Tariff Revisions to Address Commission's EL26-71 Order to Show Cause
PDF page 1
Duncan
&Allen LLP
1730 Rhode Island Avenue, Northwest
Washington, D.C. 20036
Telephone (202) 289-8400
FAX (202) 289-8450
COUNSELLORS AT LAW
November 16, 2026
VIA ELECTRONIC FILING
Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, NW
Washington, DC 20426
Re:
Citizens Sunrise Transmission LLC Tariff Revisions to
Address Commission’s Docket No. EL26-71 Order to Show
Cause, Docket No. ER27-___-000
Dear Secretary Reese:
On June 18, 2026 the Commission issued its Order Instituting Proceeding Under Section 206 of the Federal Power Act (“Show Cause Order”),1 requiring each Participating Transmission Owner (“PTO”) within the California Independent System Operator’s (“CAISO”) system to address issues associated with serving large load and co-location arrangements. In this filing, pursuant to Section 205 of the Federal Power Act, Citizens Sunrise Transmission LLC (“Citizens Sunrise”) files proposed revisions to its Transmission Owner Tariff (“TO Tariff”) to address the issues raised in the Show Cause Order. Citizens Sunrise respectfully requests that the Commission accept these TO Tariff revisions to become effective January 15, 2027, which is sixty (60) days from the date of this filing.
I. BACKGROUND ON CITIZENS SUNRISE
Citizens Sunrise is a wholly owned subsidiary of Citizens Energy Corporation, a non-profit organization dedicated to making life’s basic needs
1 CAISO et al., 195 FERC ¶61,214 (2026).
PDF page 2
Duncan
& Allen LLP
- 2 -
more affordable through successful business ventures. To date, Citizens Energy Corporation has donated more than $600 million to programs supporting the most vulnerable in our communities.
In 2012, Citizens Sunrise invested approximately $86 million with San Diego Gas & Electric Company (“SDG&E”) in the Sunrise Powerlink Project (“Sunrise Project”) in exchange for a 30-year leasehold interest in approximately 50% interest in a specific segment of the Sunrise Project.2 Citizens Sunrise does not own any of the actual facilities. SDG&E retains ownership and operation and maintenance responsibilities. Citizens Sunrise became a CAISO PTO, turned its interest in the Sunrise Project over to the CAISO’s operational control and recovers its costs through its TO Tariff. As reflected in its TO Tariff, Citizens Sunrise is a “Non-Load-Serving Participating TO and has no End-Use Customers.”3
As part of Citizens Energy Corporation’s charitable mission, Citizens Sunrise is contractually committed to dedicate 50% of its net after-tax cash flows from the Sunrise Project to programs assisting low-income families in Imperial County. To date, the Sunrise Project has generated $20 million in charitable donations, which are currently being used to support the country’s largest community solar project which is saving low-income ratepayers in the Imperial Valley an average of $350 a year on their electric bills. Citizens Sunrise estimates its involvement in the Sunrise Project will generate approximately $45 million in charitable assistance over the term of the lease.
II. RESPONSE TO SHOW CAUSE ORDER
The Commission’s Show Cause Order determined that the TO Tariffs of the CAISO PTOs, including Citizens Sunrise, “lack provisions that address, with sufficient clarity and consistency” how each PTO “will timely study…the provision of transmission service to Eligible Customers on behalf of large loads.”4 The Commission directed each PTO to either justify why its
2 Sunrise TO Tariff Section 3.70 definition of “Project”.3 Sunrise TO Tariff Section 1 “Preamble”.4 Show Cause Order, 195 FERC ¶61,214 at P 38.
PDF page 3
Duncan
& Allen LLP
- 3 -
TO Tariff remained just and reasonable, or to provide TO Tariff revisions necessary to remedy the Commission’s concerns.
As discussed in more detail below, Citizens Sunrise has a limited, leasehold interest in only a portion of the overall Sunrise Project transmission line. Ownership of the transmission line, as well as responsibility for operating and maintaining the line, remains with SDG&E. For these reasons, Citizens Sunrise proposes revisions to its TO Tariff to make clear that any study, planning, interconnection or expansion requests related to Citizens Sunrise’s interest in the Sunrise Project will be governed by the relevant provisions of the SDG&E TO Tariff.
