ER27-500-000 · 2026-11-16 · Citizens Sycamore-Penasquitos Transmission LLC

Tariff Revisions to Address Commission's ER26-71 Order to Show Cause

PDF page 1

Duncan
&Allen LLP

1730 Rhode Island Avenue, Northwest
Washington, D.C. 20036
Telephone (202) 289-8400
FAX (202) 289-8450

COUNSELLORS AT LAW

November 16, 2026

VIA ELECTRONIC FILING

Debbie-Anne A. Reese
 Secretary
Federal Energy Regulatory Commission
888 First Street, NW
Washington, DC 20426

Re:
Citizens Sycamore-Penasquitos Transmission LLC Tariff
Revisions to Address Commission’s Docket No. EL26-71 Order to Show Cause, Docket No. ER27-_____-000

Dear Secretary Reese:

On June 18, 2026 the Commission issued its Order Instituting Proceeding Under Section 206 of the Federal Power Act (“Show Cause Order”),1 requiring each Participating Transmission Owner (“PTO”) within the California Independent System Operator’s (“CAISO”) system to address issues associated with serving large load and co-location arrangements.  In this filing, pursuant to Section 205 of the Federal Power Act, Citizens Sycamore-Penasquitos Transmission LLC (“Citizens Sycamore”) files proposed revisions to its Transmission Owner Tariff (“TO Tariff”) to address the issues raised in the Show Cause Order.  Citizens Sycamore respectfully requests that the Commission accept these TO Tariff revisions to become effective January 15, 2027, which is sixty (60) days from the date of this filing.

1 CAISO et al., 195 FERC ¶61,214 (2026).

PDF page 2

Duncan
& Allen LLP
- 2 -

I. BACKGROUND ON CITIZENS SYCAMORE

Citizens Sycamore is a wholly owned subsidiary of Citizens Energy Corporation, a non-profit organization dedicated to making life’s basic needs more affordable through successful business ventures.  To date, Citizens Energy Corporation has donated more than $600 million to programs supporting the most vulnerable in our communities.

In 2019, Citizens Sycamore invested approximately $27 million with San Diego Gas & Electric Company (“SDG&E”) in the Sycamore-Penasquitos Project (“Sycamore Project”) in exchange for a 30-year leasehold interest in approximately 12.92% interest in the underground segment of the Sycamore Project.2  Citizens Sycamore does not own any of the actual facilities. SDG&E retains ownership and operation and maintenance responsibilities. Citizens Sycamore became a CAISO PTO, turned its interest in the Sycamore Project over to the CAISO’s operational control and recovers its costs through its TO Tariff.  As reflected in its TO Tariff, Citizens Sycamore is a “Non-Load- Serving Participating TO and has no End-Use Customers.”3

As part of Citizens Energy Corporation’s charitable mission, Citizens Sycamore is contractually committed to dedicate 50% of its net after-tax cash flow from the Sycamore Project to programs assisting low-income families in SDG&E’s service area.  To date, the Sycamore Project has generated $3.7 million in charitable donations, which are currently being used to purchase electric vehicles for community aid organizations, including Meals on Wheels and the Indian Health Council, among others.  Citizens Sycamore estimates its involvement in the Sycamore Project will generate approximately $14 million in charitable assistance over the term of the lease.

II. RESPONSE TO SHOW CAUSE ORDER

The Commission’s Show Cause Order determined that the TO Tariffs of the CAISO PTOs, including Citizens Sycamore, “lack provisions that address, with sufficient clarity and consistency” how each PTO “will timely study…the provision of transmission service to Eligible Customers on behalf

2 Sycamore TO Tariff Section 3.70 definition of “Project”.
3 Sycamore TO Tariff Section 1 “Preamble”.

PDF page 3

Duncan
& Allen LLP
- 3 -

of large loads.”4  The Commission directed each PTO to either justify why its TO Tariff remained just and reasonable, or to provide TO Tariff revisions necessary to remedy the Commission’s concerns.

As discussed in more detail below, Citizens Sycamore has a limited, less than 13% leasehold interest in a single segment of the overall Sycamore Project transmission line.  Ownership of the transmission line, as well as responsibility for operating and maintaining the line, remains with SDG&E. For these reasons, Citizens Sycamore proposes revisions to its TO Tariff to make clear that any study, planning, interconnection or expansion requests related to Citizens Sycamore’s interest in the Sycamore Project will be governed by the relevant provisions of the SDG&E TO Tariff.

