Tariff Revisions to Address Commission's EL26-71 Order to Show Cause
Citizens Sunrise Transmission LLC files tariff revisions under section 205 on November 16, 2026, in ER27-499-000, answering the CAISO show cause order. It leases part of SDG&E's Sunrise Powerlink, so its revisions say SDG&E's tariff governs study, interconnection and expansion requests. The text matches the Citizens Sycamore-Penasquitos filing except for project facts.
Asks FERC to: Accept the revisions effective January 15, 2027, and find that Citizens Sunrise has satisfied the concerns in the show cause order.
Filed under section 205 to answer the E-10 show cause order for CAISO and its transmission owners. It sends large load study and interconnection matters to SDG&E's tariff rather than setting up a process of its own.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25)
Key points
- Citizens Sunrise owns none of the line. SDG&E keeps ownership, operation and maintenance.
Citizens Sunrise does not own any of the actual facilities. SDG&E retains ownership and operation and maintenance responsibilities. PDF p. 2
- It is a non-load-serving transmission owner with no end-use customers.
Non-Load-Serving Participating TO and has no End-Use Customers PDF p. 2
- Its current tariff already hands the interconnection and expansion sections to SDG&E's tariff while the lease with SDG&E is in effect.
superseded by the corresponding sections of the TO Tariff of San Diego Gas & Electric PDF p. 3
- Study, planning, interconnection and expansion requests would be governed by SDG&E's tariff.
any study, planning, interconnection or expansion requests related to Citizens Sunrise’s interest in the Sunrise Project will be governed by the relevant provisions of the SDG&E TO Tariff PDF p. 3
- New language in Sections 8, 9 and 10 repeats the point, one section at a time.
Added new language to Section 10, Interconnection Process, to confirm that all conduct that falls under Section 10 will be governed by SDG&E’s TO Tariff PDF p. 4
- Definitions are revised to say SDG&E's tariff provisions govern.
each to clarify that SDG&E’s TO Tariff provisions will govern PDF p. 4
- It commits to a compliance filing if CAISO or SDG&E changes its tariff in a way that affects these revisions.
Citizens Sunrise commits to making a compliance filing to ensure its TO Tariff remains consistent PDF p. 5
- It asks for an effective date 60 days after filing.
accept these TO Tariff revisions to become effective January 15, 2027, which is sixty (60) days from the date of this filing PDF p. 1
Text extracted from the eLibrary original (SHA-256 837ee55209e15cd1…). Download the original from the official source.
Contents · 6 sections
Topics in the text: Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
Citizens Sunrise respectfully requests that the Commission accept these TO Tariff revisions to become effective January 15, 2027, which is sixty (60) days from the date of this filing.Read this passage
I. BACKGROUND ON CITIZENS SUNRISE
printed heading · Topic match: Cost allocation
To date, the Sunrise Project has generated $20 million in charitable donations, which are currently being used to support the country’s largest community solar project which is saving low-income ratepayers in the Imperial Valley an average of $350 a year on their electric bills.Read this passage
II. RESPONSE TO SHOW CAUSE ORDER
printed heading
For these reasons, Citizens Sunrise proposes revisions to its TO Tariff to make clear that any study, planning, interconnection or expansion requests related to Citizens Sunrise’s interest in the Sunrise Project will be governed by the relevant provisions of the SDG&E TO Tariff.Read this passage
A. Relevant Existing TO Tariff Provisions
printed heading
Relevant Existing TO Tariff Provisions Citizens Sunrise’s current TO Tariff recognizes the limited nature of its interest in the Sunrise Project.Read this passage
B. Proposed TO Tariff Provision Revisions
printed heading
To the extent that the CAISO or SDG&E propose TO Tariff revisions that impact the revisions Citizens Sunrise proposes in this filing, Citizens Sunrise commits to making a compliance filing to ensure its TO Tariff remains consistent.Read this passage
III. REQUESTED EFFECTIVE DATE
printed heading
REQUESTED EFFECTIVE DATE Citizens Sunrise requests an effective date for the revised TO Tariff of January 15, 2027.Read this passage
VIII. CONCLUSION
printed heading
CONCLUSION Citizens Sunrise respectfully requests that the Commission accept these proposed tariff revision effective as of January 15, 2027, and determine that Citizens Sunrise has satisfied the concerns the Commission identified in its Show Cause Order.Read this passage