Preliminary Answer of PJM Interconnection L.L.C. Opposing Fast-Track Processing and Motion for Extension of Time to Answer Exelon Corporation’s 11/03/2026…
Text extracted from the eLibrary original (SHA-256 2e2b979b70cd5051…). Download the original from the official source.
Contents · 6 sections
- I. PRELIMINARY ANSWER OPPOSING FAST-TRACK PROCESSING
- II. MOTION FOR EXTENSION OF TIME
- A. Legal Consequences Do Not Attach Merely When Planning Parameters Are
- B. Market Participants Receive Adequate Prior Notice Upon Establishment of
- C. PJM is Scheduled to Post Planning Parameters By March 1, 2027 for the
- III. CONCLUSION
Topics in the text: Filing procedure · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
PJM also requests a four-week extension of time to answer the Complaint on the merits.Read this passage
I. PRELIMINARY ANSWER OPPOSING FAST-TRACK PROCESSING
printed heading · Topic match: Reliability and curtailment
PRELIMINARY ANSWER OPPOSING FAST-TRACK PROCESSING The Complaint requests fast-track processing of its Complaint and asks the Commission to find that the existing three-year forward procurement period employed in PJM’s Reliability Pricing Model is no longer just and reasonable and to replace it with…Read this passage
II. MOTION FOR EXTENSION OF TIME
printed heading · Topic match: Filing procedure
PJM respectfully requests that the Commission extend that deadline by four weeks, until December 21, 2026. 10 PJM, Powering Reliability Through Market Design Paper (May 6, 2026), https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-…Read this passage
A. Legal Consequences Do Not Attach Merely When Planning Parameters Are
printed heading
Legal Consequences Do Not Attach Merely When Planning Parameters Are Posted.Read this passage
B. Market Participants Receive Adequate Prior Notice Upon Establishment of
printed heading
To be clear, the Commission has historically been reluctant to order refunds with respect to final market results, and PJM has opposed such requests for refund relief.Read this passage
C. PJM is Scheduled to Post Planning Parameters By March 1, 2027 for the
printed heading · Topic match: Filing procedure
ER26-3661-000 (Oct. 30, 2026). 27 See Tariff, Attachment DD, section 5.10(a)(iv)(B). 11 For this additional reason, granting PJM’s request for a four-week extension of time to answer the Complaint, through December 21, 2026, will not prejudice any party, constrain the Commission’s consideration of…Read this passage
III. CONCLUSION
printed heading · Topic match: Filing procedure
PJM further requests that the Commission promptly grant PJM’s request for an extension of time, through December 21, 2026, to answer the Complaint.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Audubon, PA., this 4th day of November 2026. /s/ Chenchao Lu Associate General Counsel PJM Interconnection, L.L.C. 2750 Monroe Blvd.Read this passage