A. Relevant Existing TO Tariff Provisions

Citizens Sycamore’s current TO Tariff recognizes the limited nature of its interest in the Sycamore Project.  Section 16.12 of Citizens Sycamore’s current TO Tariff states that for so long as the Transfer Capability Lease between Citizens Sycamore and SDG&E is in effect, Sections 8 (“Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades”), 9 (“Expansion Process”), and 10 (“Interconnection Process”) of the Citizens Sunrise Tariff will be “superseded by the corresponding sections of the TO Tariff of San Diego Gas & Electric.”5  Article III of the Transfer Capability Lease, which is included at Appendix II to the Sycamore TO Tariff, outlines the division of responsibility between SDG&E and Citizens Sycamore, with SDG&E retaining all responsibility for operation and maintenance6 and to act as the interconnection agent for the Sycamore Project.7

4 Show Cause Order, 195 FERC ¶61,214 at P 38.
5 Sycamore TO Tariff Section 16.12.
6 Section 3.2 of the Transfer Capability Lease, Appendix II to the Sycamore TO Tariff.
7 Section 3.6 of the Transfer Capability Lease, Appendix II to the Sycamore TO Tariff.

PDF page 4

Duncan
& Allen LLP
- 4 -

These existing provisions illustrate that any responsibility for studying or serving large load customers or addressing the needs of co-located arrangements is beyond the scope of Citizens Sycamore’s limited authority as a non-load serving PTO with no end-use customers and a limited interest in a portion of a single transmission line segment within SDG&E’s system.

B. Proposed TO Tariff Provision Revisions

In response to the Show Cause Order, Citizens Sycamore is proposing a series of revisions to its TO Tariff to ensure it is clear that when it comes to all interconnection matters, including interconnection and service of large load customers or co-located arrangements, the appropriate TO Tariff provisions are those of SDG&E.  These revisions include the following:

• Revisions to the definitions of Expedited Interconnection Agreement, Facilities Study Agreement, Facility or Facilities Study, Interconnection, Interconnection Agreement, Interconnection Application, Reliability Upgrade, Requests for Expedited

Interconnection Procedures, System Impact Study, and System Impact Study Agreement, each to clarify that SDG&E’s TO Tariff provisions will govern.

• Added new language to Section 8, Obligations to Interconnect or Construct Transmission and Expansions and Facility Upgrades, to confirm that all conduct that falls under Section 8 will be governed by SDG&E’s TO Tariff.

• Added new language to Section 9, Expansion Process, to confirm that all conduct that falls under Section 9 will be governed by SDG&E’s TO Tariff.

• Added new language to Section 10, Interconnection Process, to confirm that all conduct that falls under Section 10 will be governed by SDG&E’s TO Tariff.

• Citizens Sycamore additionally makes a series of administrative revisions to address typos, update addresses, and similar type changes with this filing.

PDF page 5

Duncan
& Allen LLP
- 5 -

Each of these revisions is shown in redline in Attachment B to this filing, which is a redline of the Citizens Sycamore TO Tariff.  A clean version of the revised TO Tariff is included as Attachment A.

Citizens Sycamore respectfully submits that these revisions address the concerns raised in the Show Cause Order within the bounds of Citizens Sycamore’s limited interest in, and control over, the Sycamore Project.  Put simply, Citizens Sycamore is bound by the terms of its Transfer Capability Lease with SDG&E, and that agreement makes it clear that SDG&E, as the owner and operator of the Sycamore Project, has the authority and responsibility for all operational and interconnection related matters.

To the extent that the CAISO or SDG&E propose TO Tariff revisions that impact the revisions Citizens Sycamore proposes in this filing, Citizens Sycamore commits to making a compliance filing to ensure its TO Tariff remains consistent.

III. REQUESTED EFFECTIVE DATE

Citizens Sycamore requests an effective date for the revised TO Tariff of January 15, 2027.

VIII. CONCLUSION

Citizens Sycamore respectfully requests that the Commission accept these proposed tariff revisions effective as of January 15, 2027, and determine that Citizens Sycamore has satisfied the concerns the Commission identified in its Show Cause Order.

PDF page 6

Duncan
& Allen LLP
- 6 -

Respectfully submitted,

/s/ Ashley M. Bond

Ashley M. Bond

Amy E. McDonnell
Duncan & Allen LLP
1730 Rhode Island Ave. N.W.
Suite 700
Washington, D.C.  20036
(202) 289-8400
amb@duncanallen.com
aem@duncanallen.com

Counsel for Citizens Sycamore-
Penasquitos Transmission LLC

November 16, 2026