how NFCD transmission service and Interim NITS shall be curtailed, in particular the curtailment trigger.1074 Joint Co-Location Developers maintain that the curtailment trigger significantly affects rates and service…Read this passage Filed comments: Reliability and curtailment
H. Rates, Terms, and Conditions for Interim NITS
printed heading · Topic match: Connecting load and generation
PJM proposes load shedding and curtailment provisions applicable to Interim NITS, including that prior to commencement of service, the Eligible Customer must demonstrate its ability to comply with PJM's load shedding and curtailment procedures.1094 PJM proposes to require Eligible Customers taking…Read this passage Filed comments: Connecting load and generation
Attachment F-3A. Last, Indicated TOs request that PJM add a placeholder section for
printed heading · Topic match: Connecting load and generation
Enchanted Rock reiterates that PJM's implementation of Interim NITS is fundamentally flawed because, while an Eligible Customer takes Interim NITS on behalf of a Co-Located Load, PJM proposes not to allow that Co-Located Load to receive any capacity or energy from a Co-Located Generator and instead…Read this passage Filed comments: Connecting load and generation
I. Annual Report on New Transmission Services
printed heading · Topic match: Connecting load and generation
Maryland OPC requests that the Commission at minimum require PJM demonstrate how its proposal meets ratepayer protection standards set forth in the Statement of Principles and Ratepayer Protection Pledge and defer action on the proposed revisions until after PJM proposes tariff revisions to…Read this passage Filed comments: Connecting load and generation
ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0)
printed heading
ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0) •Read this passage
ATTACHMENT F-4, OATT ATTACHMENT F-4 (0.0.0)
printed heading · Topic match: Cost allocation
In today's order, the Commission addresses rehearing requests and the paper hearing and compliance record regarding the rates, terms, and conditions through which Co-Located Loads may take transmission service from the PJM Interconnection, L.L.C. (PJM) system.Read this passage Filed comments: Cost allocation
ATTACHMENT D
printed heading · Topic match: Filing procedure
As provided in 16 U.S.C. § 8251(a), the requests for rehearing of the above-cited order filed in this proceeding will be addressed in a future order to be issued consistent with the requirements of such section.Read this passage Filed comments: Filing procedure
ATTACHMENT E
printed heading
ATTACHMENT E SERVICE LIST 442 of 515 Andrew Hinz Andrew Hinz 1427 PARK AVE BALTIMORE, MARYLAND 21217 UNITED STATES ahinz61@outlook.com Primary Person or Counsel of Record to be Served Party Michael Haugh Policy Director Advanced Energy United 1010 VERMONT AVE NW WASHINGTON, DISTRICT OF COLUMBIA…Read this passage
F. Alvin Taylor
printed heading
Linda Walsh Husch Blackwell LLP , 1801 Pennsylvania Ave.Read this passage
F. Alvin Taylor
printed heading
Alvin Taylor Attorney McCarter & English, LLP 1301 K Street, NW Suite 1000 West Washington, DISTRICT OF COLUMBIA 20005 ataylor@mccarter.com Lee County Electric Cooperativ e, Inc.Read this passage
F. Alvin Taylor
printed heading · Topic match: Registry access
Dearborn Street Chicago, ILLINOIS 60603 UNITED STATES carlos.isaac@exeloncorp.com Stan Berman 3502 Fremont Ave N, #1 Seattle, WASHINGTON 98103 stan@bermlaw.com Pennsylvan is Office of Consumer ' Advocate Melanie El Atieh Deputy Consumer Advocate Pennsylvania Office of Consumer Advocate 555 WALNUT…Read this passage Filed comments: Registry access
F. Alvin Taylor
printed heading
P. 17 (a), the agency must file the record with this Court within forty (40) days after being served with the petition for review, unless the statute authorizing review provides otherwise.Read this passage