A. Relevant Existing TO Tariff Provisions
Citizens Sunrise’s current TO Tariff recognizes the limited nature of its interest in the Sunrise Project. Section 16.12 of Citizens Sunrise’ current TO Tariff states that for so long as the Transfer Capability Lease between Citizens Sunrise and SDG&E is in effect, Sections 8 (“Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades”), 9 (“Expansion Process”), and 10 (“Interconnection Process”) of the Citizens Sunrise Tariff will be “superseded by the corresponding sections of the TO Tariff of San Diego Gas & Electric.”5 Article III of the Transfer Capability Lease, which is included at Appendix II to the Sunrise TO Tariff, outlines the division of responsibility between SDG&E and Citizens Sunrise, with SDG&E retaining all responsibility for operation and maintenance6 and to act as the interconnection agent for the Sunrise Project.7
These existing provisions illustrate that any responsibility for studying or serving large load customers or addressing the needs of co-located arrangements is beyond the scope of Citizens Sunrise’s limited authority as a non-load serving PTO with no end-use customers and a limited interest in a portion of a single transmission line segment within SDG&E’s system.
5 Sunrise TO Tariff Section 16.12.6 Section 3.2 of the Transfer Capability Lease, Appendix II to the Sunrise TO Tariff.7 Section 3.6 of the Transfer Capability Lease, Appendix II to the Sunrise TO Tariff.
PDF page 4
Duncan
& Allen LLP
- 4 -
B. Proposed TO Tariff Provision Revisions
In response to the Show Cause Order, Citizens Sunrise is proposing a series of revisions to its TO Tariff to ensure it is clear that when it comes to all interconnection matters, including interconnection and service of large load customers or co-located arrangements, the appropriate TO Tariff provisions are those of SDG&E. These revisions include the following:
• Revisions to the definitions of Expedited Interconnection Agreement, Facilities Study Agreement, Facility or Facilities Study, Interconnection, Interconnection Agreement, Interconnection Application, Reliability Upgrade, Requests for Expedited
Interconnection Procedures, System Impact Study, and System Impact Study Agreement, each to clarify that SDG&E’s TO Tariff provisions will govern.
• Added new language to Section 8, Obligations to Interconnect or Construct Transmission and Expansions and Facility Upgrades, to confirm that all conduct that falls under Section 8 will be governed by SDG&E’s TO Tariff.
• Added new language to Section 9, Expansion Process, to confirm that all conduct that falls under Section 9 will be governed by SDG&E’s TO Tariff.
• Added new language to Section 10, Interconnection Process, to confirm that all conduct that falls under Section 10 will be governed by SDG&E’s TO Tariff.
• Citizens Sunrise additionally makes a series of administrative revisions to address typos, update addresses, and similar type changes with this filing.
Each of these revisions is shown in redline in Attachment B to this filing, which is a redline of the Citizens Sunrise TO Tariff. A clean version of the revised TO Tariff is included as Attachment A.
Citizens Sunrise respectfully submits that these revisions address the concerns raised in the Show Cause Order within the bounds of Citizens Sunrise’s limited interest in, and control over, the Sunrise Project. Put simply, Citizens Sunrise is bound by the terms of its Transfer Capability
PDF page 5
Duncan
& Allen LLP
- 5 -
Lease with SDG&E, and that agreement makes it clear that SDG&E, as the owner and operator of the Sunrise Project, has the authority and responsibility for all operational and interconnection related matters.
To the extent that the CAISO or SDG&E propose TO Tariff revisions that impact the revisions Citizens Sunrise proposes in this filing, Citizens Sunrise commits to making a compliance filing to ensure its TO Tariff remains consistent.
III. REQUESTED EFFECTIVE DATE
Citizens Sunrise requests an effective date for the revised TO Tariff of January 15, 2027.
VIII. CONCLUSION
Citizens Sunrise respectfully requests that the Commission accept these proposed tariff revision effective as of January 15, 2027, and determine that Citizens Sunrise has satisfied the concerns the Commission identified in its Show Cause Order.
Respectfully submitted,
/s/ Ashley M. Bond
Ashley M. Bond
Amy E. McDonnell
Duncan & Allen LLP
1730 Rhode Island Ave. N.W.
Suite 700
Washington, D.C. 20036
(202) 289-8400
amb@duncanallen.com
aem@duncanallen.com
Counsel for Citizens Sunrise
Transmission LLC
November 16, 2026